This is a Facility Maintenance Plan (FMP) template spreadsheet containing detailed maintenance requirements and schedules for fuel facilities at Goodfellow Air Force Base in San Angelo, TX. The template includes multiple tabs for tracking facility information, maintenance tasks, filter separator schedules, and component identifiers.

The FMP template provides comprehensive guidance for contractor personnel in the operation, inspection, and maintenance of permanently installed fuel facilities, covering components like above/underground storage tanks, filter separators, valves, meters, pumps, monitoring equipment, and fire fighting systems. It includes detailed maintenance schedules and requirements for specific equipment at the facility, such as air compressors, breakaways, canopies, dispensers, and emergency equipment. The template requires tracking of unique component identifiers, maintenance frequencies, manufacturer requirements, operator requirements, and system availability impacts. This appears to be version 2.2 of a standardized template rather than a completed maintenance plan for the specific facility.

View the file

Other files

File Type Posted
Sources Sought FUELS - Programmatic Rev1 7 May 25.docx DOCX document
3.4 Appendix B - Attachment 4 - SO Tracker-20210628.xlsx XLSX spreadsheet
6.0 - Appendix E ISR 15-Bulk_Fuel_Facilities FY25.xlsx XLSX spreadsheet
2.0 Appendix A RM_SO Process_20241220_PgM Reviewed Incorporated.docx DOCX document
3.1 Appendix B - Attachment 1 - Three Week Look Ahead_20230420.xlsx XLSX spreadsheet
3.2 Appendix B - Attachment 2 - Monthly Report Format 20240910.docx DOCX document
2.2 Appendix A - Attachment 2 Contractor Travel Expense Report_20240910.xlsx XLSX spreadsheet
9.0 Appendix H - Minor Repairs Incidental to Maintenance Activities POJ 20231009.xlsx XLSX spreadsheet
7.0 CUID - v2.1.pdf PDF
8.0 Appendix G_UFC 3-460-03 Maintenance Table- v4.3.pdf PDF
6.0 Appendix E ISR 14_operational_fuel_facilities FY25.xlsx XLSX spreadsheet
3.0 Appendix B Reporting Requirements_20240910.docx DOCX document
4.0 Appendix C Task Order Specifications_202401216.docx DOCX document
5.0 Appendix D Antiterrorism and OPSEC 20230206.docx DOCX document
PWS LEX FMP Template - v2.2.xlsx XLSX spreadsheet
PWS VNC FMP Template - v2.2.xlsx XLSX spreadsheet
PWS KEQ FMP Template - v2.2.xlsx XLSX spreadsheet
PWS CVZ FMP Template - v2.2.xlsx XLSX spreadsheet
PWS SHP FMP Template - v2.2.xlsx XLSX spreadsheet
PWS PBA FMP Template - v2.2.xlsx XLSX spreadsheet
PWS GRB FMP Template - v2.2.xlsx XLSX spreadsheet
PWS BRO FMP Template - v2.2.xlsx XLSX spreadsheet
PWS BAR FMP Template - v2.2.xlsx XLSX spreadsheet
PWS EFS FMP Template - v2.2.xlsx XLSX spreadsheet
PWS LAU FMP Template - v2.2.xlsx XLSX spreadsheet
PWS CHF FMP Template - v2.2.xlsx XLSX spreadsheet
PWS BEU FMP Template - v2.2.xlsx XLSX spreadsheet
PWS BLI FMP Template - v2.2.xlsx XLSX spreadsheet
PWS TKR FMP Template - v2.2.xlsx XLSX spreadsheet
PWS RBN FMP Template - v2.2.xlsx XLSX spreadsheet
PWS MAA FMP Template - v2.2.xlsx XLSX spreadsheet
PWS FSH FMP Template - v2.2.xlsx XLSX spreadsheet
PWS FSO FMP Template - v2.2.xlsx XLSX spreadsheet
PWS LRG FMP Template - v2.2.xlsx XLSX spreadsheet
PWS RRT FMP Template - v2.2.xlsx XLSX spreadsheet
PWS ALT FMP Template - v2.2.xlsx XLSX spreadsheet
PWS TUL FMP Template - v2.2.xlsx XLSX spreadsheet
PWS BL2 FMP Template - v2.2.xlsx XLSX spreadsheet
PWS ELL FMP Template - v2.2.xlsx XLSX spreadsheet
PWS WRF FMP Template - v2.2.xlsx XLSX spreadsheet
PWS LLD FMP Template - v2.2.xlsx XLSX spreadsheet
PWS DYE FMP Template - v2.2.xlsx XLSX spreadsheet
12.0 PWS Appendix K Real Property Data_20230420.xlsx XLSX spreadsheet
PWS RAN FMP Template - v2.2.xlsx XLSX spreadsheet
PWS FSM FMP Template - v2.2.xlsx XLSX spreadsheet
PWS _Fuels RMMR 20241220.docx DOCX document
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Administrative

LocationSite NameGoodfellow AFB Site #1
RPSUID2127
DLA Site CodeGDF
Hours of Operation24 Hours of Operation
Address351 Kearney Blvd, San Angelo, TX 76908
ContractContractor
Contract #
Local POCsQAE Name
QAE Phone
QAE Email
Alt QAE Name
Alt QAE Phone
Alt QAE Email
DLA/SCP POCsDLA PM Name
DLA PM Phone
DLA PM Email
SCP PM Name
SCP PM Phone
SCP PM Email
Contractor POCsContractor PM Name
Contractor PM Phone
Contractor PM Email
Contractor QC Name
Contractor QC Phone
Contractor QC Email
Contractor SM Name
Contractor SM Phone
Contractor SM Email
USACE POCsUSACE PM/COR Name
USACE PM/COR Phone
USACE PM/COR Email
USACE PE Name
USACE PE Phone
USACE PE Email
USACE KO Name
USACE KO Phone
USACE KO Email

Facility Maintenance Plan

FMP v2.2 &P of &N

Instructions:

This table shows the minimum information required. Additional details should be included based on site specific requirements. Additional POCs may be required.

General Facility Description Facility Description

Purpose:

This Facility Maintenance Plan provides guidance for Contractor personnel in the operation, inspection, and maintenance of permanently installed fuel facilities operated under the control of the Quality Assurance Evaluators. Federal, state, and local environmental laws and regulations shall be complied with if this plan is in conflict with them.

Scope:

The instructions prescribed by this plan outline general fuels maintenance information associated with fuel storage and dispensing systems and provides the minimum periodic contractor maintenance and inspection criteria requirements for the systems. This plan is to be used in conjunction with other existing directives governing fuel system operations and maintenance requirements. Conotractor will properly maintain and repair federally funded petroleum systems and facilities in order to provide compliance with applicable code, criteria, and federal, state, local and/or host nation regulations.

Fuels Facilities:

Organizational tanks, and associated dispensing equipment are maintained and operated by the owning organization. Fuel system maintenance contractors shall perform all maintenance and associated procurement actions on installed fuel systems.

Each installation under the Southwest Division contract are military land-based facilities who receive, store, distribute, and/or dispense liquid fuels.

Standard fuel system equipment includes:

a) Above Ground Sorage Stanks (AST), Underground Storage Tanks (UST)

b) Filter/separator and other filtration device maintenance access, particularly element removal.

c) Manual valves

d) Meter Registers, and Flow Meters.

e) Control Valves.

f) Pumps

g) Tank Monitoring Equipment and Instruments

h) Alarms

i) Fire Fighting Equipment

Site Specific General Information:

Facility Maintenance Plan

FMP v2.2 &P of &N

Instructions:

Include a general facility overview and description of each fuel system for the sites in accordance with UFC 3-460-01. Examples include: Bulk Storage Facilities, Aircraft Fueling Facilities, Marine and Dispensing Facilities, Ground Products Fueling Facilities, Alternate POL Facilities, and Support Facilities. Also include facility #s, facility names, fuel type, photos, and any other pertinent information.

Include Site Specific Conditions and Restrictions in this tab.

Communication Plan

Facility Maintenance Plan

FMP v2.2 &P of &N

Instructions:

Communication plan shall address in/out briefs, lines of communication, coordination for access, etc.

Safety

Facility Maintenance Plan

FMP v2.2 &P of &N

Instructions:

Site Specific Addendum and Activity Hazard Analysis, which are Attachments to the APP, specific to activities or tasks related to recurring maintenance for this site.

RM Schedule

Facility Maintenance Plan

FMP v2.2 &P of &N

Instructions:

Link RM schedule here

Task Matrix

Applicable Facility AssetsUFC System Level Maintenance FrequencySpecial Considerations
Real Property Unique Identifier
(RPUID)Real Property Facility #Real Property Facility NameOperational AreaComponent TypeBase Asset IDComponent Unique Identifier (CUID)MakeModelCapacity/SizeQSAUFC Section ReferenceAdditional Manufacturer RM RequirementsOperator/ equipment RequirementsSystem availabilityOther ContractComments
3427Service StationOperations BldgAir CompressorsAir CompressorQuincy300648 1N/AXX0Air CompressorsNo Additional Manufacturer RequirementsNo Operator/equipment RequirementsNo Mission Impact
3427Service StationDispensersBall ValvesBall Valve/AirlineConbracoApollo0.5 in.X006-6.2.4Check operation of gauge. Ensure gauge is indicating pressure of the system. Inspect liquid level, and clean exterior glass. Calibrate as required dependent on use.Monthly - Check operation of gauge. Ensure gauge is indicating pressure of the system.Partial System OOS
3427Service StationDispensersBall ValvesBall Valve/AirlineConbracoApollo0.5 in.X006-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator RequirementNo Mission Impact
3427Service StationOperations BldgBall ValvesBall ValveMCDWOG6000.5 in.X006-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator RequirementNo Mission Impact
3427Service StationOperations BldgBall ValvesBall ValveMCDWOG6001.0 in.X006-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator RequirementNo Mission Impact
3427Service StationDispensersBreakawaysMogas Dispenser 4 BreakawayHuskyUnmarked0.75 in.0007-4Inspect for expiration date. Inspect for loose connections and signs of damage.Daily - Inspect breakaways for loose connections and signs of damage to poppets. Ensure breakaways are clean and free of fuel.
Monthly - Inspect breakaway for an expiration date established by the manufacturer. Breakaways must be replaced before the indicated expiration date.No Mission Impact
3427Service StationDispensersBreakawaysDS2 Dispenser 3 BreakawayHuskyUnmarked0.75 in.0007-4Inspect for expiration date. Inspect for loose connections and signs of damage.Daily - Inspect breakaways for loose connections and signs of damage to poppets. Ensure breakaways are clean and free of fuel.
Monthly - Inspect breakaway for an expiration date established by the manufacturer. Breakaways must be replaced before the indicated expiration date.No Mission Impact
3427Service StationDispensersBreakawaysDS2 Dispenser 1 BreakawayHuskyUnmarked0.75 in.0007-4Inspect for expiration date. Inspect for loose connections and signs of damage.Daily - Inspect breakaways for loose connections and signs of damage to poppets. Ensure breakaways are clean and free of fuel.
Monthly - Inspect breakaway for an expiration date established by the manufacturer. Breakaways must be replaced before the indicated expiration date.No Mission Impact
3427Service StationDispensersBreakawaysMogas Dispenser 2 BreakawayHuskyUnmarked0.75 in.0007-4Inspect for expiration date. Inspect for loose connections and signs of damage.Daily - Inspect breakaways for loose connections and signs of damage to poppets. Ensure breakaways are clean and free of fuel.
Monthly - Inspect breakaway for an expiration date established by the manufacturer. Breakaways must be replaced before the indicated expiration date.No Mission Impact
3427Service StationDispensersCanopiesCanopyUnmarkedUnmarkedN/AXX011-2.2No Additional Manufacturer RequirementsNo Operator/equipment RequirementsNo Mission Impact
3427Service StationDispensersDispenser CabinetMogas Dispenser 4Wayne3/G7201D/29GHJ/HN/A00X7-7Inspect for damage, ensure door panels and locks are functional.Monthly - Inspect outside of cabinet and ensure it is free of damage. Inspect for fuel stains on the concrete island around the cabinet and on the outside of the cabinet. Ensure the cabinet is free of dirt and fuel. Open both sides of the cabinet and inspect the inside of the cabinet. Ensure the inside of the cabinet and all of the components inside the cabinet are clean and free of fuel.Partial System OOS
3427Service StationDispensersDispenser CabinetDS2 Dispenser 3Wayne3/G7201D/29GHJ/HN/A00X7-7Inspect for damage, ensure door panels and locks are functional.Monthly - Inspect outside of cabinet and ensure it is free of damage. Inspect for fuel stains on the concrete island around the cabinet and on the outside of the cabinet. Ensure the cabinet is free of dirt and fuel. Open both sides of the cabinet and inspect the inside of the cabinet. Ensure the inside of the cabinet and all of the components inside the cabinet are clean and free of fuel.Partial System OOS
3427Service StationDispensersDispenser CabinetMogas Dispenser 2Wayne3/G7201D/29GHJ/HN/A00X7-7Inspect for damage, ensure door panels and locks are functional.Monthly - Inspect outside of cabinet and ensure it is free of damage. Inspect for fuel stains on the concrete island around the cabinet and on the outside of the cabinet. Ensure the cabinet is free of dirt and fuel. Open both sides of the cabinet and inspect the inside of the cabinet. Ensure the inside of the cabinet and all of the components inside the cabinet are clean and free of fuel.Partial System OOS
3427Service StationDispensersDispenser CabinetDS2 Dispenser 1Wayne3/G7201D/29GHJ/HN/A00X7-7Inspect for damage, ensure door panels and locks are functional.Monthly - Inspect outside of cabinet and ensure it is free of damage. Inspect for fuel stains on the concrete island around the cabinet and on the outside of the cabinet. Ensure the cabinet is free of dirt and fuel. Open both sides of the cabinet and inspect the inside of the cabinet. Ensure the inside of the cabinet and all of the components inside the cabinet are clean and free of fuel.Partial System OOS
3427Service StationDispensersDispenser FiltersMogas Dispenser 4 FilterPetroClear40530P-AD0.05 in.00X7-9Check exterior for damageNo Operator RequirementPartial System OOS
3427Service StationDispensersDispenser FiltersDS2 Dispenser 1 FilterPetroClear40530P-AD0.05 in.00X7-9Check exterior for damageNo Operator RequirementPartial System OOS
3427Service StationDispensersDispenser FiltersDS2 Dispenser 3 FilterPetroClear40530P-AD0.05 in.00X7-9Check exterior for damageNo Operator RequirementPartial System OOS
3427Service StationDispensersDispenser FiltersMogas Dispenser 2 FilterPetroClear40530P-AD0.05 in.00X7-9Check exterior for damageNo Operator RequirementPartial System OOS
3427Service StationDispensersDispenser HosesMogas Dispenser 4 HoseFlex-ing559N0.75 in.0007-3Check for expiration date, and physical condition/damage leaks.Daily - Inspect dispenser hoses and hose whips for gouges, cuts, blisters, or outside wear that may lead to rupture during use. Replace hose or hose whips that show signs of wear. Inspect connection points of hoses and hose whips to the dispenser, breakaways, swivels, and the nozzle and ensure the connection points are clean and free of fuel.Partial System OOS
3427Service StationDispensersDispenser HosesDS2 Dispenser 3 HoseHuskyEagleFlex0.75 in.0007-3Check for expiration date, and physical condition/damage leaks.Daily - Inspect dispenser hoses and hose whips for gouges, cuts, blisters, or outside wear that may lead to rupture during use. Replace hose or hose whips that show signs of wear. Inspect connection points of hoses and hose whips to the dispenser, breakaways, swivels, and the nozzle and ensure the connection points are clean and free of fuel.Partial System OOS
3427Service StationDispensersDispenser HosesDS2 Dispenser 1 HoseHuskyEagleFlex0.75 in.0007-3Check for expiration date, and physical condition/damage leaks.Daily - Inspect dispenser hoses and hose whips for gouges, cuts, blisters, or outside wear that may lead to rupture during use. Replace hose or hose whips that show signs of wear. Inspect connection points of hoses and hose whips to the dispenser, breakaways, swivels, and the nozzle and ensure the connection points are clean and free of fuel.Partial System OOS
3427Service StationDispensersDispenser HosesMogas Dispenser 2 HoseFlex-Ing559N0.75 in.0007-3Check for expiration date, and physical condition/damage leaks.Daily - Inspect dispenser hoses and hose whips for gouges, cuts, blisters, or outside wear that may lead to rupture during use. Replace hose or hose whips that show signs of wear. Inspect connection points of hoses and hose whips to the dispenser, breakaways, swivels, and the nozzle and ensure the connection points are clean and free of fuel.Partial System OOS
3427Service StationDispensersDispenser MetersMogas Dispenser 4 MeterWayneDM10-15 GPM/SCFM00X7-8Inspect for damage, smooth operation and legibility.Monthly - Inspect meter and ensure meter is clean and free of fuel. Ensure calibration mechanism is sealed.Partial System OOS
3427Service StationDispensersDispenser MetersDS2 Dispenser 3 MeterWayneDM10-15 GPM/SCFM00X7-8Inspect for damage, smooth operation and legibility.Monthly - Inspect meter and ensure meter is clean and free of fuel. Ensure calibration mechanism is sealed.Partial System OOS
3427Service StationDispensersDispenser MetersMogas Dispenser 2 MeterWayneDM10-15 GPM/SCFM00X7-8Inspect for damage, smooth operation and legibility.Monthly - Inspect meter and ensure meter is clean and free of fuel. Ensure calibration mechanism is sealed.Partial System OOS
3427Service StationDispensersDispenser MetersDS2 Dispenser 1 MeterWayneDM10-15 GPM/SCFM00X7-8Inspect for damage, smooth operation and legibility.Monthly - Inspect meter and ensure meter is clean and free of fuel. Ensure calibration mechanism is sealed.Partial System OOS
3427Service StationDispensersDispenser NozzlesMogas Dispenser 4 NozzleHuskyUnmarked0.75 in.00X7-2Start flow into approved test container; place nozzle

in low clip position. Immerse nozzle spout tip in the gasoline in the approved test container. The nozzle tip must be at least three (3) inches from the bottom of the container

to prevent back-pressure in the spout. Nozzle must shut off five consective tests.Daily - Inspect dispenser nozzle spout. Ensure it is tight, round, has no cracks, or excessive wear. Inspect automatic shutoff hole. Ensure the hole is open and free of obstructions. Inspect nozzle hold-open latch. Ensure the latch is straight, moves freely, and the return spring operates correctly. Inspect body of nozzle. Ensure the body is in good condition and that the valve stem is clean and free of fuel. Inspect the nozzle to hose connection and ensure it is clean and free of fuel.
Monthly - Dispenser nozzle handles shall be inspected for an expiration date established by the manufacturer. Nozzles must be replaced before the indicated expiration date.Partial System OOS
3427Service StationDispensersDispenser NozzlesMogas Dispenser 2 NozzleHuskyUnmarked0.75 in.00X7-2Start flow into approved test container; place nozzle

in low clip position. Immerse nozzle spout tip in the gasoline in the approved test container. The nozzle tip must be at least three (3) inches from the bottom of the container

to prevent back-pressure in the spout. Nozzle must shut off five consective tests.Daily - Inspect dispenser nozzle spout. Ensure it is tight, round, has no cracks, or excessive wear. Inspect automatic shutoff hole. Ensure the hole is open and free of obstructions. Inspect nozzle hold-open latch. Ensure the latch is straight, moves freely, and the return spring operates correctly. Inspect body of nozzle. Ensure the body is in good condition and that the valve stem is clean and free of fuel. Inspect the nozzle to hose connection and ensure it is clean and free of fuel.
Monthly - Dispenser nozzle handles shall be inspected for an expiration date established by the manufacturer. Nozzles must be replaced before the indicated expiration date.Partial System OOS
3427Service StationDispensersDispenser NozzlesDS2 Dispenser 1 NozzleHuskyUnmarked0.75 in.00X7-2Start flow into approved test container; place nozzle

in low clip position. Immerse nozzle spout tip in the gasoline in the approved test container. The nozzle tip must be at least three (3) inches from the bottom of the container

to prevent back-pressure in the spout. Nozzle must shut off five consective tests.Daily - Inspect dispenser nozzle spout. Ensure it is tight, round, has no cracks, or excessive wear. Inspect automatic shutoff hole. Ensure the hole is open and free of obstructions. Inspect nozzle hold-open latch. Ensure the latch is straight, moves freely, and the return spring operates correctly. Inspect body of nozzle. Ensure the body is in good condition and that the valve stem is clean and free of fuel. Inspect the nozzle to hose connection and ensure it is clean and free of fuel.
Monthly - Dispenser nozzle handles shall be inspected for an expiration date established by the manufacturer. Nozzles must be replaced before the indicated expiration date.Partial System OOS
3427Service StationDispensersDispenser NozzlesDS2 Dispenser 3 NozzleHuskyUnmarked0.75 in.00X7-2Start flow into approved test container; place nozzle

in low clip position. Immerse nozzle spout tip in the gasoline in the approved test container. The nozzle tip must be at least three (3) inches from the bottom of the container

to prevent back-pressure in the spout. Nozzle must shut off five consective tests.Daily - Inspect dispenser nozzle spout. Ensure it is tight, round, has no cracks, or excessive wear. Inspect automatic shutoff hole. Ensure the hole is open and free of obstructions. Inspect nozzle hold-open latch. Ensure the latch is straight, moves freely, and the return spring operates correctly. Inspect body of nozzle. Ensure the body is in good condition and that the valve stem is clean and free of fuel. Inspect the nozzle to hose connection and ensure it is clean and free of fuel.
Monthly - Dispenser nozzle handles shall be inspected for an expiration date established by the manufacturer. Nozzles must be replaced before the indicated expiration date.Partial System OOS
3427Service StationDispensersDispenser SumpsDispenser SumpUnmarkedUnmarkedN/AXXX7-13Inspect sump pipe transition fittings for tears, cracks, or other signs of deterioration. Test sumps and ensure they are liquid tight by using vacuum, pressure, or liquid testing in accordance with 40 CFR 280, Section 43.Monthly - Inspect for signs of water, fuel, trash, and debris inside sumps. Remove and properly dispose of collected water, fuel, trash, and debris. Visually inspect penetration fittings. If fuel or water is detected investigate the source and repair.Partial System OOS
3427Service StationDispensersElectrical EquipmentEmergency Fuel ShutoffPower Integrity CorpESOCA/T/RDN/AXX09-1.2No Additional Manufacturer RequirementsNo Operator/equipment RequirementsNo Mission Impact
3427Service StationOperations BldgElectrical EquipmentEmergency Fuel Shutoff ButtonPower Integrity CorpESOCA/T/RDN/AXX09-1.2No Additional Manufacturer RequirementsNo Operator/equipment RequirementsNo Mission Impact
3427Service StationOperations BldgElectronic EquipmentAutomatic Tank GaugeRonanX76CTM-4XN/A00X9-1.9No Additional Manufacturer RequirementsNo Operator/equipment RequirementsNo Mission Impact
3427Service StationDispensersEmergency Eyewash/ShowersEmergency Eyewash/ShowerUnmarkedUnmarkedN/AXXX11-3Weekly - Equipment installed within 10 seconds from the hazard and on the same plane as the hazard Pathway is clear of obstructions Plumbed equipment activated to ensure compliant operation and to clear any sediment Self-contained equipment checked to determine if the flushing fluid needs to be changed or supplemented Equipment free of broken or missing parts Equipment protected against freezing User protected from scalding waterNo Operator RequirementNo Mission Impact
3427Service StationDispensersEmergency Shutoff ValvesShear Valve/Mogas Dispenser 4UnmarkedUnmarked1.5 in.00X7-12Inspect fusible link and ensure it is not obstructed. Ensure valve body is clean and free of fuel. Inspect mechanical links of the valve for correct operation. Conduct test of valve to ensure it operates correctly.Monthly - Inspect stabilizer bar to ensure that it is securely mounted below the base of the dispenser. Inspect the mounting bolts that secure the emergency shutoff valve to the stabilizer bar. Inspect fusible link and ensure it is not obstructed. Ensure valve body is clean and free of fuel.Partial System OOS
3427Service StationDispensersEmergency Shutoff ValvesMogas Dispenser 2 Shear ValveUnmarkedUnmarked1.5 in.00X7-12Inspect fusible link and ensure it is not obstructed. Ensure valve body is clean and free of fuel. Inspect mechanical links of the valve for correct operation. Conduct test of valve to ensure it operates correctly.Monthly - Inspect stabilizer bar to ensure that it is securely mounted below the base of the dispenser. Inspect the mounting bolts that secure the emergency shutoff valve to the stabilizer bar. Inspect fusible link and ensure it is not obstructed. Ensure valve body is clean and free of fuel.Partial System OOS
3427Service StationDispensersEmergency Shutoff ValvesDS2 Dispenser 1 Shear ValveUnmarkedUnmarked1.5 in.00X7-12Inspect fusible link and ensure it is not obstructed. Ensure valve body is clean and free of fuel. Inspect mechanical links of the valve for correct operation. Conduct test of valve to ensure it operates correctly.Monthly - Inspect stabilizer bar to ensure that it is securely mounted below the base of the dispenser. Inspect the mounting bolts that secure the emergency shutoff valve to the stabilizer bar. Inspect fusible link and ensure it is not obstructed. Ensure valve body is clean and free of fuel.Partial System OOS
3427Service StationDispensersEmergency Shutoff ValvesDS2 Dispenser 3 Shear ValveUnmarkedUnmarked1.5 in.00X7-12Inspect fusible link and ensure it is not obstructed. Ensure valve body is clean and free of fuel. Inspect mechanical links of the valve for correct operation. Conduct test of valve to ensure it operates correctly.Monthly - Inspect stabilizer bar to ensure that it is securely mounted below the base of the dispenser. Inspect the mounting bolts that secure the emergency shutoff valve to the stabilizer bar. Inspect fusible link and ensure it is not obstructed. Ensure valve body is clean and free of fuel.Partial System OOS
3427Service StationOperations BldgExternally Mounted Level AlarmsLevel AlarmVeeder RootUnmarkedN/A0008-9.9.11. Remove the installation crank and thumbscrew.

2. When a transmitter or other auxiliary equipment is to be installed, ensure the equipment hole size and bolt pattern matches the 2500 ATG. Remove and discard the cap and red fiber washers from the back cover. Each transmitter’s slotted coupling should properly engage the sprocket sheave auxiliary drive pin. Use the cap screws to attach the transmitter to the back cover. Refer to the transmitter documentation for detailed installation, configuration, and operation.

3. Replace the back cover and its gasket.

4. Torque the back cover bolts to 6 ft-lb. Do not over-torque!

5. Replace the bolts, gaskets, and covers on the elbows.

6. Close the tank manholes and inspection covers.

7. Check the operation of the auxiliary unit as appropriateDaily - Visually inspect the gauge to ensure the power is on, there are no warning alarms or lights and a liquid measurement is indicated and the tank level reading appears to be accurate.Partial System OOS
3427Service StationDispensersHose RetrieverMogas Dispenser 4 Hose RetractorCNIUnmarkedN/A0007-6No Additional Manufacturer RequirementsNo Operator/equipment RequirementsNo Mission Impact
3427Service StationDispensersHose RetrieverMogas Dispenser 2 RetractorCNIUnmarkedN/A0007-6No Additional Manufacturer RequirementsNo Operator/equipment RequirementsNo Mission Impact
3427Service StationDispensersHose RetrieverDS2 Dispenser 1 RetractorCNIUnmarkedN/A0007-6No Additional Manufacturer RequirementsNo Operator/equipment RequirementsNo Mission Impact
3427Service StationDispensersHose RetrieverDS2 Dispenser 3 RetractorCNIUnmarkedN/A0007-6No Additional Manufacturer RequirementsNo Operator/equipment RequirementsNo Mission Impact
3427Service StationDispensersLightingCanopy LightingUnmarkedUnmarkedN/AXXX9-1.8No Additional Manufacturer RequirementsNo Operator/equipment RequirementsNo Mission Impact
3427Service StationOperations BldgLightingArea LightingUnmarkedUnmarkedN/AXXX9-1.8No Additional Manufacturer RequirementsNo Operator/equipment RequirementsNo Mission Impact
3427Service StationDispensersLightning Protection SystemsCanopy Lightning ProtectionUnmarkedUnmarkedN/A00X9-4Measure the ground resistance with an instrument designed specifically to measure and document earth/ground resistance, soil resistivity, and current flow. Conduct the test by using the fall-of-potential method as described in the Institute of Electronic and Electrical Engineers (IEEE) Standard 81.If fall-of-potential tests cannot be performed, it is acceptable to measure resistance at each accessible ground rod using a clamp-on ground resistance tester. Provide the Engineer with written, certified test results for each testing location.No Operator RequirementNo Mission Impact
3427Service StationOperations BldgPressure and Pressure/Vacuum GaugesPressure GaugeUnmarkedUnmarked0.25 in. 0 - 300 PSIXXX6-7.1Check operation of gauge. Ensure gauge is indicating pressure of the system. Inspect liquid level, and clean exterior glass. Calibrate as required dependent on use.Monthly - Check operation of gauge. Ensure gauge is indicating pressure of the system.Partial System OOS
3427Service StationDispensersStatic Grounding SystemsGround ReelHannayHGR 50-50N/AXXX9-1.6.2Measure the ground resistance with an instrument designed specifically to measure and document earth/ground resistance, soil resistivity, and current flow. Conduct the test by using the fall-of-potential method as described in the Institute of Electronic and Electrical Engineers (IEEE) Standard 81.If fall-of-potential tests cannot be performed, it is acceptable to measure resistance at each accessible ground rod using a clamp-on ground resistance tester. Provide the Engineer with written, certified test results for each testing location.No Operator RequirementPartial System OOS
3427Service StationDispensersSwivelsMogas Dispenser 2 SwivelHuskyUnmarked0.75 in.0007-5Inspect for expiration date. Inspect for loose connections and signs of damage.Daily - Inspect swivel for loose connections and signs of damage. Ensure swivel rotates easily and is clean and free of fuel.
Monthly - Inspect swivel for expiration date established by manufacturer. Swivels must be replaced before the indicated expiration date.Partial System OOS
3427Service StationDispensersSwivelsMogas Dispenser 2 SwivelHuskyGNF6000.75 in.0007-5Inspect for expiration date. Inspect for loose connections and signs of damage.Daily - Inspect swivel for loose connections and signs of damage. Ensure swivel rotates easily and is clean and free of fuel.
Monthly - Inspect swivel for expiration date established by manufacturer. Swivels must be replaced before the indicated expiration date.Partial System OOS
3427Service StationDispensersSwivelsDS2 Dispenser 1 SwivelHuskyGKO1400.75 in.0007-5Inspect for expiration date. Inspect for loose connections and signs of damage.Daily - Inspect swivel for loose connections and signs of damage. Ensure swivel rotates easily and is clean and free of fuel.
Monthly - Inspect swivel for expiration date established by manufacturer. Swivels must be replaced before the indicated expiration date.Partial System OOS
3427Service StationDispensersSwivelsDS2 Dispenser 1 SwivelHuskyGKO1400.75 in.0007-5Inspect for expiration date. Inspect for loose connections and signs of damage.Daily - Inspect swivel for loose connections and signs of damage. Ensure swivel rotates easily and is clean and free of fuel.
Monthly - Inspect swivel for expiration date established by manufacturer. Swivels must be replaced before the indicated expiration date.Partial System OOS
3427Service StationDispensersSwivelsDS2 Dispenser 3 SwivelHuskyGKO1400.75 in.0007-5Inspect for expiration date. Inspect for loose connections and signs of damage.Daily - Inspect swivel for loose connections and signs of damage. Ensure swivel rotates easily and is clean and free of fuel.
Monthly - Inspect swivel for expiration date established by manufacturer. Swivels must be replaced before the indicated expiration date.Partial System OOS
3427Service StationDispensersSwivelsDS2 Dispenser 3 SwivelHuskyDCV1000.75 in.0007-5Inspect for expiration date. Inspect for loose connections and signs of damage.Daily - Inspect swivel for loose connections and signs of damage. Ensure swivel rotates easily and is clean and free of fuel.
Monthly - Inspect swivel for expiration date established by manufacturer. Swivels must be replaced before the indicated expiration date.Partial System OOS
3427Service StationDispensersSwivelsMogas Dispenser 4 SwivelHuskyGNG6300.75 in.0007-5Inspect for expiration date. Inspect for loose connections and signs of damage.Daily - Inspect swivel for loose connections and signs of damage. Ensure swivel rotates easily and is clean and free of fuel.
Monthly - Inspect swivel for expiration date established by manufacturer. Swivels must be replaced before the indicated expiration date.Partial System OOS
3427Service StationDispensersSwivelsMogas Dispenser 4 SwivelHuskyGNG6300.75 in.0007-5Inspect for expiration date. Inspect for loose connections and signs of damage.Daily - Inspect swivel for loose connections and signs of damage. Ensure swivel rotates easily and is clean and free of fuel.
Monthly - Inspect swivel for expiration date established by manufacturer. Swivels must be replaced before the indicated expiration date.Partial System OOS
3431Mogas TankMogas TankElectronic EquipmentATGRonanUnmarkedN/A00X9-1.9No Additional Manufacturer RequirementsNo Operator/equipment RequirementsNo Mission Impact
3431Mogas TankMogas TankUnderground Double-walled Shop-Fabricated TanksMogas TankUnmarkedUnmarked12,000 GallonsXXX8-5.4.2No Manufacturer Requirements AvailableMonthly - Monthly External Inspection (Identified as P in Table 8-4): Ensure all tank port covers are present, are in good condition, and seated firmly on the correct tank. Inspect tank stick gauge and ensure markings are legible and that the stick gauge is not warped or broken. Inspect tank for water using ATG or stick gauge with water-finding paste. Remove water found in tank. Open and inspect tank-top containment sumps and ensure no fuel or water is collected in the sumps. Check for and remove obstructions in tank fill pipe.Partial System OOS
3431Mogas TankMogas TankVertical Turbine/Submerged Turbine PumpsMogas PumpRed JacketIllegible0-15 GPM/SCFMXXX3-8.1.3During routine pump inspections only the easy to monitor factors such as pressure, temperature, vibration etc can be checKed. But during quarterly inspections, shaft alignment and oil levels should also be checked. Change Oil AnnuallyNo Operator RequirementsPartial System OOS
3432Diesel TankDiesel TankElectronic EquipmentATGRonanUnmarkedN/A00X9-1.9No Additional Manufacturer RequirementsNo Operator/equipment RequirementsNo Mission Impact
3432Diesel TankDiesel TankUnderground Double-walled Shop-Fabricated TanksDiesel TankUnmarkedUnmarked12,000 GallonsXXX8-5.4.2No Manufacturer Requirements AvailableMonthly - Monthly External Inspection (Identified as P in Table 8-4): Ensure all tank port covers are present, are in good condition, and seated firmly on the correct tank. Inspect tank stick gauge and ensure markings are legible and that the stick gauge is not warped or broken. Inspect tank for water using ATG or stick gauge with water-finding paste. Remove water found in tank. Open and inspect tank-top containment sumps and ensure no fuel or water is collected in the sumps. Check for and remove obstructions in tank fill pipe.Partial System OOS
3432Diesel TankDiesel TankVertical Turbine/Submerged Turbine PumpsDiesel PumpRed JacketIllegible0-15 GPM/SCFMXXX3-8.1.3During routine pump inspections only the easy to monitor factors such as pressure, temperature, vibration etc can be checKed. But during quarterly inspections, shaft alignment and oil levels should also be checked. Change Oil AnnuallyNo Operator RequirementsPartial System OOS

&"Times New Roman,Bold"&14Facility Maintenance Plan

FMP v2.2 2

Instructions:

1. Input all data as indicated on the sheet.

2. Additional documents referred to in the Special Considerations column shall be included as an appendix to this FMP.

3. The contractor shall generate a Component Unique Identifier (CUID) for each component utilizing the Component Acronym Sheet within this Work Book. The unique identifier must use the following:

Three letter Site Code - Facility # - Component Acronym - Sequential number Example: AAD-00063A-RCVL-0001

If component acronym is not listed, the contractor shall request an acronym be established through the HNC Project Manager and Project Engineer via email. Contractors may utilize other means of tracking/labeling assets such as QR codes in addition to the required CUID however, tracking/labeling must correlate with the CUID. This CUID shall be the standard for all DLA capitalized equipment. Base Asset ID if used by site shall be cross referenced with CUID appropriately.

4. Utilize the UFC Section Reference Work Category as noted on the Component Acronym Sheet.

5. Enter any applicable manufacturer requirements not stated in the UFC. References are acceptable with attachments.

6. Enter any applicable operator support or government owned equipment required to complete the RM task.

7. Enter impact on system availability by performing the RM task. This could include shutdown, lockout, or similar impacts.

8. Enter contract information for any other contract, contractor, or government personnel performing the applicable task. This is applicable to other Centrally Managed Programs, SRM, MILCON, or Public Works/Civil Engineering projects.

9. Print Hard Copies as 11x17.

FS-PF Schedule

FILTER SEPARATOR/PRE-FILTER MAINTENANCE SCHEDULES
Applicable Facility AssetsCoalescer/Separator InformationSpecial Considerations
Real Property Unique Identifier
(RPUID)Real Property Facility #Real Property Facility NameOperational AreaComponent TypeBase Asset IDComponent Unique Identifier (CUID)MakeModelCapacity (GPM)UFC Section ReferenceNumber of Coalescer CartridgesNumber of
Separator CartridgesCoalescer Cartridges
Model #Separator Cartridge
Model #Clean or Replace
Separator CartridgeGasket
Model #Date Last ReplacedReplacement Due DateOperator/Equipment RequirementsSystem AvailabilitySite Self Performs
(Y/N)Comments

&"Times New Roman,Bold"&14Facility Maintenance Plan

FMP v2.2 2

Instructions:

1. Input all data as indicated on the sheet.

2. Additional documents referred to in the Special Considerations column shall be included as an appendix to this FMP.

3. The contractor shall generate a Component Unique Identifier (CUID) for each component utilizing the Component Acronym Sheet within this Work Book. The unique identifier must use the following:

Three letter Site Code - Facility # - Component Acronym - Sequential number Example: AAD-00063A-RCVL-0001

If component acronym is not listed, the contractor shall request an acronym be established through the HNC Project Manager and Project Engineer via email. Contractors may utilize other means of tracking/labeling assets such as QR codes in addition to the required CUID however, tracking/labeling must correlate with the CUID. This CUID shall be the standard for all DLA capitalized equipment.

4. Utilize the UFC Section Reference Work Category as noted on the Component Acronym Sheet.

5. Enter any applicable manufacturer requirements not stated in the UFC. References are acceptable with attachments.

6. Enter any applicable operator support or government owned equipment required to complete the RM task.

7. Enter impact on system availability by performing the RM task. This could include shutdown, lockout, or similar impacts.

8. Filter Separators and Pre-Filters identified here shall also be provided in the Task Matrix Tab.

9. Print Hard Copies as 11x17.

Component Acronym

Component Unique Identifier:Site Code-Facility #-Component Acronym-Sequential #
Example:AAD-00063A-RCVL-0001
NOTE: If component acronym is not listed, the contractor shall request an acronym be established through the HNC Project Manager and Project Engineer via email. Contractors may utilize other means of tracking/labeling assets such as QR codes in addition to the required CUID however, tracking/labeling must correlate with the CUID. This CUID shall be the standard for all DLA capitalized equipment
DLA Work Type CategoryUFC Section Reference Work Category
(Revised per Change 1, 29 April 2021)Component Acronym
Air CompressorsAir CompressorsAIRC
AlarmsExternally Mounted Level Alarms (Section 8-9.9.1)EMLA
Internally Mounted Level Alarms (Section 8-9.9.3)IMLA
BollardBollardsBLRD
BuildingBuilding HVACBHVAC
Building Domestic Water SystemBWTR
Building Waste WaterBWSW
Building - LightingBLTG
Building - ArchitecturalBARCH
Building - Fire Sprinkler SystemBFIRE
Containment/JointsContainment Systems (General) (Section 8-10.1)CSGEN
Concrete and Cement Brick Dike/Berm Walls (Section 8-10.2.1)DKBW
Dike/Berm Floors (Section 8-10.2.2)DKBF
Earthen Dike Walls (Section 8-10.3)ETHDW
Self-Diking or Vaulted Tank Containment (Section 8-10.4)SDVTCS
Flexible Membrane Liners (Section 8-10.5)FXML
Fuel Truck and Rail Car Containment Areas (Section 11-1.1)FTKRCC
Remote Spill Containment (Section 11-1.2)RSCS
Piers and Wharves Fuel Containment Systems (Section 5-1.2) - TestingFPWCT
Fuel Pier/Wharf Containment (PWS Section 3)FPWC
Corrosion Control/CoatingsAboveground Piping and Equipment Coatings (Section 6-10.1)AGPCT
MiscellaneousMiscellaneous Deactivated Components (Section 12-5)MDEAC
Electrical/LightingLighting (Section 9-1.8)LIGHT
Electrical/PowerElectrical Equipment (Section 9-1.2)ELEQ
Power Cables (Section 9-1.3)PWRCBL
Motor Controls (Section 9-1.4)MTRCT
Panelboards (Section 9-1.5)PNLB
Electric Motors (Section 9-1.7)ELEMT
Electronic Equipment (9-1.9)ELTREQ
Card and Key Locks (Section 9-3)CKLK
Electrical/ProtectionPower Grounding Systems (Section 9-1.6.1)PWRGS
Static Grounding Systems (Section 9-1.6.2)STGS
Cathodic Protection (Section 9-2.1)CP
Lightning Surge Arresters (Section 9-2.2.1)LSAR
Lightning Protection Systems (Section 9-4)LPTS
Ground Verification System (Section 9-5)GRVS
Electronic Overfill Protection Systems (Section 9-6)EOPS
Eyewash/ShowerEmergency Eyewash/Showers (Section 11-3)EMEWSH
Fencing/
GatesFencingFENC
GatesGATE
FiltrationPre-Filters (Section 3-6.1)PFVSL
Filter Separators (Section 3-6.2)FLSP
Haypack Filters (Section 3-6.3)HPKF
Basket Strainers (Section 3-6.4)BSTR
Filter Separator Sump Heaters (Section 3-6.5)FSSH
Sidestream Filtration Systems (Section 8-9.11)SSFTS
Fire Suppression EquipmentFlame Arrestors (Section 8-9.5)FLMARR
Foam Fire Protection Systems (Section 8-9.15)FFPS
Fire Protection Systems - Wet PipeFPRS
Fuel LaboratoriesVentilation Hoods (Section 11-4.1)VENTHD
GaugesPressure and Pressure/Vacuum Gauges (Section 6-7.1)PVGA
Differential Pressure Gauges (Section 6-7.2)DPGA
Mechanical Tape Gauges (Section 8-9.7)MTGA
Mechanically Operated Tape Gauge (Section 8-9.8.1)MOTGA
Magnetostrictive Probes (Section 8-9.8.2)MRPRB
Servo Gauge (Section 8-9.8.3)SRVGA
GeneratorsBack-Up Power GeneratorsBGEN
Heating CoilsSteam Type Heating Coils (Section 8-9.16.1)STHC
Thermal Fluid Type Heating Coils (Section 8-9.16.2)TFTHC
Electric Rod Type Heating (Section 8-9.16.3)ERTH
HosesLoading Fuel Hoses (Section 3-9.1)LDHS
Offloading Fuel Hoses (Section 3-9.2)OLHS
Aircraft Fueling Hoses (Section 4-7.5)ACFHS
HydrazineHydrazine Charging Units (Section 10-3)HDZCU
InspectionsTrouble ShootTRBST
API 510 InspectionsAPI510
API 653 or STI InspectionAPI653
Coatings Condition SurveyCCS
Issue/Receive - GroundDispenser Nozzles (Section 7-2)DSNZ
Dispenser Hoses (Section 7-3)DSHS
Breakaways (Section 7-4)DSBW
Swivels (Section 7-5)DSSW
Hose Retriever (Section 7-6)HSRTV
Dispenser Cabinet (Section 7-7)DSCB
Dispenser Meters (Section 7-8)DSMTR
Dispenser Filters (Section 7-9)DSFLR
Dispenser Strainers (Section 7-10)DSSTR
Ground Vehicle Fuel Piping (Section 7-11)GVFP
Emergency Shutoff Valves (Shear Valves) (Section 7-12)ESHVL
Dispenser Sumps (Section 7-13)DSSMP
Transition Sumps (Section 7-14)TRSMP
Remote Dispenser Pumps (Section 7-15.1)RDSP
Self-Contained Dispenser Pumps (Section 7-15.2)SCDSP
EFSO Systems (Section 7-16)EFSO
Stage I Vapor Recovery (Section 7-17.1)SIVP
Stage II Vapor Recovery (Section 7-17.2)SIIVP
Vapor Burners (Section 7-17.3)VPBNR
Point Sensor - Dry (Section 7-19.1.1)PSDRY
Automatic Line Leak Detector (Section 7-19.1.2)ALLD
Visual Monitoring (Section 7-20.1)VSLM
Issue/Receive - MarineMarine Receipt (Section 5-2)MRNRCP
Marine Issue (Section 5-3)MRNISU
Marine Loading Arms (Section 5-4)MRNLA
Marine Transfer Hoses (Section 5-5.1)MBTHS
Underwater Hoses (Section 5-5.2)UWHS
Single Point Mooring Systems (Section 5-7.1)SPMSS
Multi Point Mooring Systems (Section 5-7.2)MPMSS
Submerged Piping Systems (Section 5-8)SMPS
Boom Reels (Section 5-9)BMRL
Liquefied PetroleumLiquefied Petroleum Tanks (Section 10-1.1)LPTANK
Liquefied Petroleum Pipelines (Section 10-1.2)LPPIPE
Liquefied Petroleum Vapor Lines (Section 10-1.3)LPVPL
LPG Vaporizers (Section 10-1.4)LPGVPZ
Petroleum Gas Regulators (Section 10-1.5)PGREG
Liquefied Petroleum Gas Hoses (Section 10-1.6)LPGHS
Meter/
calibrationsPositive Displacement Meters (Section 3-7.1)PDMT
Turbine Flow Meters (Section 3-7.2)TBFMT
Orifice Flow Meters (Section 3-7.3)OFMT
Natural DisasterNatural Disaster
Natural GasCNG Piping (Section 10-2.1)NGPIPE
CNG Compressors (Section 10-2.2)NGCOMP
CNG Storage (Section 10-2.3)NGSTOR
CNG Dispensers (Section 10-2.4)NGDS
CNG Dispenser Hoses (Section 10-2.5)NGDSHS
NozzleHydrant Adapters (Section 4-7.2)HADP
Fueling Nozzles (Section 4-7.3)FLNZ
OtherFuel Additive Injectors (Section 3-11)FAIJ
PantographFixed Pantographs (Section 4-7.1.1)FXPNT
Detachable Pantographs (Section 4-7.1.2)DTPNT
PipingOn-Base Pipelines (Section 6-1.1)OBPL
Non-DOT Regulated (Section 6-1.2.1)NDPL
Aboveground Piping (Section 6-1.3)AGPL
Double-Wall Piping (Section 6-1.4)DWPL
Low Point Drains (Section 6-12.1)LPDN
High Point Vents (Section 6-12.2)HPVT
Sight Flow Indicators (Section 6-12.3)SFND
Rope Sensor Systems (Section 6-13.1.1)RPSS
Point Sensor - Dry (Section 6-13.1.2)PSDRY
Visual Monitoring (Section 6-14.1)VSLM
Pipe Penetrations (Section 8-10.6)PPEN
Deactivated Petroleum Fuel Pipelines (Section 12-3)DEACPL
Pressure/Temperature ControlAir Eliminator Tanks (Section 3-10.1)AELT
Automatic Air Vents (Section 3-10.2)AAVT
Surge Suppressors (Section 4-7.4)SRGSP
Thermal and Pressure Relief Valves (Section 6-6.3)TPRVL
Pressure Transmitters (Section 6-7.3)PRTR
Differential Pressure Transmitters (Section 6-7.4)DPTR
Flexible Ball Joints (Section 6-8)FBLJT
Dial Thermometer (Section 6-9.1)DTHMR
Emergency Vents (Section 8-9.4)EMGVT
PumpCentrifugal Pumps (Section 3-8.1)CENP
Vertical Inline Pumps (Section 3-8.2)VILP
Vertical Turbine/Submerged Turbine Pumps (Section 3-8.3)VTSP
Sliding Vane Pumps (Section 3-8.5)SLVP
Gear Pumps (Section 3-8.6)GERP
Diaphragm Pumps (Section 3-8.7)DIAP
Internal Combustion Drives (Section 3-8.8)ICDR
Gearboxes (Section 3-8.9)GRBX
Deactivated Petroleum Fuel Pumps (Section 12-4)DEACP
Signage/MarkingsSignage and Markings (Section 2-7)SIGN
StructuresPumphouse/Filter Buildings (Section 11-2.1)PFBLDG
Canopies (Section 11-2.2)CNPY
Cranes and Hoists (Section 11-6)CRNHST
TankAboveground Field-Erected Tanks (Section 8-4)AGFET
Geodesic Dome Roofs (Section 8-4.2)GEODR
Foundations (Section 8-4.3)FOUND
Aboveground Shop Fabricated Tanks (Section 8-5.1)AGSFP
Self-Diking or Vaulted Tanks (Section 8-5.2)SDVT
Rectangular Concrete-Encased Tanks (Section 8-5.3)RCET
Single-Walled Underground Shop-Fabricated Tanks (Section 8-5.4.1)UGSSFT
Double-Walled Underground Shop-Fabricated Tanks (Section 8-5.4.2)UGDSFT
Underground Field-Constructed Tanks (Cut and Cover Tanks) (Section 8-6)UGFET
Tank Cleaning (Section 8-7)TCLEAN
Aluminum Honeycomb Floating Pans (Section 8-9.1.1)AHFP
Steel Floating Pans (Section 8-9.1.2)STLFP
Pontoon Floating Pans (Section 8-9.1.3)PTNFP
Floating Roofs (Section 8-9.1.4)FLTRF
Floating Roof and Pan Pressure/Vacuum Vents (Section 8-9.1.5)FPPVV
Floating Roof and Pan Legs (Section 8-9.1.6)FRPLG
Secondary Tank Bottoms (Section 8-9.2)SNDTB
Tank Pressure/Vacuum Vents (Section 8-9.3)TPVVT
Product Saver Tanks (Section 8-9.10)PRDST
Fill Ports (Section 8-9.12)FPRT
Point Sensor - Dry (Section 8-9.13.1)PSDRY
Point Sensor - Wet (Section 8-9.13.2)PSWET
Point Sensor - Pressure/Vacuum (Section 8-9.13.3)PSPV
Visual Leak Detection (Section 8-9.13.4)VSLLD
Floating Suction Lines (Section 8-9.14)FLTSL
Stilling Wells (Section 8-9.17)STGW
Deactivated Petroleum Fuel Tanks (Section 12-2)DEACT
TestingPressure Testing
Underground PitsIsolation Valve Pits (Section 6-11.1)ISVLP
Hydrant Fuel Pits (Section 6-11.2)HDFP
High Point Vent Pits (Section 6-11.3)HPVP
Low Point Drain Pits (Section 6-11.4)LPDP
Lateral Control Pits (Section 6-11.5)LTCP
ValvesGeneral System Control Valves (Section 4-3.2.1)GSCVL
Refuel Control Valves (Section 4-3.2.5)RCVL
Pressure Relief Valves (Section 4-3.2.6)PRCVL
Defuel Control Valve (Section 4-3.2.7)DFCVL
Dual Rate-of-Flow Control Valves (Section 4-3.2.8)DRFCVL
Combination Dual Rate-of-Flow Control and Solenoid Valves (Section 4-3.3.1)CFSCVL
Dual Pressure Relief, Solenoid Shutoff, and Check Valves (Section 4-3.3.2)DPSCVL
Non-Surge Check Valves (Section 4-4.2.1)NSCKVL
Filter Separator Control Valves (Section 4-4.2.2)FSCVL
Defuel/Flush Valves (Section 4-4.2.3)DFFCVL
Issue Venturi (Section 4-4.2.4)ISVTR
Return Venturi (Section 4-4.2.5)RTVTR
Back Pressure Control Valves (Section 4-4.2.6)BPCVL
Pressure Control Valves (Section 4-4.2.7)PCVL
Hydrant Control Valves (Section 4-4.2.8)HCVL
Emergency Shut-off Valves (Section 4-4.2.9)ESOVL
Pantograph Control Valves (Section 4-5.2.12)PTCVL
Pantograph Pressure Control Valves (Section 4-5.2.13)PTPCVL
Overfill Valve for Product Recovery Tanks (Section 4-8.1)OVLPRT
Plug Valves - Lubricated (Section 6-6.2.1)PLVL
Plug Valves - Non-lubricated (Section 6-6.2.2)NPLVL
Gate Valves (Section 6-6.2.3)GTVL
Ball Valves (Section 6-6.2.4)BLVL
Double Block and Bleed Valves (Section 6-6.2.5)DBBVL
Butterfly Valves (Section 6-6.2.6)BFVL
Globe Valves (Section 6-6.2.7)GLVL
Check Valves (Section 6-6.2.8)CKVL
Line Blanks, Ring Spacers, and Spectacle Blinds (Section 6-6.2.9)BLIND
Manual Valve Gear Operators (Section 6-6.2.10)MVLGO
Fire Valves (Section 6-6.4.1)FRVL
Fusible Link Butterfly Valves (Section 6-6.4.2)FLBFVL
Truck Fill Valves (Section 6-6.5.1)TFVL
Motor Operators (Section 6-6.6)MTROP
External High Level Shutoff Valves (HLSO) (Section 8-9.6.1)EHLSVL
Internal HLSO Valves (Section 8-9.6.2)IHLSVL
WasteOil/Water Separators (Section 11-5)OWS

&"Times New Roman,Bold"&14APPENDIX F - Component Unique Identifier (CUID)

&P

Versions and Notes

VersionDateDescription of changes
v2.08/18/21Updated Task Matrix to meet UFC 3-460-03 Change 1 , 29 April 2021
Updated Component Acronym Tab to meet UFC 3-460-03 Change 1 , 29 April 2021
v2.14/20/22Task Matrix Tab - Deleted all services facility # columns and combined into one. Renamed "Real Property Facility #"
Task Matrix Tab - Added "RPUID" to Real Property Unique Identifier column
Task Matrix Tab - Added "Real Property" to Facility Name
Task Matrix Tab - Added column for "Base Asset ID"
Task Matrix Tab - Added "Additional" and "RM" to Manufacturer Requirements
Task Matrix Tab - Changed Comment note for Filter Separator
Task Matrix Tab - Changed Note #3 To add "Base Asset ID if used by site shall be cross referenced with CUID appropriately."
Task Matrix Tab - Changed note #7 under instructions for Task Matrix to clarify this column
Task Matrix Tab - Changed note #8 under instructions for Task Matrix to clarify this column
Added new tab for RM schedule to be included
Added new Tab for Filter Separator/Pre-Filter Schedule with instructions