Atch 5-AF form 66 VLSB 24-0019 V2.xlsx
XLSX spreadsheet 27 KB Posted
- Attached to
- Family Camp RV Parking Expansion
- Solicitation number
- FA480325B001
About this file
This is an AF Form 66 (Schedule of Material Submittals) for the FAMCAMP Expansion project at Shaw Air Force Base, solicitation number VLSB 24-0019. The form outlines required contractor submittals including construction schedule (due within 1 week of Notice to Proceed), light pole specifications, light specifications, Wi-Fi pole specifications, 95% drawings, as-built drawings, asphalt mix design (due at time of paving), and soil compaction test results (required prior to paving).
The related solicitation (FA480325B001) is a Non-Appropriated Fund Instrumentality (NAFI) requirement to add 14 recreational vehicle parking spaces at Shaw AFB Family Camp Site. The project includes asphalt drive, electrical systems, concrete RV pads, water, sewer installations with an estimated construction magnitude of $250,000-$500,000. A site visit was conducted on February 7, 2025. Offers are due April 7, 2025 at 2:00 PM EST, with bid opening scheduled for April 9, 2025 at 10:00 AM EST.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NCOC-A
| PROJECT NUMBER : | PROJECT TITLE: | SOLICITATION/CONTRACT NO.: | |
| SCHEDULE OF MATERIAL SUBMITTALS | VLSB 24-0019 | FAMCAMP Expansion | |
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR |
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURER'S RECOMMENDATIONS | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | OTHER | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | |
| APPROVED | DIS- APPROVED | |||||||||||||||||||
| 1 | Construction Schedule | x | Within 1 week of NTP | |||||||||||||||||
| 2 | Light Pole Specs | x | x | Before ordering | ||||||||||||||||
| 3 | Light Specs | x | Before ordering | |||||||||||||||||
| 4 | Wi-Fi Pole Specs | x | x | Before ordering | ||||||||||||||||
| 5 | 95% Drawings | |||||||||||||||||||
| 6 | As-Built Drawings | |||||||||||||||||||
| 7 | Asphalt Mix Design | x | At time of paving | |||||||||||||||||
| 8 | Soil Compaction Test Results | x | Prior to paving | |||||||||||||||||
| 9 | ||||||||||||||||||||
| 10 | ||||||||||||||||||||
| 11 | ||||||||||||||||||||
| 12 | ||||||||||||||||||||
| 13 | ||||||||||||||||||||
| 14 | ||||||||||||||||||||
| 15 | ||||||||||||||||||||
| 16 | ||||||||||||||||||||
| 17 | ||||||||||||||||||||
| 18 | ||||||||||||||||||||
| 19 |
Solicitation No. F38604-99-1480 Attachment 6
AF FORM 66
(Computer Generated) PAGE &P of &N
File details come from the government source that posted it. Updated .