This is a Task Assignment (TA) document issued by the State of Florida Department of Environmental Protection (FDEP) to Golder Associates USA Inc. for groundwater monitoring services at the Clotheshanger Cleaners site in Tallahassee, Leon County, Florida. The Task Assignment is executed under Contract Number HW685 and is designated as TA DC005A. The project involves environmental remediation activities under Florida's Drycleaning Solvent Cleanup Program, with Ben Grubbs serving as the FDEP Project Manager and Matt Crews as the Contractor's Project Manager.

The scope of work consists of three subtasks: project management, annual groundwater monitoring of nine monitoring wells with chemical analysis for chlorinated volatile organic compounds, and preparation of a groundwater monitoring report with GIS data updates. The contract uses a fixed unit rate pricing structure with a total Task Assignment value of $8,821.91, broken into two invoicing milestones: $5,332.32 upon submittal and FDEP approval of field documentation and laboratory reports by May 23, 2022, and $3,489.59 upon submittal and FDEP approval of the annual groundwater monitoring report and GIS updates by June 30, 2022. The work encompasses 54 total labor hours across multiple staff categories, direct costs for laboratory analysis ($877.00), field equipment ($882.00), vehicle rental ($120.00), and investigation-derived waste disposal ($100.00 to Erwin Remediation). The original proposal cost of $9,037.50 was negotiated down to the final amount of $8,821.91, with all work scheduled for completion by August 31, 2022.

View the file

Other files

File Type Posted
CN-370000-HW685-BF01C.pdf PDF
CN-370000-HW685-BF05ACO2.pdf PDF
CN-370000-HW685-BF05ACO3.pdf PDF
CN-370000-HW685-BF06A.pdf PDF
CN-370000-HW685-BF1ACO1.pdf PDF
CN-370000-HW685-BF6ACO1.pdf PDF
CN-370000-HW685-BIL01C.pdf PDF
CN-370000-HW685-BIL01CO1.pdf PDF
CN-370000-HW685-BIL03A.pdf PDF
CN-370000-HW685-BIL2ACO1.pdf PDF
CN-370000-HW685-BIL2CCO1.pdf.crdownload CRDOWNLOAD file
CN-370000-HW685-DC001A.pdf PDF
CN-370000-HW685-DC002G.pdf PDF
CN-370000-HW685-DC003A.pdf PDF
CN-370000-HW685-DC005C.pdf PDF
CN-370000-HW685-DC006B.pdf PDF
CN-370000-HW685-DC006C.pdf PDF
CN-370000-HW685-DC007C.pdf PDF
CN-370000-HW685-DC008A.pdf PDF
CN-370000-HW685-DC009B.pdf PDF
CN-370000-HW685-DC010A.pdf PDF
CN-370000-HW685-DC011A.pdf PDF
CN-370000-HW685-DC012C.pdf PDF
CN-370000-HW685-DC013A.pdf PDF
CN-370000-HW685-DC013C.pdf PDF
CN-370000-HW685-DC015B.pdf PDF
CN-370000-HW685-DC015C.pdf PDF
CN-370000-HW685-DC016A.pdf PDF
CN-370000-HW685-DC018A.pdf PDF
CN-370000-HW685-DC019B.pdf PDF
CN-370000-HW685-DC01ACO6.pdf PDF
CN-370000-HW685-DC01ACO8.pdf PDF
CN-370000-HW685-DC01ACO9.pdf PDF
CN-370000-HW685-DC020B.pdf PDF
CN-370000-HW685-DC022A.pdf PDF
CN-370000-HW685-DC022B.pdf PDF
CN-370000-HW685-DC022D.pdf PDF
CN-370000-HW685-DC023B.pdf PDF
CN-370000-HW685-DC023C.pdf PDF
CN-370000-HW685-DC027B.pdf PDF
CN-370000-HW685-DC027C.pdf PDF
CN-370000-HW685-DC029B.pdf PDF
CN-370000-HW685-DC029C.pdf PDF
CN-370000-HW685-DC02CCO1.pdf PDF
CN-370000-HW685-DC02FCO1.pdf PDF
CN-370000-HW685-DC031A.pdf PDF
CN-370000-HW685-DC031C.pdf PDF
CN-370000-HW685-DC032B.pdf PDF
CN-370000-HW685-DC035A.pdf PDF
CN-370000-HW685-DC037A.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW685

DC005A Completion August 31, 2022

This Task Assignment authorizes Golder to conduct groundwater monitoring activities in accordance with the March 18, 2022, Scope of Work, Cost Estimate, and Bid Documentation.

Ben Grubbs 850-245-8992 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

Golder Associates USA Inc.

Golder Associates USA Inc.

Matt Crews 904-363-3430

ERIC_4874

1818 North Monroe Street, Tallahassee, Leon County

Clotheshanger Cleaners

✔ $ 8,821.91

$ 8,821.91

Scope of Work

Donald Miller

Principal

Donald Miller Digitally signed by Donald Miller Date: 2022.03.25 08:00:36 -04'00'

William E. Burns, Jr.

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2022.03.24 13:53:01 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Subtask 2: Groundwater Monitoring Field Documentation and Laboratory Report;

IDW Disposal Documentation 05/23/2022

Subtasks 1 & 3: Annual Groundwater Monitoring Report; ADaPT/GIS Update; Project Management 06/30/2022

Subtask 2: Submittal and FDEP approval of the Groundwater Monitoring Field Documentation and Laboratory Report; IDW Disposal Documentation $ 5,332.32

Subtasks 1 & 3: Submittal and FDEP approval of the Annual Groundwater Monitoring Report; ADaPT/GIS Update; Project Management $ 3,489.59

$ 8,821.91

HW685

DC005A

Printed on recycled paper.

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

To: HW685 Contract Negotiation File Clotheshanger Cleaners Tallahassee, Leon County

ERIC_4874

From: Ben Grubbs, Project Manager Date: March 24, 2022 Subject: Negotiation Summary

HW685 DC005A

This Task Assignment authorizes Golder to conduct groundwater monitoring activities in accordance with the March 18, 2022, Scope of Work, Cost Estimate, and Bid Documentation.

Subtask 1: Project Management An automatic calculation based upon total direct labor hours determines the labor hours within this subtask.

Subtask 2: Annual Groundwater Monitoring Golder will collect groundwater samples from monitoring wells MW004, MW006, MW015, MW017 – MW019, MW058, RW002, and RW012. Prior to sampling, depth-to-water will be measured. The wells will then be purged, and field parameters will be recorded. The groundwater samples will be collected using low flow sampling methods and analyzed for chlorinated volatile organic compounds (VOCs). Investigation-derived waste (IDW) will be temporarily stored in a 55-gallon drum. Golder requested bids for IDW drum treatment and disposal from Clark, Erwin, Whatever Waste, and M & D Industrial Services. Erwin was selected as the lowest responsive and responsible bidder.

Subtask 3: Reporting Golder will submit the Annual Groundwater Monitoring Report and ADaPT and GIS deliverables to FDEP.

Golder and the FDEP confirmed on March 18, 2022, that an Access Agreement with the current real property owner of the Clotheshanger Cleaners (ERIC_4874) site has been executed.

The original Task Assignment totaled $9,037.50 with 55 labor hours but after negotiations and corrections with contractor costs are reflected as below:

The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost for this Task Assignment is $8,821.91 with 54 labor hours.

MEMORANDUM

Clotheshanger Cleaners March 24, 2022 Page Two

Golder may invoice following the schedule established in the Deliverables and Invoice Schedule Attachment, which accompanies the Task Assignment Notification Form.

FDEP COST ESTIMATEContractor: Golder Associates USA Inc.

Date: 3/23/2022

Task #: DC005A SubTask 1 Project Management SubTask 6

Site: Clotheshanger Cleaners SubTask 2 Annual GW Monitoring SubTask 7

Activity/Phase: Assessment SubTask 3 Reporting SubTask 8

Project Manager: Ben Grubbs SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$51.23 Project Manager (RFM) 5 5.1 $0.00 Program Leader - X-14 0 0 0 0 0 0 0 0 0 0

$63.65 Practice Leader - X-13 (JCB) 2 0 2 0 0 0 0 0 0 0 $0.00 Senior Consultant - X-12 0 0 0 0 0 0 0 0 0 0

$51.23 Senior Sci/Eng - X-11 (RFM) 5 5 0 0 0 0 0 0 0 0 $45.42 Senior Project Sci/Eng - P-10 (BL) 3 0 3 0 0 0 0 0 0 0 $44.15 Project Sci/Eng - P-10 (JT) 2 0 2.0 0 0 0 0 0 0 0 $40.38 Staff Sci/Eng - P-9 (LC) 24 12 12 0 0 0 0 0 0 0 $34.06 Staff Sci/Eng - P-8 (EO) 11 11 0 0 0 0 0 0 0 0 $32.75 Staff Sci/Eng - P-8 (AS) 2 0 2 0 0 0 0 0 0 0

$0.00 Sci/Eng/Admin - P-7 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 54 5.1 28.0 21.0 0 0 0 0 0 0 0

Direct Labor $2,279.54 $262.25 $1,115.37 $901.92 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 172.50% $3,932.20 $452.38 $1,924.01 $1,555.81 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $6,211.74 $714.63 $3,039.38 $2,457.73 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF GOLDER Page 1

FDEP COST ESTIMATEContractor: Golder Associates USA Inc.

Date: 3/23/2022

Task #: DC005A SubTask 1 Project Management SubTask 6

Site: Clotheshanger Cleaners SubTask 2 Annual GW Monitoring SubTask 7

Activity/Phase: Assessment SubTask 3 Reporting SubTask 8

Project Manager: Ben Grubbs SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle Rental $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utility Location $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $10.00 $10.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $767.00 $767.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $877.00 $877.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $742.00 $742.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $882.00 $882.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $8,200.74 $714.63 $5,028.38 $2,457.73 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $621.17 $71.46 $303.94 $245.77 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $8,821.91 $786.09 $5,332.32 $2,703.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF GOLDER Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Clotheshanger Cleaners SUBTASK 2: Annual GW Monitoring

DATE: 3/23/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Sci/Eng (R Mongillo) 5

Staff Sci/Eng (L. Chappell) 12

Project Sci/Eng (E. Oien) 11

TOTAL LABOR 28

VEHICLE TYPE RATE UNIT USEAGE

Truck (GW sampling) $120.00 Per Day 1 $120.00

TOTAL VEHICLE $120.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Erwin IDW T&D - Liquids $100.00 Per Drum 1 $100.00

TOTAL $100.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

Chlorinated VOCs - EPA Method 8260B Total VOHs EPA Method 8260B $73.00 9 $657.00 Total VOCs EPA Method 8260B - IDW $110.00 1 $110.00 Sample Shipping Small $110.00 1 $110.00

TOTAL LAB $877.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Miscellaneous Expendables $40.00 Per Day 1 $40.00 Deep Groundwater Sampling Kit $415.00 Per Day 1 $415.00 Tubing, Poly HDPE $0.30 Per Foot 1000 $300.00 Tubing, Silicon 3/16 x 3/8 $3.00 Per Foot 9 $27.00 Drum, 55-gallon $100.00 Per Drum 1 $100.00

TOTAL EQUIPMENT $882.00

Mobilization 1 hour per day 1 day (1.0 hr). Field event preparation (1 hour). Measurement of water levels, instrument calibration, and sampling 9 wells (MW004, MW006, MW015, MW017, MW018, MW019, MW058, RW002, and RW012) and IDW management (10 hours).

Communication with RPO and verification of property ownership prior to site access, prepare and submit field notes, sample forms, laboratory report in an email deliverable to the DEP, and characterization and waste profile for transportation and disposal of IDW drum(s) (5 hours).

Mobilization 1 hour per day x 1 day (1.0 hr). Measurement of water levels, instrument calibration, and sampling sampling 9 wells (MW004, MW006, MW015, MW017, MW018, MW019, MW058, RW002, and RW012) and IDW management (10 hours).

FINAL --7/24/96

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Clotheshanger Cleaners SUBTASK 3: Reporting

DATE: 3/23/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Practice Leader (J. Brown) 2 Senior Sci/Eng (L Chappell) 12

Senior Project Sci/Eng (J. Thomas) 2

Senior Project Sci/Eng (B. Lucero) 3

Staff Sci/Eng (A. Strayer) 2

TOTAL LABOR 21

VEHICLE TYPE RATE UNIT USEAGE

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT $0.00

Reporting: Updating tables, document production, binding and shipping. Create pdf for

OCULUS.

Develop conclusions and recommendations and prepare final Annual Monitoring Report.

Data entry, prepare tables and figures, and draft Annual Monitoring Report Update FDEP GIS Tables, run data checker, create and edit error report, and annotate error report (9 data points x 8 min/point = 72 minutes). Submit DEPGIS tables; submit ADaPT

( )CADD Update Figures (one groundwater flow and two CVOC detections) .

FINAL --7/24/96

Golder Associates USA Inc.

9428 Baymeadows Road, Suite 400, Jacksonville, Florida, USA 32256

T: +1 904 363-3430 F: +1 904 363-3445 golder.com

March 18, 2022 Proposal No. 202208346

Mr. Ben Grubbs Florida Department of Environmental Protection Division of Waste Management Drycleaning Solvent Cleanup Program 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400

RE: COST PROPOSAL FOR CLOTHESHANGER CLEANERS

ANNUAL GROUNDWATER MONIORING

1816 NORTH MONROE STREET

TALLAHASSEE, LEON COUNTY, FLORIDA

FACILITY ID NUMBER: ERIC_4874

PROPOSED TASK ASSIGNMENT: HW685_DC005A

Dear Mr. Grubbs:

Golder Associates USA Inc. (Golder) is pleased to provide the Florida Department of Environmental Protection (DEP) with this cost proposal for groundwater monitoring at the Clotheshanger Cleaners site, located in Tallahassee, Leon County, Florida. This proposal includes a description of the proposed scope of services, level of effort (LOE) sheets for each subtask, and a Cost Estimate Form (CEF) that summarizes the costs of the proposed services. The scope of work is based on the recommendations accepted by the DEP in the July 21, 2021 electronic mail correspondence to Golder. The proposed scope of services is described below.

SUBTASK 1 – PROJECT MANAGEMENT

To facilitate project quality and satisfactory completion of the proposed scope of work, all aspects of this project will be overseen by an experienced project manager. The project manager will be responsible for the schedule, budget, invoicing, project activities, and communications with DEP and the field team. Project management will include coordination of field activities; resource allocation to confirm the work is conducted by qualified professionals in accordance with the project schedule; cost control and tracking of the budget status; and submittal of project invoices in accordance with DEP Drycleaning Solvent Cleanup Program requirements. The project manager will oversee the work so that it is conducted in a manner that is consistent with the requirements of the DEP-approved task assignment.

SUBTASK 2 – ANNUAL GROUNDWATER MONITORING

Golder will collect nine groundwater monitoring well samples (MW004, MW006, MW015, MW017, MW018, MW019, MW058, RW002, and RW012) and one waste characterization sample. The attached figures from the June 2021 annual groundwater monitoring report are showing the monitoring well locations, potentiometric map for in the

Mr. Ben Grubbs Proposal No. 202208346

Florida Department of Environmental Protection March 18, 2022 shallow surficial aquifer zone, PCE isoconcentration contour map, and source zone map for chlorinated volatile organic compound (VOC) results.

Prior to groundwater sampling, the depth to groundwater will be measured at accessible monitoring well locations (MW004, MW006, MW015, MW017, MW018, MW019, MW058, RW002, and RW012) using an electronic water level indicator to determine groundwater elevations and flow direction. During the sampling event, the locks and well caps will be inspected for damage or degradation and repaired or replaced as necessary. Groundwater samples will be collected from the wells in accordance with DEP Standard Operating Procedures (SOPs) for Field Activities (DEP-SOP-001/01) dated January 2017 (effective April 16, 2018). Prior to collecting the groundwater sample, each well will be purged and field parameters including temperature, pH, specific conductance, dissolved oxygen, turbidity, and oxidation-reduction potential will be monitored. Purge volumes and field parameters will be recorded on field data sheets, and the field monitoring equipment will be calibrated in accordance with the manufacturer’s recommended procedures.

Groundwater samples will be collected using low flow sampling methods. The groundwater samples will be placed in laboratory-supplied containers, labeled with a unique identification number attached to the outside of the sample container, preserved on ice in a laboratory-provided cooler at a maximum temperature of four degrees Celsius, and delivered to a Florida Department of Health and National Environmental Laboratory Accreditation Program-certified fixed-base laboratory along with the completed chain-of-custody documentation to be analyzed for chlorinated VOCs using EPA Method 8260B.

Golder will temporarily store the investigation derived waste (IDW) purge water generated from the groundwater sampling event in a 55-gallon steel drum(s). A waste characterization sample will be collected from the IDW drum(s) for analysis of total VOCs using EPA Method 8260. If the waste characterization sample is acceptable to the disposal subcontractor, the IDW drum(s) will be picked up and transported to a facility for proper disposal. A non-hazardous waste manifest will be provided by the disposal subcontractor upon delivery to the disposal facility.

Upon completion of Subtask 2, an e-mail deliverable will be submitted and include copies of the field data sheets, equipment calibration forms, field notes, laboratory analytical report, and laboratory chain-of-custody documentation.

SUBTASK 3 – REPORTING

The annual groundwater monitoring report will include a description of sampling procedures, evaluation of analytical results, comparison of current to historical data, tabulated summary of the current and historical analytical data, a site map showing the groundwater analytical results, water level elevation information in tables and figures, laboratory analytical data, conclusions, and recommendations. Golder will update the DEP GIS tables with the new water level data, field parameter measurements, and VOC data; run the DEP data checker on the completed tables;

and submit the updated tables and error report. Additionally, Golder will forward Automated Data Processing Tool (ADaPT) data deliverables provided by the laboratory for each groundwater sampling event.

HEALTH AND SAFETY

Golder will update the site-specific Health and Safety Plan for the field work. The work will be completed in accordance with Golder’s safety policies and procedures. At a minimum, Golder will wear safety glasses, high visibility safety vests, and steel-toed boots. A safety job briefing will be conducted prior to the start of work activities, and anytime the scope of work or site conditions change.

Mr. Ben Grubbs Proposal No. 202208346

Florida Department of Environmental Protection March 18, 2022

COST AND SCHEDULE

The estimated cost to complete the monitoring is $9,037.50. Golder will tentatively schedule the annual sampling event for late March or middle April 2022. The LOE/CEF cost sheets and subcontractor bids are included in Attachment A. The following table summarizes the proposed costs and deliverable schedule.

Task Proposed Cost Proposed Schedule/Deliverables

Subtask 1 – Project Management $810.89 July 31, 2022

Subtask 2 – Annual Groundwater Monitoring

$5,523.11 May 23, 2022 (Field Documentation and Laboratory Report)

Subtask 3 – Reporting $2,703.50 June 30, 2022 (Groundwater Monitoring Report, GIS Tables, ADaPT Deliverables)

Total/Completion Date $9,037.50 August 31, 2022

Please be aware that Golder has been acquired by and is now a Member of the WSP family of companies. Golder remains as a legal entity and is the proposed contracting entity for this proposal. We are in the process of integrating the resources of our companies. Correspondence for this proposal should continue to be addressed to the undersigned.

Golder appreciates the opportunity to provide services under the Drycleaning Solvent Cleanup Program. Should you require additional information or clarifications, please contact us at (904) 363-3430.

Sincerely, Golder Associates USA Inc.

Logan Chappell, PE Jesse C. Brown, PE Consultant Director, Environmental Engineer

LC/JCB/as

Attachments: Figure 3 Potentiometric Map (April 12, 2021)

Figure 4 Groundwater Analytical Results (April 2021) Figure 5 Source Area Groundwater Chlorinated VOC Analytical Results (April 2021)

Attachment A Level of Effort Sheets / Cost Estimate Form and Subcontractor Bids

G:\Projects\DEP-Drycleaning\Projects\Tallahassee\Clotheshanger - HW685\Proposal\HW685 Annual Groundwater Monioring Proposal - ERIC_4874.docx

MW004

MW014

MW015

MW016

MW017

MW018

MW020 MW019

RW004

RW002

RW005

RW006

RW007

RW008RW009RW010

RW012

RW001

VEW003

VEW002

VEW001

MW003

VEW005S

VEW007S

VEW010S

VEW006S

VEW004S

VEW005D

VEW007D

VEW010D

VEW006D

VEW004D

VEW003S

VEW003D

VEW009S

VEW009D

VEW008S

VEW008D

(154.92)

(155.86)

(155.65)

(148.00)

(159.74)

(168.55)

(152.99)

RW003

LEGEND

REFERENCE(S)

in

FDEP-DC021

Control No.

FDEP-DC021-K003

FIGURE

2021-04-19

BCL

JWS

RFM

JCB

CLOTHESHANGER DRYCLEANERS

TALLAHASSEE, LEON COUNTY, FLORIDA

FL. DEPT. OF ENVIRONMENTAL PROTECTION

POTENTIOMETRIC MAP

(APRIL 13, 2021)

TITLE

PROJECT NO. REV.

PROJECTCLIENT

CONSULTANT

PREPARED

DESIGNED

REVIEWED

APPROVED

YYYY-MM-DD

IF

T

H

IS

M

EA

SU

R

EM

EN

T D

O

ES

N O

T M

AT

C

H W

H

AT

IS

S

H O

W N

, T H

E

SH

EE

T

SI

ZE

H

AS

B

EE

N M

O D

IF

IE

D F

R O

M : A

N

SI

B

Pa th

\g ol de r.g ds

\c om pl ex da ta

\O ffi ce \J ac ks on vi lle \d ra fti ng \F ile \F

D

EP

\F D

EP

-D

C \D

C N o

C lo th es ha ng er

\K

A nn ua l G

W R pt \A ct iv e D ra w in gs

Fi le

N am e:

F

D

EP

-D C

1-

K0

.d w g

SCALE

0 10 20

FEET

1. SITE PLAN DEVELOPED FROM SITE PLAN BY HARDING ESE,

DATED OCTOBER 2002.

MONITORING WELL LOCATION

SOIL VAPOR WELL LOCATION

EXISTING RECOVERY WELL LOCATION

BUILDING

FORMER CLOTHESHANGER CLEANERS

VEW002

MW014

RW001

PROPERTY BOUNDARY

(159.37) GROUNDWATER ELEVATION - MARCH 2017

GROUNDWATER CONTOUR INTERVAL

(DASHED WHERE INFERRED)

ESTIMATED GROUNDWATER FLOW DIRECTION

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text

SPORTS & IMPORTS (USED CARS)

AutoCAD SHX Text

PAPA JOHN'S FORMERLY CLOTHESHANGER CLEANERS

AutoCAD SHX Text

SAN MIGUEL RESTAURANT

AutoCAD SHX Text

OPEN COURTYARD (DINING AREA)

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text

SEWER CLEANOUTS

AutoCAD SHX Text

GRASS

AutoCAD SHX Text

GRASS

AutoCAD SHX Text

ASPHALT PARKING AREA

AutoCAD SHX Text

ASPHALT

AutoCAD SHX Text

ASPHALT PARKING AREA

AutoCAD SHX Text

ESTIMATED SEWER LATERAL LOCATION

AutoCAD SHX Text

RETAINING WALL

AutoCAD SHX Text

25" WOOD RETAINING WALL

AutoCAD SHX Text

CURB

AutoCAD SHX Text

NORTH MONROE STREET

AutoCAD SHX Text

HYDRAULIC LIFT

AutoCAD SHX Text

5/8" CITY OF TALLAHASSEE MPE DISCHARGE FLOW METER IN 12" ROUND VAULT

AutoCAD SHX Text

4" SEWER CLEANOUT

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text

FORMER SVE EQUIPMENT COMPOUND

AutoCAD SHX Text V

VEW001

MW-U

MW017

MW019

MW006

MW022

MW007

MW012

MW015

MW020

PMW008

MW004

MW018

MW008

RW002

RW003

RW008

RW009

RW012

MW058

MW009

RW001

MW021

RW006

LEGEND

in

FDEP-DC021

Control No.

FDEP-DC021-K004

FIGURE

2021-04-27

BCL

JWS

RFM

JCB

GROUNDWATER PCE ANALYTICAL RESULTS

TITLE

PROJECT NO. REV.

PROJECTCLIENT

CONSULTANT

PREPARED

DESIGNED

REVIEWED

APPROVED

YYYY-MM-DD

IF

T

H

IS

M

EA

SU

R

EM

EN

T D

O

ES

N O

T M

AT

C

H W

H

AT

IS

S

H O

W N

, T H

E

SH

EE

T

SI

ZE

H

AS

B

EE

N M

O D

IF

IE

D F

R O

M : A

N

SI

B

Pa th

\g ol de r.g ds

\c om pl ex da ta

\O ffi ce \J ac ks on vi lle \d ra fti ng \F ile \F

D

EP

\F D

EP

-D

C \D

C N o

C lo th es ha ng er

\K

A nn ua l G

W R pt \A ct iv e D ra w in gs

Fi le

N am e:

F

D

EP

-D C

1-

K0

.d

0 100 200

FEET

1. SITE PLAN DEVELOPED FROM SITE PLAN BY HARDING ESE, DATED OCTOBER

2002.

MONITORING WELL LOCATION

SOIL VAPOR WELL LOCATION

EXISTING RECOVERY WELL LOCATION

BUILDING

VEW002

MW014

RW001

DATE SAMPLED

MW004

4/26/2012 3 4/9/2013 300

1.) ALL RESULTS ARE REPORTED IN MICROGRAMS PER LITER (µg/L).

2.) U - INDICATES THE COMPOUND WAS ANALYZED FOR BUT NOT DETECTED. THE

VALUE SHOWN IS THE METHOD DETECTION LIMIT.

3.) i - THE REPORTED VALUE IS BETWEEN THE LABORATORY METHOD DETECTION

LIMIT AND THE LABORATORY PRACTICAL QUANTITATION LIMIT.

4.) GCTL - GROUNDWATER CLEANUP TARGET LEVEL PER CHAPTER 62-777, TABLE I, OF

THE FLORIDA ADMINISTRATIVE CODE (FAC).

5.) NADC - NATURAL ATTENUATION DEFAULT CONCENTRATION PER CHAPTER 62-777,

TABLE V, OF THE FAC.

6.) BOLD/SHADED CONCENTRATIONS EXCEEDS GROUNDWATER CLEANUP TARGET

LEVEL (GCTL).

7.) ISOCONCENTRATION CONTOURS DASHED WHERE INFERRED.

8.) V - INDICATES ANALYTE WAS DETECTED IN BOTH THE SAMPLE AND ASSOCIATED

METHOD BLANK.

9.) BDL - BELOW LABORATORY METHOD DETECTION LIMIT.

10.) PCE - TETRACHLOROETHENE.

ESTIMATED EXTENT OF VOLATILE ORGANIC COMPOUNDS

(VOCs) EXCEEDING GCTLs

ESTIMATED EXTENT OF VOLATILE ORGANIC COMPOUNDS

EXCEEDING NADCs

PMW008

5/12/2005 1.7 6/3/2009 5.1 4/26/2010 0.42 i 4/28/2011 0.56 i 3/25/2014 0.75 i 3/12/2015 0.74 U

RW003

1/21/2003 2,040 8/13/2003 48 3/31/2004 940

MW020

2/13/2001 1,930 2/20/2001 1,190 5/12/2005 1,600 2/5/2008 3,100

RW008

4/2/2004 46

9/24/2004 70 3/17/2005 20 3/28/2006 30 3/12/2015 53 3/28/2017 30

RW009

1/21/2003 69.2 9/16/2003 48 4/2/2004 13

MW004

3/1/2000 1,360

5/12/2005 1.0 3/13/2015 49 3/31/2016 25 3/28/2017 13 4/12/2018 4.9 4/17/2019 28 4/2/2020 30 4/13/2021 45

RW012

4/2/2004 88

3/17/2005 1,800 3/28/2006 250

10/27/2006 380 V 3/28/2017 270 4/12/2018 500 4/17/2019 650 4/2/2020 650 4/13/2021 730

VEW001

10/8/2002 575 1/21/2003 2,150 3/17/2005 4,700 3/28/2006 3,400 3/12/2015 370

MW007

5/6/1997 1 U 3/1/2000 1 U

1/30/2002 1 U 5/12/2005 0.18 U

MW012

5/6/1997 1 U

5/12/2005 0.18 U

MW015

4/26/2010 230 4/28/2011 53 4/26/2012 5.9 4/9/2013 9.6

3/25/2014 7.9 3/12/2015 6.0 3/31/2016 11 3/28/2017 6.9 4/12/2018 9.9 4/17/2019 9.2 4/2/2020 8.4 4/13/2021 13

RW001

4/2/2004 1,100

3/17/2005 3,400 3/28/2006 790

10/27/20061,100 V 3/12/2015 820

RW002

9/24/2004 860 3/28/2006 1,100

10/27/2006 800 V 2/5/2008 1,200

3/12/2015 1,100 3/31/2016 870 3/28/2017 700 4/13/2018 870 4/17/2019 890 4/2/2020 870 4/13/2021 740

MW018

4/26/2010 1,500 4/28/2011 1,500 4/26/2012 1,200 4/9/2013 1,400

3/25/2014 840 3/12/2015 1,800 3/31/2016 260 3/28/2017 790 4/13/2018 910 4/17/2019 2,600 4/2/2020 2,300 4/13/2021 1,600

MW009

6/3/2009 15 4/28/2011 7.4 4/26/2012 13 5/8/2013 5.8 3/25/2014 15 3/13/2015 0.74 U 3/31/2016 6.5

MW006

4/30/1997 1 U 3/1/2000 1 U

5/12/2005 0.18 U 2/6/2008 2.4

3/31/2016 1.7 3/28/2017 2.9 4/12/2018 0.89 I 4/17/2019 210 4/2/2020 1.9

4/13/2021 0.90 I

MW022

8/27/2000 BDL

5/12/2005 0.18 UMW-U

4/26/2012 1.1 4/9/2013 2.0

MW017

3/12/2015 710 3/31/2016 840 3/28/2017 1,200 4/13/2018 800 4/17/2019 1,300 4/2/2020 1,400 4/13/2021 1,400

MW019

3/12/2015 1,300 4/13/2018 2,000 4/17/2019 1,600 4/2/2020 2,400 4/13/2021 2,300

NOTE(S)

REFERENCE(S)

MW058

3/28/2017 0.50 U 4/12/2018 7.3 4/17/2019 5.8 4/2/2020 2.3 4/13/2021 6.6

ABANDONED WELLS

TETRACHLOROETHENE (PCE)

CONCENTRATION (µg/L) AND GCTL

PCE CONCENTRATION (µg/L) AND NADC

WELL ID

RW006

4/17/2019 99

AutoCAD SHX Text Retaining wall

AutoCAD SHX Text KAYO Station

AutoCAD SHX Text Former

AutoCAD SHX Text Wok'n Roll

AutoCAD SHX Text Restaurant

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text

SPORTS & IMPORTS (USED CARS)

AutoCAD SHX Text

PAPA JOHN'S FORMERLY CLOTHESHANGER CLEANERS

AutoCAD SHX Text

SAN MIGUEL RESTAURANT

AutoCAD SHX Text

OPEN COURTYARD (DINING AREA)

AutoCAD SHX Text

SEWER CLEANOUTS

AutoCAD SHX Text

GRASS

AutoCAD SHX Text

GRASS

AutoCAD SHX Text

ASPHALT PARKING AREA

AutoCAD SHX Text

ASPHALT

AutoCAD SHX Text

ASPHALT PARKING AREA

AutoCAD SHX Text

ESTIMATED SEWER LATERAL LOCATION

AutoCAD SHX Text

RETAINING WALL

AutoCAD SHX Text

MPE EQUIPMENT COMPOUND

AutoCAD SHX Text

25" WOOD RETAINING WALL

AutoCAD SHX Text

CURB

AutoCAD SHX Text

ASPHALT

AutoCAD SHX Text

NORTH MONROE STREET

AutoCAD SHX Text

HYDRAULIC LIFT

AutoCAD SHX Text V

MW004

MW014

MW015

MW016

MW017

MW018

MW020 MW019

RW004

RW002

RW005

RW003

RW006

RW007

RW008RW009RW010

RW012

VEW003

VEW002

VEW001

VEW003

VEW001

VEW003

VEW001

VEW005S

VEW007S

VEW010S

VEW006S

VEW004S

VEW005D

VEW007D

VEW010D

VEW006D

VEW004D

VEW003S

VEW003D

VEW009S

VEW009D

VEW008S

VEW008D

RW001

DRY

in

FDEP-DC021

Control No.

FDEP-DC021-K005

FIGURE

2021-04-27

BCL

JWS

RFM

JCB

SOURCE AREA GROUNDWATER CHLORINATED VOC

ANALYTICAL RESULTS

TITLE

PROJECT NO. REV.

PROJECTCLIENT

CONSULTANT

PREPARED

DESIGNED

REVIEWED

APPROVED

YYYY-MM-DD

IF

T

H

IS

M

EA

SU

R

EM

EN

T D

O

ES

N O

T M

AT

C

H W

H

AT

IS

S

H O

W N

, T H

E

SH

EE

T

SI

ZE

H

AS

B

EE

N M

O D

IF

IE

D F

R O

M : A

N

SI

B

Pa th

\g ol de r.g ds

\c om pl ex da ta

\O ffi ce \J ac ks on vi lle \d ra fti ng \F ile \F

D

EP

\F D

EP

-D

C \D

C N o

C lo th es ha ng er

\K

A nn ua l G

W R pt \A ct iv e D ra w in gs

Fi le

N am e:

F

D

EP

-D C

1-

K0

.d

0 10 20

FEET

MONITORING WELL LOCATION

SOIL VAPOR WELL LOCATION

EXISTING RECOVERY WELL LOCATION

BUILDING

FORMER CLOTHESHANGER CLEANERS

VEW002

MW014

RW001

PROPERTY BOUNDARY

TETRACHLOROETHENE (PCE)

TRICHLOROETHENE (TCE)

cis-1,2-DICHLOROETHENE

VINYL CHLORIDE

SAMPLE DATE

WELL ID

MW015

4/12/18 4/17/19 4/2/20 4/13/21

9.9 9.2 8.4 13

0.61 U 0.61 U 0.61 U 0.25 U

0.32 U 0.32 U 0.32 U 0.50 U

0.26 U 0.26 U 0.26 U 0.25 U

MW018

4/13/18 4/17/19 4/2/20 4/13/21

910 2,600 2,300 1,600

3.1 U 6.1 U 0.76 I 5.0 U

1.6 U 3.2 U 0.24 U 10 U

1.3 U 2.6 U 0.20 U 5.0 U

RW002

4/13/18 4/17/19 4/2/20 4/13/21

870 890 870 740

3.1 U 1.2 U 0.89 I 2.5 U

3.7 I 9.6 7.5 31

1.3 U 0.51 U 0.20 U 2.5 U

RW001

3/28/06 10/27/06 3/12/15 790 1,100 V 820

0.30 I 3.3 U 4.8 U

0.18 U 4.5 U 4.1 U

0.29 U 2.8 U 5.0 U

RW012

4/12/18 4/17/19 4/2/20 4/13/21 500 650 650 730

1.2 U 1.2 U 0.45 I 2.5 U

0.65 U 0.65 U 0.24 U 5.0 U

0.51 U 0.51 U 0.20 U 2.5 U

VEW001

3/28/06 3/12/15 3,400 370

11 U 2.4 U 18 U 2.1 U 29 U 2.5 U

RW008

3/28/06 3/12/15 3/28/17

30 53 30

0.34 I 0.48 U 0.61 U

0.18 U 0.41 U 0.65 U

0.29 U 0.50 U 0.71 U

MW020

5/12/05 2/5/08 1,600 3,100

BDL 2.6 U

BDL 9.0 U

BDL 2.9 U

MW004

4/9/13

GCTLs

1.) ALL RESULTS ARE REPORTED IN MICROGRAMS PER LITER (µg/L).

2.) U - INDICATES THE COMPOUND WAS ANALYZED FOR BUT NOT DETECTED.

THE VALUE SHOWN IS THE METHOD DETECTION LIMIT.

3.) I - THE REPORTED VALUE IS BETWEEN THE LABORATORY METHOD

DETECTION LIMIT AND THE LABORATORY PRACTICAL QUANTITATION LIMIT.

4.) V - INDICATES ANALYTE WAS DETECTED IN BOTH THE SAMPLE AND

ASSOCIATED METHOD BLANK.

5.) BOLD/SHADED CONCENTRATIONS EXCEEDS GROUNDWATER CLEANUP

TARGET LEVEL (GCTL).

6.) VOC - VOLATILE ORGANIC COMPOUNDS.

MW004

4/12/18 4/17/19 4/2/20 4/13/21

4.9 28 30 45

0.61 U 0.61 U 0.29 U 0.25 U

0.95 I 1.1 0.54 I 0.50 U

0.26 U 0.26 U 0.20 U 0.25 U

MW017

4/13/18 4/17/19 4/2/20 4/13/21

800 1,300 1,400 1,400

1.2 U 3.1 U 0.86 I 2.5 U

0.65 U 9.3 0.43 I 5.0 U

0.51 U 1.3 U 0.20 U 2.5 U

MW019

4/13/18 4/17/19 4/2/20 4/13/21 2,0001,6002,400 2,300

6.1 U 6.1 U 0.56 I 5.0 U

3.2 U 14 0.24 U 10 U

2.6 U 2.6 U 0.20 U 5.0 U

NOTE(S)

LEGEND

REFERENCE(S)

1. SITE PLAN DEVELOPED FROM SITE PLAN BY HARDING ESE, DATED

OCTOBER 2002.

RW001 ABANDONED WELL

RW006

4/17/19

0.61 U

0.32 U

0.26 U

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text B

AutoCAD SHX Text

SPORTS & IMPORTS (USED CARS)

AutoCAD SHX Text

PAPA JOHN'S FORMERLY CLOTHESHANGER CLEANERS

AutoCAD SHX Text

SAN MIGUEL RESTAURANT

AutoCAD SHX Text

OPEN COURTYARD (DINING AREA)

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text

SEWER CLEANOUTS

AutoCAD SHX Text

GRASS

AutoCAD SHX Text

GRASS

AutoCAD SHX Text

ASPHALT PARKING AREA

AutoCAD SHX Text

ASPHALT

AutoCAD SHX Text

ASPHALT PARKING AREA

AutoCAD SHX Text

ESTIMATED SEWER LATERAL LOCATION

AutoCAD SHX Text

RETAINING WALL

AutoCAD SHX Text

25" WOOD RETAINING WALL

AutoCAD SHX Text

CURB

AutoCAD SHX Text

NORTH MONROE STREET

AutoCAD SHX Text

HYDRAULIC LIFT

AutoCAD SHX Text

5/8" CITY OF TALLAHASSEE MPE DISCHARGE FLOW METER IN 12" ROUND VAULT

AutoCAD SHX Text

4" SEWER CLEANOUT

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text V

AutoCAD SHX Text

FORMER SVE EQUIPMENT COMPOUND

From: Fred Portofe To: Mongillo, Ralph Cc: Madison Rogers; Roger Pragle; Crews, Matt Subject: RE: Investigative Derived Waste Drum Costs for Transportation and Disposal at a Regulated Facility Date: Wednesday, March 9, 2022 9:33:38 AM Attachments: F0152F28A2B5418EBC7A4FD870EC8D28.png

AD282F6C3391468088CDA42829B8E703.png A719914B10184314957B0CA910CA8D14.png F1DF3C4322764E8A9076F1ADFF76864A.png 3409DF389C3B4156BA232DDC85C60E09.png

EXTERNAL EMAIL

EXTERNAL EMAIL - We could not verify the authenticity of this message. Please be cautious when clicking on links or opening attachments.

Ralph

We are not going to provide annual Pricing for the Statewide Contract . After reviewing the scope with my partners and the variability with respect to disposal costing and ever changing fuel costs, we feel we can not bid this work given the current uncertainty in the market. We would be please to bid this work on a casa by case basis.

Fred G. Portofe, PG President of Environmental Services (Professional Geologist in FL, GA, AL, MS, TX, SC, NC, TN, IN, LA, WI and AK) M & D Industrial Services, LLC 5896 Azalea Street Port Orange, Florida 32127 Email: Fportofe@mdindustrialservices.com Website: mdindustrialservices.com Cell: 813-951-1012 Emergencies: 888-307-2790

Sent from Mail for Windows

From: Mongillo, Ralph Sent: Tuesday, March 8, 2022 12:46 PM To: Fred Portofe Cc: Madison Rogers; Roger Pragle; Eddy Mendoza; Crews, Matt mailto:fportofe@mdindustrialservices.com mailto:ralph.mongillo@wsp.com mailto:mrogers@mdindustrialservices.com mailto:rpragle@mdindustrialservices.com mailto:matt.crews@wsp.com mailto:Fportofe@mdindustrialservices.com https://nam10.safelinks.protection.outlook.com/?url=http%3A%2F%2Fmdindustrialservices.com%2F&data=04%7C01%7Cmculbreth%40ectinc.com%7Cbfdc4a6d2ce945e1eaf008d9dcf8eabf%7C911eb1cc54d34d8ca5773bf3ccc8105c%7C0%7C0%7C637783784008834159%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C2000&sdata=ntkZP1OGe7McYRA722JXtcGwkbgN9EEhQtSgBSKqC3E%3D&reserved=0 https://go.microsoft.com/fwlink/?LinkId=550986 mailto:Ralph_Mongillo@golder.com mailto:fportofe@mdindustrialservices.com mailto:mrogers@mdindustrialservices.com mailto:rpragle@mdindustrialservices.com mailto:emendoza@mdindustrialservices.com mailto:Matt_Crews@golder.com