This is a Task Assignment (TA) document executed between the State of Florida Department of Environmental Protection (FDEP) and Golder Associates USA Inc., a contractor providing environmental consulting services. The task assignment is designated as TA Number DC014A under Contract Number HW685, and it pertains to groundwater monitoring activities at the Drycleaning Art Inc. site located at 3337 Sheridan Street, Hollywood, Broward County, Florida (FDEP Facility ID: ERIC_4061). The document was executed on April 19, 2022, with a completion date of September 30, 2022, with Ben Grubbs serving as the FDEP Project Manager and Matt Crews representing Golder Associates USA Inc.

The task assignment authorizes Golder to conduct groundwater monitoring activities in accordance with an April 13, 2022 Scope of Work, Cost Estimate, and Bid Documentation. The work is divided into three subtasks: Subtask 1 (Project Management) at $736.07; Subtask 2 (Annual Groundwater Monitoring) at $5,103.96; and Subtask 3 (Reporting) at $2,324.08, for a total TA value of $8,164.11 on a fixed unit rate basis with 57 labor hours. Deliverables include groundwater monitoring field documentation and laboratory reports due June 24, 2022, and an annual groundwater monitoring report with ADaPT/GIS updates due July 22, 2022. The work involves collecting groundwater samples from six monitoring wells, analyzing for chlorinated volatile organic compounds using EPA Method 8260B, managing investigation-derived waste, and submitting updated GIS tables. Erwin Remediation was selected as the lowest responsive and responsible bidder for investigation-derived waste drum treatment and disposal at $100.00 per drum.

View the file

Other files

File Type Posted
CN-370000-HW685-BF01C.pdf PDF
CN-370000-HW685-BF05ACO2.pdf PDF
CN-370000-HW685-BF05ACO3.pdf PDF
CN-370000-HW685-BF06A.pdf PDF
CN-370000-HW685-BF1ACO1.pdf PDF
CN-370000-HW685-BF6ACO1.pdf PDF
CN-370000-HW685-BIL01C.pdf PDF
CN-370000-HW685-BIL01CO1.pdf PDF
CN-370000-HW685-BIL03A.pdf PDF
CN-370000-HW685-BIL2ACO1.pdf PDF
CN-370000-HW685-BIL2CCO1.pdf.crdownload CRDOWNLOAD file
CN-370000-HW685-DC001A.pdf PDF
CN-370000-HW685-DC002G.pdf PDF
CN-370000-HW685-DC003A.pdf PDF
CN-370000-HW685-DC005C.pdf PDF
CN-370000-HW685-DC006B.pdf PDF
CN-370000-HW685-DC006C.pdf PDF
CN-370000-HW685-DC007C.pdf PDF
CN-370000-HW685-DC008A.pdf PDF
CN-370000-HW685-DC009B.pdf PDF
CN-370000-HW685-DC010A.pdf PDF
CN-370000-HW685-DC011A.pdf PDF
CN-370000-HW685-DC012C.pdf PDF
CN-370000-HW685-DC013A.pdf PDF
CN-370000-HW685-DC013C.pdf PDF
CN-370000-HW685-DC015B.pdf PDF
CN-370000-HW685-DC015C.pdf PDF
CN-370000-HW685-DC016A.pdf PDF
CN-370000-HW685-DC018A.pdf PDF
CN-370000-HW685-DC019B.pdf PDF
CN-370000-HW685-DC01ACO6.pdf PDF
CN-370000-HW685-DC01ACO8.pdf PDF
CN-370000-HW685-DC01ACO9.pdf PDF
CN-370000-HW685-DC020B.pdf PDF
CN-370000-HW685-DC022A.pdf PDF
CN-370000-HW685-DC022B.pdf PDF
CN-370000-HW685-DC022D.pdf PDF
CN-370000-HW685-DC023B.pdf PDF
CN-370000-HW685-DC023C.pdf PDF
CN-370000-HW685-DC027B.pdf PDF
CN-370000-HW685-DC027C.pdf PDF
CN-370000-HW685-DC029B.pdf PDF
CN-370000-HW685-DC029C.pdf PDF
CN-370000-HW685-DC02CCO1.pdf PDF
CN-370000-HW685-DC02FCO1.pdf PDF
CN-370000-HW685-DC031A.pdf PDF
CN-370000-HW685-DC031C.pdf PDF
CN-370000-HW685-DC032B.pdf PDF
CN-370000-HW685-DC035A.pdf PDF
CN-370000-HW685-DC037A.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW685

DC014A Completion September 30, 2022

This Task Assignment authorizes Golder to conduct groundwater monitoring activities in accordance with the April 13, 2022, Scope of Work, Cost Estimate, and Bid Documentation.

Ben Grubbs 850-245-8992 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

Golder Associates USA Inc.

Golder Associates USA Inc.

Matt Crews 904-363-3430

ERIC_4061

3337 Sheridan Street, Hollywood, Broward County

Drycleaning Art Inc

✔ $ 8,164.11

$ 8,164.11

Scope of Work

Donald Miller

Principal

Donald Miller Digitally signed by Donald Miller Date: 2022.04.19 11:40:31 -04'00'

William E. Burns, Jr.

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2022.04.19 10:53:26 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Subtask 2: Groundwater Monitoring Field Documentation and Laboratory Report;

IDW Disposal Documentation 06/24/2022

Subtasks 1 & 3: Annual Groundwater Monitoring Report; ADaPT/GIS Update; Project Management 07/22/2022

Subtask 2: Submittal and FDEP approval of the Groundwater Monitoring Field Documentation and Laboratory Report; IDW Disposal Documentation $ 5,103.96

Subtasks 1 & 3: Submittal and FDEP approval of the Annual Groundwater Monitoring Report; ADaPT/GIS Update; Project Management $ 3,060.15

$ 8,164.11

HW685

DC014A

Printed on recycled paper.

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

To: HW685 Contract Negotiation File Drycleaning Art Inc Hollywood, Broward County

ERIC_4061

From: Ben Grubbs, Project Manager Date: April 19, 2022 Subject: Negotiation Summary

HW685 DC014A

This Task Assignment authorizes Golder to conduct groundwater monitoring activities in accordance with the April 13, 2022, Scope of Work, Cost Estimate, and Bid Documentation.

Subtask 1: Project Management An automatic calculation based upon total direct labor hours determines the labor hours within this subtask.

Subtask 2: Annual Groundwater Monitoring Golder will collect groundwater samples from monitoring wells MW001, MW002, MW005, and MW007 – MW009. Prior to sampling, depth-to-water will be measured. The wells will then be purged, and field parameters will be recorded. The groundwater samples will be collected using low flow sampling methods and analyzed for chlorinated volatile organic compounds (VOCs).

Investigation-derived waste (IDW) will be temporarily stored in a 55-gallon drum. Golder requested bids for IDW drum treatment and disposal from Clark, Erwin, Whatever Waste, and M & D Industrial Services. Erwin was selected as the lowest responsive and responsible bidder.

Subtask 3: Reporting Golder will submit the Annual Groundwater Monitoring Report and ADaPT and GIS deliverables to FDEP.

Golder and the FDEP confirmed on April 13, 2022, that an Access Agreement with the current real property owner of the Drycleaning Art Inc (ERIC_4061) site has been executed.

The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost for this Task Assignment is $8,164.11 with 57 labor hours.

Golder may invoice following the schedule established in the Deliverables and Invoice Schedule Attachment, which accompanies the Task Assignment Notification Form.

FDEP COST ESTIMATEContractor: Golder Associates USA Inc.

Date: 4/13/2022

Task #: DC014A SubTask 1 Project Management SubTask 6

Site: Dry Cleaning Art Inc. SubTask 2 Annual GW Monitoring SubTask 7

Activity/Phase: Assessment SubTask 3 Reporting SubTask 8

Project Manager: Ben Grubbs SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$34.55 Project Manager (SN) 7 7.1 $0.00 Program Leader - X-14 0 0 0 0 0 0 0 0 0 0

$63.65 Practice Leader - X-13 (JB) 2 0 2 0 0 0 0 0 0 0 $0.00 Senior Consultant - X-12 0 0 0 0 0 0 0 0 0 0

$51.23 Senior Sci/Eng - X-11 (RFM) 6 6 0 0 0 0 0 0 0 0 $45.42 Senior Project Sci/Eng - P-10 (BL) 3 0 3 0 0 0 0 0 0 0 $44.15 Project Sci/Eng - P-10 (JT) 2 0 1.5 0.0 0 0 0 0 0 0 $34.55 Project Sci/Eng - P-9 (SN) 26 15 11 0 0 0 0 0 0 0 $30.31 Staff Sci/Eng - P-8 (PC) 10 9.5 0 0 0 0 0 0 0 0 $32.75 Staff Sci/Eng - P-8 (AS) 2 0 2 0 0 0 0 0 0 0

$0.00 Sci/Eng/Admin - P-7 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 57 7.1 30.5 19.5 0.0 0 0 0 0 0 0

Direct Labor $2,134.48 $245.56 $1,113.58 $775.34 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 172.50% $3,681.98 $423.59 $1,920.93 $1,337.46 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $5,816.46 $669.15 $3,034.51 $2,112.80 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF GOLDER Page 1

FDEP COST ESTIMATEContractor: Golder Associates USA Inc.

Date: 4/13/2022

Task #: DC014A SubTask 1 Project Management SubTask 6

Site: Dry Cleaning Art Inc. SubTask 2 Annual GW Monitoring SubTask 7

Activity/Phase: Assessment SubTask 3 Reporting SubTask 8

Project Manager: Ben Grubbs SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle Rental $240.00 $240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $125.00 $125.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $365.00 $365.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utility Location $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $10.00 $10.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $548.00 $548.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $220.00 $220.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $768.00 $768.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $383.00 $383.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $523.00 $523.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $7,582.46 $669.15 $4,800.51 $2,112.80 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $581.65 $66.92 $303.45 $211.28 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $8,164.11 $736.07 $5,103.96 $2,324.08 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF GOLDER Page 2

SITE : Dry Cleaning Art Inc.

SUBTASK 2: Annual GW Monitoring

DATE: 4/13/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Sci/Eng (R. Mongillo) 6

Project Sci/Eng (S. Neal) 15

Staff Sci/Eng (P. Kuhn) 9.5

TOTAL LABOR 30.5

VEHICLE TYPE RATE UNIT USEAGE

Truck (S. Neal) $120.00 Per Day 1 $120.00 Truck (P Kuhn) $120.00 Per Day 1 $120.00

TOTAL VEHICLE $240.00

PER DIEM STAFF RATE UNIT USEAGE

Per Diem Project Sci/Eng (S Neal) $36.00 Per Day 1 $36.00 Hotel Project Sci/Eng (S. Neal) $89.00 Per Day 1 $89.00

TOTAL PER DIEM $125.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Erwin IDW devel and sampling water $100.00 Per Drum 1 $100.00

TOTAL $100.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

Chlorinated VOCs - EPA Method 8260B Total VOHs EPA Method 8260B $73.00 6 $438.00 Total VOCs EPA Method 8021 - IDW $110.00 1 $110.00 Sample Shipping Small $110.00 2 $220.00

TOTAL LAB $768.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Miscellaneous Expendables $40.00 Per Day 1 $40.00 Shallow Groundwater Sampling Kit $290.00 Per Day 1 $290.00 Tubing, Poly HDPE $0.30 Per Day 250 $75.00 Tubing, Silicon 3/16 x 3/8 $3.00 Per Day 6 $18.00 Drum, 55-gallon $100.00 Per Day 1 $100.00

TOTAL EQUIPMENT $523.00

Contact property owner and DEP scheduling field work, locate wells at the new site, collect depth to water measurements from 12 monitoring wells and groundwater samples from 7 monitoring wells for chlorinated VOC analysis, and management of IDW for transportation and disposal. Mobilization demobilization from Jacksonville to Miami will be a total of 12 hours divided by four locations (ERIC_4399, ERIC_4487, ERIC 4066, and 4221) for Scott Neal Correspondence with RPO for site access (1 hour), contact DEP with initial results of the groundwater samples and prepare an email deliverable with sample field notes and forms and laboratory report (3 hours). Contact with IDW disposal subcontractor and provide waste characterization data (2 hours).

Conduct groundwater sampling event. Development of Health and Safety Plan (3 hours), 1/4 mobe demobe from Jacksonville to Miami (3 hours), Local mobe (1 hour), locate wells at the new site, including instrument calibration, groundwater measure water levels (3 wells), and sample 6 wells MW001, MW002, MW005, MW007I, MW008, and MW009 and measure field parameters and securing the IDW drum(s) (8 hours).

Conduct groundwater sampling event. Local mobe (1.5 hour), locate wells at new site, including instrument calibration, groundwater measure water levels (3 wells), and sample 6 wells MW001, MW002, MW005, MW007I, MW008, and MW009 and measure field parameters and securing the IDW drum(s) (8 hours).

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Dawn Laundry SUBTASK 3: Reporting

DATE: 4/14/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Practice Leader (J. Brown) 2 Senior Sci/Eng (S Neal) 13

Senior Project Sci/Eng (J. Thomas) 1.5

Senior Project Sci/Eng (B. Lucero) 5

Staff Sci/Eng (A. Strayer) 3

TOTAL LABOR 24.5

VEHICLE TYPE RATE UNIT USEAGE

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT $0.00

Update FDEP GIS Tables, run data checker, create and edit error report, and annotate error report (8 data points x 8 min/point = 40 minutes). Submit DEP GIS tables; submit ADaPT deliverable (0.5)

Data entry, prepare tables and figures, and draft Annual Monitoring Report

CADD Update Figures (two groundwater flow and two CVOC detections) received from another consultant to the Golder report format.

Develop conclusions and recommendations and prepare final Annual Monitoring Report.

Reporting: Updating tables from another consultant to the Golder report format, document production, binding and shipping. Create pdf for OCULUS.

FINAL --7/24/96

Golder Associates USA Inc.

9428 Baymeadows Road, Suite 400, Jacksonville, Florida, USA 32256

T: +1 904 363-3430 F: +1 904 363-3445 golder.com

April 13, 2022 Proposal No. 202208346

Mr. Ben Grubbs Florida Department of Environment Protection Division of Waste Management Drycleaning Solvent Cleanup Program 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400

RE: COST PROPOSAL FOR DRY CLEANING ART INC.

ANNUAL GROUNDWATER MONITORING

3337 SHERIDAN STREET

HOLLYWOOD, BROWARD COUNTY, FLORIDA

FACILITY ID NUMBER: ERIC_4061

PROPOSED TASK ASSIGNMENT: HW685__DC014A

Dear Mr. Grubbs:

Golder Associates USA Inc. (Golder) is pleased to provide the Florida Department of Environmental Protection (DEP) with this cost proposal for groundwater monitoring at the Dry Cleaning Art Inc. site, located in Hollywood, Broward County, Florida. This proposal includes a description of the proposed scope of services, level of effort (LOE) sheets for each subtask, and a Cost Estimate Form (CEF) that summarizes the costs of the proposed services. The scope of work is based on the recommendations accepted by the DEP in the April 20, 2021 electronic mail correspondence AECOM. The proposed scope of services is described below.

SUBTASK 1 – PROJECT MANAGEMENT

To facilitate project quality and satisfactory completion of the proposed scope of work, all aspects of this project will be overseen by an experienced project manager. The project manager will be responsible for the schedule, budget, invoicing, project activities, and communications with DEP. Project management will include coordination of field activities; resource allocation to confirm the work is conducted by qualified professionals in accordance with the project schedule; cost control and tracking of the budget status; and submission of project invoices in accordance with DEP Drycleaning Solvent Cleanup Program requirements. The project manager will be responsible seeing that the work is conducted in a manner that is consistent with the requirements of the DEP approved task assignment.

SUBTASK 2 – ANNUAL GROUNDWATER MONITORING

Golder will collect groundwater samples from six monitoring wells (MW001, MW002, MW005, MW007I, MW008, and MW009). The attached figures (Figures 1 through 3) from the February 2021 annual groundwater monitoring report showing the monitoring well locations, potentiometric map of the shallow flow zone, 3 to 13 feet below ground

Mr. Ben Grubbs Proposal No. 202208346

Florida Department of Environment Protection April 13, 2022 surface, and chlorinated volatile organic compound (VOC) results for the shallow and intermediate zones of the surficial aquifer.

Prior to groundwater sampling, the depth to groundwater will be measured at accessible monitoring well locations (MW003, MW004, and MW006) in addition to the wells sampled using an electronic water level indicator to determine groundwater elevations and flow direction. During the sampling event, the locks and well caps will be inspected for damage or degradation and repaired or replaced as necessary. Groundwater samples will be collected from the wells in accordance with DEP Standard Operating Procedures (SOPs) for Field Activities (DEP-SOP-001/01) dated January 2017 (effective April 16, 2018). Prior to collecting the groundwater sample, each well will be purged and field parameters including temperature, pH, specific conductance, dissolved oxygen, turbidity, and oxidation-reduction potential will be monitored. Purge volumes and field parameters will be recorded on field data sheets, and the field monitoring equipment will be calibrated in accordance with the manufacturer’s recommended procedures.

Groundwater samples will be collected using low flow sampling methods. The groundwater samples will be placed in laboratory-supplied containers, labeled with a unique identification number attached to the outside of the sample container, preserved on ice in a laboratory-provided cooler at a maximum temperature of four degrees Celsius, and delivered to a Florida Department of Health and National Environmental Laboratory Accreditation Program-certified fixed-base laboratory along with the completed chain-of-custody documentation to be analyzed for chlorinated VOCs using EPA Method 8260B.

Golder will temporarily store the investigation derived waste (IDW) purge water generated from the groundwater sampling event in a 55-gallon steel drum(s). A waste characterization sample will be collected from the IDW drum(s) for analysis of total VOCs using EPA Method 8021. If the waste characterization sample is acceptable to the disposal subcontractor, the IDW drum(s) will be picked up and transported to a facility for proper disposal. A non-hazardous waste manifest will be provided by the disposal subcontractor upon delivery to the disposal facility.

Mobilization this site will be divided between the four sites that will be visited during the week including Dawn Laundry, Drycleaning Arts Inc, Classic French Dry Cleaners, and Cinderella Cleaners. Scott Neal will travel down to Miami on Sunday and return on Friday. The total time for mobilization and demobilization from Jacksonville to Miami is 12 hours. This time will be divided among the four sites totaling 3 hours of mobilization for each site by Scott Neal. Paul Kuhn is based in our Miami office and will be used as the second person for the work and will be charged the daily mobilization from the office to the site.

Upon completion of Subtask 2, an e-mail deliverable will be submitted and include copies of the field data sheets, equipment calibration forms, field notes, laboratory analytical report, and laboratory chain-of-custody documentation.

SUBTASK 3 – REPORTING

The annual groundwater monitoring report will include a description of the sampling procedures, evaluation of the analytical results, comparison of current to historical data, tabulated summary of the current and historical analytical data, a site map showing the groundwater analytical results, water level elevation information in tables and figures, laboratory analytical data, conclusions, and recommendations. Golder will also update the DEP GIS tables with the new water level data, field parameter measurements, and VOC data; run the DEP data checker on the completed tables; and submit the updated tables and error reports under this subtask. Additionally, Golder will forward the

Automated Data Processing Tool (ADaPT) data deliverables for the groundwater sampling event provided by the laboratory.

HEALTH AND SAFETY

Golder will prepare a site-specific Health and Safety Plan for the field work. The work will be completed in accordance with Golder’s safety policies and procedures. At a minimum, Golder will wear safety glasses, high visibility safety vests, and steel-toed boots. A safety job briefing will be conducted prior to the start of work activities, and anytime the scope of work or site conditions change.

COST AND SCHEDULE

The estimated cost to complete the proposed scope of work is $8,164.11. Golder anticipates the well installation will be completed late May/early June 2022 and the groundwater monitoring event will take place approximately 2 weeks later. The LOE/CEF sheets and the subcontractor bids are included in Attachment A. The following table summarizes the proposed costs and deliverable schedule.

Task Proposed Cost Proposed Schedule and Deliverables

Subtask 1: Project Management $ 736.07 August 26, 2022

Subtask 2: Annual Groundwater Monitoring

$5,103.96 June 24, 2022 (Field notes, sampling logs, IDW disposal, and laboratory report submittal)

Subtask 3: Reporting $2,324.08 July 22, 2022 (Groundwater Monitoring Report, GIS Tables, ADaPT Deliverables)

Total/Completion Date $8,164.11 September 30, 2022

Please be aware that Golder has been acquired by and is now a Member of the WSP family of companies. Golder remains as a legal entity and is the proposed contracting entity for this proposal. We are in the process of integrating the resources of our companies. Correspondence for this proposal should continue to be addressed to the undersigned.

Golder appreciates the opportunity to provide services under the Drycleaning Solvent Cleanup Program. Should you require additional information or clarifications, please contact us at 904 363-3430.

Sincerely, Golder Associates USA Inc.

Ralph F. Mongillo, Jr. PG Jesse C. Brown, PE Lead Consultant / Senior Geologist Director, Environmental Engineer

RFM/JCB/as

Attachments: Figure 1 Site Map

Figure 2 Groundwater Contour Map (February 25, 2021) Figure 3 Groundwater Contamination Map (February 2021)

Attachment A Level of Effort Sheets / Cost Estimate Form and Subcontractor Bids

G:\Projects\DEP-Drycleaning\Projects\Miami\Drycleaning Art, Inc - HW685\Proposal\HW685 Annual Groundwater Monitoring Proposal ERIC_4061.docx

DRYCLEANING ART

CLEANERS

8/21/2019

FIGURE 1

SITE MAP

DRY CLEANING ART (PARK SHERIDAN CLEANERS)

3337 SHERIDAN ST., HOLLYWOOD, BROWARD COUNTY, FL

FDEP FACILITY ID NO.: ERIC_4061

60608655

LEGEND

SHALLOW MONITOR WELL

INTERMEDIATE MONITOR WELL

ABANDONED MONITOR WELL

AutoCAD SHX Text

MW005

AutoCAD SHX Text

MW006

AutoCAD SHX Text

MW001

AutoCAD SHX Text

MW002/TW003

AutoCAD SHX Text

MW003

AutoCAD SHX Text

MW004

AutoCAD SHX Text

MW008

AutoCAD SHX Text

MW009

AutoCAD SHX Text

MW007

AutoCAD SHX Text

TW001

AutoCAD SHX Text

TW002

AutoCAD SHX Text N

AutoCAD SHX Text

DRAWN BY:

AutoCAD SHX Text

REVISED BY:

AutoCAD SHX Text p:\dcs\projects\env\fdep\hw551\dc\dc art inc\dc028f nam 2019_60608655\900-cad- gis\910-cad\cad\f1_site map.dwg

AutoCAD SHX Text

MAR

AutoCAD SHX Text 0'

AutoCAD SHX Text 50'

AutoCAD SHX Text

SCALE

AutoCAD SHX Text 25'

AutoCAD SHX Text 100'

DRY CLEANING ART

LEGEND

SHALLOW MONITOR WELL

INTERMEDIATE MONITOR WELL

ABANDONED MONITOR WELL

GROUNDWATER ELEVATION (FT.)

GROUNDWATER CONTOUR (FT.)

APPARENT DIRECTION OF GROUNDWATER FLOW

(1.11)

1.14

3/23/2021

FIGURE 2

GROUNDWATER CONTOUR MAP

FEBRUARY 25, 2021

DRY CLEANING ART (PARK SHERIDAN CLEANERS)

3337 SHERIDAN ST., HOLLYWOOD, BROWARD COUNTY, FL

FDEP FACILITY ID NO.: ERIC_4061

60652816

AutoCAD SHX Text

MW005

AutoCAD SHX Text (0.40)

AutoCAD SHX Text

MW006

AutoCAD SHX Text (0.39)

AutoCAD SHX Text

MW001

AutoCAD SHX Text (0.34)

AutoCAD SHX Text

MW002

AutoCAD SHX Text (0.33)

AutoCAD SHX Text

MW003

AutoCAD SHX Text (0.39)

AutoCAD SHX Text

MW004

AutoCAD SHX Text (0.42)

AutoCAD SHX Text

MW008

AutoCAD SHX Text (0.37)

AutoCAD SHX Text

MW009

AutoCAD SHX Text (0.36)

AutoCAD SHX Text

MW007

AutoCAD SHX Text N

AutoCAD SHX Text

DRAWN BY:

AutoCAD SHX Text

REVISED BY:

AutoCAD SHX Text p:\dcs\projects\env\fdep\hw551\dc\dc art inc\dc028h - 2021 nam 60652816\900-cad- gis\910-cad\cad\f2_gw contour map.dwg

AutoCAD SHX Text

MAR

AutoCAD SHX Text 0'

AutoCAD SHX Text 50'

AutoCAD SHX Text

SCALE

AutoCAD SHX Text 25'

100'

DRY CLEANING ART

2/25/21

0.2 U

0.2 U

0.23 I

0.2 U

0.2 U

2/25/21

1.2

0.2 U

0.2 U

0.2 U

0.2 U

2/25/21

3.1

0.2 U

0.49 I

0.2 U

0.2 U

2/25/21

0.2 U

0.2 U

0.2 U

0.2 U

0.2 U

2/25/21

0.2 U

0.2 U

0.2 U

0.2 U

0.2 U

2/25/21

0.2 U

0.2 U

0.2 U

0.2 U

0.2 U

3/23/2021

FIGURE 3

GROUNDWATER CONTAMINATION MAP

FEBRUARY 2021

DRY CLEANING ART (PARK SHERIDAN CLEANERS)

3337 SHERIDAN ST., HOLLYWOOD, BROWARD COUNTY, FL

FDEP FACILITY ID NO.: ERIC_4061

60652816

DATE

TETRACHLOROETHENE

TRICHLOROETHENE

cis-1,2-DICHLOROETHENE trans-1,2-DICHLOROETHENE

7/8/2019

VINYL CHLORIDE

NOTES:

· RESULTS SHOWN IN µg/L

· U = INDICATES THAT THE CHEMICAL OF CONCERN WAS UNDETECTED

· I = INDICATES THE CHEMICAL WAS DETECTED BUT BELOW THE

REPORTING LIMIT; THEREFORE, AN ESTIMATED VALUE

· D = DATA REPORTED FROM A DILUTION

· GCTL = GROUNDWATER CLEANUP TARGET LEVELS AS PROVIDED IN

62-777, F.A.C.

· BOLD INDICATES ANALYTE DETECTED

· BOLD BLUE INDICATES CONCENTRATION GREATER THAN GCTLs

LEGEND

SHALLOW MONITOR WELL

INTERMEDIATE MONITOR WELL

ABANDONED MONITOR WELL

AutoCAD SHX Text

MW005

AutoCAD SHX Text

MW006

AutoCAD SHX Text

MW001

AutoCAD SHX Text

MW002

AutoCAD SHX Text

MW003

AutoCAD SHX Text

MW004

AutoCAD SHX Text

MW008

AutoCAD SHX Text

MW009

AutoCAD SHX Text

MW007

AutoCAD SHX Text

TW001

AutoCAD SHX Text

TW002

AutoCAD SHX Text PCE TCE cis-1,2-DCE trans-1,2-DCE VC

AutoCAD SHX Text PCE TCE cis-1,2-DCE trans-1,2-DCE VC

AutoCAD SHX Text PCE TCE cis-1,2-DCE trans-1,2-DCE VC

AutoCAD SHX Text PCE TCE cis-1,2-DCE trans-1,2-DCE VC

AutoCAD SHX Text PCE TCE cis-1,2-DCE trans-1,2-DCE VC

AutoCAD SHX Text PCE TCE cis-1,2-DCE trans-1,2-DCE VC

AutoCAD SHX Text N

AutoCAD SHX Text

DRAWN BY:

AutoCAD SHX Text

REVISED BY:

AutoCAD SHX Text p:\dcs\projects\env\fdep\hw551\dc\dc art inc\dc028h - 2021 nam 60652816\900-cad- gis\910-cad\cad\f3_gw contam map.dwg

AutoCAD SHX Text

MAR

AutoCAD SHX Text 0'

AutoCAD SHX Text 50'

AutoCAD SHX Text

SCALE

AutoCAD SHX Text 25'

AutoCAD SHX Text 100'

AutoCAD SHX Text PCE TCE cis-1,2-DCE trans-1,2-DCE VC

APPROXIMATE EXTENT OF GROUNDWATER CONTAMINATION ABOVE GCTLs. (DASHED WHERE INFERRED)

From: Fred Portofe To: Mongillo, Ralph Cc: Madison Rogers; Roger Pragle; Crews, Matt Subject: RE: Investigative Derived Waste Drum Costs for Transportation and Disposal at a Regulated Facility Date: Wednesday, March 9, 2022 9:33:38 AM Attachments: F0152F28A2B5418EBC7A4FD870EC8D28.png

AD282F6C3391468088CDA42829B8E703.png A719914B10184314957B0CA910CA8D14.png F1DF3C4322764E8A9076F1ADFF76864A.png 3409DF389C3B4156BA232DDC85C60E09.png

EXTERNAL EMAIL

EXTERNAL EMAIL - We could not verify the authenticity of this message. Please be cautious when clicking on links or opening attachments.

Ralph

We are not going to provide annual Pricing for the Statewide Contract . After reviewing the scope with my partners and the variability with respect to disposal costing and ever changing fuel costs, we feel we can not bid this work given the current uncertainty in the market. We would be please to bid this work on a casa by case basis.

Fred G. Portofe, PG President of Environmental Services (Professional Geologist in FL, GA, AL, MS, TX, SC, NC, TN, IN, LA, WI and AK) M & D Industrial Services, LLC 5896 Azalea Street Port Orange, Florida 32127 Email: Fportofe@mdindustrialservices.com Website: mdindustrialservices.com Cell: 813-951-1012 Emergencies: 888-307-2790

Sent from Mail for Windows

From: Mongillo, Ralph Sent: Tuesday, March 8, 2022 12:46 PM To: Fred Portofe Cc: Madison Rogers; Roger Pragle; Eddy Mendoza; Crews, Matt mailto:fportofe@mdindustrialservices.com mailto:ralph.mongillo@wsp.com mailto:mrogers@mdindustrialservices.com mailto:rpragle@mdindustrialservices.com mailto:matt.crews@wsp.com mailto:Fportofe@mdindustrialservices.com https://nam10.safelinks.protection.outlook.com/?url=http%3A%2F%2Fmdindustrialservices.com%2F&data=04%7C01%7Cmculbreth%40ectinc.com%7Cbfdc4a6d2ce945e1eaf008d9dcf8eabf%7C911eb1cc54d34d8ca5773bf3ccc8105c%7C0%7C0%7C637783784008834159%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C2000&sdata=ntkZP1OGe7McYRA722JXtcGwkbgN9EEhQtSgBSKqC3E%3D&reserved=0 https://go.microsoft.com/fwlink/?LinkId=550986 mailto:Ralph_Mongillo@golder.com mailto:fportofe@mdindustrialservices.com mailto:mrogers@mdindustrialservices.com mailto:rpragle@mdindustrialservices.com mailto:emendoza@mdindustrialservices.com mailto:Matt_Crews@golder.com