HVAC Renovation for Bldg 174 Aerial Delivery Facility
Solicitation number
FA4418-19-R-A004
Issued by

About this file

FA4418-19-R-A004 AF 66

View the file

Other versions and copies of AF Form 66

File Revision Posted Attached to
Attachment 2 AF Form 66.pdf Revision not stated REPAIR AC PAVING
AF form 66 Blank.pdf Revision not stated Demo Mini mute sites
Attach 9_AF Form 66 Submittal Register.pdf Revision not stated PKAA Dorm Water Damage Repair (Construction)
AF Form 66-EEPZ260842 Renovate Convert Comm to SAPR B730.xlsx Revision not stated B730 Renovate Convert Comm to SAPR
AF Form 66_EEPZ254664-B972 UOQ.xlsx Revision not stated B972 Renovate UOQ Community Commons
AF Form 66 B268.xlsx Revision not stated B268 Replace STUS Backup Generator
AF Form 66 B730.xlsx Revision not stated B730 - Renovate RM106 for Emergency Operations Center
AF Form 66.xlsx Revision not stated B836 Replace Electrical in Airfield Lighting Vault
AF Form 66 OSI Flooring.xlsx Revision not stated OSI B926 Flooring
EEPZ254660 Repair Control Tower HVAC B1806 - AF Form 66.xlsx Revision not stated B1806 Repair Control Tower HVAC
AF Form 66 Template.xlsx Revision not stated Replace AAS BAK-15 Controls, B2001, B2003
AF Form 66 EEPZ216808 Replace Security Forces Elevator B926.xlsx Revision not stated B926 Replace Security Forces Elevator
WT 17518487 AF Form 66.xlsx Revision not stated Repair Structural Fire Trainer B17903, 17904
AF Form 66.xlsx Revision not stated RENOVATE/CONVERT 50th 49th SQ OPS, B230
AF Form 66.xlsx Revision not stated T-6 Flightline Shacks
AF Form 66 Template.xlsx Revision not stated Replace Fire Alarms, Multi Facility
EEPZ248229 -- AF Form 66.xlsx Revision not stated Repair Kiddie Pool
Atch 2 AF Form 66.pdf Revision not stated Removal of Underground Storage Tank at Launch Facility E-10 (Laramie County, WY)
Attachment 4 - AF Form 66 Submittal Register.pdf Revision not stated Bldg 65 - Renovation of Telephone Office Area, FE Warren AFB, WY AMENDMENT 03
Attachment 7 - AF Form 66.xlsx Revision not stated Replace Chapel Windows B912
Show all 20

Who attaches AF Form 66

State Files
Iowa 1
Massachusetts 1

Other files

File Type Posted
Site_Visit_Questions.pdf PDF
Addendum_1_FA4418-19-R-A0004.pdf PDF
30_Nov_18_(Correct)_General_Drawings.pdf PDF
Specifications_.pdf PDF
Electrical_Drawings.pdf PDF
Mechanical_Drawings.pdf PDF
Wage_Determination.pdf PDF
Solicitation_-_FA441819RA0040001.pdf PDF
General_Drawings.pdf PDF
Green_Procurement_Form.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

Line

Acti vity

Trans-mittal #

Specification

Section

SD

# Submittal Description Item Submitted

Paragraph

Classificati on: GOVT or A/E

Revwr Submit

Approval

Needed

By

Material

Needed

By

Action

Code

Date Of

Action

Date FWD to APPR /

Auth Date

RCD From

CONTR

Date

FWD To

Other

Revwr

Date

RCD

From

Other

Revwr

Action

Code

Date Of

Action

Mailed To

CONTR/

Date RCD

From

APPR

Authority Remarks

1 01 11 00 01 Preconstruction Submittals Utility Outage G

2 01 11 00 01 Preconstruction Submittals Road Closure Requests G

3 01 11 00 01 Preconstruction Submittals Air Force Work Clearance Permit G

4 01 11 00 01 Preconstruction Submittals Contractor's Proposed Laydown Area

Plan G

5 01 14 00 01 Preconstruction Submittals List of Contact Personnel 1.2.1.1 G

6 01 30 00 01 Preconstruction Submittals Digital Photograph Location Map 1.2 G

7 01 30 00 01 Preconstruction Submittals Progress and Completion Pictures 1.3 G

8 01 30 00 01 Preconstruction Submittals Resume for Superintendent G

9 01 32 16.00 20 01 Preconstruction Submittals Qualifications 1.2 G

10 01 32 16.00 20 01 Preconstruction Submittals Baseline Project Schedule 1.3.1 G

11 01 32 16.00 20 01 Preconstruction Submittals Initial Contract Progress Report (AF

IMT 3065)

1.4.1 G

12 01 32 16.00 20 01 Preconstruction Submittals Initial Contract Progress Schedule (AF

IMT 3064)

1.4.2 G

13 01 32 16.00 20 07 Certificates Monthly Project Schedule Update G

14 01 32 16.00 20 07 Certificates Bi-Weekly Contract Progress Reports

(AF IMT 3065)

G

15 01 32 16.00 20 07 Certificates Monthly Contract Progress Schedule

(AF IMT 3064)

1.4.2 G

16 01 33 00 01 Preconstruction Submittals Submittal register 1.7 G

17 01 35 26 01 Preconstruction Submittals Accident Prevention Plan (APP) 1.6 G

18 01 35 26 01 Preconstruction Submittals Activity Hazard Analysis (AHA) 1.7 G

19 01 35 26 01 Preconstruction Submittals Crane Critical Lift Plan 1.6.1 G

20 01 35 26 01 Preconstruction Submittals Crane Operators 1.5.1.2 G

21 01 35 26 06 Test Reports Notifications and Reports 1.11

22 01 35 26 06 Test Reports Accident Reports 1.11.2 G

23 01 35 26 06 Test Reports Crane Reports 1.11.3

24 01 35 26 07 Certificates Confined Space Entry Permit 1.8 G

25 01 35 26 07 Certificates Hot work permit 1.8 G

26 01 35 26 07 Certificates License Certificates

27 01 45 00 01 Preconstruction Submittals Construction Quality Control (QC) Plan 1.6.1 G

28 01 50 00 01 Preconstruction Submittals Construction Site Plan 1.3 G

29 01 50 00 01 Preconstruction Submittals Traffic Control Plan 3.4.1 G

30 01 50 10 01 Preconstruction Submittals Material Safety Data Sheet (MSDS) 1.4.1 G

31 01 50 10 06 Test Reports Monthly Green Procurement Report 1.7 G

32 01 50 10 06 Test Reports Annual Green Procurement Report 1.7 G

33 01 50 10 06 Test Reports Monthly Recycling Report 1.3 G

34 01 50 10 06 Test Reports Annual Recycling Report G

TITLE: Repair HVAC, Aerial Delivery Facility, Building 174

SUBMITTAL REGISTER

JOB NAME:

LOCATION: JBC AB B174

CONTRACT NO: DKFX 08-10306

CONTRACTOR:

APPROVING AUTHORITY

(d)

CONTRACTOR SCHEDULE

DATES

CONTRACTOR

ACTION

TITLE: Repair HVAC, Aerial Delivery Facility, Building 174

SUBMITTAL REGISTER

JOB NAME:

LOCATION: JBC AB B174

CONTRACT NO: DKFX 08-10306

CONTRACTOR:

APPROVING AUTHORITY

(d)

CONTRACTOR SCHEDULE

DATES

CONTRACTOR

ACTION

35 01 54 00 03 Product Data Affirmative Procurement Reporting

Form

36 01 54 00 03 Product Data Proposed environmentally preferred products.

37 01 57 20 01 Preconstruction Submittals Construction Waste Management Plan G

38 01 57 50 01 Preconstruction Submittals Preconstruction Survey 1.7.1 G

39 01 57 50 01 Preconstruction Submittals Solid Waste Disposal Permit 1.7.2

40 01 57 50 01 Preconstruction Submittals Regulatory Notifications 1.7.6 G

41 01 57 50 01 Preconstruction Submittals Environmental Protection Plan 1.5 G

42 01 57 50 01 Preconstruction Submittals Storm Water Pollution Prevention Plan G

43 01 57 50 01 Preconstruction Submittals Dirt and Dust Control Plan 1.6 G

44 01 57 50 01 Preconstruction Submittals JB CHS Transient Organization

Hazardous Material Form

3.3.4 G

45 01 57 50 06 Test Reports Laboratory Analysis 3.5.2

46 01 57 50 06 Test Reports Disposal Requirements 3.5.2

47 01 57 50 06 Test Reports Solid Waste Disposal Report 1.7.7 G

48 01 57 50 07 Certificates Contractor 40 CFR employee training records

1.7.5 G

49 01 57 50 11 Closeout Submittals Notice of Termination G

50 01 57 50 11 Closeout Submittals Waste Determination Documentation 1.7.3

51 01 57 50 11 Closeout Submittals Disposal Documentation for Hazardous and Regulated Waste 1.7.4

52 01 57 50 11 Closeout Submittals Contractor 40 CFR Employee Training

Records 1.7.5

53 01 57 50 11 Closeout Submittals Solid Waste Disposal Permit 1.7.2

54 01 57 50 11 Closeout Submittals Solid Waste Disposal Report 1.7.7

55 01 57 50 11 Closeout Submittals JB CHS Transient Organization

Hazardous Material Form

3.3.4 G

56 01 57 50 11 Closeout Submittals Hazardous Waste/Debris Management 3.3.2

57 01 57 50 11 Closeout Submittals Regulatory Notifications 1.7.6

58 01 78 00 03 Product Data Warranty Management Plan 1.5.1

59 01 78 00 03 Product Data Warranty Tags 1.5.4

60 01 78 00 03 Product Data Spare Parts Data 1.4

61 01 78 00 08 Manufacturer’s Instructions Instructions 1.5.1

62 01 78 00 10 Operation and Maintenance Data Operation and Maintenance Manuals 3.7

63 01 78 00 10 Operation and Maintenance Data Condition Monitoring (Predictive

Testing

64 01 78 00 10 Operation and Maintenance Data Inspection

65 01 78 00 10 Operation and Maintenance Data Posted Instructions

66 01 78 00 11 Closeout Submittals As-Built Drawings 3.1 G

67 01 78 00 11 Closeout Submittals Record Drawings G

68 01 78 00 11 Closeout Submittals Final Approved Shop Drawings

69 01 78 00 11 Closeout Submittals Construction Contract Specifications

SUBMITTAL REGISTER

JOB NAME:

LOCATION: JBC AB B174

CONTRACT NO: DKFX 08-10306

CONTRACTOR:

APPROVING AUTHORITY

(d)

CONTRACTOR SCHEDULE

DATES

CONTRACTOR

ACTION

70 01 78 00 11 Closeout Submittals Interim DD Form 1354 G

71 01 78 00 11 Closeout Submittals Checklist for DD Form 1354 G

72 02 41 00 01 Preconstruction Submittals Demolition Plan 1.2.1 G

73 02 41 00 07 Certificates Notification 1.5 G

74 02 41 00 11 Closeout Submittals Receipts

75 03 30 00 01 Preconstruction Submittals Concrete Curing Plan

76 03 30 00 01 Preconstruction Submittals Quality Control Plan G

77 03 30 00 01 Preconstruction Submittals Quality Control Personnel Certifications G

78 03 30 00 01 Preconstruction Submittals Quality Control Organizational Chart

79 03 30 00 01 Preconstruction Submittals Laboratory Accreditation G

80 03 30 00 01 Preconstruction Submittals Form Removal Schedule G

81 03 30 00 02 Shop Drawings Formwork

82 03 30 00 02 Shop Drawings Reinforcing Steel G

83 03 30 00 03 Product Data Joint Sealants 2.4.6

84 03 30 00 03 Product Data Joint Filler 2.4.5

85 03 30 00 03 Product Data Materials for Forms 2.1

86 03 30 00 03 Product Data Recycled Aggregate Materials

87 03 30 00 03 Product Data Cementitious Materials 2.4.1

88 03 30 00 03 Product Data Vapor Retarder and Vapor Barrier

89 03 30 00 03 Product Data Concrete Curing Materials 2.3.3

90 03 30 00 03 Product Data Reinforcement 2.5

91 03 30 00 03 Product Data Liquid Chemical Floor Hardener

92 03 30 00 03 Product Data Admixtures

93 03 30 00 03 Product Data Synthetic Reinforcing Fibers 2.5.5

94 03 30 00 03 Product Data Mechanical Reinforcing Bar

Connectors 2.5.2

95 03 30 00 03 Product Data Waterstops

96 03 30 00 03 Product Data Pumping Concrete

97 03 30 00 05 Design Data Mix Design 2.3.1 G

98 03 30 00 06 Test Reports Concrete Mix Design G

99 03 30 00 06 Test Reports Fly Ash

100 03 30 00 06 Test Reports Pozzolan

101 03 30 00 06 Test Reports Ground Granulated Blast-Furnace Slag

102 03 30 00 06 Test Reports Aggregates 2.4.3

103 03 30 00 06 Test Reports Compressive Strength Tests 3.11.2.3 G

104 03 30 00 06 Test Reports Slump Tests 3.11.2.1

105 03 30 00 06 Test Reports Water 2.4.2

106 03 30 00 07 Certificates Reinforcing Bars 2.5.1

107 03 30 00 07 Certificates Welder Qualifications

SUBMITTAL REGISTER

JOB NAME:

LOCATION: JBC AB B174

CONTRACT NO: DKFX 08-10306

CONTRACTOR:

APPROVING AUTHORITY

(d)

CONTRACTOR SCHEDULE

DATES

CONTRACTOR

ACTION

108 03 30 00 07 Certificates

VOC Content for Form Release

Agents, Curing Compounds, and

Concrete Penetrating Sealers

109 03 30 00 07 Certificates Material Safety Data Sheets

110 03 30 00 07 Certificates Forest Stewardship Council (FSC)

Certification

111 03 30 00 07 Certificates Field Testing Technician and Testing

Agency

112 03 30 00 08 Manufacturer’s Instructions Liquid Chemical Floor Hardener

113 03 30 00 08 Manufacturer’s Instructions Curing Compound 2.3.3

114 22 00 00 03 Product Data Backflow Prevention Assemblies 3.4.1.1 G

115 22 00 00 03 Product Data Test of Backflow Prevention

Assemblies

3.4.1.1 G

116 22 00 00 10 Operation and Maintenance Data Plumbing System 3.4.1 G

117 23 00 00 02 Shop Drawings Detail Drawings 1.4.4 G

118 23 00 00 03 Product Data Duct Connectors

119 23 00 00 03 Product Data Manual Balancing Dampers G

120 23 00 00 03 Product Data Air Handling Unit Coils G

121 23 00 00 03 Product Data Test Procedures

122 23 00 00 03 Product Data Diagrams G

123 23 00 00 06 Test Reports Performance Tests 3.6 G

124 23 00 00 06 Test Reports Damper Acceptance Test G

125 23 00 00 07 Certificates Bolts 1.4.1

126 23 00 00 07 Certificates Ozone Depleting Substances

127 23 00 00 08 Manufacturer’s Instructions Manufacturer's Installation Instructions 3.2

128 23 00 00 08 Manufacturer’s Instructions Operation and Maintenance Training 3.8.2

129 23 00 00 10 Operation and Maintenance Data Operation and Maintenance Manuals 3.8.1 G

130 23 00 00 10 Operation and Maintenance Data Manual Balancing Dampers G

131 23 00 00 10 Operation and Maintenance Data Air Handling Unit Coils G

132 23 05 48.00 40 02 Shop Drawings Installation Drawings 1.2 G

133 23 05 48.00 40 02 Shop Drawings Outline Drawings 1.2 G

134 23 05 48.00 40 03 Product Data Equipment and Performance Data 1.2 G

135 23 05 48.00 40 03 Product Data Isolators G

136 23 05 48.00 40 06 Test Reports Type of Isolator 2.4 G

137 23 05 48.00 40 06 Test Reports Type of Base 2.4 G

138 23 05 48.00 40 06 Test Reports Allowable Deflection 2.4 G

139 23 05 48.00 40 06 Test Reports Measured Deflection 2.4 G

140 23 05 93 01 Preconstruction Submittals Records of Existing Conditions G

141 23 05 93 02 Shop Drawings TAB Schematic Drawings and Report

Forms

1.3.2 G

142 23 05 93 03 Product Data Equipment and Performance Data 1.3 G

143 23 05 93 03 Product Data TAB Related HVAC Submittals G

SUBMITTAL REGISTER

JOB NAME:

LOCATION: JBC AB B174

CONTRACT NO: DKFX 08-10306

CONTRACTOR:

APPROVING AUTHORITY

(d)

CONTRACTOR SCHEDULE

DATES

CONTRACTOR

ACTION

144 23 05 93 07 Certificates Independent TAB Agency and

Personnel Qualifications

1.5.1 G

145 23 05 93 07 Certificates TAB Submittal and Work Schedule G

146 23 05 93 07 Certificates TAB Pre-Field Engineering Report G

147 23 07 00 02 Shop Drawings Pipe Insulation Systems 2.3

148 23 07 00 02 Shop Drawings Pipe Insulation Systems 3.1

149 23 07 00 02 Shop Drawings Equipment Insulation Systems 3.2

150 23 07 00 03 Product Data Pipe Insulation Systems 2.3 G

151 23 07 00 03 Product Data Pipe Insulation Systems 3.1 G

152 23 07 00 03 Product Data Equipment Insulation Systems 3.2 G

153 23 07 00 08 Manufacturer’s Instructions Pipe Insulation Systems 2.3 G

154 23 07 00 08 Manufacturer’s Instructions Pipe Insulation Systems 3.1 G

155 23 07 00 08 Manufacturer’s Instructions Equipment Insulation Systems 3.2 G

156 23 09 00 02 Shop Drawings DDC Contractor Design Drawings 3.10 G

157 23 09 00 02 Shop Drawings Draft As-Built Drawings 3.10 G

158 23 09 00 02 Shop Drawings Final As-Built Drawings 3.10 G

159 23 09 00 03 Product Data Manufacturer's Product Data 2.2 G

160 23 09 00 06 Test Reports Existing Conditions Report 3.1.1

161 23 09 00 10 Operation and Maintenance Data Operation and Maintenance (O&M)

Instructions

3.11 G

162 23 09 00 10 Operation and Maintenance Data Training Documentation G

163 23 09 00 11 Closeout Submittals Enclosure Keys 2.5 G

164 23 09 00 11 Closeout Submittals Password Summary Report 3.2.4.1 G

165 23 64 10 03 Product Data Water Chiller G

166 23 64 10 03 Product Data Verification of Dimensions 1.5.1

167 23 64 10 03 Product Data Demonstrations 3.8

168 23 64 10 03 Product Data Water Chiller - Field Acceptance Test

Plan 3.6.1

169 23 64 10 06 Test Reports Field Acceptance Testing 3.6

170 23 64 10 06 Test Reports Water Chiller - Field Acceptance Test

Report 3.6.2

171 23 64 10 06 Test Reports System Performance Tests 3.7

172 23 64 10 07 Certificates Refrigeration System 3.2.7 G

173 23 64 10 08 Manufacturer’s Instructions Water Chiller - Installation Instructions 3.2 G

174 23 64 10 10 Operation and Maintenance Data Operation and Maintenance Manuals 3.8 G

175 23 64 10 11 Closeout Submittals Energy Efficient Equipment for Chillers 2.1.1 S

176 23 64 10 11 Closeout Submittals Indoor Air Quality During Construction S

177 23 64 10 11 Closeout Submittals Ozone Depleting Substances 2.1.2 S

178 23 64 26 03 Product Data Grooved Mechanical Connections For

Steel G

179 23 64 26 03 Product Data Grooved Mechanical Connections For

Copper G

SUBMITTAL REGISTER

JOB NAME:

LOCATION: JBC AB B174

CONTRACT NO: DKFX 08-10306

CONTRACTOR:

APPROVING AUTHORITY

(d)

CONTRACTOR SCHEDULE

DATES

CONTRACTOR

ACTION

180 23 64 26 03 Product Data Calibrated Balancing Valves 2.4.4 G

181 23 64 26 03 Product Data Automatic Flow Control Valves G

182 23 64 26 03 Product Data Pump Discharge Valve

183 23 64 26 03 Product Data Water Temperature Mixing Valve G

184 23 64 26 03 Product Data Water Temperature Regulating Valves G

185 23 64 26 03 Product Data Water Pressure Reducing Valve 2.4.5

186 23 64 26 03 Product Data Pressure Relief Valve 2.4.6

187 23 64 26 03 Product Data Combination Pressure and

Temperature Relief Valves 2.4.7

188 23 64 26 03 Product Data Expansion Joints 2.5.8 G

189 23 64 26 03 Product Data Pumps 2.6 G

190 23 64 26 03 Product Data Combination Strainer and Pump

Suction Diffuser 2.5.3

191 23 64 26 03 Product Data Expansion Tanks 2.7

192 23 64 26 03 Product Data Air Separator Tanks 2.8

193 23 64 26 03 Product Data Water Treatment Systems 2.9 G

194 23 64 26 06 Test Reports Piping Welds NDE Report 3.1.1.3

195 23 64 26 06 Test Reports Pressure Tests Reports 3.4.2 G

196 23 64 26 06 Test Reports Condenser Water Quality Test Reports G

197 23 64 26 06 Test Reports One-Year Inspection Report For

Cooling Water G

198 23 64 26 07 Certificates Employer's Record Documents (For

Welding) 3.1.1.1

199 23 64 26 07 Certificates Welding Procedures and Qualifications 3.1.1.2

200 23 64 26 08 Manufacturer’s Instructions Lesson plan for the Instruction Course 3.5 G

201 23 64 26 10 Operation and Maintenance Data Water Treatment Systems 2.9 G

202 23 64 26 10 Operation and Maintenance Data Calibrated Balancing Valves 2.4.4 G

203 23 64 26 10 Operation and Maintenance Data Automatic Flow Control Valves G

204 23 64 26 10 Operation and Maintenance Data Pump Discharge Valve G

205 23 64 26 10 Operation and Maintenance Data Water Temperature Mixing Valve G

206 23 64 26 10 Operation and Maintenance Data Water Temperature Regulating Valves G

207 23 64 26 10 Operation and Maintenance Data Water Pressure Reducing Valve 2.4.5 G

208 23 64 26 10 Operation and Maintenance Data Pressure Relief Valve 2.4.6 G

209 23 64 26 10 Operation and Maintenance Data Combination Pressure and

Temperature Relief Valves

2.4.7 G

210 23 64 26 10 Operation and Maintenance Data Expansion Joints 2.5.8 G

211 23 64 26 10 Operation and Maintenance Data Pumps 2.6 G

212 23 64 26 10 Operation and Maintenance Data Combination Strainer and Pump

Suction Diffuser

2.5.3 G

SUBMITTAL REGISTER

JOB NAME:

LOCATION: JBC AB B174

CONTRACT NO: DKFX 08-10306

CONTRACTOR:

APPROVING AUTHORITY

(d)

CONTRACTOR SCHEDULE

DATES

CONTRACTOR

ACTION

213 23 64 26 10 Operation and Maintenance Data Expansion Tanks 2.7 G

214 23 64 26 10 Operation and Maintenance Data Air Separator Tanks 2.8 G

215 26 05 48.00 10 03 Product Data Contractor Designed Bracing 1.2.3 G

216 26 08 00 06 Test Reports Acceptance tests and inspections 3.1 G

217 26 08 00 07 Certificates Qualifications 1.4.1 G

218 26 08 00 07 Certificates Acceptance test and inspections procedure

1.4.3 G

219 26 20 00 03 Product Data Receptacles 2.9 G

220 26 20 00 03 Product Data Circuit breakers G

221 26 20 00 06 Test Reports 600-volt wiring test 3.4.2 G

222 26 20 00 06 Test Reports Grounding system test 3.4.3 G

223 26 20 00 07 Certificates Fuses 2.8 G

224 26 20 00 10 Operation and Maintenance Data Electrical Systems 1.5.1 G

225 26 24 16.00 40 03 Product Data Panelboards 1.3 G

226 26 24 16.00 40 03 Product Data Directory Card and Holder 2.1.2

227 26 24 16.00 40 06 Test Reports Continuity Tests 3.2

228 26 24 16.00 40 06 Test Reports Insulation Tests 3.2 G

229 26 24 16.00 40 07 Certificates Statements 1.4 G

230 26 24 16.00 40 08 Manufacturer’s Instructions Panelboards 1.3 G

231 32 31 13 02 Shop Drawings Fence Assembly 2.1 G

232 32 31 13 02 Shop Drawings Location of Gate, Corner, End, and Pull

Posts

3.2.2.1 G

233 32 31 13 02 Shop Drawings Gate Hardware and Accessories 2.2.14 G

234 32 31 13 02 Shop Drawings Erection/Installation Drawings Part 3 G

235 32 31 13 03 Product Data Fence Assembly 2.1 G

236 32 31 13 03 Product Data Gate Assembly 2.1 G

237 32 31 13 03 Product Data Gate Hardware and Accessories 2.2.14 G

238 32 31 13 03 Product Data Zinc Coating 2.3.1 G

239 32 31 13 03 Product Data PVC Coating G

240 32 31 13 03 Product Data Stretcher Bars 2.2.9 G

241 32 31 13 03 Product Data Concrete 2.3.3 G

242 32 31 13 07 Certificates Certificates of Compliance 1.3.1

243 32 31 13 08 Manufacturer’s Instructions Fence Assembly 2.1

244 32 31 13 08 Manufacturer’s Instructions Accessories 2.1

245 32 31 13 11 Closeout Submittals Recycled Material Content 3.3 S