3.1 Appendix B - Attachment 1 - Three Week Look Ahead_20230420.xlsx
XLSX spreadsheet 40 KB Posted
- Attached to
- Sources Sought - CEHNC FUELS PROGRAM
- Solicitation number
- PANHES-25-P-0000-001794
About this file
This file is an Excel spreadsheet titled "Three Week Look Ahead Schedule" for fuel program recurring maintenance execution at various military installations. The schedule covers the period of June 3-24, 2024, and details maintenance activities across multiple Army and Air Force bases in the Southwestern Division (SWD-A/AF).
The schedule tracks different types of maintenance activities including Quarterly (Q), Annual (A), Semi-Annual (SA), Initial Site Visits (ISV), and Service Orders (SO) across facilities such as Fort Chaffee, Pine Bluff Arsenal, Fort Bliss, Vance Air Force Base, and various Joint Base San Antonio (JBSA) locations. Specific maintenance activities are scheduled for sites like Pine Bluff Arsenal (Q1/A1 maintenance for 5 days), Fort Bliss AAA Ranges (Q1 for 3 days), and Sheppard AFB (Q1/SA1 for 3 days). The document includes separate tracking sheets for recurring maintenance and service orders, with project management oversight from both contractor (ABC-PM) and HNC project managers.
View the file
Other files
Show all 46
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RM - SWD AAF
Fuels Recurring Maintenance Execution - SWD-A/AF
| Phase: | SWD-A/AF | Date Prepared: | 5/27/24 | ||
| Contractor Project Manager: | ABC-PM | Three Week Date Range: | 6/3/24 | - | 6/24/24 |
| Contractor: | KTR NAME |
| HNC Project Manager: | HNC-PM | LEGEND: | Q | Quarterly | A | Annual | No Work | |
| SA | Semi-Annual | ISV | Initial Site Visit | C | Calibration |
| RPSUID | Site | Location | Recurring Maintenance Activity Descrition | KTR/SUB | Start Date | End Date | Total Working Days | 3-Jun | 4-Jun | 5-Jun | 6-Jun | 7-Jun | 8-Jun | 9-Jun | 10-Jun | 11-Jun | 12-Jun | 13-Jun | 14-Jun | 15-Jun | 16-Jun | 17-Jun | 18-Jun | 19-Jun | 20-Jun | 21-Jun | 22-Jun | 23-Jun |
| M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | ||||||||
| 4263 | RBN | CAMP JOSEPH T ROBINSON | ||||||||||||||||||||||||||
| 4990 | CHF | FORT CHAFFEE MTC | ISV-A | ISV-A | ISV-A | ISV-A | ||||||||||||||||||||||
| 6798 | PBA | PINE BLUFF ARSENAL | Q1/A1 | Q1/A1 | Q1/A1 | Q1/A1 | Q1/A1 | |||||||||||||||||||||
| 7302 | BEU | CAMP BEAUREGARD | ||||||||||||||||||||||||||
| 4986 | BL2 | FORT BLISS AAA RANGES | Q1 | Q1 | Q1 | |||||||||||||||||||||||
| 4255 | GRB | CAMP GRUBER | Q1 | Q1 | Q1 | |||||||||||||||||||||||
| 5050 | FSO | FORT SILL | ||||||||||||||||||||||||||
| 5890 | LEX | LEXINGTON AASF NO 1 | ||||||||||||||||||||||||||
| 6120 | MAA | MCALESTER AAP | ||||||||||||||||||||||||||
| 4985 | BLI | FORT BLISS | ||||||||||||||||||||||||||
| 5010 | CVZ | FORT CAVAZOS | Q1/SA1 | Q1/SA1 | Q1/SA1 | Q1/SA1 | ||||||||||||||||||||||
| 6955 | RRT | RED RIVER ARMY DEPOT | ||||||||||||||||||||||||||
| 2102 | FSM | FT SMITH MAP SITE 1 | ||||||||||||||||||||||||||
| 2496 | LRG | LITTLE ROCK AFB SITE # 1 | ||||||||||||||||||||||||||
| 1431 | BAR | BARKSDALE AIR FORCE BASE SITE # 1 | ||||||||||||||||||||||||||
| 1361 | ALT | ALTUS AIR FORCE BASE SITE # 1 | ||||||||||||||||||||||||||
| 3342 | TKR | TINKER AFB SITE # 1 | ||||||||||||||||||||||||||
| 3365 | TUL | TULSA IAP SITE # 1 | ||||||||||||||||||||||||||
| 3375 | VNC | VANCE AIR FORCE BASE SITE # 1 | ISV-A | ISV-A | ISV-A | ISV-A | ||||||||||||||||||||||
| 3522 | WRF | WILL ROGERS WORLD APT | ||||||||||||||||||||||||||
| 1672 | DYE | DYESS AIR FORCE BASE SITE # 1 | ||||||||||||||||||||||||||
| 1708 | ELL | ELLINGTON FIELD SITE # 1 | ||||||||||||||||||||||||||
| 190177 | EFS | ELLINGTON FIELD SITE # 2 | ||||||||||||||||||||||||||
| 2127 | GDF | GOODFELLOW AFB SITE # 1 | Q1/A1 | Q1/A1 | Q1/A1 | |||||||||||||||||||||||
| 4236 | BRO | JBSA-BULLIS | ||||||||||||||||||||||||||
| 2334 | KEQ | JBSA-KELLY FIELD ANNEX | ||||||||||||||||||||||||||
| 2461 | LLD | JBSA-LACKLAND SITE #1 | ||||||||||||||||||||||||||
| 3209 | RAN | JBSA-RANDOLPH | ||||||||||||||||||||||||||
| 5047 | FSH | JBSA-SAM HOUSTON | ||||||||||||||||||||||||||
| 2483 | LAU | LAUGHLIN AFB SITE # 1 | ||||||||||||||||||||||||||
| 3274 | SHP | SHEPPARD AFB SITE # 1 | Q1/SA1 | Q1/SA1 | Q1/SA1 |
Notes:
SO - SWD AAF
Fuels Service Order Execution - SWD-A/AF
| Phase: | SWD-A/AF | Date Prepared: | 5/27/24 | ||
| Contractor Project Manager: | ABC-PM | Three Week Date Range: | 6/3/24 | - | 6/24/24 |
| Contractor: | KTR NAME |
| HNC Project Manager: | HNC-PM | LEGEND: | SO | Service Order |
| No Work |
| RPSUID | Site | Location | Service Order Number | KTR/SUB | Start Date | End Date | Total Working Days | 3-Jun | 4-Jun | 5-Jun | 6-Jun | 7-Jun | 8-Jun | 9-Jun | 10-Jun | 11-Jun | 12-Jun | 13-Jun | 14-Jun | 15-Jun | 16-Jun | 17-Jun | 18-Jun | 19-Jun | 20-Jun | 21-Jun | 22-Jun | 23-Jun |
| M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | ||||||||
| 4263 | RBN | CAMP JOSEPH T ROBINSON | SO | SO | SO | |||||||||||||||||||||||
| 4990 | CHF | FORT CHAFFEE MTC | SO | SO | SO | |||||||||||||||||||||||
| 6798 | PBA | PINE BLUFF ARSENAL | ||||||||||||||||||||||||||
| 7302 | BEU | CAMP BEAUREGARD | ||||||||||||||||||||||||||
| 4986 | BL2 | FORT BLISS AAA RANGES | ||||||||||||||||||||||||||
| 4255 | GRB | CAMP GRUBER | ||||||||||||||||||||||||||
| 5050 | FSO | FORT SILL | ||||||||||||||||||||||||||
| 5890 | LEX | LEXINGTON AASF NO 1 | SO | SO | ||||||||||||||||||||||||
| 6120 | MAA | MCALESTER AAP | ||||||||||||||||||||||||||
| 4985 | BLI | FORT BLISS | ||||||||||||||||||||||||||
| 5010 | CVZ | FORT CAVAZOS | ||||||||||||||||||||||||||
| 6955 | RRT | RED RIVER ARMY DEPOT | ||||||||||||||||||||||||||
| 2102 | FSM | FT SMITH MAP SITE 1 | ||||||||||||||||||||||||||
| 2496 | LRG | LITTLE ROCK AFB SITE # 1 | ||||||||||||||||||||||||||
| 1431 | BAR | BARKSDALE AIR FORCE BASE SITE # 1 | ||||||||||||||||||||||||||
| 1361 | ALT | ALTUS AIR FORCE BASE SITE # 1 | ||||||||||||||||||||||||||
| 3342 | TKR | TINKER AFB SITE # 1 | ||||||||||||||||||||||||||
| 3365 | TUL | TULSA IAP SITE # 1 | ||||||||||||||||||||||||||
| 3375 | VNC | VANCE AIR FORCE BASE SITE # 1 | ||||||||||||||||||||||||||
| 3522 | WRF | WILL ROGERS WORLD APT | ||||||||||||||||||||||||||
| 1672 | DYE | DYESS AIR FORCE BASE SITE # 1 | ||||||||||||||||||||||||||
| 1708 | ELL | ELLINGTON FIELD SITE # 1 | ||||||||||||||||||||||||||
| 190177 | EFS | ELLINGTON FIELD SITE # 2 | SO | SO | SO | |||||||||||||||||||||||
| 2127 | GDF | GOODFELLOW AFB SITE # 1 | SO | SO | SO | |||||||||||||||||||||||
| 4236 | BRO | JBSA-BULLIS | ||||||||||||||||||||||||||
| 2334 | KEQ | JBSA-KELLY FIELD ANNEX | ||||||||||||||||||||||||||
| 2461 | LLD | JBSA-LACKLAND SITE #1 | ||||||||||||||||||||||||||
| 3209 | RAN | JBSA-RANDOLPH | ||||||||||||||||||||||||||
| 5047 | FSH | JBSA-SAM HOUSTON | ||||||||||||||||||||||||||
| 2483 | LAU | LAUGHLIN AFB SITE # 1 | SO | SO | SO | SO | ||||||||||||||||||||||
| 3274 | SHP | SHEPPARD AFB SITE # 1 |
Notes:
Appendix B-Attachment 1 Fuels Recurring Maintenance Execution - SWD-A/AF
| Phase: | SWD-A/AF | Date Prepared: | 5/27/24 | ||
| Contractor Project Manager: | ABC-PM | Three Week Date Range: | 6/3/24 | - | 6/24/24 |
| Contractor: | KTR NAME |
| HNC Project Manager: | HNC-PM | LEGEND: | Q | Quarterly | A | Annual | No Work | |
| SA | Semi-Annual | ISV | Initial Site Visit | C | Calibration |
| RPSUID | Site | Location | Recurring Maintenance Activity Descrition | KTR/SUB | Start Date | End Date | Total Working Days | 3-Jun | 4-Jun | 5-Jun | 6-Jun | 7-Jun | 8-Jun | 9-Jun | 10-Jun | 11-Jun | 12-Jun | 13-Jun | 14-Jun | 15-Jun | 16-Jun | 17-Jun | 18-Jun | 19-Jun | 20-Jun | 21-Jun | 22-Jun | 23-Jun |
| M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | ||||||||
| 4263 | RBN | CAMP JOSEPH T ROBINSON | ||||||||||||||||||||||||||
| 4990 | CHF | FORT CHAFFEE MTC | ISV-A | ISV-A | ISV-A | ISV-A | ||||||||||||||||||||||
| 6798 | PBA | PINE BLUFF ARSENAL | Q1/A1 | Q1/A1 | Q1/A1 | Q1/A1 | Q1/A1 | |||||||||||||||||||||
| 7302 | BEU | CAMP BEAUREGARD | ||||||||||||||||||||||||||
| 4986 | BL2 | FORT BLISS AAA RANGES | Q1 | Q1 | Q1 | |||||||||||||||||||||||
| 4255 | GRB | CAMP GRUBER | Q1 | Q1 | Q1 | |||||||||||||||||||||||
| 5050 | FSO | FORT SILL | ||||||||||||||||||||||||||
| 5890 | LEX | LEXINGTON AASF NO 1 | ||||||||||||||||||||||||||
| 6120 | MAA | MCALESTER AAP | ||||||||||||||||||||||||||
| 4985 | BLI | FORT BLISS | ||||||||||||||||||||||||||
| 5010 | CVZ | FORT CAVAZOS | Q1/SA1 | Q1/SA1 | Q1/SA1 | Q1/SA1 | ||||||||||||||||||||||
| 6955 | RRT | RED RIVER ARMY DEPOT | ||||||||||||||||||||||||||
| 2102 | FSM | FT SMITH MAP SITE 1 | ||||||||||||||||||||||||||
| 2496 | LRG | LITTLE ROCK AFB SITE # 1 | ||||||||||||||||||||||||||
| 1431 | BAR | BARKSDALE AIR FORCE BASE SITE # 1 | ||||||||||||||||||||||||||
| 1361 | ALT | ALTUS AIR FORCE BASE SITE # 1 | ||||||||||||||||||||||||||
| 3342 | TKR | TINKER AFB SITE # 1 | ||||||||||||||||||||||||||
| 3365 | TUL | TULSA IAP SITE # 1 | ||||||||||||||||||||||||||
| 3375 | VNC | VANCE AIR FORCE BASE SITE # 1 | ISV-A | ISV-A | ISV-A | ISV-A | ||||||||||||||||||||||
| 3522 | WRF | WILL ROGERS WORLD APT | ||||||||||||||||||||||||||
| 1672 | DYE | DYESS AIR FORCE BASE SITE # 1 | ||||||||||||||||||||||||||
| 1708 | ELL | ELLINGTON FIELD SITE # 1 | ||||||||||||||||||||||||||
| 190177 | EFS | ELLINGTON FIELD SITE # 2 | ||||||||||||||||||||||||||
| 2127 | GDF | GOODFELLOW AFB SITE # 1 | Q1/A1 | Q1/A1 | Q1/A1 | |||||||||||||||||||||||
| 4236 | BRO | JBSA-BULLIS | ||||||||||||||||||||||||||
| 2334 | KEQ | JBSA-KELLY FIELD ANNEX | ||||||||||||||||||||||||||
| 2461 | LLD | JBSA-LACKLAND SITE #1 | ||||||||||||||||||||||||||
| 3209 | RAN | JBSA-RANDOLPH | ||||||||||||||||||||||||||
| 5047 | FSH | JBSA-SAM HOUSTON | ||||||||||||||||||||||||||
| 2483 | LAU | LAUGHLIN AFB SITE # 1 | ||||||||||||||||||||||||||
| 3274 | SHP | SHEPPARD AFB SITE # 1 | Q1/SA1 | Q1/SA1 | Q1/SA1 |
Notes:
Fuels Service Order Execution - SWD-A/AF
| Phase: | SWD-A/AF | Date Prepared: | 5/27/24 | ||
| Contractor Project Manager: | ABC-PM | Three Week Date Range: | 6/3/24 | - | 6/24/24 |
| Contractor: | KTR NAME |
| HNC Project Manager: | 0 | LEGEND: | SO | Service Order |
| No Work |
| RPSUID | Site | Location | Service Order Number | KTR/SUB | Start Date | End Date | Total Working Days | 3-Jun | 4-Jun | 5-Jun | 6-Jun | 7-Jun | 8-Jun | 9-Jun | 10-Jun | 11-Jun | 12-Jun | 13-Jun | 14-Jun | 15-Jun | 16-Jun | 17-Jun | 18-Jun | 19-Jun | 20-Jun | 21-Jun | 22-Jun | 23-Jun |
| M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | ||||||||
| 4263 | RBN | CAMP JOSEPH T ROBINSON | SO | SO | SO | |||||||||||||||||||||||
| 4990 | CHF | FORT CHAFFEE MTC | SO | SO | SO | |||||||||||||||||||||||
| 6798 | PBA | PINE BLUFF ARSENAL | ||||||||||||||||||||||||||
| 7302 | BEU | CAMP BEAUREGARD | ||||||||||||||||||||||||||
| 4986 | BL2 | FORT BLISS AAA RANGES | ||||||||||||||||||||||||||
| 4255 | GRB | CAMP GRUBER | ||||||||||||||||||||||||||
| 5050 | FSO | FORT SILL | ||||||||||||||||||||||||||
| 5890 | LEX | LEXINGTON AASF NO 1 | SO | SO | ||||||||||||||||||||||||
| 6120 | MAA | MCALESTER AAP | ||||||||||||||||||||||||||
| 4985 | BLI | FORT BLISS | ||||||||||||||||||||||||||
| 5010 | CVZ | FORT CAVAZOS | ||||||||||||||||||||||||||
| 6955 | RRT | RED RIVER ARMY DEPOT | ||||||||||||||||||||||||||
| 2102 | FSM | FT SMITH MAP SITE 1 | ||||||||||||||||||||||||||
| 2496 | LRG | LITTLE ROCK AFB SITE # 1 | ||||||||||||||||||||||||||
| 1431 | BAR | BARKSDALE AIR FORCE BASE SITE # 1 | ||||||||||||||||||||||||||
| 1361 | ALT | ALTUS AIR FORCE BASE SITE # 1 | ||||||||||||||||||||||||||
| 3342 | TKR | TINKER AFB SITE # 1 | ||||||||||||||||||||||||||
| 3365 | TUL | TULSA IAP SITE # 1 | ||||||||||||||||||||||||||
| 3375 | VNC | VANCE AIR FORCE BASE SITE # 1 | ||||||||||||||||||||||||||
| 3522 | WRF | WILL ROGERS WORLD APT | ||||||||||||||||||||||||||
| 1672 | DYE | DYESS AIR FORCE BASE SITE # 1 | ||||||||||||||||||||||||||
| 1708 | ELL | ELLINGTON FIELD SITE # 1 | ||||||||||||||||||||||||||
| 190177 | EFS | ELLINGTON FIELD SITE # 2 | SO | SO | SO | |||||||||||||||||||||||
| 2127 | GDF | GOODFELLOW AFB SITE # 1 | SO | SO | SO | |||||||||||||||||||||||
| 4236 | BRO | JBSA-BULLIS | ||||||||||||||||||||||||||
| 2334 | KEQ | JBSA-KELLY FIELD ANNEX | ||||||||||||||||||||||||||
| 2461 | LLD | JBSA-LACKLAND SITE #1 | ||||||||||||||||||||||||||
| 3209 | RAN | JBSA-RANDOLPH | ||||||||||||||||||||||||||
| 5047 | FSH | JBSA-SAM HOUSTON | ||||||||||||||||||||||||||
| 2483 | LAU | LAUGHLIN AFB SITE # 1 | SO | SO | SO | SO | ||||||||||||||||||||||
| 3274 | SHP | SHEPPARD AFB SITE # 1 |
Notes:
&"Times New Roman,Bold"&14APPENDIX B - ATTACHMENT 1 - THREE WEEK LOOK AHEAD SCHEDULE
File details come from the government source that posted it. Updated .