Attachment_5_-_AF_Form_66_Submittal_Register.pdf

PDF 308 KB Posted

Attached to
Repair Squadron Operations Facility, Bldg 709 Federal contract opportunity
Solicitation number
FA4418-19-R-0001
Issued by
Department of the Air Force Air Mobility Command

About this file

Attachment 5 - AF Form 66, Submittal Register

View the file

Other files for this federal contract opportunity

Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP NUMBER

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

01 11 00, Para 1.6.2, "Outage Requests"; G

01 11 00, Para 1.6.2, "Road

Closure Requests"; G

01 11 00, Para 1.6, "Work

Clearance"; G

01 14 00, Para 1.2.1.1, "List of Contact Personnel"; G

01 30 00, Para 1.2, "View

Location Map"; G

01 30 00, Para 1.3, "Progress and Completion

Pictures"; G

01 30 00, Para 1.6.2, "Resume for the proposed

Superintendent"; G

01 32 16.00 20, Para 1.2, "Qualifications"; G

01 32 16.00 20, Para 1.3, "Project Schedule"; G

01 32 16.00 20, Para 1.4.1, "Initial Contract Progress

Report (AF IMT 3065)"; G

01 32 16.00 20, Para 1.4.2, "Initial Contract Progress

Schedule (AF IMT 3064)"; G

01 32 16.00 20, Para 1.3.3, "Project Schedule Updates";

G

01 32 16.00 20, Para 1.4.1, "Monthly Contract Progress

Reports (AF IMT 3065)"; G

01 32 16.00 20, Para 1.4.2, "Monthly Contract Progress

Schedules (AF IMT 3064)";

G

01 33 00, Para 1.6, "Submittal Register"; G

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

IO

N

S U

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E R

'S

IN

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N C

E

D A

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

L

P O

R T

S

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C Typewritten Text Attachment 5

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

01 35 26, Para 1.6, "Accident

Prevention Plan (APP)"; G

01 35 26, Para 1.7, "Activity

Hazard Analysis (AHA)"; G

01 35 26, Para 1.6.1.1, "Critical Lift Plan"; G

01 35 26, Para 1.5.1.3, "Crane Operators"; G

01 35 26, Para 1.11, "Notifications and Reports"

01 35 26, Para 1.11.2, "Accident Reports"; G

01 35 26, Para 1.11.3, "Crane Reports"

01 35 26, Para 1.8.1, "Confined Space Entry

Permit"

01 35 26, Para 1.8.1, "Hot

Work Permit"

01 35 26, Para 1.13, "License Certificates"

01 45 00, Para 1.6, "QC

Plan"; G

01 45 35, Para 3.1.1, "SIOR

Letter of Acceptance"

01 45 35, Para 3.1.1, "Project Manual"

01 45 35, Para 3.1.1, "Project Manual"

01 45 35, Para 3.1.1, "Written Practices"

01 45 35, Para 3.1.3, "Written Practices"

01 45 35, Para 3.1.1, "NDT

Procedures and Equipment

Calibration Records"

01 45 35, Para 3.1.3, "NDT

Procedures and Equipment

Calibration Records"

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

01 45 35, Para 3.1.1, "Daily

Reports"

01 45 35, Para 3.1.3, "Daily

Reports"

01 45 35, Para 3.1.3, "Daily

Reports"

01 45 35, Para 3.1.1, "Biweekly Reports"

01 45 35, Para 3.1.2, "Biweekly Reports"

01 45 35, Para 2.1, "Fabrication Plant"

01 45 35, Para 2.1, "Steel

Truss Plant"

01 45 35, Para 2.1, "Wood

Truss Plant"

01 45 35, Para 2.1, "AC472

Accreditation"

01 45 35, Para 2.1, "Steel

Joist Institute Membership"

01 45 35, Para 2.1, "Certified

Plant"

01 45 35, Para 2.1, "Certificate of Compliance"

01 45 35, Para 1.5.17, "Special Inspector of Record"

01 45 35, Para 1.5, "Special

Inspector"

01 45 35, Para 3.1.1, "Qualification Records"

01 45 35, Para 3.1.3, "Qualification Records"

01 45 35, Para 3.1.1, "Comprehensive Final

Report"

01 45 35, Para 3.1.3, "Comprehensive Final

Report"

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

01 50 00, Para 1.3, "Construction Site Plan"; G

01 50 00, Para 3.4.1, "Traffic

Control Plan"; G

01 50 00, Para 1.4, "Backflow Preventers"

01 50 00, Para 2.2.5, "Backflow Preventer Tests"

01 50 00, Para 1.4.1, "Backflow Tester"

01 50 00, Para 1.4, "Backflow Preventers"

01 54 00.00 31, Para 1.5.2.1, "Affirmative Procurement

Reporting Form"; G

01 57 19.00 31, Para 1.7.1, "Preconstruction Survey"; G

01 57 19.00 31, Para 1.8.3, "Regulatory Notifications"; G

01 57 19.00 31, Para 1.5, "Environmental Protection

Plan"; G

01 57 19.00 31, Para 1.6, "Dirt and Dust Control Plan";

G

01 57 19.00 31, Para 3.9.2, "Disposal Requirements"

01 57 19.00 31, Para 1.8.4, "Erosion and Sediment

Control Inspection Reports"

01 57 19.00 31, Para 3.4, "Erosion and Sediment

Control Inspection Reports"

01 57 19.00 31, Para 3.4, "Storm Water Inspection

Reports for General Permit"

01 57 19.00 31, Para 1.8.5, "Solid Waste Disposal

Report"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

01 57 19.00 31, Para 1.8.2, "Contractor 40 CFR employee training records";

G

01 57 19.00 31, Para 3.4.2, "Storm Water Pollution

Prevention Plan compliance notebook"; G

01 57 19.00 31, Para 1.8, "Waste Determination

Documentation"

01 57 19.00 31, Para 3.7.2, "Waste Determination

Documentation"

01 57 19.00 31, Para 1.8.1, "Disposal Documentation for

Hazardous and Regulated

Waste"

01 57 19.00 31, Para 1.8.2, "Contractor 40 CFR

Employee Training Records"

01 57 19.00 31, Para 1.7.2, "Solid Waste Disposal

Permit"

01 57 19.00 31, Para 1.8.5, "Solid Waste Disposal

Report"

01 57 19.00 31, Para 3.7.2, "Hazardous Waste/Debris

Management"

01 57 19.00 31, Para 1.8.3, "Regulatory Notifications"

01 57 20.00 31, Para , "Material Safety Data Sheets

(MSDS)"

01 57 20.00 31, Para 1.8, "Green Procurement"

01 57 20.00 31, Para 1.8, "Green Procurement"

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

01 57 20.00 31, Para 1.3, "Recycling Report"

01 57 20.00 31, Para 1.3, "Recycling Report"

01 74 19.00 31, Para 1.3.3, "Construction Waste

Management Plan"; G

01 78 00, Para 1.5.1, "Warranty Management

Plan"

01 78 00, Para 1.5.4, "Warranty Tags"

01 78 00, Para 1.4, "Spare

Parts Data"

01 78 00, Para 3.9, "Preventative Maintenance"

01 78 00, Para 3.9, "Condition Monitoring"

01 78 00, Para 3.9, "Inspection"

01 78 00, Para 1.5.1, "Instructions"

01 78 00, Para 3.7, "Operation and Maintenance

Manuals"; G

01 78 00, Para 3.1, "As-Built

Drawings"; G

01 78 00, Para 3.3, "Record

Drawings"; G

01 78 00, Para 3.6, "As-Built

Record of Equipment and

Materials"

01 78 00, Para 3.4, "Final

Approved Shop Drawings"

01 78 00, Para 3.5, "Construction Contract

Specifications"

01 78 00, Para 3.1, "Interim

DD FORM 1354"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

01 78 00, Para 3.1, "Checklist for DD FORM

1354"; G

02 41 00, Para 1.2.1, "Demolition Plan"; G

02 41 00, Para 1.1, "Existing

Conditions"

02 41 00, Para 1.6, "Notification"; G

02 41 00, Para 3.2.2, "Receipts"

03 30 00, Para 1.6.3, "Quality Control Plan"

03 30 00, Para 1.6.4, "Quality Control Personnel

Certifications"

03 30 00, Para 1.6.4, "Quality Control

Organizational Chart"

03 30 00, Para 1.6.6, "Laboratory Accreditation"

03 30 00, Para 1.6.2.1, "Reinforcing Steel"; G

03 30 00, Para 2.4.5, "Joint

Sealants"

03 30 00, Para 2.1, "Materials for Forms"

03 30 00, Para 2.4.1, "Cementitious Materials"

03 30 00, Para 2.3.3, "Concrete Curing Materials"

03 30 00, Para 2.5, "Reinforcement"

03 30 00, Para 2.6.1, "Liquid

Chemical Floor Hardener"

03 30 00, Para 2.4.4, "Admixtures"

03 30 00, Para 2.4.6, "Biodegradable Form

Release Agent"

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

03 30 00, Para 2.3.1, "Mix

Design"; G

03 30 00, Para 1.6.1.1, "Concrete Mix Design"; G

03 30 00, Para 2.4.3, "Aggregates"

03 30 00, Para 3.11.2.2, "Compressive Strength

Tests"; G

03 30 00, Para 3.11.2.3, "Air

Content"

03 30 00, Para 3.11.2.1, "Slump Tests"

03 30 00, Para 2.4.2, "Water"

03 30 00, Para 2.5.1, "Reinforcing Bars"

03 30 00, Para 2.3.3, "Curing

Compound"

03 30 00, Para 1.6.4.2, "Field

Testing Technician and

Testing Agency"

03 45 00, Para 1.8.1, "Precast Drawings"; G

03 45 00, Para 1.8.2, "Concrete Shapes and

Finish"; G

03 45 00, Para 2.1.1, "Contractor-Furnished Mix

Design"; G

03 45 00, Para 2.3.9, "Repair of Surface Defects"; G

03 45 00, Para 1.4, "Manufacturer's

Qualifications"; G

03 45 00, Para 3.3, "Installation"; G

03 45 00, Para 3.7, "Cleaning"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

04 20 00, Para 2.5.3, "Cement"; G

04 20 00, Para 1.6.2, "Cold

Weather Installation"; G

04 20 00, Para 2.2, "Clay or

Shale Brick"; G

136 04 20 00, Para 2.7, "Anchors

04 20 00, Para 2.1, "Expansion-Joint Materials";

G

04 20 00, Para 2.8, "Joint

Reinforcement"; G

04 20 00, Para 2.5.4, "Pre-mixed Mortar"; G

04 20 00, Para 1.2.1.1, "Unit

Strength Method"; G

04 20 00, Para 2.2, "Clay or

Shale Brick"

142 04 20 00, Para 2.7, "Anchors

04 20 00, Para 2.1, "Expansion-Joint Materials"

04 20 00, Para 2.8, "Joint

Reinforcement"

04 20 00, Para 2.5.3, "Masonry Cement"

04 20 00, Para 2.5.3, "Masonry Cement"

05 12 00, Para 1.4.1.1, "Erection Drawings"

05 12 00, Para 1.4.2, "Fabrication Drawings"; G

05 12 00, Para 2.6.2, "Shop

Primer"

05 12 00, Para 2.4.1, "Welding Electrodes and

Rods"

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

05 12 00, Para 2.3.2.3, "Direct Tension Indicator

Washers"

05 12 00, Para 2.4.2, "Non-

Shrink Grout"

05 12 00, Para 2.3.3, "Tension Control Bolts"

154 05 12 00, Para 2.3, "Bolts

05 12 00, Para 3.7.2.1, "Direct Tension Indicator

Washer Inspection Reports"

156 05 12 00, Para 2.2, "Steel" 5

05 12 00, Para 2.5, "Galvanizing"

05 12 00, Para 1.3, "AISC

Fabrication Plant Quality

Certification"

05 12 00, Para 1.3, "AISC

Erector Quality Certification"

05 12 00, Para 1.4.3.1, "Welding Procedures and

Qualifications"

161 05 40 00, Para 2.1, "Studs

05 40 00, Para 2.1, "Recycled Content of Steel

Products"

06 41 16.00 10, Para 2.1, "Shop Drawings"; G

06 41 16.00 10, Para 3.1, "Installation"; G

06 41 16.00 10, Para 2.1, "Wood Materials"; G

06 41 16.00 10, Para

2.10.8.3, "Finish Schedule";

G

06 41 16.00 10, Para 2.6, "Cabinet Hardware"; G

06 41 16.00 10, Para 2.8, "Adhesives

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

06 41 16.00 10, Para 2.3, "Plastic Laminates"; G

06 41 16.00 10, Para 1.4, "Quality Assurance"; G

06 41 16.00 10, Para 3.1, "Laminate Clad Casework";

G

06 61 16, Para 1.4.2, "Detail

Drawings"; G

06 61 16, Para 3.1, "Installation"; G

06 61 16, Para 2.1, "Solid polymer material"; G

06 61 16, Para 1.4.1, "Qualifications"; G

06 61 16, Para 2.3, "Fabrications"; G

06 61 16, Para 2.1, "Material"; G

06 61 16, Para 2.3.4, "Countertops"; G

06 61 16, Para 2.1, "Solid polymer material"; G

06 61 16, Para 2.3, "Fabrications"; G

06 61 16, Para 1.4.1, "Qualifications"; G

06 61 16, Para 3.2, "Clean-up"; G

07 84 00, Para 2.1, "Firestopping System"; G

07 84 00, Para 2.2, "Firestopping Materials"; G

07 84 00, Para 3.3, "Inspection"; G

07 84 00, Para 1.5.2, "Inspector Qualifications"

07 84 00, Para 2.2, "Firestopping Materials"

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

07 84 00, Para 1.5.1, "Installer Qualifications"; G

07 92 00, Para 2.1, "Sealants"; G

07 92 00, Para 2.2, "Primers"; G

07 92 00, Para 2.3, "Bond

Breakers"; G

07 92 00, Para 2.4, "Backstops"; G

08 11 13, Para 2.1, "Doors";

G

08 11 13, Para 2.1, "Doors";

G

08 11 13, Para 2.4, "Frames"; G

08 11 13, Para 2.4, "Frames"; G

08 11 13, Para 2.2, "Accessories"; G

08 11 13, Para 2.5, "Weatherstripping"; G

08 11 13, Para 2.1, "Doors";

G

08 11 13, Para 2.4, "Frames"; G

08 11 13, Para 2.2, "Accessories"; G

08 14 00, Para 2.1, "Doors";

G

08 14 00, Para 2.1, "Doors";

G

08 14 00, Para 1.5, "Warranty"; G

08 14 00, Para 2.1, "Doors";

G

08 14 00, Para 2.2.4.1, "Door

Finish Colors"; G

08 14 00, Para 2.3, "Cycle-

Slam"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

08 14 00, Para 2.3, "Hinge

Loading Resistance"; G

08 14 00, Para 1.3.1, "Certificates of Grade"; G

08 14 00, Para 1.5, "Warranty"; G

08 31 00, Para 1.3, "Access

Panels"; G

08 31 00, Para 1.3, "Access

Panels"; G

08 31 00, Para 1.3.2, "Hardware"; G

08 31 00, Para 2.1.6, "Accessories"; G

08 31 00, Para 2.4, "Finishes"; G

08 33 13, Para 1.3, "Detail

Drawings"; G

08 33 13, Para 1.5, "Warranty"; G

08 33 13, Para 2.1, "Rolling

Counter Doors"; G

08 33 13, Para 3.1, "Installation"; G

08 33 13, Para 3.3, "Cleaning"; G

08 33 13, Para 2.3, "Rolling

Counter Door (Non-Rated)"

08 43 13, Para 1.2.1, "Sample Warranty"; G

08 43 13, Para 1.2.1, "Listing of Product Installations"; G

08 43 13, Para 1.2.1, "Installation Drawings"; G

08 43 13, Para 1.2.1, "Fabrication Drawings"; G

08 43 13, Para 1.2.1, "Manufacturer's Catalog

Data"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

08 43 13, Para 1.2.1, "Finish and Color Samples"; G

08 43 13, Para 1.2.1, "Certified Test Reports"; G

08 43 13, Para 3.4, "Manufacturer's Product

Warranty"; G

08 71 00, Para 1.3, "Hardware schedule"; G

08 71 00, Para 2.3.5, "Keying system"; G

08 71 00, Para 2.3, "Hardware items"; G

08 71 00, Para 3.1, "Installation"; G

08 71 00, Para 1.3, "Hardware Schedule"; G

08 71 00, Para 1.4, "Key

Bitting"; G

08 81 00, Para 1.6.1, "Insulating Glass"; G

08 81 00, Para 1.3, "Glazing

Accessories"; G

08 81 00, Para 1.6.1, "Insulating Glass"; G

08 81 00, Para 2.3, "Setting and sealing materials"; G

08 81 00, Para 3.2, "Glass setting"; G

09 22 00, Para 2.1, "Metal support systems"; G

09 29 00, Para 1.3, "Certifications"; G

09 29 00, Para 2.2.1, "Gypsum Board"; G

09 29 00, Para 2.2, "Asbestos Free Materials"; G

09 29 00, Para 1.3.1, "Indoor

Air Quality"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

09 29 00, Para 2.2.1, "Indoor

Air Quality for Gypsum

Board"; G

09 29 00, Para 2.2.2, "VOC

Content of Joint Compound";

G

09 30 10, Para 3.2, "Detail

Drawings"; G

09 30 10, Para 2.1, "Porcelain Tile"; G

09 30 10, Para 2.1, "Glazed

Wall Tile"; G

09 30 10, Para 2.2, "Setting-

Bed"; G

252 09 30 10, Para 2.4, "Mortar

253 09 30 10, Para 2.1, "Tile"; G 2

09 30 10, Para 2.1, "Accessories"; G

09 30 10, Para 2.1, "Transition Strips"; G

09 30 10, Para 2.5, "Transition Strips"; G

09 30 10, Para 2.4.3, "Grout"; G

09 30 10, Para 3.7, "Maintenance Instructions"

09 30 10, Para 3.2, "Installation"; G

09 51 00, Para 2.1, "Approved Detail Drawings";

G

09 51 00, Para 2.1, "Acoustical Ceiling Systems";

G

09 51 00, Para 2.2, "Acoustical Units"; G

09 51 00, Para 2.2.1.1, "Acoustical Ceiling Tiles"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

09 65 00, Para 2.1, "Resilient

Flooring and Accessories"; G

09 65 00, Para 2.6, "Adhesives"

09 65 00, Para 2.1, "Resilient

Flooring and Accessories"; G

09 65 00, Para 2.2, "Rubber

Tile"; G

09 65 00, Para 2.4, "Wall

Base"; G

09 65 00, Para 2.1, "Vinyl

Composition Tile"; G

09 65 00, Para 2.3, "Luxury

Vinyl Tile"; G

271 09 65 00, Para 3.3, "Moisture

09 65 00, Para 3.2, "Surface

Preparation"; G

09 65 00, Para 3.1, "Installation"; G

09 65 00, Para 2.1, "Resilient

Flooring and Accessories"; G

09 68 00, Para 3.4, "Installation Drawings"; G

09 68 00, Para 2.2, "Carpet";

G

09 68 00, Para 2.5, "Moldings"; G

09 68 00, Para 2.2, "Carpet";

G

09 68 00, Para 2.5, "Moldings"; G

09 68 00, Para 3.2, "Moisture and Alkalinity Tests"; G

09 68 00, Para 1.3.1, "Indoor

Air Quality"

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

09 68 00, Para 1.6, "Warranty"; G

09 68 00, Para 3.1, "Surface

Preparation"; G

09 68 00, Para 3.5, "Cleaning and Protection"; G

09 68 00, Para 2.4, "Indoor

Air Quality for Aerosol

Adhesives and Sealants"; G

09 68 00, Para 2.4, "Indoor

Air Quality for Non-Aerosol

Adhesives"; G

09 68 00, Para 2.4, "Indoor

Air Quality for Concrete

Primer"; G

09 68 00, Para 1.6, "Warranty"

09 90 00, Para 3.1, "Piping identification"

290 09 90 00, Para 3.1, "stencil" 5

09 90 00, Para 2.1, "Coating"; G

09 90 00, Para 2.1, "Manufacturer's Technical

Data Sheets"

09 90 00, Para 1.9, "Color";

G

09 90 00, Para 1.3, "Applicator's qualifications"

09 90 00, Para 1.4.1.2, "Qualification Testing"; G

09 90 00, Para 3.6.1, "Application instructions"

09 90 00, Para 3.6.2, "Mixing"

09 90 00, Para 1.7.2, "Manufacturer's Material

Safety Data Sheets"

09 90 00, Para 2.1, "Coatings:"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

10 14 00.20, Para 1.4.2, "Detail Drawings"; G

10 14 00.20, Para 3.1, "Installation"; G

10 14 00.20, Para 1.6, "Warranty"; G

10 14 00.20, Para 1.4.1, "Interior Signage"; G

10 14 00.20, Para 3.1, "Approved Manufacturer's

Instructions"; G

10 14 00.20, Para 3.1.2, "Protection and Cleaning"; G

10 21 13, Para 2.1, "Fabrication Drawings"; G

10 21 13, Para 3.3, "Installation Drawings"; G

10 21 13, Para 2.1, "Cleaning and Maintenance

Instructions"; G

10 21 13, Para 2.7, "Colors

And Finishes"; G

10 21 13, Para 2.2.1, "Sound-

Deadening Cores"; G

10 21 13, Para 2.2.2, "Anchoring Devices and

Fasteners"; G

10 21 13, Para 2.2.4, "Hardware and Fittings"; G

10 21 13, Para 2.2.3, "Brackets"; G

10 21 13, Para 2.2.5, "Door

Hardware"; G

10 21 13, Para 2.5, "Pilaster

Shoes"; G

10 21 13, Para 2.2.4.2, "Finishes"; G

10 21 13, Para 2.7, "Colors and Finishes"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

10 21 13, Para 1.5, "Warranty"; G

10 21 13, Para 2.3, "Recycled content for plastic

10 22 19, Para 3.3, "Installation"; G

10 22 19, Para 1.6, "Warranty"; G

10 22 19, Para 2.2, "Partition

System"; G

10 22 19, Para 2.2, "Partition

System"; G

10 22 19, Para 2.4, "Partition

System Samples"; G

10 22 19, Para 2.1.1, "Burning Characteristics"; G

10 22 19, Para 2.1.2, "Acoustical Performance"; G

10 22 19, Para 2.1.3, "Structural Performance"; G

10 22 19, Para 2.3.1, "Assembly Manuals"; G

10 22 19, Para 3.5, "Maintenance Manuals"; G

10 28 13, Para 2.1.2, "Finishes"; G

10 28 13, Para 2.2, "Accessory Items"; G

10 28 13, Para 2.1.2, "Finishes"; G

10 28 13, Para 2.2, "Accessory Items"; G

10 28 13, Para 2.2, "Accessory Items"

10 44 16, Para 2.1.1, "Fire

Extinguishers"; G

10 44 16, Para Part 2, "Cabinets"; G

10 44 16, Para 2.1.1, "Fire

Extinguishers"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

10 44 16, Para Part 2, "Cabinets"; G

10 44 16, Para 3.2.1, "Replacement Parts List"; G

10 44 16, Para 2.1.1, "Fire

Extinguishers"; G

10 44 16, Para 2.1.1, "Manufacturer's Warranty with Inspection Tag"; G

10 51 13, Para 2.1, "Types";

G

10 51 13, Para 1.4, "Location"; G

10 51 13, Para 3.1, "Installation"

10 51 13, Para 3.2, "Numbering system"

10 51 13, Para 2.2, "Material"; G

10 51 13, Para 2.3.1, "Locking Devices"; G

10 51 13, Para 2.3.3, "Handles"; G

10 51 13, Para 2.2.3, "Finish"; G

10 51 13, Para 2.3, "components"; G

10 51 13, Para 3.1, "Assembly"

10 51 13, Para 1.5.1, "Color chips"; G

12 21 00, Para 3.3, "Installation"; G

12 21 00, Para 2.1, "Window

Blinds"; G

12 21 00, Para 3.3, "Installation"

12 21 00, Para 2.1, "Window

Blinds"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

12 21 00, Para 2.1, "Window

Blinds"

12 21 00, Para 2.1, "Window

Blinds"; G

12 21 00, Para 2.1, "Window

Blinds"; G

21 13 13.00 20, Para 1.5.2, "Shop Drawings"; G

21 13 13.00 20, Para 2.1.1, "Pipe"; G

21 13 13.00 20, Para 2.1.1, "Fittings"; G

21 13 13.00 20, Para 2.1.5, "Valves"; G

21 13 13.00 20, Para 2.1.4, "Sprinklers"; G

21 13 13.00 20, Para 2.1.6, "Pipe hangers and supports";

G

21 13 13.00 20, Para 2.1.1, "Mechanical couplings"; G

21 13 13.00 20, Para 2.1.6, "Seismic Bracing"; G

21 13 13.00 20, Para 1.3, "Hydraulic Calculations"; G

21 13 13.00 20, Para 3.6, "request to schedule

Preliminary Tests"; G

21 13 13.00 20, Para 3.6, "Preliminary Test Report"; G

21 13 13.00 20, Para 3.7, "request to schedule Final

Acceptance Test"; G

21 13 13.00 20, Para 3.7, "Final Acceptance Test

Report"; G

21 13 13.00 20, Para 3.1, "Inspection by Fire

Protection Engineer"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

21 13 13.00 20, Para 1.5.1, "Fire Protection Engineer"; G

21 13 13.00 20, Para 1.5.2, "Sprinkler System Installer";

G

21 13 13.00 20, Para 3.8, "Operating and Maintenance

Instructions"

21 13 13.00 20, Para 3.7, "As-built drawings"

21 13 13.00 20, Para 3.8, "On-site training"

22 00 00, Para 2.4, "Fixtures"

22 00 00, Para 2.4.1, "Flush

Valve Water Closets"

22 00 00, Para 2.4.2, "Flush

Valve Urinals"

22 00 00, Para 2.4.4, "Countertop Lavatories"

22 00 00, Para 2.4.5, "Kitchen Sinks"

22 00 00, Para 2.5.2, "Shower Faucets"; G

22 00 00, Para 1.5.1, "Welding"

386 22 00 00, Para 3.6, "Tests

22 00 00, Para 1.3, "Materials and Equipment"

388 22 00 00, Para 2.1.1, "Bolts" 5

23 00 00, Para 1.4.3, "Detail

Drawings"; G

23 00 00, Para 2.8.1.1, "Metallic Flexible Duct"

23 00 00, Para 2.8.2, "Duct

Access Doors"; G

23 00 00, Para 2.8.4, "Registers And Grilles"; G

23 00 00, Para 2.9.1.1, "In-

Line Centrifugal Fans"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

23 00 00, Para 2.1, "Air

Handling Units"; G

23 00 00, Para 2.11.1.1, "Variable Volume

23 00 00, Para 2.11.1.2, "Variable Volume

23 00 00, Para 1.4.4, "Test

Procedures"; G

23 00 00, Para 2.8.3, "Fire

Dampers"

23 00 00, Para 2.9.3, "Air

Filters"; G

23 00 00, Para 2.9.3.1, "Air

Filters"; G

23 00 00, Para 2.11.1.3, "Reheat Units"; G

23 00 00, Para 3.9, "Performance Tests"; G

23 00 00, Para 3.7, "Damper

Acceptance Test"; G

23 00 00, Para 3.2, "Manufacturer's Installation

Instructions"; G

23 00 00, Para 3.11.2, "Operation and Maintenance

Training"

23 00 00, Para 3.11.1, "Operation and Maintenance

Manuals"; G

23 00 00, Para 2.9.1.1, "In-

Line Centrifugal Fans"; G

23 00 00, Para 2.1, "Air

Handling Units"; G

23 00 00, Para 2.11.1.1, "Variable Volume

23 00 00, Para 2.11.1.2, "Variable Volume

23 05 48.00 40, Para 1.2, "Installation Drawings"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

23 05 48.00 40, Para 1.2, "Outline Drawings"; G

23 05 48.00 40, Para 1.2, "Equipment and

Performance Data"; G

23 05 48.00 40, Para 2.2.5, "Isolators"; G

23 05 48.00 40, Para 2.4, "Type of Isolator"; G

23 05 48.00 40, Para 2.4, "Type of Base"; G

23 05 48.00 40, Para 2.4, "Allowable Deflection"; G

23 05 48.00 40, Para 2.4, "Measured Deflection"; G

23 05 93, Para 1.3.3, "TAB

Schematic Drawings and

Report Forms"; G

23 05 93, Para 1.3, "Equipment and

Performance Data"; G

23 05 93, Para 3.3.5, "Completed Pre-Final DALT

Report"; G

23 05 93, Para 3.3.8, "Certified Final DALT

Report"; G

23 05 93, Para 1.5.1, "Independent TAB Agency and Personnel

Qualifications"; G

23 07 00, Para 3.2.2.4, "MICA Plates"; G

23 07 00, Para 2.3, "Pipe

Insulation Systems"; G

23 07 00, Para 3.2, "Pipe

Insulation Systems"; G

23 07 00, Para 3.3, "Duct

Insulation Systems"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

23 07 00, Para 3.4, "Equipment Insulation

Systems"; G

23 07 00, Para 2.3, "Pipe

Insulation Systems"; G

23 07 00, Para 3.2, "Pipe

Insulation Systems"; G

23 07 00, Para 3.3, "Duct

Insulation Systems"; G

23 07 00, Para 3.4, "Equipment Insulation

Systems"; G

23 07 00, Para 2.2.1.3, "Thermal Insulation"; G

23 07 00, Para 2.3, "Pipe

Insulation Systems"; G

23 07 00, Para 3.2, "Pipe

Insulation Systems"; G

23 07 00, Para 3.3, "Duct

Insulation Systems"; G

23 07 00, Para 3.4, "Equipment Insulation

Systems"; G

23 09 23.13 20, Para 1.4.1.1, "Control system drawings title sheet"; G

23 09 23.13 20, Para 1.4.1.2, "List of I/O Points"; G

23 09 23.13 20, Para 1.4.1.3, "Control System

Components List"; G

23 09 23.13 20, Para 1.4.1.4, "Control system schematics";

G

23 09 23.13 20, Para 1.4.1.5, "HVAC Equipment Electrical

Ladder diagrams"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

23 09 23.13 20, Para 1.4.1.6, "Component wiring diagrams"; G

23 09 23.13 20, Para 1.4.1.7, "Terminal strip diagrams"; G

23 09 23.13 20, Para 1.4.1.8, "BACnet communication architecture schematic"; G

23 09 23.13 20, Para 2.1.1, "Direct Digital Controllers"; G

23 09 23.13 20, Para

2.1.1.13, "BACnet

Gateways"; G

23 09 23.13 20, Para 2.1.3, "BACnet Protocol Analyzer";

G

23 09 23.13 20, Para 2.1.2, "DDC Software"; G

23 09 23.13 20, Para 2.2, "Sensors and Input

Hardware"; G

23 09 23.13 20, Para 2.2.6, "Air Flow Monitoring Station";

G

23 09 23.13 20, Para 2.3, "Output Hardware"; G

23 09 23.13 20, Para 2.4.2, "Surge and transient protection"; G

23 09 23.13 20, Para 2.6, "Indicators"; G

23 09 23.13 20, Para 2.5.1, "Duct smoke detectors"; G

23 09 23.13 20, Para 2.7, "Variable frequency (motor) drives"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

23 09 23.13 20, Para 3.4.2, "Performance Verification

Testing Plan"; G

23 09 23.13 20, Para 3.4.4, "Pre-Performance

Verification Testing

Checklist"; G

23 09 23.13 20, Para 3.4.11, "Performance Verification

Testing Report"; G

23 09 23.13 20, Para 1.6.6, "Contractor's Qualifications";

G

23 09 23.13 20, Para 3.4.1, "Pre-PVT Checklist"; G

23 09 23.13 20, Para 1.4, "BACnet Direct Digital

Control Systems"; G

23 09 23.13 20, Para 3.3, "Controls System Operators

Manuals"; G

23 09 23.13 20, Para 2.7.2, "VFD Service Manuals"; G

23 09 23.13 20, Para 3.5.1, "Training documentation"; G

23 11 25, Para 1.5.3, "Gas

Piping System"; G

23 11 25, Para 2.2, "Gas

Piping System"; G

23 11 25, Para 3.2, "Gas

Piping System"; G

23 11 25, Para 1.6.1, "Pipe and Fittings"; G

23 11 25, Para 1.5.3, "Gas

Equipment Connectors"; G

23 11 25, Para 1.5.3, "Gas

Piping System"; G

23 11 25, Para 2.2, "Gas

Piping System"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

1179187112C Typewritten Text

FA441819R0002

1179187112C

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

L

I

N

E

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

PROJECT TITLE

Repair Squadron Operations Facility, Building 709

CONTRACT NO. / TASK ORDER NO.

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SUBMITTAL REGISTER

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

23 11 25, Para 3.2, "Gas

Piping System"; G

23 11 25, Para 2.1, "Pipe

Coating Materials"; G

23 11 25, Para 2.6, "Pressure Regulators"; G

23 11 25, Para 2.4, "Risers";

G

23 11 25, Para 2.3, "Valves";

G

23 11 25, Para 2.2.4, "Warning and Identification

Tape"; G

23 11 25, Para 3.16, "Testing"; G

23 11 25, Para 3.16.1, "Pressure Tests"; G

23 11 25, Para 3.16.2, "Test with Gas"; G

23 11 25, Para 1.5.1, "Welders Procedures and

Qualifications"; G

23 11 25, Para 1.5.1, "Assigned Number

23 11 25, Para 1.5.2, "PE

Pipe and Fittings"; G

23 11 25, Para 2.1, "Pipe

Coating Materials"; G

23 11 25, Para 1.3.1, "Gas

Facility System and

Equip…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it.