This is a Task Assignment (TA) document issued by the State of Florida Department of Environmental Protection (FDEP) under Contract HW685, designating TA Number DC028C. The assignment authorizes WSP USA Inc., an environmental consulting firm based in Jacksonville, Florida, to conduct annual groundwater sampling and expanded PFAS (per- and polyfluoroalkyl substances) monitoring at The Music Man property located at 799 Lane Avenue, Jacksonville, Duval County, Florida (DEP Facility ID: ERIC_4619). The task assignment is effective as of March 18, 2024, with a completion date of September 6, 2024. Patrick McGrane serves as the FDEP Project Manager, while Matt Crews represents WSP USA Inc. as the contractor's project manager.
The scope of work comprises four subtasks: (1) Project Management, calculated as a percentage of total labor in accordance with Contract HW685; (2) Annual Groundwater Monitoring, including collection and analysis of groundwater samples from 28 monitoring wells with specialized testing for chlorinated volatile organic compounds (VOCs), methane, ethane, and ethene (MEE), and PFAS analysis at the DEP Central Laboratory; (3) PFAS-related costs and investigative derived waste (IDW) transportation and disposal; and (4) preparation of an Annual Groundwater Monitoring Report with updated analytical results and conclusions. The total task assignment value is $24,705.04 on a fixed unit rate basis. Invoicing is structured in three phases: Subtask 2 for $8,412.58 (due May 24, 2024), Subtask 3 for $8,406.61 (due June 7, 2024), and Subtasks 1 & 4 for $7,885.85 (due July 5, 2024). The work includes 137 total labor hours and incorporates subcontractor costs for IDW disposal through Erwin Remediation, Inc., estimated at $390.00 for non-hazardous PFAS waste transportation and disposal.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number) Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
Additional signatures attached on separate page.
HW685
DC028C Completion September 6, 2024
This Task Assignment authorizes WSP to conduct Annual Groundwater Sampling at The Music Man in accordance with the March 11, 2024 Scope of Work, Cost Estimate, and Bid Documentation.
Patrick McGrane 850-245-8899 Contractor WSP USA Inc. Contractor
Contractor Matt Crews Contractor 904-363-3430
ERIC_4619
799 Lane Avenue, Jacksonville, Duval County
The Music Man
Contractor Contractor
✔ $ 24,705.04
$ 24,705.04
Scope of Work
WSP USA Inc.
Contractor Matthew Crews
Environmental Engineer
3/18/2024
Crews, Matt (USMC700671) Digitally signed by Crews, Matt (USMC700671) Date: 2024.03.18 16:12:11 -04'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2024.03.14 14:17:21 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Subtask 2 - Annual Groundwater Monitoring 05/24/2024
Subtask 3 - PFAS Related Costs and IDW Mangement 06/07/2024
Subtask 1 & 4 - Project Management; 2024 Annual Groundwater Report 07/05/2024
Subtask 2 - Submittal and FDEP approval of email summary with field documentation and certified laboratory analytical report for chlorinated VOCs and MEE $ 8,412.58
Subtask 3 - Submittal and FDEP approval of email summary with field documentation, certified laboratory analytical results for PFAS, IDW waste manifest $ 8,406.61
Subtask 1 & 4 - Project Management; Submittal and FDEP approval of the Annual Groundwater Report $ 7,885.85
$ 24,705.04
HW685
DC028C
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette NNuñez
Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: Negotiation File
Jacksonville, Duval County The Music Man
ERIC_4619
FROM: Patrick McGrane, Project Manager
SUBJECT: Negotiation Summary Task Assignment DC028C (HW685)
DATE: March 12, 2024
This Task Assignment authorizes WSP USA Inc. (WSP) to conduct Annual Groundwater Monitoring and expanded PFAS sampling at The Music Man (ERIC_4619) site.
The total cost for this project is $24,705.04 with 137 total labor hours. All work is to be completed in accordance with the March 11, 2024, scope of work, cost estimate, and bid documentation.
WSP may invoice according to the included schedule.
Subtask 1:
Project Management is automatically calculated as a percentage of total labor in accordance with
Contract HW685.
Subtask 2:
Following confirmation of an up-to-date access agreement with the current real property owner, WSP will collect groundwater samples from 28 monitoring wells. Out of these groundwater samples:
12 will be analyzed for chlorinated volatile organic compounds (VOCs) using EPA Method 8260B.
Eight will be analyzed for methane, ethane, and ethene (MEE) utilizing RSK 175.
o Unless significant changes in concentrations of MEE are found, this analysis will be dropped in future sampling events.
All 28 will be analyzed at the DEP Central Laboratory in Tallahassee, Florida for PFAS.
Subtask 3:
This subtask includes all costs involved with the labor for expanded PFAS sampling, labor for reporting
PFAS results, and IDW subcontractor costs.
Subtask 4:
Following the groundwater sampling event, WSP will submit an Annual Groundwater Report summarizing findings with updated analytical results and tables as well as conclusions and recommendations based on the most recent data.
FD
EP
C O
ST
E
ST
IM
A
TE
C on tra ct or
W S
P U
S A
In c.
D at e:
3/
/2
Ta sk
D C
8C
S ub Ta sk
P ro je ct
M an ag em en t
S ub
Ta sk
S ite
M us ic
M an
Ta sk
A nn ua l G ro un dw at er M on ito rin g
S ub
Ta sk
A ct iv ity
/P ha se
M on ito rin g
Ta sk
P
FA
S
R el at ed
C os ts a nd
ID
W T
D
S ub
Ta sk
P ro je ct
M an ag er
P at ric k M cG ra ne
Ta sk
R ep or tin g
S ub
Ta sk
S ub
Ta sk
S ub Ta sk
T T ot al s
La bo r R at e
C at eg or y $6
9.
PP
ro je ct
M an ag er
(R D
M
.1 $7
0.
P ro gr am
L ea de r -
X -1
(J
C B
0.
0.
3.
$6 9.
P ra ct ic e
Le ad er
X -1
(R
D M
4.
.0
.0
$0 .0
P ra ct ic e
Le ad er
X -1
0.
0.
0.
$0 .0
S en io r S ci
/E ng
X
-1
0.
0.
0.
$4
8.
S en io r P ro je ct S ci /E ng
P -1
(B
L)
0.
3.
4.
$0 .0
P ro je ct S ci /E ng
P -9
0.
0.
0.
$0
.0
S ta ff S ci /E ng
P -8
0.
0.
0.
$3 9.
S ta ff
S ci
/E ng
P
-8 (L
S
.0
.0 0.
$3
4.
S ta ff S ci /E ng
P -8
(A S
0.
0.
2.
$3 3.
S ta ff
S ci
/E ng
P
-8 (J
W
.0
.0 0.
$0
.0
0.
0.
0.
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
T ot al
H ou rs
.1
.0
.0
.0
D ire ct L ab or
$6
,6
.2
$7
.9
$1 ,5
.8
$2
,5
.6
$1 ,8
.9
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
O ve rh ea d
2.
$1
1, 4.
$1 ,3
.0
$2
,6
.7
$4 ,3
.2
$3
,2
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
G en
A dm in
0.
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
Fr in ge 0.
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
T ot al
L ab or
$1 8, 6.
$2
,0
.0
$4 ,2
.5
$6
,8
.9
$5 ,0
.9
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
RE
V:
2/
CE
F
GO
LD
ER
Pa ge
FD
EP
C O
ST
E
ST
IM
A
TE
C on tra ct or
W S
P U
S A
In c.
at e:
3/
/2
Ta sk
D C
8C
Ta sk
P ro je ct
M an ag em en t
S ub
Ta sk
S ite
M us ic
M an
Ta sk
A nn ua l G ro un dw at er M on ito rin g
S ub
Ta sk
A ct iv ity
/P ha se
M on ito rin g
Ta sk
P
FA
S
R el at ed
C os ts a nd
ID
W T
D
S ub
Ta sk
P ro je ct
M an ag er
P at ric k M cG ra ne
Ta sk
R ep or tin g
S ub
Ta sk
S ub
Ta sk
S ub Ta sk
T T ot al s
T ra ve l
V eh ic le
R en ta l
$2
.0
$2
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
M ile ag e
C os ts $0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
A ir Fa re $0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
P er d ie m
H ot el
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
To ta l T ra ve l
$2
.0
$2
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
S ub co nt ra ct or (E qu ip m en t P ro cu re m en t)
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
S ub co nt ra ct or
S ub to ta l $0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
P ro cu re m en t F ee $0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
T ot al
S ub co nt ra ct or C os t
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
S ub co nt ra ct or (S er vi ce s
P ro cu re m en t) ril lin g
(C on ve nt io na
l) $0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
D ril lin g (N on -c on ve nt io na l)
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
M ob ile L ab or at or y $0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
S ur ve yi ng
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
ID
W
$3
.0
$0 .0
$3
.0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
U til iti es
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
U til ity L oc at io n
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
S ub co nt ra ct or S ub to ta l
$3
.0
$0 .0
$3
.0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
H an dl in g Fe e $3
9.
$0 .0
$3
9.
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
T ot al
S ub co nt ra ct or C os t
$4
.0
$0 .0
$4
.0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
La bo ra to ry
A na ly tic al C os ts
$2 ,4
.0
$2
,4
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
Fa st
T ur na ro un d
C ha rg es
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
S am pl e
S hi pp in g $3
.0
$3
.0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
T ot al
L ab or at or y
$2 ,7
.0
$2
,7
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
Fi el d E xp en se s
P er so na l P ro te ct io n $0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
E xp en da bl es $8
0.
$8 0.
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
E qu ip m en t ( D ril lin g re la te
d) $0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
E qu ip m en t ( A na ly tic al re la te d)
$9
.0
$7
.0
$2
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
E qu ip m en t (
ID
W re la te
d) $2
.0
$0
.0
$2
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
E qu ip m en t ( O th er
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
T ot al
F ie ld E xp en se s
$1 ,2
.0
$8
.0
$4
.0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
S ub to ta l $2
2, 1.
$2 ,0
.0
$7
,9
.5
$7 ,7
.9
$5
,0
.9
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
C om pl et io n
Fe e
$1 ,8
.6
$2
.8
$4
.0
$6
.6
$5
.1
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
T ot al E st im at ed
C os t $2
4, 5.
$2 ,3
.8
$8
,4
.5
$8 ,4
.6
$5
,5
.0
$0 .0
$0
.0
$0 .0
$0
.0
$0 .0
$0
.0
RE
V:
2/
CE
F
GO
LD
ER
Pa ge
SITE : Music Man SUBTASK 2: Annual Groundwater Monitoring
DATE: 3/11/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Practice Leader (R. McCann) 4.0
Staff Sci/Eng (L. Swindle) 18.0
Staff Sci/Eng (J. Whipple) 17.0
TOTAL LABOR 39.0
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 Per Day 2 $240.00
TOTAL VEHICLE $240.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
Chlorinated VOCs - EPA Method 8260B
Total VOHs EPA Method 8260B $73.00 12 $876.00
MEE RSK175 $180.00 8 $1,440.00
PID/Hall Series EPA Method 8021 - IDW $110.00 1 $110.00
Sample Shipping Large $150.00 2 $300.00
TOTAL LAB $2,726.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Miscellaneous Expendables $40.00 Per Day 2 $80.00
Shallow Groundwater Sampling Kit $290.00 Per Day 2 $580.00 Tubing, Poly HDPE $0.30 Per Foot 350 $105.00 Tubing, Silicon 3/16 x 3/8 $3.00 Per Foot 13 $39.00
TOTAL EQUIPMENT $804.00
Verification of property ownership prior to groundwater sampling (1 hour). Prepare and submit email summary with field documentation and certified laboratory report with chlorinated VOC results (3 hours).
Round trip travel (1 hour per day x 2 days = 2 hours). Field event preparation (1 hour).
Instrument calibration, measure water levels, measure field parameters, collect samples from 12 wells: five shallow zone monitoring wells (SW-4, SW-10, SW-13, SW-15, and SW-17), and seven intermediate zone monitoring wells (IW-1, IW-4, IW-9, IW-10, IW-13, IW-15, and IW-17), including IDW sampling and staging (15 hours).
Round trip travel (1 hour per day x 2 days = 2 hours). Instrument calibration, measure water levels, measure field parameters, collect samples from 12 wells: five shallow zone monitoring wells (SW-4, SW-10, SW-13, SW-15, and SW-17), and seven intermediate zone monitoring wells (IW-1, IW-4, IW-9, IW-10, IW-13, IW-15, and IW-17), including IDW sampling and staging (15 hours).
LEVEL OF EFFORT/EXPENSE WORKSHEET
SUBTASK 3: PFAS Related Costs and IDW T&D
DATE: 3/11/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Practice Leader (R. McCann) 11.0
Staff Sci/Eng (L. Swindle) 24.0
Staff Sci/Eng (J. Whipple) 20.0
Senior Project Sci/Eng (B. Lucero) 3.0
TOTAL LABOR 58.0
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Erwin T&D - Non-Haz PFOS/PFAS Water $195.00 per drum 2 $390.00
TOTAL $390.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $110.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Tubing, Poly HDPE $0.30 Per Day 650 $195.00 Tubing, Silicon 3/16 x 3/8 $3.00 Per Day 17 $51.00
Drum, 55-gallon $100.00 Per Day 2 $200.00
TOTAL EQUIPMENT $446.00
Complete forms to arrange for PFAS sample bottle order delivery and shipment from DEP Central Laboratory (1 hour). Characterize IDW and prepare waste profile for transportation and disposal of IDW (3 hours). Prepare and submit email summary with field documentation and certified laboratory report with PFAS results (3 hours). Prepare PFAS section for the draft annual report (4 hours).
Collect samples from 16 wells for PFAS analysis only; collect samples from 12 wells listed in Subtask 2 for PFAS analysis; collect equipment blank for PFAS analysis (18 hours). Package and deliver PFAS samples to shipping point for DEP Central Laboratory (2 hours). Prepare data tables with PFAS analytical results (4 hours).
Collect samples from 16 wells for PFAS analysis only; collect samples from 12 wells listed in Subtask 2 for PFAS analysis; collect equipment blank for PFAS analysis (18 hours). Package and deliver PFAS samples to shipping point for DEP Central Laboratory (2 hours).
Prepare CADD Figures (shallow and intermediate zones) with PFAS data for Annual Groundwater Monitoring Report.
FINAL --7/24/96
LEVEL OF EFFORT/EXPENSE WORKSHEET
SUBTASK 4: Reporting
DATE: 3/11/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Practice Leader (J. Brown) 3.0
Practice Leader (R. McCann) 20.0
Sr Project Sci/Eng (B. Lucero) 4.0
Staff Sci/Eng (A. Strayer) 2.0
TOTAL LABOR 29.0
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
Develop conclusions and recommendations and prepare final Annual Monitoring Report.
Data entry, prepare tables and figures, and draft Annual Monitoring Report
Prepare potentiometric maps and VOC figures for Annual Monitoring Report.
Reporting: Updating tables, document production. Create pdf for OCULUS.
FINAL --7/24/96
WSP USA Inc.
9428 Baymeadows Road, Suite 400, Jacksonville, Florida 32256 USA
T: +1 904 363-3430 F: +1 904 363-3445 wsp.com
March 11, 2024 Proposal No. 2024US208823
Mr. Patrick McGrane Florida Department of Environmental Protection Division of Waste Management Waste Site Cleanup Section 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400
RE: COST PROPOSAL FOR ANNUAL GROUNDWATER MONITORING
THE MUSIC MAN
799 LANE AVENUE
JACKSONVILLE, DUVAL COUNTY, FLORIDA
DEP FACILITY ID NUMBER: ERIC_4619
PROPOSED TASK ASSIGNMENT: DC028C
Dear Mr. McGrane:
WSP USA Inc. (WSP) is pleased to provide the Florida Department of Environmental Protection (DEP) with this cost proposal for annual groundwater monitoring and expanded Per- and Polyfluoroalkyl Substances (PFAS) monitoring at the above-referenced site. This proposal includes a description of the proposed scope of services, level of effort sheets for each subtask, and a cost estimate form that summarizes the costs of the proposed services.
The proposed scope of services is described below.
SUBTASK 1 – PROJECT MANAGEMENT
To facilitate project quality and satisfactory completion of the proposed scope of work, all aspects of this project will be overseen by an experienced project manager. The project manager will be responsible for the schedule, budget, invoicing, project activities, and communications with DEP and the field team. Project management will include coordination of field activities; resource allocation to confirm the work is conducted by qualified professionals in accordance with the project schedule; cost control and tracking of the budget status; and submittal of project invoices in accordance with DEP Waste Site Cleanup Section requirements. The project manager will oversee the work so that it is conducted in a manner that is consistent with the requirements of the DEP-approved task assignment.
SUBTASK 2 – ANNUAL GROUNDWATER MONITORING
Groundwater Monitoring Following authorization to proceed, WSP will coordinate with the real property owner for access to complete the scope of work. WSP will collect groundwater samples from 28 monitoring wells. The attached Figures 3 through 6 from the February 2023 sampling event show the monitoring well locations, groundwater flow direction, and chlorinated volatile organic compound (VOC) results for each zone. The attached Figure 7 shows the 2021 PFAS screening results.
Mr. Patrick McGrane Proposal No. 2024US208823
Florida Department of Environmental Protection March 11, 2024
Prior to groundwater sampling, the depth-to-groundwater will be measured at the wells sampled using an electronic water level indicator to determine groundwater elevations and flow direction. During the sampling event, the locks and well caps will be inspected for damage or degradation and repaired or replaced, as necessary.
Groundwater sampling activities will be completed in accordance with DEP Standard Operating Procedures (SOPs) for Field Activities (DEP SOP-001/01), dated January 2017 (effective April 16, 2018) and DEP SOPs for Sampling with and Analysis of PFAS, dated August 2020. Prior to collecting the groundwater sample, each well will be purged and field parameters including temperature, pH, specific conductance, dissolved oxygen, turbidity, and oxidation-reduction potential will be monitored. Purge volumes and field parameters will be recorded on field data sheets, and the field monitoring equipment will be calibrated in accordance with the manufacturer’s recommended procedures.
The groundwater samples to be analyzed for chlorinated VOCs and methane, ethane, and ethene (MEE) will be delivered to a Florida Department of Health and National Environmental Laboratory Accreditation Program certified, fixed-base laboratory along with the completed chain-of-custody documentation. The selected groundwater samples to be analyzed for PFAS will be shipped to the DEP Central Laboratory in Tallahassee, Florida. Upon receipt of the laboratory analytical results, WSP will evaluate the constituent concentrations to determine if off-site notification is required.
The samples will be analyzed as follows:
Sample ID Chlorinated VOCs (EPA Method 8260B)
MEE
(RSK 175)
PFAS
(DEP SOP: LC001-3 or
Similar)
SW-1 --- X X
SW-2 --- --- X
SW-3 --- --- X
SW-4 X X X
SW-5 --- --- X
SW-6 --- --- X
SW-7 --- --- X
SW-9 --- --- X
SW-10 X X
X
(Sampled in July 2021)
SW-13 X --- X
SW-14 --- --- X
SW-15 X X
X
(Sampled in July 2021)
SW-16 --- --- X
SW-17 X --- X
IW-1 X X
X
(Sampled in July 2021)
Sample ID Chlorinated VOCs (EPA Method 8260B)
MEE
(RSK 175)
PFAS
(DEP SOP: LC001-3 or
Similar)
IW-2 --- --- X
IW-3 --- --- X
IW-4 X --- X
IW-5 --- --- X
IW-6 --- --- X
IW-7 --- --- X
IW-9 X X X
IW-10 X X X
IW-12 --- --- X
IW-13 X --- X
IW-15 X X
X
(Sampled in July 2021)
IW-16 --- --- X
IW-17 X --- X
Equipment Blank --- --- X
Investigative Derived Waste (IDW) Total VOCs --- X
Interim Deliverable Upon completion of Subtask 2, an e-mail deliverable will be submitted for the chlorinated VOC samples and include copies of the field data sheets, equipment calibration forms, field notes, laboratory analytical report, and laboratory chain-of-custody documentation.
SUBTASK 3 – PFAS-RELATED COSTS AND IDW TRANSPORTATION AND DISPOSAL
WSP will include costs associated with the expanded PFAS monitoring activities in this subtask. These activities include completing bottle order requests with the DEP Central Laboratory; waste characterization and waste profiling; packaging and shipping PFAS samples to the DEP Central Laboratory; labor involved in sampling wells associated with PFAS analysis only; and investigation derived waste (IDW) transportation and disposal.
Quality Assurance/Quality Control WSP will collect one equipment blank sample during the groundwater sampling event. The equipment blank will be collected by pumping (peristaltic pump) PFAS-free water through silicon and/or HDPE tubing and into laboratory-supplied containers. The equipment blank will be analyzed for PFAS using DEP SOP: LC001-3 (or similar), as shown in the above table.
IDW Transportation and Disposal WSP will containerize the IDW purge water and decontamination water in a 55-gallon drum(s). WSP will collect a waste characterization sample from the drum for analysis of total VOCs using EPA Method 8260 and PFAS using DEP SOP: LC001-3 (or similar), as shown in the above table. The drum(s) will be temporarily staged onsite, pending waste characterization. For cost estimating purposes, WSP has assumed that the IDW can be transported and disposed of as non-hazardous waste at an approved facility. The IDW transportation and disposal subcontractor will provide WSP with a non-hazardous waste manifest upon delivery to the disposal facility. WSP estimates two drums of IDW purge water will be generated during the field activities.
Interim Deliverable Upon completion of Subtask 3, an e-mail deliverable will be submitted for the PFAS samples and include copies of the field data sheets, equipment calibration forms, field notes, laboratory analytical report, laboratory chain-of-custody documentation, and updated data tables and figures.
SUBTASK 4 – REPORTING
WSP will prepare an Annual Groundwater Monitoring Report that will include a description of the sampling procedures, evaluation of the analytical results; comparison of current to historical data; tabulated summary of the current and historical analytical data; a site map showing the groundwater analytical results; water level elevation information in tables and figures; laboratory analytical data; and conclusions and recommendations.
HEALTH AND SAFETY
WSP will update the existing site-specific Health and Safety Plan for the fieldwork. The work will be completed in accordance with WSP’s safety policies and procedures. At a minimum, WSP will wear safety glasses, high visibility safety vests, and steel-toed boots. A safety job briefing will be conducted prior to the start of work activities, and anytime the scope of work or site conditions change.
COST AND SCHEDULE
The estimated cost to complete the proposed scope of work is $24,705.04. WSP anticipates the groundwater monitoring event will take place in March or April 2024. The level of effort sheets and cost estimate form are included in Attachment A. The IDW disposal subcontractor quotes are included in Attachment B. The following table summarizes the proposed costs and deliverable schedule.
Task Proposed Cost Proposed Schedule/Deliverables
Subtask 1 – Project Management $ 2,307.80 July 19, 2024
Subtask 2 – Annual Groundwater Monitoring
$ 8,412.58 May 10, 2024 (E-mail summary with field documentation and certified laboratory analytical report for chlorinated VOCs)
Subtask 3 – PFAS Related Costs and IDW Transportation and Disposal
$ 8,406.61 May 24, 2024 (E-mail summary with field documentation and certified laboratory analytical report for PFAS and non-hazardous waste manifest for IDW)
Task Proposed Cost Proposed Schedule/Deliverables
Subtask 4 – Reporting $ 5,578.05 June 21, 2024 (Annual Groundwater Monitoring Report)
Total/Completion Date $ 24,705.04 August 16, 2024
WSP appreciates the opportunity to provide services to the DEP. Should you require additional information or clarifications, please contact us at (904) 363-3430.
Sincerely, WSP USA Inc.
Richard D. "Rick" McCann, PG Matthew C. Crews, PE Vice President, Geologist (US) Assistant Vice President, Environmental Engineer
RDM/MCC/as
Attachments: Figure 3 – Potentiometric Map - Shallow Zone of the Surficial Aquifer (February 23, 2023) Figure 4 – Potentiometric Map – Intermediate Zone of the Surficial Aquifer (February 23, 2023) Figure 5 – Chlorinated Hydrocarbon Concentrations in the Shallow Zone of the Surficial Aquifer
(February 2023) Figure 6 – Chlorinated Hydrocarbon Concentrations in the Intermediate Zone of the Surficial Aquifer
(February 2023) Figure 7 – PFOA and PFOS Concentrations in the Shallow and Intermediate Surficial Aquifer (July 2021)
Attachment A – Level of Effort Sheets and Cost Estimate Form Attachment B – Subcontractor Quotes
G:\Projects\DEP-Drycleaning\Projects\Jax\Music Man\HW685\DC028C - 2024 Ann GW Mon\Proposal\DC028C - Music Man Annual GW Mon Proposal.docx
L
N E
V E
N U
E
HOME DEPOT ENTRANCE
SW-21
SW-18
UES TMW-1
IW-7
PICCADILLY
CAFETERIA
IW-16
IW-8
UES TMW-2
R A M O N A B O U L E V A R D
MUSIC
DEPOT
BONO'S
BAR B QUE
O F F I C E D E P O T
IW-21
IW-9
IW-11
IW-12
IW-2
IW-1
DW-1
IW-3
IW-6
IW-10
IW-4
IW-5
IW-13
IW-14 IW-15
IW-20
IW-19
IW-18
SW-20
SW-19
SW-14
SW-5
SW-16
SW-15
SW-13
SW-4
SW-10
SW-7
SW-9
SW-8
SW-2
SW-1
SW-3
SW-6
IW-17
SW-17
MW-24
MW-27
MW-25
MW-15
MW-17R
MW-8R
MW-18 MW-7
MW-23
MW-6R
MW-21MW-19
MW-5R
MW-26
MW-12R
MW-22
9.67
11.08*
10.23
10.40
10.70
11.22
FORMER
BUILDING
FOOTPRINT
10.00
10.00
10.50
10.50
11.00
11.00
GROUNDWATER ELEVATION CONTOUR
INFERRED DIRECTION OF GROUNDWATER FLOW
(DASHED WHERE INFERRED)
GROUNDWATER ELEVATION IN FEET ABOVE MEAN
SEA LEVEL
9.57
DICK ENVIRONMENTAL SERVICES WELL
SHALLOW MONITORING WELL LOCATION
TEMPORARY MONITORING WELL LOCATION
INTERMEDIATE MONITORING WELL LOCATION
DEEP MONITORING WELL LOCATION
in
31404452.4619 Control No.
4619-DC028B-003
FIGURE
2023-03-07
BCL
RFM
RFM
MCC
GRACE PROPERTY
JACKSONVILLE, DUVAL COUNTY, FLORIDA
FL. DEPT. OF ENVIRONMENTAL PROTECTION
POTENTIOMETRIC MAP - SHALLOW ZONE OF THE SURFICIAL
AQUIFER (APPROXIMATELY 2 TO 14 FT. BGS)
(FEBRUARY 23, 2023)
TITLE
PROJECT NO. REV.
PROJECTCLIENT
IF
T
H
IS
M
EA
SU
R
EM
EN
T D
O
ES
N O
T M
AT
C
H W
H
AT
IS
S
H O
W N
, T H
E
SH
EE
T
SI
ZE
H
AS
B
EE
N M
O D
IF
IE
D F
R O
M : A
N
SI
B
CONSULTANT
PREPARED
DESIGNED
REVIEWED
APPROVED
YYYY-MM-DD
Path: \\golder.gds\complexdata\Office\Jacksonville\drafting\Projects\FDEP\FDEP-DC\31404452\31404452_4619_Music_Man\DC028B\Active Drawings\ | File Name: 4619-DC028B-003.dwg
LEGEND
0 1000 2000
1. BASE MAP OBTAINED FROM GANNETT FLEMING, TITLED "SITE
DRAWING GRACE PROPERTIES, INC JACKSONVILLE FLORIDA
FEBRUARY 2005", DATED 3/21/05.
2. BASE MAP UPDATED FROM CADD FILE PREPARED BY WALTON
F. POPPELL, INC., LAND SURVEYORS, JOB No. 07-061, FIELD
SURVEYED ON 03/15/07 IN RELATION TO THE NATIONAL
GEODETIC VERTICAL DATUM OF 1988 (NAVD 88).
3. GROUNDWATER ELEVATION FROM SW-15 WAS NOT USED
BECAUSE OF ERRONEOUS DEPTH TO WATER MEASUREMENT.
REFERENCE(S)
E
N U
E
HOME DEPOT ENTRANCE
R A M O N A B O U L E V A R D
PICCADILLY
CAFETERIA
MUSIC
DEPOT
BONO'S
BAR B QUE
O F F I C E D E P O T
UES TMW-2UES TMW-1
IW-7IW-9
IW-8
IW-11
IW-12
IW-2
IW-1DW-1
IW-3
IW-6
IW-10
IW-4
IW-5
IW-13
IW-14 IW-15
IW-16
IW-20
IW-19
IW-18
IW-21
SW-18
SW-21
SW-19 SW-20
SW-14
SW-15
SW-16
SW-5
SW-13
SW-4
SW-10
SW-7
SW-9
SW-8
SW-2
SW-1
SW-3
SW-6
IW-17
SW-17
MW-15
MW-25
MW-23
MW-17R
MW-24
MW-7MW-21
MW-18
MW-19
MW-5R
MW-6R
MW-12R
MW-8R
MW-22
MW-26
MW-27
9.72
10.23
10.26
10.46
10.49
10.55
10.65
FORMER
BUILDING
FOOTPRINT
10.50
10.25 10.25
10.50
9.75
9.75
10.00
10.00
GROUNDWATER ELEVATION CONTOUR
INFERRED DIRECTION OF GROUNDWATER FLOW
(DASHED WHERE INFERRED)
GROUNDWATER ELEVATION IN FEET ABOVE MEAN
SEA LEVEL
9.95
DICK ENVIRONMENTAL SERVICES WELL
SHALLOW MONITORING WELL LOCATION
TEMPORARY MONITORING WELL LOCATION
INTERMEDIATE MONITORING WELL LOCATION
DEEP MONITORING WELL LOCATION
in
31404452.4619 Control No.
4619-DC028B-004
FIGURE
2023-03-07
BCL
RFM
RFM
MCC
GRACE PROPERTY
JACKSONVILLE, DUVAL COUNTY, FLORIDA
FL. DEPT. OF ENVIRONMENTAL PROTECTION
POTENTIOMETRIC MAP - INTERMEDIATE ZONE OF THE SURFICIAL
AQUIFER (APPROXIMATELY 14 TO 31 FT. BGS)
(FEBRUARY 23, 2023)
TITLE
PROJECT NO. REV.
PROJECTCLIENT
IF
T
H
IS
M
EA
SU
R
EM
EN
T D
O
ES
N O
T M
AT
C
H W
H
AT
IS
S
H O
W N
, T H
E
SH
EE
T
SI
ZE
H
AS
B
EE
N M
O D
IF
IE
D F
R O
M : A
N
SI
B
CONSULTANT
PREPARED
DESIGNED
REVIEWED
APPROVED
YYYY-MM-DD
Path: \\golder.gds\complexdata\Office\Jacksonville\drafting\Projects\FDEP\FDEP-DC\31404452\31404452_4619_Music_Man\DC028B\Active Drawings\ | File Name: 4619-DC028B-004.dwg
LEGEND
0 40 80
1. BASE MAP OBTAINED FROM GANNETT FLEMING, TITLED "SITE
DRAWING GRACE PROPERTIES, INC JACKSONVILLE FLORIDA
FEBRUARY 2005", DATED 3/21/05.
2. BASE MAP UPDATED FROM CADD FILE PREPARED BY WALTON
F. POPPELL, INC., LAND SURVEYORS, JOB No. 07-061, FIELD
SURVEYED ON 03/15/07 IN RELATION TO THE NATIONAL
GEODETIC VERTICAL DATUM OF 1988 (NAVD 88).
REFERENCE(S)
NOTE(S)
E
N U
E
HOME DEPOT ENTRANCE
CONCRETE
POWER POLE
POWER POLE
CONCRETE
FIRE HYDRANT
BACK OF WALK
GRASS ISLAND
TELEPHONE
WIRE
AREA OF
EXCAVATION
CONCRETE
POWER POLE
R A M O N A B O U L E V A R D
PICCADILLY
CAFETERIA
MUSIC
DEPOT
BONO'S
BAR B QUE
O F F I C E D E P O T
UES TMW-2
UES TMW-1
IW-7
IW-9
IW-8
IW-11
IW-12
IW-2
DW-1
IW-3
IW-6
IW-10
IW-4
IW-5
IW-13
IW-14 IW-15
IW-16
IW-20
IW-19
IW-18
IW-21
SW-18
SW-21
SW-19
SW-20
SW-14 SW-15
SW-16
SW-5
SW-13
SW-4
SW-10
SW-7
SW-9
SW-8
SW-2
SW-1
SW-3
SW-6
IW-17
SW-17
MW-25
MW-15
MW-23
MW-17R
MW-24
MW-7MW-21MW-18MW-19
MW-5R
MW-6R
MW-12R
MW-8R
MW-22
MW-26
MW-27
IW-1
FORMER
BUILDING
FOOTPRINT
INFERRED EXTENT OF
CHLORINATED
HYDROCARBONS
EXCEEDING THE FDEP
NADCs
INFERRED EXTENT OF CHLORINATED
HYDROCARBONS (EXCEEDING THE
FDEP GROUNDWATER CLEANUP
TARGET LEVELS)
DICK ENVIRONMENTAL SERVICES WELL
SHALLOW MONITORING WELL LOCATION
TEMPORARY MONITORING WELL LOCATION
INTERMEDIATE MONITORING WELL LOCATION
DEEP MONITORING WELL LOCATION
CHITIN COLUMNS
in
31404452.4619 Control No.
4619-DC028B-005
FIGURE
2023-03-07
BCL
RFM
RFM
MCC
GRACE PROPERTY
JACKSONVILLE, DUVAL COUNTY, FLORIDA
FL. DEPT. OF ENVIRONMENTAL PROTECTION
CHLORINATED HYDROCARBON CONCENTRATIONS IN THE
SHALLOW ZONE OF THE SURFICIAL AQUIFER
(FEBRUARY 2023)
TITLE
PROJECT NO. REV.
PROJECTCLIENT
IF
T
H
IS
M
EA
SU
R
EM
EN
T D
O
ES
N O
T M
AT
C
H W
H
AT
IS
S
H O
W N
, T H
E
SH
EE
T
SI
ZE
H
AS
B
EE
N M
O D
IF
IE
D F
R O
M : A
N
SI
B
CONSULTANT
PREPARED
DESIGNED
REVIEWED
APPROVED
YYYY-MM-DD
Path: \\golder.gds\complexdata\Office\Jacksonville\drafting\Projects\FDEP\FDEP-DC\31404452\31404452_4619_Music_Man\DC028B\Active Drawings\ | File Name: 4619-DC028B-005.dwg
LEGEND
1. ALL UNITS REPORTED IN MICROGRAMS PER LITER (μg/L).
2. < = BELOW THE LABORATORY REPORTED METHOD
DETECTION LIMIT.
3. I - REPORTED VALUE IS BETWEEN THE LABORATORY METHOD
DETECTION LIMIT AND LABORATORY PRACTICAL
QUANTITATION LIMIT.
4. BOLD/YELLOW HIGHLIGHTED VALUE INDICATES
CONCENTRATION IS ABOVE THE FDEP GROUNDWATER
CLEANUP TARGET LEVEL (GCTL).
5. BOLD/BLUE HIGHLIGHTED VALUE INDICATES CONCENTRATION
IS ABOVE THE FDEP NATURAL ATTENUATION DEFAULT
CONCENTRATION (NADC).
6. FT-BGS = FEET BELOW GROUND SURFACE
0 40 80
NOTE(S)
1. BASE MAP OBTAINED FROM GANNETT FLEMING, TITLED "SITE
DRAWING GRACE PROPERTIES, INC JACKSONVILLE FLORIDA
FEBRUARY 2005", DATED 3/21/05.
2. BASE MAP UPDATED FROM CADD FILE PREPARED BY WALTON
F. POPPELL, INC., LAND SURVEYORS, JOB No. 07-061, FIELD
SURVEYED ON 03/15/07 IN RELATION TO THE NATIONAL
GEODETIC VERTICAL DATUM OF 1988 (NAVD 88).
REFERENCE(S)
WELL ID (SCREEN INTERVAL DEPTH IN FT-BGS)
DATE SAMPLED
TETRACHLOROETHYLENE CONCENTRATION
TRICHLOROETHYLENE CONCENTRATION
CIS-1,2-DICHLOROETHYLENE CONCENTRATION
VINYL CHLORIDE CONCENTRATION
SW-00 (3.6-13.6)
APR 2017
3 300
3 300
70 700
1 100
FDEP NATURAL ATTENUATION
DEFAULT CONCENTRATION (NADC)
FDEP GROUNDWATER CLEANUP
TARGET LEVEL (GCTL)
SW-1 (3.6-13.6)
Feb 2016 < 0.50 < 0.50 < 0.50 < 0.50
SW-3 (3.8-13.8)
Feb 2016 < 0.50 < 0.50 14.2
< 0.50
SW-6 (3.7-13.7)
Feb 2016 < 0.50 < 0.50 < 0.50 < 0.50
SW-14 (3.5-13.5)
Feb 2016 < 0.50 < 0.50 < 0.50 < 0.50
SW-21 (3.6-13.6)
Feb 2016
<0.50 <0.50 <0.50 <0.50
SW-9 (3.8-13.8)
Feb 2016 Jun 2023 < 0.50 < 0.50 < 0.50 < 0.50 < 0.50 < 0.50 < 0.50 < 0.50
SW-16 (3.6-13.6)
Feb 2016 Jun 2018 < 0.50 < 0.50 < 0.50 < 0.50 < 0.50 < 0.50 < 0.50 < 0.50
SW-19 (3.5-13.5)
Feb 2016 Apr 2017 Jun 2018 < 0.50 < 0.22 < 0.50 < 0.50 < 0.36 < 0.50 < 0.50 < 0.36 < 0.50 < 0.50 < 0.36 < 0.50
SW-4 (4.1-14.1)
Jun 2019 Jun 2020 Jul 2021 Aug 2022 Feb 2023
0.38 U 0.38 U 0.38 U 0.38 U 0.38 U
1.3 0.36 U 0.36 U 0.36 U 0.36 U 230 68.2 177 253 2.7
51.7 62.1 87.4 106 0.91 I
SW-10 (3.8-13.8)
Jun 2019 Jun 2020 Jul 2021 Aug 2022 Feb 2023
0.38 U 0.38 U 0.38 U 0.38 U 0.38 U
0.54 I 0.36 U 0.63 I 0.36 U 0.88 I
1,390 704 382 673 582 452 256 165 307 406
SW-13 (4-14)
Jun 2019 Jun 2020 Jul 2021 Aug 2022 Feb 2023
0.38 U 0.38 U 0.38 U 0.38 U 0.38 U
3.7 3.6 3.8 3.3 2.9
56.8 53.4 67.8 66.6 96.2
4.1 4.6 11.5 9.1 8.6
SW-15 (3.4-13.4)
Jun 2019 Jun 2020 Jul 2021 Aug 2022 Feb 2023
0.38 U 0.38 U 0.38 U 0.38 U 0.38 U
0.36 U 0.36 U 0.36 U 0.36 U 0.36 U
591 466 197 13.0 12.0 274 164 161 61.0 116
SW-17 (3.6-13.6)
Jun 2019 Jun 2020 Jul 2021 Aug 2022 Feb 2023
0.38 U 0.38 U 0.38 U 0.38 U 0.38 U
0.36 U 0.36 U 0.36 U 0.36 U 0.36 U
2.2 0.27 U 0.27 U 0.27 U 0.55 I
0.39 U 0.39 U 0.39 U 0.39 U 0.39 U
E
N U
E
HOME DEPOT ENTRANCE
CONCRETE
POWER POLE
POWER POLE
CONCRETE
FIRE HYDRANT
BACK OF WALK
GRASS ISLAND
TELEPHONE
WIRE
AREA OF
EXCAVATION
CONCRETE
POWER POLE
R A M O N A B O U L E V A R D
PICCADILLY
CAFETERIA
MUSIC
DEPOT
BONO'S
BAR B QUE
O F F I C E D E P O T
UES TMW-2UES TMW-1
IW-7
IW-9
IW-8
IW-11
IW-12
IW-2
IW-1
DW-1
IW-3
IW-6IW-10
IW-4
IW-5
IW-13
IW-14 IW-15
IW-16
IW-20
IW-19
IW-18
IW-21
SW-18
SW-21
SW-19
SW-20
SW-14
SW-15
SW-16
SW-5
SW-13
SW-4
SW-10
SW-7
SW-9
SW-8
SW-2
SW-1
SW-3
SW-6
IW-17
SW-17
MW-25
MW-15
MW-23
MW-17R
MW-24
MW-7MW-21MW-18MW-19
MW-5R
MW-6R
MW-12R
MW-8R
MW-22
MW-26
MW-27
FORMER
BUILDING
FOOTPRINT
INFERRED EXTENT OF
CHLORINATED HYDROCARBONS
(EXCEEDING THE FDEP
GROUNDWATER CLEANUP
TARGET LEVELS)
INFERRED EXTENT OF
CHLORINATED
HYDROCARBONS
EXCEEDING THE FDEP
NADCs
DICK ENVIRONMENTAL SERVICES WELL
SHALLOW MONITORING WELL LOCATION
TEMPORARY MONITORING WELL LOCATION
INTERMEDIATE MONITORING WELL LOCATION
DEEP MONITORING WELL LOCATION
CHITIN COLUMNS
in
31404452.4619 Control No.
4619-DC028B-006
FIGURE
2023-03-07
BCL
RFM
RFM
MCC
GRACE PROPERTY
JACKSONVILLE, DUVAL COUNTY, FLORIDA
FL. DEPT. OF ENVIRONMENTAL PROTECTION
CHLORINATED HYDROCARBON CONCENTRATIONS IN THE
INTERMEDIATE ZONE OF THE SURFICIAL AQUIFER
(FEBRUARY 2023)
TITLE
PROJECT NO. REV.
PROJECTCLIENT
IF
T
H
IS
M
EA
SU
R
EM
EN
T D
O
ES
N O
T M
AT
C
H W
H
AT
IS
S
H O
W N
, T H
E
SH
EE
T
SI
ZE
H
AS
B
EE
N M
O D
IF
IE
D F
R O
M : A
N
SI
B
CONSULTANT
PREPARED
DESIGNED
REVIEWED
APPROVED
YYYY-MM-DD
Path: \\golder.gds\complexdata\Office\Jacksonville\drafting\Projects\FDEP\FDEP-DC\31404452\31404452_4619_Music_Man\DC028B\Active Drawings\ | File Name: 4619-DC028B-006.dwg
LEGEND
0 40 80
1. BASE MAP OBTAINED FROM GANNETT FLEMING, TITLED "SITE
DRAWING GRACE PROPERTIES, INC JACKSONVILLE FLORIDA
FEBRUARY 2005", DATED 3/21/05.
2. BASE MAP UPDATED FROM CADD FILE PREPARED BY WALTON
F. POPPELL, INC., LAND SURVEYORS, JOB No. 07-061, FIELD
SURVEYED ON 03/15/07 IN RELATION TO THE NATIONAL
GEODETIC VERTICAL DATUM OF 1988 (NAVD 88).
REFERENCE(S)
1. ALL UNITS REPORTED IN MICROGRAMS PER LITER (μg/L).
2. < = BELOW THE LABORATORY REPORTED METHOD
DETECTION LIMIT.
3. I - REPORTED VALUE IS BETWEEN THE LABORATORY
METHOD DETECTION LIMIT AND LABORATORY PRACTICAL
QUANTITATION LIMIT.
4. BOLD/YELLOW HIGHLIGHTED VALUE INDICATES
CONCENTRATION IS ABOVE THE FDEP GROUNDWATER
CLEANUP TARGET LEVEL (GCTL).
5. BOLD/BLUE HIGHLIGHTED VALUE INDICATES
CONCENTRATION IS ABOVE THE FDEP NATURAL
ATTENUATION DEFAULT CONCENTRATION (NADC).
6. * = RESULT DETERMINED NOT TO EXCEED THE GCTL BASED
ON THE FDEP MEMORANDUM "ROUNDING ANALYTICAL DATA
FOR THE SITE REHABILITATION COMPLETION", DATED
NOVEMBER 17, 2011.
7. FT-BGS = FEET BELOW GROUND SURFACE
NOTE(S)
DATE SAMPLED
TETRACHLOROETHYLENE CONCENTRATION
TRICHLOROETHYLENE CONCENTRATION
CIS-1,2-DICHLOROETHYLENE CONCENTRATION
VINYL CHLORIDE CONCENTRATION
IW-00 (15.2-20.2)
APR 2017
3 300 3 300
70 700
1 100
FDEP NATURAL ATTENUATION
DEFAULT CONCENTRATION (NADC)
FDEP GROUNDWATER CLEANUP
TARGET LEVEL (GCTL)
WELL ID (SCREEN INTERVAL DEPTH IN FT-BGS)IW-3 (25.8-30.8)
Feb 2016 < 0.50 < 0.50 < 0.50 < 0.50
IW-6 (16.5-21.5)
Feb 2016 < 0.50 < 0.50 < 0.50 < 0.50
IW-14 (15.5-20.5)
Feb 2016 < 0.50 < 0.50 < 0.50 < 0.50
IW-16 (14.4-19.4)
Feb 2016 Jun 2018 < 0.50 < 0.50 < 0.50 < 0.50 < 0.50 < 0.50 < 0.50 < 0.50
IW-19 (15.5-20.5)
Feb 2016 Apr 2017 Jun 2018 < 0.50 < 0.22 < 0.50 < 0.50 < 0.36 < 0.50
50.1 38 37.2
3.9 1.1* 0.72 I
IW-21 (15.5-20.5)
Feb 2016 Jun 2018 < 0.50 < 0.50 < 0.50 < 0.50 < 0.50 < 0.50 < 0.50 < 0.50
IW-1 (14.3-19.3)
Jun 2019 Jun 2020 Jul 2021 Aug 2022 Feb 2023
0.38 U 0.38 U 0.38 U 0.38 U 0.38 U
0.36 U 0.36 U 0.36 U 0.36 U 0.36 U
232 149 669 651 332 136 121 231 182 164
IW-9 (16-21)
Jun 2019 Jun 2020 Jul 2021 Aug 2022 Feb 2023
0.38 U 0.38 U 0.38 U 0.38 U 0.38 U
0.36 U 0.36 U 0.36 U 0.36 U 0.36 U
153 23 683 936 404 115 16.7 497 488 469
IW-15 (15.6-20.6)
Jun 2019 Jun 2020 Jul 2021 Aug 2022 Feb 2023
0.38 U 0.38 U 0.38 U 0.38 U 0.38 U
0.36 U 0.36 U 0.36 U 0.36 U 0.36 U
410 273 154 83.5 43.9 136 99.4 109 60.9 59.3
IW-17 (14.6-19.6)
Jun 2019 Jun 2020 Jul 2021 Aug 2022 Feb 2023
0.38 U 0.38 U 0.38 U 0.38 U 0.38 U
0.50 I 0.36 U 0.36 U 0.36 U 0.36 U
11.6 5 1.5 0.54 I 0.86 I
0.48 I 0.39 U 0.39 U 0.39 U 0.39 U
IW-10 (15.2-20.2)
Jun 2019 Jun 2020 Jul 2021 Aug 2022 Feb 2023
0.38 U 0.38 U 0.38 U 0.38 U 0.38 U
0.44 I 0.36 U 0.36 U 0.36 U 0.36 U
383 179 169 30.6 26.5 136 110 162 107 130
IW-4 (16.7-21.7)
Jun 2019 Jun 2020 Jul 2021 Aug 2022 Feb 2023
0.38 U 0.38 U 0.38 U 0.38 U 0.38 U
0.36 U 0.36 U 0.36 U 0.36 U 0.36 U
75 69.3 77.2 60.5 525
0.88 I 0.70 I 0.49 I 0.39 U 143
IW-13 (17-22)
Jun 2019 Jun 2020 Jul 2021 Aug 2022 Feb 2023
0.38 U 0.38 U 0.38 U 0.38 U 0.38 U
0.47 I 0.65 I 0.36 U 0.36 U 0.36 U
102 89.5 106 85.8 85.9
4.4 5.5 5.9 10.6 8.3
E
N U
E
HOME DEPOT ENTRANCE
CONCRETE
POWER POLE
POWER POLE
CONCRETE
FIRE HYDRANT
BACK OF WALK
GRASS ISLAND
TELEPHONE
WIRE
AREA OF
EXCAVATION
CONCRETE
POWER POLE
R A M O N A B O U L E V A R D
PICCADILLY
CAFETERIA
MUSIC
DEPOT
BONO'S
BAR B QUE
O F F I C E D E P O T
IW-7
IW-9
IW-8
IW-11
IW-12
IW-2
IW-1
IW-3
IW-6IW-10
IW-4
IW-5
IW-13
IW-14 IW-15
IW-16
IW-20
IW-19
IW-18
IW-21
SW-18
SW-21
SW-19
SW-20
SW-14
SW-15
SW-16
SW-5
SW-13
SW-4
SW-10
SW-7
SW-9
SW-8
SW-2
SW-1
SW-3
SW-6
IW-17
SW-17
FORMER
BUILDING
FOOTPRINT
SHALLOW MONITORING WELL LOCATION
INTERMEDIATE MONITORING WELL LOCATION
in
FDEP-DC025
Control No.
FDEP-DC025-L007
FIGURE
2021-08-05
BCL
RFM
RFM
JCB
FL. DEPT. OF ENVIRONMENTAL PROTECTION
PFOA AND PFOS CONCENTRATIONS IN THE SHALLOW AND
INTERMEDIATE SURFICIAL AQUIFER
(JULY 2021)
TITLE
PROJECT NO. REV.
PROJECT
PROPERTY
JACKSONVILLE, DUVAL COUNTY, FLORIDA
CLIENT
IF
T
H
IS
M
EA
SU
R
EM
EN
T D
O
ES
N O
T M
AT
C
H W
H
AT
IS
S
H O
W N
, T H
E
SH
EE
T
SI
ZE
H
AS
B
EE
N M
O D
IF
IE
D F
R O
M : A
N
SI
B
CONSULTANT
PREPARED
DESIGNED
REVIEWED
APPROVED
YYYY-MM-DD
Path: \\golder.gds\complexdata\Office\Jacksonville\drafting\File\FDEP\FDEP-DC\DC No 025 Grace Properties\L - 2021_AGWMR\Active Drawings\ | File Name: FDEP-DC025-L007.dwg
LEGEND
0 40 80
1. BASE MAP OBTAINED FROM GANNETT FLEMING, TITLED "SITE
DRAWING GRACE PROPERTIES, INC JACKSONVILLE FLORIDA
FEBRUARY 2005", DATED 3/21/05.
2. BASE MAP UPDATED FROM CADD FILE PREPARED BY WALTON
F. POPPELL, INC., LAND SURVEYORS, JOB No. 07-061, FIELD
SURVEYED ON 03/15/07 IN RELATION TO THE NATIONAL
GEODETIC VERTICAL DATUM OF 1988 (NAVD 88).
REFERENCE(S)
1. ALL UNITS REPORTED IN NANOGRAMS PER LITER (ng/L).
2. I - REPORTED VALUE IS BETWEEN THE LABORATORY METHOD
DETECTION LIMIT AND LABORATORY PRACTICAL
QUANTITATION LIMIT.
3. BOLD FONT INDICATES CONSTITUENT CONCENTRATION WAS
DETECTED ABOVE THE METHOD DETECTION LIMIT
4. PFOA - PERFLOURIDE-N-OCTANOIC ACID
5. PFOS - PERFLOUROOCTANESULFUNIC ACID
6. FT-BGS - FEET BELOW GROUND SURFACE
NOTE(S)
SW-10
JULY 2021
3.80 - 13.80
WELL NUMBER
DATE SAMPLED
SCREEN INTERVAL DEPTH (FT-BGS)
PFOS CONCENTRATION
PFOA CONCENTRATION
SUM OF PFOS AND PFOA
IW-00
JULY 2021
3.80 - 13.80
IW-1
JULY 2021
14.30 - 19.30
IW-15
JULY 2021
15.61 - 20.61
6.0 I
SW-15
JULY 2021
3.42 - 13.42
SW-1
SW-4
SW-10
SW-13
SW-14
SW-15
SW-16
SW-17
SW-6
SW-5
SW-9
SW-2
IW-1
IW-3
SW-3
IW-4
IW-6IW-10
IW-9
IW-15
IW-13
IW-12
IW-17
IW-5
IW-16
SW-7
IW-7
U
Ec ol og y*
H
EP
AC
O
T& D
N on
H az
S oi l - V
O C s pe r d ru m
$1
.0
$0 .0
T&
D N on H az M ud /w at er
VO
C s pe r d ru m
$1
.0
$0
.0
Fa ls e M ob iliz at io n (n o dr um fo un d)
$8
5.
$0 .0
PF
AS
P ro fil e Fe e (1 p er s ite
$3
.0
$3
.0
T& D
N on
H az
S oi l - P
FA
S/
PF
O
S pe r d ru m
$1
.0
$0 .0
T&
D N on H az M ud /w at er
-P
FA
S/
PF
O S pe r d ru m
$1
.0
$3
.0
D is po sa l N on H az S oi l -
V O
C s pe r d ru m
$1
.0
$0
.0
D is po sa l N on
H az
M ud
/w at er
VO
C s pe r d ru m
$1
.0
$0 .0
PF
AS
P ro fil e Fe e (1 p er s ite
$9 5.
$9
5.
D is po sa l N on
H az
S oi l - P
FA
S/
PF
O
S
$6
.0
$0 .0
D is po sa l
N on
H az
M ud
/w at er -P
FA
S/
PF
O
S
$6
.0
$1 ,3
.0
Ap pr ov al F ee (p er s ite
$7
.0
$7
.0
N on H az S ol ifi ca tio n W as te
P ro fil e fe e
$5
0.
$0 .0
N on H az S ol id s D is po sa l
(p er d ru m
$1
.0
$0
.0
N on
H az
S lu dg e
D is po sa l
$1
.0
$0 .0
PF
AS
W as te ga l d ru m e m el le
A L
$8
.0
$1
,6
.0
Tr uc k w ith li ft ga te a nd d riv er
$1
.0
$1
.0 no n ha z liq ui ds d is po sa l ( pe r d ru m
$1
.7
$0
.0 g al lo n re co nd iti on ed d ru m
$1
.6
$0 .0
LT
L fe es (l es s th an dr um s
$1
.0
$1
.0
En er gy s ec ur ity re co ve ry fe e
$2
.0
$2
.0
To ta l C os t $7
.0
$2
,1
.0
$2
,1
.0
N ot es
* T ra ns po rta tio n co st s w ill be c al cu la te d ba se d on p ic ku ps a t v ar io us s ite s an d w as te s tre am v ol um e
ID
W
S U
B C
O N
TR
AC
TO
R
C O
ST
E
ST
IM
AT
ES
F O
R P
FA
S
M
AT
ER
IA
L
Er w in
Su m m ar y of
ID
W
S ub co nt ra ct or s
C os ts
3_
6_
P
FA
S dr um s Pa ge o f 1
408 Ditmar Street Pensacola, FL 32503
To: Mr. Ralph Mongillo
WSP
9428 Baymeadows Road, Suite 400 Jacksonville, FL 32256
June 16, 2023
Re: Non-Hazardous Disposal of PFOS/PFAS Impacted Materials
Mr. Mongillo:
The price for the transportation and disposal (T&D) of non-hazardous soil, mud, and water is listed below:
For Non-Hazardous Chlorinated Solvent Impacted Materials:
Description Rate Unit T&D - Non-Haz Chlorinated Solvents Impacted Soil $ 125.00 Per Drum T&D - Non-Haz Chlorinated Solvents Impacted Mud/Water $ 125.00 Per Drum T&D - Non-Haz Chlorinated Solvents Impacted Water $ 95.00 Per Bucket
For Non-Hazardous PFAS/PFOS Impacted Materials:
Description Rate Unit Profile Fee (Charged once per site) $ 350.00 Per Site T&D - Non-Haz PFOS/PFAS Impacted Water (5-gallon bucket) $ 95.00 Per Bucket T&D - Non-Haz PFOS/PFAS Impacted Soil $ 195.00 Per Drum T&D - Non-Haz PFOS/PFAS Impacted Mud/Water $ 195.00 Per Drum
Please ensure that all drum lids are properly secured and that drums are on a level surface like the surrounding area (i.e., not on a pallet, etc.). A single False Mobilization fee will apply if our driver is not able to locate a drum on site or if we are unable to access the property due to a locked gate, etc. This quote is valid for 90 days.
Respectfully, Robert Donado Erwin Remediation, Inc.
Email: robert@erwinremediation.com p y