This document includes a request for offer for construction services and a related federal contract opportunity notice. The Federal Aviation Administration is soliciting offers for the establishment of NAVAIDS facilities serving the extended Runway 9R-27L at O'Hare International Airport in Chicago, Illinois. The contractor will provide all labor, materials, and equipment to perform the project, including furnishing and installing an underground storage tank and associated piping and monitoring systems. The performance period is 605 calendar days, with an anticipated start date of November 15, 2020. The estimated price range for this procurement is between $5 million and $10 million. Offers are due by October 7, 2020. Interested firms must have experience with similar airport construction projects and must meet insurance and bonding requirements.
View the file
Other files
Show 40 more
Latest 50 of 158 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
o rd -d -a ls l-m .d g n
/2
/2
:3
:5
P
M G re g o ry C
T R S p e n c e r
A
B
C
D
E
F
G
H
8 7 6 5 4 3 2 1
H
G
F
E
D
C
12345678
REVDRAWING NO
DATE JCN
APPROVED BY
ISSUED BY
CHECKED
DRAWN
DESIGNED
SUBMITTED BY
REVIEWED BY
FEDERAL AVIATION ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
REV
DATE
APPROVED
DESCRIPTION JCN
DATE
REDLINE
APVD
A
NOTE 15
A M003
DETAIL - UNDERGROUND STORAGE TANK
ISOMETRIC VIEW
INSIDE E/G ROOM
MONITOR PANEL
TO TANK
FITTING
SEAL-OFF
WALL
AT SUBSTATION
CONTAINMENT
TERMINATE
FITTING
SEAL-OFF
PANEL INSIDE E/G ROOM
TO TANK MONITOR
SEE NOTE 9
DAY TANK
TO SUBSTATION
E D
M
IS
S
U E
D F
O R
NAVAIDS
IL
10/31/2019 1898272
ORD-D-ALS27L-M002
C O
N S
T R
U C
T
IO
N
ENGINEERING SERVICES
ALS
CHICAGO O’HARE INTERNATIONAL AIRPORTCHICAGO
PROJECT ENGINEER MGR: ENGINEERING
o rd -d -a ls l-m .d g n
THIS DRAWING PRODUCED ON THE AGL REGION MICROSTATION SYSTEM
ATO - TECHNICAL OPERATIONS CENTRAL SERVICE AREA
NOTES:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
18" DIAMETER STEEL MANHOLE FRAME AND COVER
36" DIAMETER STEEL MANHOLE FRAME AND COVER
UL-1238 REQUIREMENTS.
MANHOLE FRAME AND LID INSTALLATION SHALL MEET
SCREEN PIPE WITH PIPE CAP, FILTER SOCK, 18" STEEL
SUBGRADE INSPECTION WELL, CONSISTING OF 8" DIAMETER
SUPPLIER. SEE NOTES 10 AND 11.
RECOMMENDED BY THE TANK MONITOR CONTROL PANEL
NEAR MANHOLE AND AT BUILDING PENETRATIONS AS
ROOM. INSTALL WIRING AND SEAL-OFF FITTINGS IN CONDUIT
CABLES TO TANK MONITOR CONTROL PANEL INSIDE E/G
1" GRSC WITH TANK LEAK DETECTOR SENSOR SIGNAL
MONITOR CONTROL PANEL SUPPLIER. SEE NOTES 10 AND 11.
BUILDING PENETRATIONS AS RECOMMENDED BY THE TANK
SEAL OFF FITTINGS IN CONDUIT NEAR MANHOLE AND AT
CONTROL PANEL INSIDE E/G ROOM. INSTALL WIRING AND
CONTAINMENT SENSOR SIGNAL WIRES TO TANK MONITOR
1" GRSC WITH FUEL LEVEL MONITORING SENSOR AND SUMP
NUMBERED LEGEND:
DOUBLE WALL PIPING SYSTEM PER NOTE 6.
INSTALL RAINPROOF VENT CAP. GROUND PER NOTE 9.
FINISHED GRADE. SECURE TO SUBSTATION WALL AND
2" GALVANIZED STEEL TANK VENT. TOP SHALL BE 12’ ABOVE
FUEL LEVEL PROBE
3/4" DOUBLE POPPET FOOT VALVE ON SUPPLY LINE
OVERFILL SPILL CONTAINER, LOCKABLE, WITH INTERNAL DRAIN
ADAPTER. SEE NOTE 8.
FILL TUBE WITH OVERFILL SHUT-OFF DEVICE AND BRASS FILL
FUEL RETURN PIPE. SEE NOTES 4, 6, AND 7.
FUEL SUPPLY PIPE. SEE NOTES 4, 6, AND 7.
ATTACHED SUMP CONTAINMENT SENSOR
CONCRETE MAINTENANCE PAD
ACCESS COVER SHALL HAVE A WATER-TIGHT SEAL TO RISER.
42" DIAMETER RISER W/22" DIAMETER MANWAY (BY UST SUPPLIER).
42" DIAMETER ATTACHED SUMP CONTAINMENT
STRAP/TURNBUCKLE ANCHOR SYSTEM (BY UST SUPPLIER)
12" x 12" x 12’ CONCRETE DEADMAN SECTION WITH EYELETS
UNDERGROUND STORAGE TANK (UST). SEE NOTE 1.
1000 GALLON FIBERGLASS-REINFORCED PLASTIC DOUBLE-WALL
RUNWAY 27L ALSF-2 / 9R LOCALIZER
INSTALLATION
UNDERGROUND STORAGE TANK (UST)
KE
RC
17.
OR EQUIVALENT.
ALL INTERIOR FUEL PIPING SHOULD BE PAINTED YELLOW. RUSTOLEUM HI-VIS YELLOW
ALLOW FOR THE INSTALLATION OF THIS TANK.
CONTRACTOR IS RESPONSIBLE TO ACQUIRE ANY OF THE NECESSARY PERMITS TO
SEAL AROUND ALL OPENINGS INTO MANWAY TO PREVENT WATER INTRUSION.
DETERMINED BY THE FAA RESIDENT ENGINEER.
MOUNT EACH UNDER PLEXIGLAS IN THE ENGINE GENERATOR ROOM AT LOCATIONS
CONTRACTOR SHALL FURNISH A FUEL FILL CHART AND A FUEL OIL VALVE SCHEDULE AND
STORAGE TANK. COORDINATE LOCATION WITH FAA RESIDENT INSPECTOR.
CONTRACTOR TO FURNISH AND INSTALL A 12" X 12" NFPA PLACARD FOR UNDERGROUND
LOCATE SEAL-OFF FITTINGS IN TANK MANHOLE ACCESS WELL.
VEEDER ROOT MODEL 300C MEETS SPECIFICATION.
DIAGRAMS, PRODUCT DATA SHEETS, AND INSTALLATION METHODS AND PROCEDURES.
COMMUNICATIONS CAPABILITY. SYSTEM SUPPLIER MUST PROVIDE FUNCTIONAL SCHEMATIC
FUEL INDICATOR WITH REGISTRATION IN GALLONS, OVERFILL ALARM, AND REMOTE
PANELS SHALL HAVE VISUAL AND AUDIBLE, HIGH AND LOW TANK LEVEL ALARMS,
PER MANUFACTURERS INSTALLATION AND WIRING INSTRUCTIONS. ANNUNCIATOR
LIMITED TO, PROBES, CONTROL PANEL, POWER, MONITORING AND SIGNAL CABLES
FURNISH AND INSTALL FUEL LEVEL MONITORING SYSTEM INCLUDING, BUT NOT
BELOW-GRADE SECTIONS OF GRS CONDUIT SHALL BE COATED WITH ASPHALTUM.
SUBSTATION PERIMETER GROUNDING CONDUCTOR VIA EXOTHERMIC WELD.
4/0 AWG BARE COPPER#AWG BARE COPPER GROUND WIRE FROM CLAMP TO BURIED
2#INSTALL GROUNDING CLAMP AT BASE OF 2" GRSC TANK VENT PIPE AND ROUTE
H20 LOAD REQUIREMENTS.
LOCKABLE FILL TUBE COVER AND GROUND MONITOR COVER THAT MEET
FURNISH AND INSTALL BOLTED MANHOLE COVER FOR TANK COLLAR AND
FUEL OIL WITH ANTI-CLOUDING ADDITIVE.
COMPLETION OF LEAK TESTING, TANK SHALL BE FILLED USING NO. 2 DIESEL
FILLING TANK USING AN INTERNAL PRESSURE OF 5.0 PSI. UPON SUCCESSFUL
TANK AND PIPING CONNECTIONS SHALL BE TESTED FOR LEAKS PRIOR TO
SYSTEM MANUFACTURED BY XERXES, MINNEAPOLIS, MN MEETS SPECIFICATIONS.
ENTERING SUBSTATION. ENVIROFLEX DOUBLE-WALL PIPE CONTAINMENT
RESISTIVE BLACK IRON PIPE INSIDE CONTAINMENT RISER AND BEFORE
TRANSITION FROM ENVIROFLEX PIPE TO RIGID 3/4" SCHEDULE 40, CORROSION
CONTAINMENT TO DETECT LEAKS IN SUPPLY AND RETURN FUEL LINES.
RISER AND BUILDING WALL. INSTALL LEAK DETECTION SENSOR INSIDE SUMP
FITTINGS AND END CAPS REQUIRED TO TERMINATE AT SUMP CONTAINMENT
WITH TWO 3/4" PRIMARY PIPES FOR FUEL SUPPLY AND RETURN. INSTALL
DOUBLE-WALL PIPING SYSTEM SHALL CONSIST OF 4" OUTER SECONDARY PIPE
AT BUILDING WALL.
INSTALLED IN " GALVANIZED RIGID STEEL CONDUIT. SEAL PENETRATION
INSTALLATION INSTRUCTIONS. THE MONITOR SIGNAL WIRES SHALL BE
SHALL BE INSTALLED PER TANK MONITORING SYSTEM MANUFACTURER’S
THE TANK MONITOR FUEL PROBE SENSOR AND LEAK DETECTOR SENSOR
FUEL OIL AND GASOLINE STORAGE BY STATE AND LOCAL FIRE MARSHALS.
WITH FITTINGS OF BLACK MALLEABLE IRON APPROVED FOR USE WITH
ALL PIPE SHALL BE CORROSION PROTECTED BLACK IRON PIPE, SCH.40,
FURNISHED AND INSTALLED BY CONTRACTOR.
DIP TUBE (TYPE PER TANK MANUFACTURER’S RECOMMENDATION) SHALL BE
AT LEAST 48 HOURS PRIOR TO INSTALLATION TO COORDINATE INSTALLATION.
WITH ALL STATE AND LOCAL CODES. CONTACT LOCAL FIRE MARSHAL
INSTALLATION INSTRUCTIONS (PROVIDED WITH TANK) AND SHALL COMPLY
TANK SHALL BE INSTALLED IN ACCORDANCE WITH MANUFACTURER’S
OVERALL TANK INSTALLATION SHALL COMPLY WITH CFR-40, PART 280.20(B).
SUBSTITUTION OF TANK TO THE RESIDENT ENGINEER FOR APPROVAL.
MINNEAPOLIS, MN. CONTRACTOR SHALL PROVIDE SHOP DRAWINGS FOR
4’ DIA., DOUBLE-WALL, FRP TANK MANUFACTURED BY XERXES CORPORATION,
WITH UL 1316 (W/UL CERTIFICATION PLATE). DETAILS SHOWN DEPICT 1000 GAL,
AND A 30-YEAR WARRANTY. TANK SHALL BE MANUFACTURED IN ACCORDANCE
OUTLET DESIGN SHALL HAVE SECONDARY CONTAINMENT (150 GALLONS CAPACITY)
DOUBLE-WALL, UNDERGROUND STORAGE TANK (UST) FOR DIESEL FUEL.
CONTRACTOR SHALL FURNISH AND INSTALL A 1000 GALLON FIBERGLASS,
| 2020-07-02T14:09:30-0500 | |
| RAFAEL CRAME |
| 2020-07-09T15:58:32-0500 | |
| LUIS N DOMINGUEZ |
File details come from the government source that posted it. Updated .