This is a Facility Maintenance Plan template for fuel facilities at Fort Bliss AAA Ranges in Orogrande, NM. The document details maintenance requirements for various fuel system components including above-ground storage tanks, filter separators, pumps, valves, electrical equipment, and safety systems at the Dona Ana facility (Facility #8243). The template provides detailed maintenance schedules (quarterly, annual) and specific procedures for each component.

The plan includes sections for administrative information, general facility description, communication protocols, safety requirements, and a comprehensive task matrix listing all maintainable assets with their specifications, maintenance frequencies, and special considerations. Key systems covered include two aviation fuel tanks (50,000 and 20,000 gallon capacity), filtration systems, dispensing equipment, containment systems, and emergency equipment. The document serves as a maintenance tracking tool, requiring contractors to assign unique identifiers to components and document maintenance activities according to UFC 3-460-03 standards.

View the file

Other files

File Type Posted
Sources Sought FUELS - Programmatic Rev1 7 May 25.docx DOCX document
3.4 Appendix B - Attachment 4 - SO Tracker-20210628.xlsx XLSX spreadsheet
6.0 - Appendix E ISR 15-Bulk_Fuel_Facilities FY25.xlsx XLSX spreadsheet
2.0 Appendix A RM_SO Process_20241220_PgM Reviewed Incorporated.docx DOCX document
3.1 Appendix B - Attachment 1 - Three Week Look Ahead_20230420.xlsx XLSX spreadsheet
3.2 Appendix B - Attachment 2 - Monthly Report Format 20240910.docx DOCX document
2.2 Appendix A - Attachment 2 Contractor Travel Expense Report_20240910.xlsx XLSX spreadsheet
9.0 Appendix H - Minor Repairs Incidental to Maintenance Activities POJ 20231009.xlsx XLSX spreadsheet
7.0 CUID - v2.1.pdf PDF
8.0 Appendix G_UFC 3-460-03 Maintenance Table- v4.3.pdf PDF
6.0 Appendix E ISR 14_operational_fuel_facilities FY25.xlsx XLSX spreadsheet
3.0 Appendix B Reporting Requirements_20240910.docx DOCX document
4.0 Appendix C Task Order Specifications_202401216.docx DOCX document
5.0 Appendix D Antiterrorism and OPSEC 20230206.docx DOCX document
PWS LEX FMP Template - v2.2.xlsx XLSX spreadsheet
PWS VNC FMP Template - v2.2.xlsx XLSX spreadsheet
PWS KEQ FMP Template - v2.2.xlsx XLSX spreadsheet
PWS CVZ FMP Template - v2.2.xlsx XLSX spreadsheet
PWS SHP FMP Template - v2.2.xlsx XLSX spreadsheet
PWS PBA FMP Template - v2.2.xlsx XLSX spreadsheet
PWS GRB FMP Template - v2.2.xlsx XLSX spreadsheet
PWS BRO FMP Template - v2.2.xlsx XLSX spreadsheet
PWS BAR FMP Template - v2.2.xlsx XLSX spreadsheet
PWS EFS FMP Template - v2.2.xlsx XLSX spreadsheet
PWS LAU FMP Template - v2.2.xlsx XLSX spreadsheet
PWS CHF FMP Template - v2.2.xlsx XLSX spreadsheet
PWS BEU FMP Template - v2.2.xlsx XLSX spreadsheet
PWS GDF FMP Template - v2.2.xlsx XLSX spreadsheet
PWS BLI FMP Template - v2.2.xlsx XLSX spreadsheet
PWS TKR FMP Template - v2.2.xlsx XLSX spreadsheet
PWS RBN FMP Template - v2.2.xlsx XLSX spreadsheet
PWS MAA FMP Template - v2.2.xlsx XLSX spreadsheet
PWS FSH FMP Template - v2.2.xlsx XLSX spreadsheet
PWS FSO FMP Template - v2.2.xlsx XLSX spreadsheet
PWS LRG FMP Template - v2.2.xlsx XLSX spreadsheet
PWS RRT FMP Template - v2.2.xlsx XLSX spreadsheet
PWS ALT FMP Template - v2.2.xlsx XLSX spreadsheet
PWS TUL FMP Template - v2.2.xlsx XLSX spreadsheet
PWS ELL FMP Template - v2.2.xlsx XLSX spreadsheet
PWS WRF FMP Template - v2.2.xlsx XLSX spreadsheet
PWS LLD FMP Template - v2.2.xlsx XLSX spreadsheet
PWS DYE FMP Template - v2.2.xlsx XLSX spreadsheet
12.0 PWS Appendix K Real Property Data_20230420.xlsx XLSX spreadsheet
PWS RAN FMP Template - v2.2.xlsx XLSX spreadsheet
PWS FSM FMP Template - v2.2.xlsx XLSX spreadsheet
PWS _Fuels RMMR 20241220.docx DOCX document
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Administrative

LocationSite NameFort Bliss AAA Ranges
RPSUID4986
DLA Site CodeBL2
Hours of Operation0800-1600
AddressOrogrande, NM 88081
ContractContractor
Contract #
Local POCsQAE Name
QAE Phone
QAE Email
Alt QAE Name
Alt QAE Phone
Alt QAE Email
DLA/SCP POCsDLA PM Name
DLA PM Phone
DLA PM Email
SCP PM Name
SCP PM Phone
SCP PM Email
Contractor POCsContractor PM Name
Contractor PM Phone
Contractor PM Email
Contractor QC Name
Contractor QC Phone
Contractor QC Email
Contractor SM Name
Contractor SM Phone
Contractor SM Email
USACE POCsUSACE PM/COR Name
USACE PM/COR Phone
USACE PM/COR Email
USACE PE Name
USACE PE Phone
USACE PE Email
USACE KO Name
USACE KO Phone
USACE KO Email

Facility Maintenance Plan

FMP v2.2 &P of &N

Instructions:

This table shows the minimum information required. Additional details should be included based on site specific requirements. Additional POCs may be required.

General Facility Description Facility Description

Purpose:

This Facility Maintenance Plan provides guidance for Contractor personnel in the operation, inspection, and maintenance of permanently installed fuel facilities operated under the control of the Quality Assurance Evaluators. Federal, state, and local environmental laws and regulations shall be complied with if this plan is in conflict with them.

Scope:

The instructions prescribed by this plan outline general fuels maintenance information associated with fuel storage and dispensing systems and provides the minimum periodic contractor maintenance and inspection criteria requirements for the systems. This plan is to be used in conjunction with other existing directives governing fuel system operations and maintenance requirements. Conotractor will properly maintain and repair federally funded petroleum systems and facilities in order to provide compliance with applicable code, criteria, and federal, state, local and/or host nation regulations.

Fuels Facilities:

Organizational tanks, and associated dispensing equipment are maintained and operated by the owning organization. Fuel system maintenance contractors shall perform all maintenance and associated procurement actions on installed fuel systems.

Each installation under the Southwest Division contract are military land-based facilities who receive, store, distribute, and/or dispense liquid fuels.

Standard fuel system equipment includes:

a) Above Ground Sorage Stanks (AST), Underground Storage Tanks (UST)

b) Filter/separator and other filtration device maintenance access, particularly element removal.

c) Manual valves

d) Meter Registers, and Flow Meters.

e) Control Valves.

f) Pumps

g) Tank Monitoring Equipment and Instruments

h) Alarms

i) Fire Fighting Equipment

Site Specific General Information:

Facility Maintenance Plan

FMP v2.2 &P of &N

Instructions:

Include a general facility overview and description of each fuel system for the sites in accordance with UFC 3-460-01. Examples include: Bulk Storage Facilities, Aircraft Fueling Facilities, Marine and Dispensing Facilities, Ground Products Fueling Facilities, Alternate POL Facilities, and Support Facilities. Also include facility #s, facility names, fuel type, photos, and any other pertinent information.

Include Site Specific Conditions and Restrictions in this tab.

Communication Plan

Facility Maintenance Plan

FMP v2.2 &P of &N

Instructions:

Communication plan shall address in/out briefs, lines of communication, coordination for access, etc.

Safety

Facility Maintenance Plan

FMP v2.2 &P of &N

Instructions:

Site Specific Addendum and Activity Hazard Analysis, which are Attachments to the APP, specific to activities or tasks related to recurring maintenance for this site.

RM Schedule

Facility Maintenance Plan

FMP v2.2 &P of &N

Instructions:

Link RM schedule here

Task Matrix

Applicable Facility AssetsUFC System Level Maintenance FrequencySpecial Considerations
Real Property Unique Identifier
(RPUID)Real Property Facility #Real Property Facility NameOperational AreaComponent TypeBase Asset IDComponent Unique Identifier (CUID)MakeModelCapacity/SizeQSAUFC Section ReferenceAdditional Manufacturer RM RequirementsOperator/ equipment RequirementsSystem availabilityOther ContractComments
481298243Dona AnaFuel Truck Containment AreasFillstandN/AN/AN/AXX11-1.1No Manufacturer Requirements AvailableMonthly - Remove debris from around security fence. Inspect fence grounding points. Ensure connections are not loose or damage.
481258243Dona AnaRemote Spill ContainmentN/AN/AN/AXX11-1.2No Manufacturer Requirements AvailableAnnually - Secondary containment systems degrade and will collect debris which can clog drainage inlets or prevent drain valves from sealing properly. Test drain valves for leakage through the valve.
481258243Dona AnaRemote Spill ContainmentFillstandN/AN/AN/AXX11-1.2No Manufacturer Requirements AvailableAnnually - Secondary containment systems degrade and will collect debris which can clog drainage inlets or prevent drain valves from sealing properly. Test drain valves for leakage through the valve.
481258243Dona AnaRemote Spill ContainmentRecipeptN/AN/AN/AXX11-1.2No Manufacturer Requirements AvailableAnnually - Secondary containment systems degrade and will collect debris which can clog drainage inlets or prevent drain valves from sealing properly. Test drain valves for leakage through the valve.
481258243Dona AnaCanopiesFillstandN/AN/AN/A11-2.2No Manufacturer Requirements AvailableNo Operator Requirement
481258243Dona AnaCanopiesRecieptN/AN/AN/A11-2.2No Manufacturer Requirements AvailableNo Operator Requirement
481258243Dona AnaCanopiesDispensersN/AN/AN/A11-2.2No Manufacturer Requirements AvailableNo Operator Requirement
481258243Dona AnaEmergency Eyewash/ShowersN/AN/AN/AXXX11-3Weekly - Equipment installed within 10 seconds from the hazard and on the same plane as the hazard Pathway is clear of obstructions Plumbed equipment activated to ensure compliant operation and to clear any sediment Self-contained equipment checked to determine if the flushing fluid needs to be changed or supplemented Equipment free of broken or missing parts Equipment protected against freezing User protected from scalding waterNo Operator Requirement
481258243Dona AnaSignage and MarkingUnkUnkUnk2-7No Manufacturer Requirements AvailableMonthly - Check permanent signs and markings for adequacy and readability. Repair or replace deteriorated or illegible signs and markings.
481258243Dona AnaAir Eliminator TanksOffloadUnkUnkUnkX3-10.1The most common indication of mechanical air and

vapor eliminator failure is leakage in and around the cover and valve plate area. Common causes of air eliminator failure are valve plate wear, a broken reed strip, a damaged cover gasket, and a punctured float filled with product.

1. Remove the cover screws from the air eliminator cover with a 1/2 inch wrench or socket, and pull the cover, vent plate and seal ring from the housing.

2. Inspect the raised ridge of the vent port opening in the middle of the valve plate for marring or debris. Inspect the seal ring for damage.

3. Replace the seal ring and/or valve plate. Tighten the

cover screws to a torque of 17.5 - 20.5 ft-lbs.No Operator Requirement
481258243Dona AnaFilter SeparatorsReceiptFacetHCS-643-236 / 12103600 GpmX3-6.2Open drain under flow conditions until clear fuel is observed from the drain valve. Monitor differential pressure of coalescer cartridges. Replace filter cartridges when the acceptable maximum differential pressure is reached, the maximum in-service duration has passed, or the fuel becomes visibly dirty or discolored.Daily - Open drain under flow conditions until clear fuel is observed from the drain valve. Monitor differential pressure of coalescer cartridges.
481258243Dona AnaFilter SeparatorsIssueFacetHCS-643-236 / 12102600 GpmX3-6.2Open drain under flow conditions until clear fuel is observed from the drain valve. Monitor differential pressure of coalescer cartridges. Replace filter cartridges when the acceptable maximum differential pressure is reached, the maximum in-service duration has passed, or the fuel becomes visibly dirty or discolored.Daily - Open drain under flow conditions until clear fuel is observed from the drain valve. Monitor differential pressure of coalescer cartridges.
481258243Dona AnaPositive Displacement MetersFillstandVeeder Root0788700-063 / 2045747950-600X3-7.1Inspect counter head for unusual noises and smooth operation. Inspect temperature element operation of meters equipped with temperature
compensation featureMonthly - Inspect counter head for unusual noises and smooth operation.
481258243Dona AnaCentrifigal PumpsReceipt Pump 1Teco WestinghouseRS3A31-BAR / G-B160593200 GPMXX3-8.1During routine pump inspections only the easy to monitor factors such as pressure, temperature, vibration etc can be checKed. But during quarterly inspections, shaft alignment and oil levels should also be checked. Change Oil AnnuallyNo Operator Requirement
481258243Dona AnaCentrifigal PumpsReceipt Pump 2Teco WestinghouseRS3A31-BAR / 007643200 GPMXX3-8.1During routine pump inspections only the easy to monitor factors such as pressure, temperature, vibration etc can be checKed. But during quarterly inspections, shaft alignment and oil levels should also be checked. Change Oil AnnuallyNo Operator Requirement
481258243Dona AnaCentrifigal Pumps50K TankNational Pump CompanyM8HC300 GPMXX3-8.1During routine pump inspections only the easy to monitor factors such as pressure, temperature, vibration etc can be checKed. But during quarterly inspections, shaft alignment and oil levels should also be checked. Change Oil AnnuallyNo Operator Requirement
481258243Dona AnaVertical Turbine / Submerged Turbine Pumps20 K TankFEPetroSTP75-113-10UnkXXX3-8.1.3Check for unusual noise, vibration, temperature and leaks. Routinely inspect for unusual noise, vibration, temperature, leaks in pump or piping. Inspect for general condition, mechanical seal for leakage. Anytime a pump is opened, inspect the running clearances and restore them to original specifications if the running clearances have doubled.No Operator Requirement
481258243Dona AnaVertical Turbine / Submerged Turbine Pumps20 K TankFEPetroSTP75-113-10UnkXXX3-8.1.3Check for unusual noise, vibration, temperature and leaks. Routinely inspect for unusual noise, vibration, temperature, leaks in pump or piping. Inspect for general condition, mechanical seal for leakage. Anytime a pump is opened, inspect the running clearances and restore them to original specifications if the running clearances have doubled.No Operator Requirement
481258243Dona AnaLoading Fueling HosesFillstandUnkUnkUnkXX3-9.1Aircraft fueling hose shall be inspected before use each day. The hose shall be extended as it normally would be for fueling and checked for evidence of blistering, carcass saturation or separation, cuts, nicks, or abrasions that expose reinforcement material, and for slippage, misalignment, or leaks at couplings.Weekly - Visually inspect hoses for loose covers, cracks, brittle surface coatings, exposed wire braids, exposed reinforcement, flattening, kinks, and bulges or soft spots which might indicate broken or displaced reinforcement.

Monthly - Pressurize hose to normal working pressure. Check flanged and threaded connections for leaks and inspect hose couplers for fluid seepage by pushing at the base of the coupling with your thumbs; a hose softened by fluid seepage must be replaced.

481258243Dona AnaOffload Fuel HosesOffload 1UnkUnk4 InchXX3-9.2Aircraft fueling hose shall be inspected before use each day. The hose shall be extended as it normally would be for fueling and checked for evidence of blistering, carcass saturation or separation, cuts, nicks, or abrasions that expose reinforcement material, and for slippage, misalignment, or leaks at couplings.Weekly - Visually inspect hoses for cracks brittle surface coatings, exposed wire braids, exposed reinforcement, flattening, kinks, and bulges or soft spots which might indicate broken or displaced reinforcement.
481258243Dona AnaOffload Fuel HosesOffload 2UnkUnk4 InchXX3-9.2Aircraft fueling hose shall be inspected before use each day. The hose shall be extended as it normally would be for fueling and checked for evidence of blistering, carcass saturation or separation, cuts, nicks, or abrasions that expose reinforcement material, and for slippage, misalignment, or leaks at couplings.Weekly - Visually inspect hoses for cracks brittle surface coatings, exposed wire braids, exposed reinforcement, flattening, kinks, and bulges or soft spots which might indicate broken or displaced reinforcement.
481258243Dona AnaPressure Relief ValvesOffloadTaylorUnk0-150X4-3.2.6No Manufacturers Data Available. Adjustment not advised unless formal training is received.No Operator Requirement
481258243Dona AnaPressure Relief ValvesOffloadTaylorUnk0-150X4-3.2.6No Manufacturers Data Available. Adjustment not advised unless formal training is received.No Operator Requirement
481258243Dona AnaPressure Relief ValvesOffloadTaylorUnk0-150X4-3.2.6No Manufacturers Data Available. Adjustment not advised unless formal training is received.No Operator Requirement
481258243Dona AnaPressure Relief ValvesOffloadTaylorUnk0-150X4-3.2.6No Manufacturers Data Available. Adjustment not advised unless formal training is received.No Operator Requirement
481258243Dona AnaPressure Relief ValvesOffloadTaylorUnk0-150X4-3.2.6No Manufacturers Data Available. Adjustment not advised unless formal training is received.No Operator Requirement
481258243Dona AnaPressure Relief ValvesOffloadTaylorUnk0-150X4-3.2.6No Manufacturers Data Available. Adjustment not advised unless formal training is received.No Operator Requirement
481258243Dona AnaPressure Relief ValvesOffloadTaylorUnk0-150X4-3.2.6No Manufacturers Data Available. Adjustment not advised unless formal training is received.No Operator Requirement
481258243Dona AnaPressure Relief ValvesFillstandTaylorUnk0-150X4-3.2.6No Manufacturers Data Available. Adjustment not advised unless formal training is received.No Operator Requirement
481258243Dona AnaFilter Seperator Control ValvesOffloadClaValUnkUnkXX4-4.2.2No Manufacturers Data Available. Adjustment not advised unless formal training is received.No Operator Requirement
481258243Dona AnaFueling NozzlesFillstandClaValD-33 inchX4-7.4Quarterly - Inspect the condition of the dust cap at the aircraft adapter end and ensure it is in good working order. Dust caps must be attached to nozzles when they are not is use. Test leak resistance of poppet valve against full pump pressure. Inspect storage racks for moisture or dirt accumulation. Remove nozzle for inspection of content impinged upon the mesh screen. Clean and dry screens before nozzles are returned to service. Tests nozzle interlocks. Check the operation of the manual valve crank assembly for smooth and positive motion on a special test stand.Quarterly - Inspect the condition of the dust cap at the aircraft adapter end and ensure it is in good working order. Dust caps must be attached to nozzles when they are not is use. Test leak resistance of poppet valve against full pump pressure. Inspect storage racks for moisture or dirt accumulation. Remove nozzle for inspection of content impinged upon the mesh screen. Clean and dry screens before nozzles are returned to service. Tests nozzle interlocks. Check the operation of the manual valve crank assembly for smooth and positive motion on a special test stand.
481258243Dona AnaAbove Ground Piping and Equipment CoatingsUnkUnkUnkX6-10.1No Manufacturer Requirements AvailableNo Operator Requirement
481258243Dona AnaSight Flow IndicatorsOffload AreaUnkUnkUnk6-12.3Verify there are no leaks around pipe connection fittings and glass seals. Also check glass for indications of cracks.Daily or at each use - Verify there are no leaks around pipe connection fittings and glass seals. Also check glass for indications of cracks.
481258243Dona AnaSight Flow IndicatorsOffload AreaUnkUnkUnk6-12.3Verify there are no leaks around pipe connection fittings and glass seals. Also check glass for indications of cracks.Daily or at each use - Verify there are no leaks around pipe connection fittings and glass seals. Also check glass for indications of cracks.
481258243Dona AnaSight Flow IndicatorsOffload AreaUnkUnkUnk6-12.3Verify there are no leaks around pipe connection fittings and glass seals. Also check glass for indications of cracks.Daily or at each use - Verify there are no leaks around pipe connection fittings and glass seals. Also check glass for indications of cracks.
481258243Dona AnaSight Flow IndicatorsOffload AreaUnkUnkUnk6-12.3Verify there are no leaks around pipe connection fittings and glass seals. Also check glass for indications of cracks.Daily or at each use - Verify there are no leaks around pipe connection fittings and glass seals. Also check glass for indications of cracks.
481258243Dona AnaGate ValvesWater DrainUnkUnkUnkXX6-6.2.3Operate from fully open to fully closed . Conduct Tightness test as required for application.No Operator Requirement
481258243Dona AnaGate ValvesWater DrainUnkUnkUnkXX6-6.2.3Operate from fully open to fully closed . Conduct Tightness test as required for application.No Operator Requirement
481258243Dona AnaGate ValvesWater DrainUnkUnkUnkXX6-6.2.3Operate from fully open to fully closed . Conduct Tightness test as required for application.No Operator Requirement
481258243Dona AnaGate ValvesFillstandUnkUnkUnkXX6-6.2.3Operate from fully open to fully closed . Conduct Tightness test as required for application.No Operator Requirement
481258243Dona AnaGate ValvesFillstandUnkUnkUnkXX6-6.2.3Operate from fully open to fully closed . Conduct Tightness test as required for application.No Operator Requirement
481258243Dona AnaGate ValvesFillstandUnkUnkUnkXX6-6.2.3Operate from fully open to fully closed . Conduct Tightness test as required for application.No Operator Requirement
481258243Dona AnaGate ValvesFillstandUnkUnkUnkXX6-6.2.3Operate from fully open to fully closed . Conduct Tightness test as required for application.No Operator Requirement
481258243Dona AnaGate ValvesOflloadUnkUnkUnkXX6-6.2.3Operate from fully open to fully closed . Conduct Tightness test as required for application.No Operator Requirement
481258243Dona AnaGate ValvesOflloadUnkUnkUnkXX6-6.2.3Operate from fully open to fully closed . Conduct Tightness test as required for application.No Operator Requirement
481258243Dona AnaGate ValvesOflloadUnkUnkUnkXX6-6.2.3Operate from fully open to fully closed . Conduct Tightness test as required for application.No Operator Requirement
481258243Dona AnaGate ValvesOflloadUnkUnkUnkXX6-6.2.3Operate from fully open to fully closed . Conduct Tightness test as required for application.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesFillstandUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesFillstandUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesFillstandUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesFillstandUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesFillstandUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesFillstandUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesFillstandUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesFillstandUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesFillstandUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesFillstandUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesFillstandUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesFillstandUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesPump 2UnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesFillstandUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesFillstandUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesFillstandUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesFillstandUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesFillstandUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesFillstandUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesTank 8243CUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesTank 8243EUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaBall ValvesOffload AreaUnkUnkUnkX6-6.2.4Operate from fully open to fully closed with 90 degree rotation of the ball.No Operator Requirement
481258243Dona AnaPressure and Pressure Vacuum GaugesFillstandUnkUnk0-300XXX6-7.1Check operation of gauge. Ensure gauge is indicating pressure of the system. Inspect liquid level, and clean exterior glass. Calibrate as required dependent on use.Monthly - Check operation of gauge. Ensure gauge is indicating pressure of the system.
481258243Dona AnaPressure and Pressure Vacuum GaugesFillstandUnkUnk0-100XXX6-7.1Check operation of gauge. Ensure gauge is indicating pressure of the system. Inspect liquid level, and clean exterior glass. Calibrate as required dependent on use.Monthly - Check operation of gauge. Ensure gauge is indicating pressure of the system.
481258243Dona AnaPressure and Pressure Vacuum GaugesOffloadUnkUnk0-200XXX6-7.1Check operation of gauge. Ensure gauge is indicating pressure of the system. Inspect liquid level, and clean exterior glass. Calibrate as required dependent on use.Monthly - Check operation of gauge. Ensure gauge is indicating pressure of the system.
481258243Dona AnaPressure and Pressure Vacuum GaugesOffloadUnkUnk0-200XXX6-7.1Check operation of gauge. Ensure gauge is indicating pressure of the system. Inspect liquid level, and clean exterior glass. Calibrate as required dependent on use.Monthly - Check operation of gauge. Ensure gauge is indicating pressure of the system.
481258243Dona AnaDifferential Pressure GaugesReceiptGammon534-30 / 0211150-20XX6-7.2Periodic calibration of this instrument is unnecessary because the graduated scale is made to match the characteristics (load/deflection curve) of the spring. If the spring loses some of its strength for some reason, the ”free length” must be shortened. Afull length spring will always provide accurate readings. This is a fundamental truth about compression springs. This spring is at its “free full length” when there is zero differential pressure; the top of the piston is then in the “zero” band of the graduated scale.Quarterly - Clean outside of gauge glass.
481258243Dona AnaDifferential Pressure GaugesIssueGammon534-30 / 0211150-20XX6-7.2Periodic calibration of this instrument is unnecessary because the graduated scale is made to match the characteristics (load/deflection curve) of the spring. If the spring loses some of its strength for some reason, the ”free length” must be shortened. Afull length spring will always provide accurate readings. This is a fundamental truth about compression springs. This spring is at its “free full length” when there is zero differential pressure; the top of the piston is then in the “zero” band of the graduated scale.Quarterly - Clean outside of gauge glass.
481258243Dona AnaDispenser SumpsDual Dispensing Aviation / 1/2UnkUnkUnkX7-13nspect sump pipe transition fittings for tears, cracks, or other signs of deterioration. Test dispenser sumps and ensure they are liquid tight by using vacuum, pressure, or liquid testing in accordance with 40 CFR 280, Section 43.Monthly - Inspect for signs of water, fuel, trash, and debris inside sumps. Remove and properly dispose of collected water, fuel, trash, and debris. Visually inspect penetration fittings. If fuel or water is detected investigate the source and repair.Every 3 Years
481258243Dona AnaDispenser SumpsDual Dispensing Aviation / 3/4UnkUnkUnkX7-13nspect sump pipe transition fittings for tears, cracks, or other signs of deterioration. Test dispenser sumps and ensure they are liquid tight by using vacuum, pressure, or liquid testing in accordance with 40 CFR 280, Section 43.Monthly - Inspect for signs of water, fuel, trash, and debris inside sumps. Remove and properly dispose of collected water, fuel, trash, and debris. Visually inspect penetration fittings. If fuel or water is detected investigate the source and repair.Every 3 Years
481258243Dona AnaEFSO SystemsRecieptUnkUnkUnkX7-16Proper operation, box seals for integrity. Electrical connections for continuity.No Operator Requirement
481258243Dona AnaEFSO SystemsIssueUnkUnkUnkX7-16Proper operation, box seals for integrity. Electrical connections for continuity.No Operator Requirement
481258243Dona AnaEFSO SystemsOps BuildingN/AN/AN/AX7-16Proper operation, box seals for integrity. Electrical connections for continuity.No Operator Requirement
481258243Dona AnaEFSO SystemsInside FencingN/AN/AN/AX7-16Proper operation, box seals for integrity. Electrical connections for continuity.No Operator Requirement
481258243Dona AnaEFSO SystemsInside FencingN/AN/AN/AX7-16Proper operation, box seals for integrity. Electrical connections for continuity.No Operator Requirement
481258243Dona AnaEFSO SystemsInside FencingN/AN/AN/AX7-16Proper operation, box seals for integrity. Electrical connections for continuity.No Operator Requirement
481258243Dona AnaDispenser NozzlesDual Dispensing Aviation 1HuskyUnkUnkX7-2Start flow into approved test container; place nozzle

in low clip position. Immerse nozzle spout tip in the gasoline in the approved test container. The nozzle tip must be at least three (3) inches from the bottom of the container to prevent back-pressure in the spout. Nozzle must shut off five consective tests. Daily - Inspect dispenser nozzle spout. Ensure it is tight, round, has no cracks, or excessive wear. Inspect automatic shutoff hole. Ensure the hole is open and free of obstructions. Inspect nozzle hold-open latch. Ensure the latch is straight, moves freely, and the return spring operates correctly. Inspect body of nozzle. Ensure the body is in good condition and that the valve stem is clean and free of fuel. Inspect the nozzle to hose connection and ensure it is clean and free of fuel.

Monthly - Dispenser nozzle handles shall be inspected for an expiration date established by the manufacturer. Nozzles must be replaced before the indicated expiration date.

48125 8243 Dona Ana Dispenser Nozzles Dual Dispensing Aviation 2 Husky Unk Unk X 7-2 Start flow into approved test container; place nozzle in low clip position. Immerse nozzle spout tip in the gasoline in the approved test container. The nozzle tip must be at least three (3) inches from the bottom of the container to prevent back-pressure in the spout. Nozzle must shut off five consective tests. Daily - Inspect dispenser nozzle spout. Ensure it is tight, round, has no cracks, or excessive wear. Inspect automatic shutoff hole. Ensure the hole is open and free of obstructions. Inspect nozzle hold-open latch. Ensure the latch is straight, moves freely, and the return spring operates correctly. Inspect body of nozzle. Ensure the body is in good condition and that the valve stem is clean and free of fuel. Inspect the nozzle to hose connection and ensure it is clean and free of fuel.

Monthly - Dispenser nozzle handles shall be inspected for an expiration date established by the manufacturer. Nozzles must be replaced before the indicated expiration date.

48125 8243 Dona Ana Dispenser Nozzles Dual Dispensing Aviation 3 Husky Unk Unk X 7-2 Start flow into approved test container; place nozzle in low clip position. Immerse nozzle spout tip in the gasoline in the approved test container. The nozzle tip must be at least three (3) inches from the bottom of the container to prevent back-pressure in the spout. Nozzle must shut off five consective tests. Daily - Inspect dispenser nozzle spout. Ensure it is tight, round, has no cracks, or excessive wear. Inspect automatic shutoff hole. Ensure the hole is open and free of obstructions. Inspect nozzle hold-open latch. Ensure the latch is straight, moves freely, and the return spring operates correctly. Inspect body of nozzle. Ensure the body is in good condition and that the valve stem is clean and free of fuel. Inspect the nozzle to hose connection and ensure it is clean and free of fuel.

Monthly - Dispenser nozzle handles shall be inspected for an expiration date established by the manufacturer. Nozzles must be replaced before the indicated expiration date.

48125 8243 Dona Ana Dispenser Nozzles Dual Dispensing Aviation 4 Husky Unk Unk X 7-2 Start flow into approved test container; place nozzle in low clip position. Immerse nozzle spout tip in the gasoline in the approved test container. The nozzle tip must be at least three (3) inches from the bottom of the container to prevent back-pressure in the spout. Nozzle must shut off five consective tests. Daily - Inspect dispenser nozzle spout. Ensure it is tight, round, has no cracks, or excessive wear. Inspect automatic shutoff hole. Ensure the hole is open and free of obstructions. Inspect nozzle hold-open latch. Ensure the latch is straight, moves freely, and the return spring operates correctly. Inspect body of nozzle. Ensure the body is in good condition and that the valve stem is clean and free of fuel. Inspect the nozzle to hose connection and ensure it is clean and free of fuel.

Monthly - Dispenser nozzle handles shall be inspected for an expiration date established by the manufacturer. Nozzles must be replaced before the indicated expiration date.

481258243Dona AnaDispenser HosesDual Dispensing Aviation 1N/AN/A1 Inch7-3Check for expiration date, and physical condition/damage leaks.Daily - Inspect dispenser hoses and hose whips for gouges, cuts, blisters, or outside wear that may lead to rupture during use. Replace hose or hose whips that show signs of wear. Inspect connection points of hoses and hose whips to the dispenser, breakaways, swivels, and the nozzle and ensure the connection points are clean and free of fuel.
481258243Dona AnaDispenser HosesDual Dispensing Aviation 2N/AN/A1 Inch7-3Check for expiration date, and physical condition/damage leaks.Daily - Inspect dispenser hoses and hose whips for gouges, cuts, blisters, or outside wear that may lead to rupture during use. Replace hose or hose whips that show signs of wear. Inspect connection points of hoses and hose whips to the dispenser, breakaways, swivels, and the nozzle and ensure the connection points are clean and free of fuel.
481258243Dona AnaDispenser HosesDual Dispensing Aviation 3N/AN/A1 Inch7-3Check for expiration date, and physical condition/damage leaks.Daily - Inspect dispenser hoses and hose whips for gouges, cuts, blisters, or outside wear that may lead to rupture during use. Replace hose or hose whips that show signs of wear. Inspect connection points of hoses and hose whips to the dispenser, breakaways, swivels, and the nozzle and ensure the connection points are clean and free of fuel.
481258243Dona AnaDispenser HosesDual Dispensing Aviation 4N/AN/A1 Inch7-3Check for expiration date, and physical condition/damage leaks.Daily - Inspect dispenser hoses and hose whips for gouges, cuts, blisters, or outside wear that may lead to rupture during use. Replace hose or hose whips that show signs of wear. Inspect connection points of hoses and hose whips to the dispenser, breakaways, swivels, and the nozzle and ensure the connection points are clean and free of fuel.
481258243Dona AnaDispenser CabinetDual Dispensing Aviation / 1/2N/AN/AN/AX7-7Inspect for damage, ensure door panels and locks are functional.Monthly - Inspect outside of cabinet and ensure it is free of damage. Inspect for fuel stains on the concrete island around the cabinet and on the outside of the cabinet. Ensure the cabinet is free of dirt and fuel. Open both sides of the cabinet and inspect the inside of the cabinet. Ensure the inside of the cabinet and all of the components inside the cabinet are clean and free of fuel.
481258243Dona AnaDispenser CabinetDual Dispensing Aviation / 3/4N/AN/AN/AX7-7Inspect for damage, ensure door panels and locks are functional.Monthly - Inspect outside of cabinet and ensure it is free of damage. Inspect for fuel stains on the concrete island around the cabinet and on the outside of the cabinet. Ensure the cabinet is free of dirt and fuel. Open both sides of the cabinet and inspect the inside of the cabinet. Ensure the inside of the cabinet and all of the components inside the cabinet are clean and free of fuel.
481258243Dona AnaDispenser MetersDual Dispensing Aviation 1UnkUnkN/AX7-8Inspect for damage, smooth operation and legibility.Monthly - Inspect meter and ensure meter is clean and free of fuel. Ensure calibration mechanism is sealed.
481258243Dona AnaDispenser MetersDual Dispensing Aviation 2UnkUnkN/AX7-8Inspect for damage, smooth operation and legibility.Monthly - Inspect meter and ensure meter is clean and free of fuel. Ensure calibration mechanism is sealed.
481258243Dona AnaDispenser MetersDual Dispensing Aviation 3UnkUnkN/AX7-8Inspect for damage, smooth operation and legibility.Monthly - Inspect meter and ensure meter is clean and free of fuel. Ensure calibration mechanism is sealed.
481258243Dona AnaDispenser MetersDual Dispensing Aviation 4UnkUnkN/AX7-8Inspect for damage, smooth operation and legibility.Monthly - Inspect meter and ensure meter is clean and free of fuel. Ensure calibration mechanism is sealed.
481258243Dona AnaDispenser FiltersDual Dispensing Aviation 1N/A70012N/AX7-9Check exterior for damageNo Operator Requirement
481258243Dona AnaDispenser FiltersDual Dispensing Aviation 2N/A70012N/AX7-9Check exterior for damageNo Operator Requirement
481258243Dona AnaDispenser FiltersDual Dispensing Aviation 3N/A70012N/AX7-9Check exterior for damageNo Operator Requirement
481258243Dona AnaDispenser FiltersDual Dispensing Aviation 4N/A70012N/AX7-9Check exterior for damageNo Operator Requirement
481258243Dona AnaContainment Systems GeneralN/AN/AN/AX8-10.1No Manufacturer Requirements AvailableDaily - Inspect containment systems for cleanliness, if accessible.
481258243Dona AnaDike Berm FloorsConcrete DikeN/AN/AN/AX8-10.2.2No Manufacturer Requirements AvailableDaily - Inspect for vegetation that has taken root in seals or cracks. All vegetation shall be removed in all cases to prevent penetration of seals, joints or cracks in the concrete.
481258243Dona AnaDike/Berm FloorsN/AN/AN/AX8-10.2.2No Manufacturer Requirements AvailableDaily - Inspect for vegetation that has taken root in seals or cracks. All vegetation shall be removed in all cases to prevent penetration of seals, joints or cracks in the concrete.
481258243Dona AnaPipe PenetrationsN/AN/AN/AXX8-10.6No Manufacturer Requirements AvailableNo Operator Requirement
481258243Dona AnaAbove Ground Shop Fabricated TanksAviation/ 8243CBMTN/A50,000X8-5.1No Manufacturer Requirements AvailableMonthly - Monthly External Inspection (Identified as P in Table 8-2): Visually inspect for exterior signs of corrosion or coating deterioration. Visually inspect weld seams, tank-to-saddle connections, tank supports, tank anchors, foundation and anchor bolts, overfill valves and alarms, normal vents, emergency vents, leak detection probe or water/petroleum accumulation in the interstice on double-walled tanks, leaking valves, fittings, or components, spill containment systems and release prevention barriers. Leaking valves, fittings or components shall be repaired immediately or immediately removed from service and isolated to prevent further discharge. Any irregularities, (e.g., missing valve handles, bolts, nuts, screens) will be assessed for priority and repaired as soon as possible or as required depending on the nature of the defect (See Appendix E for an example of the STI SP001 Standard Monthly Inspection Checklist).

Annually - Annual External Inspection (Identified as P in Table 8-2): A more detailed examination of the tank and appurtenances shall be performed on an annual basis (See Appendix E for an example of the STI SP001 Standard Annual Inspection Checklist).

48125 8243 Dona Ana Above Ground Shop Fabricated Tanks Aviation / 8243E BMT N/A 20,000 X 8-5.1 No Manufacturer Requirements Available Monthly - Monthly External Inspection (Identified as P in Table 8-2): Visually inspect for exterior signs of corrosion or coating deterioration. Visually inspect weld seams, tank-to-saddle connections, tank supports, tank anchors, foundation and anchor bolts, overfill valves and alarms, normal vents, emergency vents, leak detection probe or water/petroleum accumulation in the interstice on double-walled tanks, leaking valves, fittings, or components, spill containment systems and release prevention barriers. Leaking valves, fittings or components shall be repaired immediately or immediately removed from service and isolated to prevent further discharge. Any irregularities, (e.g., missing valve handles, bolts, nuts, screens) will be assessed for priority and repaired as soon as possible or as required depending on the nature of the defect (See Appendix E for an example of the STI SP001 Standard Monthly Inspection Checklist).

Annually - Annual External Inspection (Identified as P in Table 8-2): A more detailed examination of the tank and appurtenances shall be performed on an annual basis (See Appendix E for an example of the STI SP001 Standard Annual Inspection Checklist).

481258243Dona AnaProduct Saver TanksFillstandUnkUnkUnkX8-9.10No Manufacturer Requirements AvailableNo Operator Requirement
481258243Dona AnaTank Pressure / Vacuum Vents8243CN/AN/AN/AX8-9.3Maintenance Annual inspection, and immediate inspection during freezing conditions, by someone familiar with the proper operation of the storage tank vents, is required to insure venting devices are functioning properly before filling or unloading a tank. Steps 1. Carefully remove vent from the riser pipe. 2. To insure that the poppets are moving freely, turn unit upside down and right side up and listen for poppet movement. 3. Inspect the vacuum, pressure, and adaptor screens for debris, if any is found clean or replace. 4. Inspect all vent components and surfaces for damage, corrosion or excessive wear. If any is found, replace the vent.Annually - On underground shop fabricated tanks, ensure tank pressure/vacuum vent is present and that the riser pipe is securely supported and vertical.
481258243Dona AnaTank Pressure / Vacuum Vents8243EN/AN/AN/AX8-9.3Maintenance Annual inspection, and immediate inspection during freezing conditions, by someone familiar with the proper operation of the storage tank vents, is required to insure venting devices are functioning properly before filling or unloading a tank. Steps 1. Carefully remove vent from the riser pipe. 2. To insure that the poppets are moving freely, turn unit upside down and right side up and listen for poppet movement. 3. Inspect the vacuum, pressure, and adaptor screens for debris, if any is found clean or replace. 4. Inspect all vent components and surfaces for damage, corrosion or excessive wear. If any is found, replace the vent.Annually - On underground shop fabricated tanks, ensure tank pressure/vacuum vent is present and that the riser pipe is securely supported and vertical.
481258243Dona AnaElectrical EquipmentUnkUnkUnkX9-1.2No Manufacturer Requirements AvailableNo Operator Requirement
481258243Dona AnaMotor Controls50K TankUnkUnkUnkXX9-1.4Moving parts should operate easily without excessive friction. Check operation of contactors and relays by hand, feeling for any binding or sticking. Look for loose pins, bolts, or bearings. If the control is dirty, it should be wiped or blown clean.

Contact inspection. Check contacts for pitting and signs of overheating, such as discoloration of metal, charred insulation, or odor. Be sure contact pressure is adequate and the same on all poles; verify with manufacturer's specification. Watch for frayed flexible leads.

Contact resistance testing. On essential controls, perform contact-resistance tests with a low-resistance ohmmeter on a regular basis. Proper contact resistance should be about 50 micro-ohms. Record readings for future comparison. This will indicate trends in the condition of contacts.

Overload relay inspection. Overload relays should receive a thorough inspection and cleaning. You also should check for proper setting.No Operator Requirement
481258243Dona AnaMotor Controls50K TankUnkUnkUnkXX9-1.4Moving parts should operate easily without excessive friction. Check operation of contactors and relays by hand, feeling for any binding or sticking. Look for loose pins, bolts, or bearings. If the control is dirty, it should be wiped or blown clean.

Contact inspection. Check contacts for pitting and signs of overheating, such as discoloration of metal, charred insulation, or odor. Be sure contact pressure is adequate and the same on all poles; verify with manufacturer's specification. Watch for frayed flexible leads.

Contact resistance testing. On essential controls, perform contact-resistance tests with a low-resistance ohmmeter on a regular basis. Proper contact resistance should be about 50 micro-ohms. Record readings for future comparison.