About this file

This Task Assignment (TA) is a state contract executed between the State of Florida Department of Environmental Protection (DEP) and WSP USA Inc., a contractor providing environmental engineering and remediation services. The contract document includes the TA, a negotiation summary memorandum dated April 9, 2025, a detailed cost proposal, level of effort worksheets, and subcontractor quotes. The project is located at Ar-Pats Dry Cleaners Inc., 720 Harrison Street, Sebastian, Indian River County, Florida (Facility ID: ERIC_4805), and operates under the underlying Contract Number HW685.

The Task Assignment (DC008D) authorizes WSP to conduct annual groundwater sampling and prepare an Interim Source Removal Work Plan for the dry cleaning facility. The contract comprises four subtasks: Subtask 1 covers project management ($2,883.27); Subtask 2 addresses groundwater monitoring activities for chlorinated volatile organic compounds and includes sample collection from 23 monitoring wells ($8,157.97); Subtask 3 covers expanded per- and polyfluoroalkyl substances (PFAS) monitoring, waste characterization, and investigation-derived waste transportation and disposal ($10,985.80); and Subtask 4 involves preparation of an Interim Source Removal Work Plan using soil vapor extraction as the presumptive remedy ($7,014.27). The total contract value is $29,051.31 with 160 total labor hours. Payment is structured as fixed unit rates with deliverables due on a staggered schedule from June 2025 through September 2025, with final project completion targeted for October 31, 2025. Subcontractor costs include $390.00 for PFAS waste transportation and disposal (Erwin Remediation) and pricing from HEPACO for non-hazardous drum disposal services.

View the file

Other files

File Type Posted
CN-370000-HW685-A1.pdf PDF
CN-370000-HW685-BF01B.pdf PDF
CN-370000-HW685-BF01D.pdf PDF
CN-370000-HW685-BF01DCO2.pdf PDF
CN-370000-HW685-BF03A.pdf PDF
CN-370000-HW685-BIL01B.pdf PDF
CN-370000-HW685-BIL02A.pdf PDF
CN-370000-HW685-BIL02B.pdf PDF
CN-370000-HW685-BIL1BCO2.pdf PDF
CN-370000-HW685-BIL2CCO2.pdf PDF
CN-370000-HW685-CSS2A.pdf PDF
CN-370000-HW685-CSS2ACO1.pdf PDF
CN-370000-HW685-DC001D.pdf PDF
CN-370000-HW685-DC002F.pdf PDF
CN-370000-HW685-DC004C.pdf PDF
CN-370000-HW685-DC005A.pdf PDF
CN-370000-HW685-DC005B.pdf PDF
CN-370000-HW685-DC005D.pdf PDF
CN-370000-HW685-DC006A.pdf PDF
CN-370000-HW685-DC010B.pdf PDF
CN-370000-HW685-DC012B.pdf PDF
CN-370000-HW685-DC013B.pdf PDF
CN-370000-HW685-DC017C.pdf PDF
CN-370000-HW685-DC01ACO2.pdf PDF
CN-370000-HW685-DC01ACO4.pdf PDF
CN-370000-HW685-DC01ACO7.pdf PDF
CN-370000-HW685-DC020A.pdf PDF
CN-370000-HW685-DC020C.pdf PDF
CN-370000-HW685-DC023E.pdf PDF
CN-370000-HW685-DC026B.pdf PDF
CN-370000-HW685-DC026C.pdf PDF
CN-370000-HW685-DC026E.pdf PDF
CN-370000-HW685-DC027A.pdf PDF
CN-370000-HW685-DC028C.pdf PDF
CN-370000-HW685-DC029D.pdf PDF
CN-370000-HW685-DC033A.pdf PDF
CN-370000-HW685-DC039A.pdf PDF
CN-370000-HW685-DC040A.pdf PDF
CN-370000-HW685-DC040B.pdf PDF
CN-370000-HW685-DC041B.pdf PDF
CN-370000-HW685-DC042B.pdf PDF
CN-370000-HW685-DC046B.pdf PDF
CN-370000-HW685-DC048B.pdf PDF
CN-370000-HW685-DC048C.pdf PDF
CN-370000-HW685-DC053B.pdf PDF
CN-370000-HW685-DC055A.pdf PDF
CN-370000-HW685-DC06ACO1.pdf PDF
CN-370000-HW685-DC06BCO1.pdf PDF
CN-370000-HW685-DC06BCO2.pdf PDF
CN-370000-HW685-DC07CCO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

HW685

DC008D October 31, 2025

This Task Assignment authorizes WSP to conduct groundwater sampling and prepare an Interim Source Removal Plan for Ar-Pats Dry Cleaners in accordance with the April 9, 2025 Scope of Work, Cost Estimate, and Bid Documentation.

Patrick McGrane 850-245-8899 WSP USA Inc.

Matt Crews 904-363-3430

ERIC_4805

720 Harrison Street, Sebastian, Indian River County

Ar-Pats Dry Cleaners Inc

$ 29,051.31

$ 29,051.31

Scope of Work

WSP USA Inc.

Matthew Crews

Environmental Engineer

4/15/2025

Crews, Matt (USMC700671) Digitally signed by Crews, Matt (USMC700671) Date: 2025.04.15 13:19:59 -04'00'

Mubeen Darji

Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.

Date: 2025.04.10 15:08:04 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

BWC TAFORM 01/18

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Alexis A. Lambert Secretary

Memorandum

TO: Negotiation File Ar-Pats Dry Cleaners Inc Sebastian, Indian River County

ERIC_4805

FROM: Patrick McGrane, Project Manager

SUBJECT: Negotiation Summary Task Assignment DC008D (HW685)

DATE: April , 2025

This Task Assignment authorizes WSP USA Inc. (WSP) to conduct annual groundwater sampling and prepare an Interim Source Removal Plan (ISRP) for the Ar-Pats Dry Cleaners Inc site.

With PFAS compounds detected well above the updated 300ng/L guidelines provided by the DSCP, expanded PFAS monitoring will be conducted with groundwater sampling activities. During supplemental site assessment activities performed in 2023, exceedances of SCTLs were found at MAG003 (2�). The

FDEP approved WSP�s recommendation for the preparation of an ISRP in early 2024, which will be submitted as the final deliverable of this Task Assignment.

The total cost for this project is $2 , .31 with 160 total labor hours. All work is to be completed in accordance with the April , 2025, Scope of Work, Cost Estimate, and Bid Documentation.

WSP may invoice according to the included schedule.

SITE : Ar-Pat's Dry Cleaning Inc. No Lift Station Sampling

SUBTASK 2: Annual GW Monitoring Activities Per Diem & Eqpmt Costs to ST3

DATE: 4/7/2025

LABOR CATEGORIES *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLES WORK DESCRIPTION HOURS

Practice Leader (R. McCann) 7.0

Practice Leader (M. Crews) 10.0

Senior Project Sci/Eng (D. McDaniels) 13.0

Staff Sci/Eng (L. Kamikazi) 12.0

TOTAL LABOR 42.0

VEHICLE TYPE RATE UNIT USAGE

Truck $120.00 Per Day 1 $120.00

TOTAL VEHICLE $120.00

PER DIEM STAFF RATES UNITS USAGES

Per Diem L. Kamikazi $36.00 Per Day 1 $36.00

Per Diem S. Svendsen $36.00 Per Day 1 $36.00

Hotel L. Kamikazi $150.00 Per Day 1 $150.00

Hotel S. Svendsen $150.00 Per Day 1 $150.00

TOTAL PER DIEM $372.00

SUBCONTRACTOR COSTS

NAME PURPOSE RATE UNIT USAGE

TOTAL SUB $0.00

LABORATORY COSTS

PARAMETERS RATES # SAMPLES #QAQC

Total VOHs EPA Method 8260B $73.00 5 $365.00

Total VOCs EPA Method 8021 - IDW $110.00 1 $110.00

Sample Shipping Small $110.00 1 $110.00

TOTAL LAB $585.00

EQUIPMENT ITEMS RATES COSTING UNITS USAGES TOTALS

Miscellaneous Expendables $40.00 Per Day 1 $40.00

Shallow Groundwater Sampling Kit $290.00 Per Day 1 $290.00

Tubing, Poly HDPE $0.30 Per Foot 150 $45.00

Tubing, Silicon 3/16 x 3/8 $3.00 Per Foot 5 $15.00

TOTAL EQUIPMENT $390.00

Verification of property ownership and current offsite owners to gain access and notify parties and DEP prior to beginning field work (3 hours). Prepare and submit email summary with field documentation of groundwater and certified laboratory report (4 hours).

Round trip travel (6 hours). Field event preparation (1 hour). Water levels, instrument calibration, sampling of 5 shallow zone monitoring wells for chlorinated VOC analysis (see Table in proposal), and IDW sampling and staging (6 hours).

Round trip travel (6 hours). Water levels, instrument calibration, sampling of 5 shallow zone monitoring wells for chlorinated VOC analysis (see Table in proposal), and IDW sampling and staging (6 hours).

Round Trip from Jacksonville to Sebastian (6 hours). Site visit related to ISR Work Plan preparation (4 hours).

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Ar-Pat's Dry Cleaning Inc. Per Diem & Eqpmt Costs From ST2

SUBTASK 3: PFAS Related Costs & IDW T&D PFAS Table Prep Remains (4 hrs.)

DATE: 4/7/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Practice Leader (R. McCann) 10.0

Senior Project Sci/Eng (D. McDaniels)

26.0

Staff Sci/Eng (L. Kamikazi) 22.0

Senior Sci/Eng (B. Lucero) 3.0

TOTAL LABOR 61.0

VEHICLE TYPE RATE UNIT USAGES

Truck $120.00 Per Day 2 $240.00

TOTAL VEHICLE $240.00

PER DIEM STAFF RATES UNITS USAGES

Per Diem L. Kamikazi $36.00 Per Day 2 $72.00

Per Diem S. Svendsen $36.00 Per Day 2 $72.00

Hotel L. Kamikazi $150.00 Per Day 2 $300.00

Hotel S. Svendsen $150.00 Per Day 2 $300.00

TOTAL PER DIEM $744.00

SUBCONTRACTOR COSTS

NAME PURPOSE RATE UNIT USAGE

Erwin Remediation T&D - Non-Haz PFOS/PFAS Water $195.00 per drum 2 $390.00

TOTAL SUB $390.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB

EQUIPMENT ITEMS RATES COSTING UNITS USAGES

Miscellaneous Expendables $40.00 Per Day 2 $80.00

Shallow Groundwater Sampling Kit $290.00 Per Day 2 $580.00

Tubing, Poly HDPE $0.30 Per Foot 650 $195.00

Tubing, Silicon 3/16 x 3/8 $3.00 Per Foot 18 $54.00

Drum (55-gallon) $100.00 Each 2 $200.00

TOTAL EQUIPMENT $1,109.00

Complete forms to arrange for PFAS sample bottle order delivery and shipment from DEP Central Laboratory (2 hours). Characterize IDW and prepare waste profile for transportation and disposal of IDW (2 hours). Prepare and submit email summary with field documentation and certified laboratory report with PFAS results (2 hours). Prepare PFAS section for the draft ISR Work Plan (4 hours).

Collect samples from 18 wells for PFAS analysis only; collect samples from 5 wells listed in Subtask 2 for PFAS analysis, collect equipment blank for PFAS analysis (20 hours). Package and deliver PFAS samples to shipping point for DEP Central Laboratory (2 hours). Prepare data tables with PFAS analytical results (4 hours).

Prepare CADD Figures with PFAS data for Annual Groundwater Monitoring Report.

Collect samples from 18 wells for PFAS analysis only; collect samples from 5 wells listed in Subtask 2 for PFAS analysis, collect equipment blank for PFAS analysis (20 hours). Package and deliver PFAS samples to shipping point for DEP Central Laboratory (2 hours).

FINAL --7/24/96

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Ar-Pat's Dry Cleaning Inc.

SUBTASK 4: ISR Work Plan Reduce Table Update Labor (-2 hrs. LK)

DATE: 4/7/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Practice Leader (M. Crews) 4.0

Senior Sci/Eng (L. Chappell) 30.0

Staff Sci/Eng (L. Kamikazi) 2.0

Senior Sci/Eng (B. Lucero) 6.0

Staff Sci/Eng (A. Strayer) 2.0

TOTAL LABOR 44.0

VEHICLE TYPE RATE UNIT USAGE

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE RATE UNIT USAGE

TOTAL SUB $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB

EQUIPMENT ITEM RATE COSTING UNIT USAGE

TOTAL EQUIPMENT $0.00

Review Draft ISR Work Plan; incorporate design comments and edits into final report

Update groundwater tables for ISR Work Plan

Prepare CADD Figures

Document Production

Prepare draft ISR Work Plan (30 hours)

FINAL --7/24/96

WSP USA Inc.

9428 Baymeadows Road, Suite 400, Jacksonville, Florida 32256 USA T: +1 904 363-3430 F: +1 904 363-3445 wsp.com

April 9, 2025 Proposal No. 2025US373774

Mr. Patrick McGrane

Florida Department of Environmental Protection

Division of Waste Management

Waste Site Cleanup Section

2600 Blair Stone Road, MS 4520

Tallahassee, FL 32399-2400

RE: COST PROPOSAL FOR GROUNDWATER MONITORING AND

INTERIM SOURCE REMOVAL WORK PLAN

AR-PAT’S DRY CLEANING INC.

SEBASTIAN, INDIAN RIVER COUNTY, FLORIDA

FACILITY ID NUMBER: ERIC_4805

PROPOSED TASK ASSIGNMENT: DC008D

Dear Mr. McGrane, WSP USA Inc. (WSP), is pleased to provide the Florida Department of Environmental Protection (DEP) with this cost proposal to complete annual groundwater monitoring activities, including expended per- and polyfluoroalkyl substances (PFAS) groundwater monitoring activities, at the above-referenced site and preparation of an Interim

Source Removal (ISR) Work Plan. This proposal includes a description of the proposed scope of services, level of effort sheets for each subtask, and a cost estimate form that summarizes the costs of the proposed services. The proposed scope of services is described below.

SUBTASK 1 – PROJECT MANAGEMENT

To facilitate project quality and satisfactory completion of the proposed scope of work, all aspects of this project will be overseen by an experienced project manager. The project manager will be responsible for the schedule, budget, invoicing, project activities, and communications with DEP and the field team. Project management will include coordination of field activities; resource allocation to confirm the work is conducted by qualified professionals in accordance with the project schedule; cost control and tracking of the budget status; and submittal of project invoices in accordance with DEP Waste Site Cleanup Section requirements. The project manager will oversee the work so that it is conducted in a manner that is consistent with the requirements of the DEP-approved Task

Assignment.

SUBTASK 2 – GROUNDWATER MONITORING ACTIVITIES

Groundwater Monitoring

Following authorization to proceed, WSP will use the Indian River County Property Appraiser’s Office website to verify that the current property owner has executed a Permission to Enter Property Agreement with the DEP. WSP will then coordinate with the real property owner for access to complete the scope of work.

Mr. Patrick McGrane Proposal No. 2025US373774

Florida Department of Environmental Protection April 9, 2025

WSP will collect samples from 16 shallow zone monitoring wells and 7 intermediate zone monitoring wells for contaminants of concern listed in the table below. Figure 1 from the January 2022 groundwater monitoring event shows the results of the initial PFAS screening. Figures 2 and 4 from the January 2023 groundwater monitoring event are provided to show the monitoring well locations, groundwater flow direction, and results for chlorinated volatile organic compounds (VOCs) in the shallow zone of the surficial aquifer.

Groundwater sampling activities will be completed in accordance with DEP Standard Operating Procedures (SOPs) for Field Activities (DEP SOP-001/01), dated January 2017 (effective April 16, 2018) and DEP SOPs for Sampling with and Analysis of PFAS, dated August 2020. Prior to groundwater sampling, the depth-to-groundwater will be measured at the wells sampled using an electronic water level indicator to determine groundwater elevations and flow direction. During the sampling event, the integrity of locks and well caps will be inspected.

Prior to collecting the groundwater sample, each well will be purged and field parameters including temperature, pH, specific conductance, dissolved oxygen, turbidity, and oxidation reduction potential will be monitored. Purge volumes and field parameters will be recorded on field data sheets, and the field monitoring equipment will be calibrated in accordance with the manufacturer’s recommended procedures. The groundwater samples to be analyzed for chlorinated VOCs will be delivered to a Florida Department of Health and National Environmental

Laboratory Accreditation Program certified laboratory along with chain-of-custody documentation. Upon receipt of the laboratory analytical results, WSP will evaluate whether off-site notification is required.

The samples will be analyzed as follows:

Sample ID Chlorinated VOCs

(EPA Method 8260B)

PFAS

(DEP SOP: LC001-3 or Similar)

Shallow Surficial Aquifer

MW001S X X

MW002S X

MW004S X X

MW008S X

MW009S X

MW011S X X

MW012S X

MW013S X

MW014S X

MW015S X

MW016S X X

MW017S X

MW018S X X

MW019S X

MW020S X

MW021S X

Subtotals 5 16

Sample ID Chlorinated VOCs

(EPA Method 8260B)

PFAS

(DEP SOP: LC001-3 or Similar)

Intermediate Surficial Aquifer

MW002I X

MW003I X

MW004I X

MW006I X

MW007I X

MW008I X

MW009I X

Subtotals 0 7

Well Totals 5 23

Equipment Blank --- X

Investigative Derived Waste

(IDW)

Total VOCs X

Interim Deliverable for Subtask 2

Upon completion of Subtask 2, an e-mail deliverable will be submitted for the chlorinated VOC samples and include copies of the field data sheets, equipment calibration forms, field notes, laboratory analytical report, and laboratory chain-of-custody documentation.

SUBTASK 3 – PFAS-RELATED COSTS AND IDW TRANSPORTATION AND DISPOSAL

WSP will include costs associated with the expanded PFAS monitoring activities in this subtask. These activities include completing bottle order requests with the DEP Central Laboratory; waste characterization and waste profiling; packaging and shipping PFAS samples to the DEP Central Laboratory; labor involved in sampling wells associated with PFAS analysis only; and investigation-derived waste (IDW) transportation and disposal.

Quality Assurance/Quality Control

WSP will collect one equipment blank sample during the groundwater sampling event. The equipment blank will be collected by pumping (peristaltic pump) PFAS-free water through silicon and/or HDPE tubing and into laboratory supplied containers. The equipment blank will be analyzed for PFAS using DEP SOP: LC001-3 (or similar), as shown in the above table.

Investigation-Derived Waste

WSP will containerize the IDW purge water and decontamination water in a 55-gallon drum. WSP will collect a waste characterization sample from the drum for analysis of total VOCs using EPA Method 8260 and PFAS using

DEP SOP: LC001-3 (or similar), as shown in the above table. The drum will be temporarily staged onsite, pending waste characterization. For cost-estimating purposes, WSP has assumed that the IDW can be transported and disposed of as non-hazardous waste at an approved facility. The IDW transportation and disposal subcontractor will provide WSP with a non-hazardous waste manifest upon delivery to the disposal facility. WSP estimates two drums of IDW purge water will be generated during the field activities.

Interim Deliverable for Subtask 3

Upon completion of Subtask 3, an e-mail deliverable will be submitted for the PFAS samples and include copies of the field data sheets, equipment calibration forms, field notes, and laboratory chain-of-custody documentation.

SUBTASK 4 – INTERIM SOURCE REMOVAL WORK PLAN

The DEP approved Soil Vapor Extraction (SVE) as the presumptive remedy for the site in an approval memorandum, dated May 6, 2024. Therefore, WSP will develop an ISR Work Plan to use SVE to address the chlorinated VOC impacts identified in the vadose zone soils during the May 2023 MAGS investigation. The ISR

Work Plan will include the following:

Site location and description.

A summary of previous site assessment and remediation activities completed at the site.

A summary of the current groundwater monitoring activities completed at the site, including sampling procedures, evaluation of the analytical results; comparison of current to historical data; tabulated summary of the current and historical analytical data; site maps showing the groundwater analytical results; water level elevation information in tables and figures; laboratory analytical data; and conclusions and recommendations.

A recommendation for a site visit to identify a location for the SVE system; identify potential electrical power drop locations; and discuss the proposed site activities with the property owner and tenants.

The proposed site preparation activities, including verification of the existing site access agreement, utility location services, and documentation of existing site conditions.

Proposed vacuum extraction well and vacuum monitoring point locations and construction details.

Proposed SVE conveyance piping layout and trenching details, where applicable.

SVE system design criteria, including system operating vacuum, wellhead vacuum and flow rates, ROI, and a piping and instrumentation diagram.

SVE system components, including the manifold, vapor-liquid separator, dilution air valve, vacuum blower, gauges (temperature, pressure, and flow), valves, and sample port locations.

Control panel and telemetry requirements.

Effluent treatment design and water entrainment management.

SVE system design details.

SVE system construction details.

System startup and operation and maintenance procedures.

SVE cleanup goals and system shutdown requirements, including groundwater monitoring requirements.

Health and safety considerations, including recommended personal protective equipment.

An estimated cost and schedule to implement the ISR Work Plan.

HEALTH AND SAFETY

WSP will update the site-specific Health and Safety Plan for the fieldwork. The work will be completed in accordance with WSP’s safety policies and procedures. At a minimum, WSP will wear safety glasses, high visibility safety vests, and steel-toed boots. A safety job briefing will be conducted prior to the start of work activities, and anytime the scope of work or site conditions change.

COST AND SCHEDULE

The estimated cost to complete the groundwater monitoring and prepare the ISR Work Plan is $29,051.31. WSP will tentatively schedule the groundwater sampling event for May 2025. The LOE/CEF cost sheets are included in

Attachment A. Subcontractor quotes are included in Attachment B. The following table summarizes the proposed costs and deliverable schedules. WSP will discuss any modifications to the proposed schedule with the DEP.

Task Proposed Costs Proposed Schedule/Deliverables

Subtask 1 – Project Management $ 2,883.27 September 12, 2025

Subtask 2 – Groundwater Monitoring Activities

$ 8,157.97 June 20, 2025 (E-mail summary with field documentation and laboratory chain-of-custody)

Subtask 3 – PFAS Related Costs and IDW Transportation and Disposal

$ 10,985.80 July 11, 2025 (E-mail summary with field documentation and certified laboratory analytical report for PFAS and non-hazardous waste manifest for IDW)

Subtask 4 – ISR Work Plan $ 7,014.27 August 22, 2025 (ISR Work Plan)

Total/Completion Date $ 29,051.31 October 10, 2025

WSP appreciates the opportunity to provide services to the DEP. Should you require additional information or clarifications, please contact us at (904) 363-3430.

Respectfully, WSP USA Inc.

Richard D. "Rick" McCann, PG Matthew C. Crews, PE

Vice President, Geology Assistant Vice President, Environmental Engineering

RDM/MCC/as

Attachments: Figure 1 PFAS Screening Results (January 2022) Figure 2 Potentiometric Map of the Shallow Zone (January 2023) Figure 4 Chlorinated VOC Concentrations in the Shallow Zone (January 2023)

Attachment A – Level of Effort Sheets and Cost Estimate Form Attachment B – Subcontractor Quotes

G:\Projects\DEP-WSCS\Projects\Sebastian\Ar-Pats Dry Cleaners\HW685\DC008D - 2025 GW Mon & ISRP\Proposal\REV2 Submittal\DC008D - Ar-Pats Dry Cleaners GW Mon & ISRP Proposal REV2_(ERIC_4805).docx

File details come from the government source that posted it. Updated .