This solicitation is for construction services to establish navigational aids facilities serving the extended Runway 9R-27L at O'Hare International Airport in Chicago, Illinois. The contractor shall provide all labor, materials, equipment, and supervision to perform the project in accordance with contract documents, drawings and specifications. Services include establishing buildings, foundations, antenna arrays, lighting systems, underground cabling and other appurtenances for the Runway 9R and 27L localizers, glide slopes, markers, precision approach path indicators, distance measuring equipment and visual range equipment. The performance period is 605 calendar days with an anticipated start date of November 15, 2020. The estimated price range for this procurement is between $5 million and $10 million. Offerors must be experienced with similar airport construction projects and must submit their offer with all required documents by October 7, 2020 to the Federal Aviation Administration Southwestern Region.
View the file
Other files
Show 40 more
Latest 50 of 158 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO.
PAGE OF PAGES
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6)
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
CODE
9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
Items 8 and 15, and returning is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required.)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14.
E. IMPORTANT: Contractor is not, is required to sign this document and return
ORDER NO. IN ITEM 10A.
1 5
0001 09/10/2020
FEDERAL AVIATION ADMINISTRATION
AAQ-500 - REGIONAL ACQUISITIONS
10101 HILLWOOD PARKWAY
FORT WORTH TX 76177-1524
AAQ520FTW-AFN
x
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By ___________ 1 x x
697DCK-20-R-00436
1 copies to the issuing office.
09/10/2020
(x)
Subject project/solicitation for the construction services for the establishment of the
NAVAIDS facilities serving extended Runway 9R-27L at O'Hare International Airport in
Chicago, Illinois is hereby amended as follows:
1. The addition of Line Item No. 00014 for the inclusion of construction services for the
Runway 27L Localizer (LOC)/Runway 9R Approach Lighting System with Sequenced Flashers II
(ALSF-2) Facility. Attached to this amendment is the revised Section B, Continuation
Sheets (Pages 3 - 6) with Item Nos. 00001 - 00014. These pages hereby replace the pages and line items listed in the solicitation.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. CONTRACT AUTHORITY 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Irene Medina
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
X
09/30/2020 Irene Medina
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 5
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
697DCK-20-R-00436/0001
2. For your information and use, starting below on this page of the amendment are questions and answers received during the solicitation phase.
3. The solicitation closing date will remain as
October 7, 2020, 2:00 pm, CDT.
All other terms and conditions remain unchanged.
QUESTIONS AND ANSWERS:
1. The drawings state the paved parking/turn-a-round areas shall be rough graded by the CDA City Contractor. Offeror assumes that this rough grade is +/- 0.1' from design subgrade and that this project will be responsible for fine grading, geotextile fabric, 6" of CA-6 aggregate and 4" of asphalt to meet proposed finish grade. Proposed finish grade shall be 1' below top of ALSF and Glide Slope finish floor or flush with top of foundations at RVR & PAPI locations. Please confirm.
The finished grade shall be 1’ below finished floor at the four shelters and flush at the RVR and PAPI locations. With the installation of 4" of asphalt and 6" of CA-6. Assume that 4" of existing grade shall be cut to make way for new pavement profile by FAA contractor at the four shelter sites.
2. As noted in the Special Specifications, all spoil that is hauled off-site shall be assumed to be CCDD acceptable. Any spoil tested that does not meet CCDD shall incur additional cost to the contract. Please confirm.
FAA confirms.
3. How is the Mid-Point RVR is to be fed electrically? 9R ALSF drawings show the
Mid-Point RVR fed from that location while drawing GS09R-C009, GS09R-E001 & E002 indicate the 9R Glide Slope feeds the Mid-Point RVR.
Please provide cable and ductbank size, quantity and location of the feed.
The MID RVR shall be fed from the 9R ALSF/27L
Continued ...
3 5
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
697DCK-20-R-00436/0001
Localizer shelter site per ORD-D-ALS09R-E010.
Utilize existing CDA installed ductbank and handholes for the routing of the power (2-#4 5kV and # 6 green ground) and control (12PR #19 and
#6 green ground) cables between the two facilities. An additional drawing will be issued showing the route from the MID RVR to the 9R
ALSF/27L LOC site when it is received from the
City of Chicago. Right now, the drawing package only shows the route by the 9R Glide Slope site.
Connections to these handholes will be installed by this contract as delineated on
ORD-D-ALS09R-C002, ORD-D-ALD-G020,
ORD-D-RVR09R-C002 & ORD-D-RVR27L-E001.
4. Please refer to GS09R-C001 and GS09R-C002.
C001 shows a handhole ductbank/casing underneath the taxiway east of the 9R Glide Slope and C002 shows routing cables for the 9R RVR & PAPI north into the CED system for the cabling. Which one is correct?
Follow the route for routing the power and control cables for the TD RVR to the north utilizing the existing CDA route
(ORD-D-GS09R-C002). The FAA is verifying if this crossing actually exists or will be installed prior to our construction start/site turnover from the City.
5. Please refer to GS09R-C003. Is the ductbank that ties the HV handhole to the 9R Glide Slope
25KV transformer not shown but still required to route from HV handhole to transformer?
The ductbank is not shown, but it is still required from the step-down transformer to the 9R
GS shelter. A modified ORD-D-GS09R-C002 drawing will be issued depicting this new route.
6. Please refer to GS09R-C001 and GS09R-C002.
C001 and C002 both show different layout for the paved parking/turnaround area for the 9 R RVR.
Which one is correct?
Please follow ORD-D-GS-09R-C002 for the paving of the 9R TD RVR.
7. The schedule received in Section C of the solicitation requires 3 out of 4 of the buildings
4 5
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
697DCK-20-R-00436/0001
to be constructed through winter and completed within 120 working days. The proposed start date of these sites puts the construction activities, namely structural and exterior work, that are most impacted by weather to occur during the winter season. There are some activities that cannot be performed with any temporary construction measures during these weather conditions. The activities that can occur will be executed in the poorest conditions and the quality of the work may suffer. Moreover, the time period between bid and award does not allow for sufficient time to submit, receive approval, and release material for construction within that time frame. This will affect our pricing.
Please clarify that pricing must be based on the proposed start and completion dates.
Due to the predicted weather, the FAA could entertain releasing the 120 day completion durations. The FAA does want the contractors to take advantage of advantageous weather conditions if they exist.
8. The Special Specifications state that the 27L
ALSF site will be available to start work on
November 15, 2020. However, we understand there are restrictions to working in this area due to other contracts. Please advise what those restrictions are and on what dates those restrictions are lifted.
The restriction is that the FAA cannot build above ground at this site until February 2021 due to the airspace determination.
9. The drawings only indicate bollards to be installed at the 27L ALSF site. Please confirm this is correct, or provide locations and quantities for the bollards to be installed.
Bollards will be required in the same manner and amount for the 9R ALSF site as the 27L ALSF site.
FOB: Destination
Add Item 00014 as follows:
00014 Runway 27L Localizer (LOC)/Runway 9R Approach 1 JB
Lighting System with Sequenced Flashers II
(ALSF-2) Facility. Establish the 27L LOC/Runway
5 5
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
697DCK-20-R-00436/0001
9R ALSF-2 Regulator Building and Foundation, Parking/Turnaround Area, Appurtenances, Underground Cabling for Extended Runway 9R-27L at O'Hare International Airport, Chicago, Illinois.
3 60
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
697DCK-20-R-00436
(A) (B) (C) (D) (E) (F)
FOB: Destination
00001 Runway 9R Localizer (LOC)/Runway 27L Approach
Lighting System with Sequenced Flashers II
(ALSF-2) Facility. Establish the 9R LOC/Runway
27L ALSF-2 Regulator Building and Foundation, Parking/Turnaround Area, Appurtenances, Underground Cabling for Extended Runway 9R-27L at
O'Hare International Airport, Chicago, Illinois.
Amount: $_________________________
Electronic & IT: 03
00002 Runway 9R Glide Slope (GS). Establish the 9R GS
Building and Foundation, Parking/Turnaround Area, Appurtenances, Underground Cabling for Extended
Runway 9R-27L at O'Hare International Airport, Chicago, Illinois.
Amount: $_________________________
Electronic & IT: 03
00003 Runway 9R Localizer (LOC). Establish the 9R LOC
Antenna Array and Underground Cabling for
Extended Runway 9R-27L at O'Hare International
Airport, Chicago, Illinois.
Amount: $_________________________
Electronic & IT: 03
00004 Runway 9R Far Field Monitor (FFM). Establish the
4 60
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
697DCK-20-R-00436
(A) (B) (C) (D) (E) (F)
9R FFM Antenna and Underground Cabling for
Extended Runway 9R-27L at O'Hare International
Airport, Chicago, Illinois.
Amount: $_________________________
Electronic & IT: 03
00005 Runway 9R Inner Marker (IM). Establish the 9R IM
Antenna and Underground Cabling for Extended
Runway 9R-27L at O'Hare International Airport, Chicago, Illinois.
Amount: $_________________________
Electronic & IT: 03
00006 Runway 9R Precision Approach Path Indicator
(PAPI). Establish the 9R PAPI Light Array, Equipment Rack and Underground Cabling for
Extended Runway 9R-27L, O'Hare International
Airport, Chicago, Illinois.
Amount: $_________________________
Electronic & IT: 03
00007 Runway 9R-27L Distance Measuring Equipment (DME).
Establish the 9R-27L DME Antenna and Foundation, Underground Cabling for Extended Runway 9R-27L, O'Hare International Airport, Chicago, Illinois.
Amount: $_________________________
5 60
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
697DCK-20-R-00436
(A) (B) (C) (D) (E) (F)
Electronic & IT: 03
00008 Runway 9R-27L Runway Visual Range (RVR).
Establish the 9R TD RVR, 27L TD RVR and 9R-27L
MID RVR Pole, Equipment Rack and Underground
Cabling for Extended Runway 9R-27L at O'Hare
International Airport, Chicago, Illinois.
Amount: $_________________________
Electronic & IT: 03
00009 Runway 27L Glide Slope (GS). Establish the 27L
GS Building and Foundation, Parking/Turnaround
Area, Appurtenances, Underground Cabling for
Extended Runway 9R-27L at O'Hare International
Airport, Chicago, Illinois.
Amount: $_________________________
Electronic & IT: 03
00010 Runway 28L Localizer (LOC). Establish the 27L
LOC Antenna Array and Underground Cabling for
Extended Runway 9R-27L at O'Hare International
Airport, Chicago, Illinois
Amount: $_________________________
Electronic & IT: 03
00011 Runway 27L Far Field Monitor (FFM). Establish
6 60
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
697DCK-20-R-00436
(A) (B) (C) (D) (E) (F)
00012
00013 the 27L FFM Antenna and Underground Cabling for Extended Runway 9R-27L at O'Hare International Airport, Chicago, Illinois
Amount: $_________________________
Electronic & IT: 03
Runway 27L Inner Marker (IM). Establish the 27L IM Antenna and Underground Cabling for Extended Runway 9R-27L at O’Hare International Airport, Chicago, Illinois
Amount: $_________________________
Electronic & IT: 03
Runway 27L Precision Approach Path Indicator
(PAPI). Establish the 27L PAPI Light Array, Equipment Rack and Underground Cabling for Extended Runway 9R-27L at O’Hare International Airport, Chicago, Illinois
Amount: $_________________________
Electronic & IT: 03
00014
TOTAL AMOUNT: $______________________________
Runway 27L Localizer (LOC)/Runway 9R Approach Lighting System with Sequenced Flashers II (ALSF-2) Facility. Establish the 27L LOC/ Runway 9R ALSF-2 Regulator Building and Foundation, Parking/Turnaround Area, Appurtenances, Underground Cabling for Extended Runway 9R-27L at O'Hare International Airport, Chicago, Illinois.
Amount: $_________________________ Electronic & IT: 03
File details come from the government source that posted it. Updated .