This is a Task Assignment (TA) under Contract HW685 between the State of Florida Department of Environmental Protection (FDEP) and WSP USA Inc. to conduct supplemental site assessment activities at AR-PAT's Dry Cleaning facility located at 720 Harrison Street, Sebastian, Indian River County, Florida (ERIC 4805). The task assignment was executed on April 5, 2023, with a completion date of October 31, 2023. The work is being performed under the FDEP Waste Cleanup Program as part of the indefinite delivery vehicle contract structure.

The scope of work is divided into three subtasks: Project Management, Soil Sampling with Modified Active Gas Sampling (MAGS) Well Installation and MAGS Investigation, and Reporting. Project deliverables include soil sampling from 12 boring locations, installation of seven MAGS wells and five vacuum monitoring point wells, MAGS investigation using vapor extraction equipment, soil vapor sampling, waste characterization, and a final Supplemental Site Assessment Report. The total task assignment value is $28,842.08 on a fixed unit rate basis, with invoicing contingent upon submittal and FDEP approval of specific deliverables: $19,527.14 for Subtask 2 (due July 15, 2023) and $9,314.94 for Subtasks 1 and 3 combined (due August 15, 2023). The work includes subcontracted services for drilling, utility location, and investigation-derived waste disposal, with supporting cost estimates and vendor quotations documented in the proposal package.

View the file

Other files

File Type Posted
CN-370000-HW685-BF01A.pdf PDF
CN-370000-HW685-BF01CCO1.pdf PDF
CN-370000-HW685-BF02A.pdf PDF
CN-370000-HW685-BF05A.pdf PDF
CN-370000-HW685-BF05ACO1.pdf PDF
CN-370000-HW685-BF1BCO1.pdf PDF
CN-370000-HW685-BIL02C.pdf PDF
CN-370000-HW685-BIL1ACO4.pdf PDF
CN-370000-HW685-BIL2CCO1.pdf PDF
CN-370000-HW685-BIL3ACO1.pdf PDF
CN-370000-HW685-CSS01.pdf PDF
CN-370000-HW685-CSS2ACO2.pdf PDF
CN-370000-HW685-DC001C.pdf PDF
CN-370000-HW685-DC001E.pdf PDF
CN-370000-HW685-DC002B.pdf PDF
CN-370000-HW685-DC002C.pdf PDF
CN-370000-HW685-DC002E.pdf PDF
CN-370000-HW685-DC003C.pdf PDF
CN-370000-HW685-DC004A.pdf PDF
CN-370000-HW685-DC007A.pdf PDF
CN-370000-HW685-DC007B.pdf PDF
CN-370000-HW685-DC008B.pdf PDF
CN-370000-HW685-DC008D.pdf PDF
CN-370000-HW685-DC009A.pdf PDF
CN-370000-HW685-DC009D.pdf PDF
CN-370000-HW685-DC009E.pdf PDF
CN-370000-HW685-DC010C.pdf PDF
CN-370000-HW685-DC012A.pdf PDF
CN-370000-HW685-DC012D.pdf PDF
CN-370000-HW685-DC014B.pdf PDF
CN-370000-HW685-DC016D.pdf PDF
CN-370000-HW685-DC017A.pdf PDF
CN-370000-HW685-DC017B.pdf PDF
CN-370000-HW685-DC018B.pdf PDF
CN-370000-HW685-DC019A.pdf PDF
CN-370000-HW685-DC019C.pdf PDF
CN-370000-HW685-DC01ACO1.pdf PDF
CN-370000-HW685-DC01ECO1.pdf PDF
CN-370000-HW685-DC021A.pdf PDF
CN-370000-HW685-DC021B.pdf PDF
CN-370000-HW685-DC021C.pdf PDF
CN-370000-HW685-DC021E.pdf PDF
CN-370000-HW685-DC022C.pdf PDF
CN-370000-HW685-DC023A.pdf PDF
CN-370000-HW685-DC023D.pdf PDF
CN-370000-HW685-DC024C.pdf PDF
CN-370000-HW685-DC025A.pdf PDF
CN-370000-HW685-DC027D.pdf PDF
CN-370000-HW685-DC028A.pdf PDF
CN-370000-HW685-DC028D.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW685

DC008C Completion October 31, 2023

This Task Assignment authorizes WSP to conduct supplemental site assessment activities completing Modified Active Gas Sampling investigation in accordance with the March 27, 2023 Scope of Work, Cost Estimate, and Bid Documentation.

Opeyemi Kehinde 850-245-8887 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

WSP USA Inc.

WSP USA Inc.

Matt Crews 904-363-3430

ERIC 4805

720 Harrison Street, Sebastian, Indian River County

AR-PAT's Dry Cleaning

✔ $ 28,842.08

$ 28,842.08

Scope of Work

Matthew Crews

Environmental Engineer

4/5/2023

Crews, Matt (USMC700671) Digitally signed by Crews, Matt (USMC700671) Date: 2023.04.05 15:26:51 -04'00' Kelly Crain Digitally signed by Kelly Crain

Date: 2023.04.04 16:57:51 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Subtask 2 - Soil Sampling, MAGS Well Installation, and MAGS Investigation 07/15/2023

Subtasks 1 & 3: Reporting; Project Management 08/15/2023

Subtask 2 - Submittal and FDEP approval of E-mail summary with Field documentation, non� hazardous waste manifest, and laboratory report $ 19,527.14

Subtasks 1 & 3: Submittal and FDEP approval of Supplemental Site Assessment Report; Project Management $ 9,314.94

$ 28,842.08

HW685

DC008C

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton Secretary

To:

From:

Date:

HW685 Contract Negotiation File AR-PAT's Dry Cleaning, Sebastian Indian River County, ERIC_4805

Opeyemi Kehinde, Project Manager March 31, 2023

Subject: Negotiation Summary

HW685 DC008C

This Task Assignment authorizes WSP to conduct groundwater monitoring activities in accordance with the March 27, 2023, Scope of Work, Cost Estimate, and Bid Documentation.

Subtask 1: Project Management An automatic calculation based upon total direct labor hours determines the labor hours within this subtask.

Subtask 2: Soil Sampling, MAGS Well Installation, and MAGS Investigation

WSP will collect Soil samples inside the building and do advance soil borings at seven (7) proposed modified active gas sampling (MAGS) well locations and five (5) proposed vacuum monitoring point (VMP) locations. If the results exceed a DEP Soil Cleanup Target Level for leachability, based on groundwater criteria, for any constituent, WSP will request DEP approval to analyze the split samples. WSP will convert the 12 soil borings into seven (7) MAGS wells (MAG001 through MAG007) and five (5) VMP wells (VMP001 through VMP005) for subsequent use during the MAGS investigation. The MAGS investigation will involve fitting a regenerative blower (Fuji Electric Model VFC508P-2T, 2.5 hp, single phase) to a MAGS well to extract soil vapor from vadose zone soil, and near the end of the MAGS extraction at each location, one soil vapor sample will be collected to provide a general assessment of the types and concentrations of remaining chlorinated VOCs in soil. WSP solicited quotes from subcontractors for the drilling, IDW disposal, and utility locate. Atlantic driling Supply, Erwin, and GeoTek, were chosen respectively, with the lowest responsive/responsible bids.

Subtask 3: Reporting WSP will submit a supplemental assessment report to include a description of the sampling procedures, evaluation of the soil, soil vapor, and groundwater screening analytical results, tabulated soil data summary of the current and historical analytical data, a site map showing the groundwater screening and soil analytical results, laboratory analytical data, conclusions, and recommendations.

WSP and the FDEP confirmed on March 31, 2023, that an Access Agreement with the current real property owner of the AR-PAT's Dry Cleaning, (ERIC_4805) site has been executed.

The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost for this Task Assignment is $28,842.08 with 141 labor hours.

Printed on recycled paper.

FDEP COST ESTIMATEContractor: WSP USA Inc.

Date: 3/27/2023

Task #: DC008C SubTask 1 Project Management SubTask 6

Site: AR-Pats Dry Cleaning Inc SubTask 2 Soil Sampling, MAGS Well Install, & MAGS Investigation SubTask 7

Activity/Phase: Supplemental Assessmen SubTask 3 Reporting SubTask 8

Project Manager: Ginger Shirah SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$53.28 Project Manager (RFM) 14 13.9 $0.00 Program Leader - X-14 0 0 0 0 0 0 0 0 0 0

$68.75 Practice Leader - X-13 (JB) 3 0 3 0 0 0 0 0 0 0 $64.39 Senior Consultant - X-12 (MCC) 26 6 20 0 0 0 0 0 0 0 $53.28 Senior Sci/Eng - X-11 (RFM) 17 5 12 0 0 0 0 0 0 0

$0.00 Senior Project Sci/Eng - P-10 0 0 0 0 0 0 0 0 0 0 $42.00 Project Sci/Eng - P-9 (BL) 4 0 4 0.0 0 0 0 0 0 0 $40.73 Project Sci/Eng - P-9 (DM) 38 38 0 0 0 0 0 0 0 0

$0.00 Staff Sci/Eng - P-8 0 0 0 0 0 0 0 0 0 0 $33.90 Staff Sci/Eng - P-8 (AS) 2 0 2 0 0 0 0 0 0 0 $30.00 Sci/Eng/Admin - P-7 (TT) 37 37 0 0 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 141 13.9 86.0 41.0 0.0 0 0 0 0 0 0

Direct Labor $6,418.05 $738.36 $3,310.48 $2,369.21 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 172.50% $11,071.14 $1,273.67 $5,710.58 $4,086.89 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $17,489.19 $2,012.03 $9,021.06 $6,456.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF GOLDER Page 1

FDEP COST ESTIMATEContractor: WSP USA Inc.

Date: 3/27/2023

Task #: DC008C SubTask 1 Project Management SubTask 6

Site: AR-Pats Dry Cleaning Inc SubTask 2 Soil Sampling, MAGS Well Install, & MAGS Investigation SubTask 7

Activity/Phase: Supplemental Assessmen SubTask 3 Reporting SubTask 8

Project Manager: Ginger Shirah SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle Rental $480.00 $480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $822.00 $822.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $1,302.00 $1,302.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) Atlantic Drilling $958.15 $958.15 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $958.15 $958.15 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $95.82 $95.82 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $1,053.97 $1,053.97 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $220.00 $220.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utility Location $750.00 $750.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $970.00 $970.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $1,067.00 $1,067.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $3,497.00 $3,497.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $450.00 $450.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $3,947.00 $3,947.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $854.00 $854.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $1,060.00 $1,060.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $200.00 $200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $2,234.00 $2,234.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $27,093.16 $2,012.03 $18,625.03 $6,456.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $1,748.92 $201.20 $902.11 $645.61 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $28,842.08 $2,213.23 $19,527.14 $7,101.71 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF GOLDER Page 2

SITE : AR-Pats Dry Cleaning Inc.

SUBTASK 2: Soil Sampling, MAGS Well Install, & MAGS Investigation

DATE: 3/27/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Consultant (M. Crews) 6

Senior Sci/Eng (R. Mongillo) 5

Project Sci/Eng (D. McDaniels) 38

Sci/Eng/Admin (T. Tassimbedo) 37

TOTAL LABOR 86

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 Per Day 4 $480.00

TOTAL VEHICLE $480.00

PER DIEM STAFF RATE UNIT USEAGE

Per Diem Staff Sci/Eng (D. McDaniels) $36.00 Per Day 4 $144.00 Per Diem Project Sci/Eng (T. Tassimbedo) $36.00 Per Day 4 $144.00

Hotel Staff Sci/Eng (D. McDaniels) $89.00 Per Day 3 $267.00 Hotel Project Sci/Eng(T. Tassimbedo) $89.00 Per Day 3 $267.00

TOTAL PER DIEM $822.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

MAGS Well & VMP Supplies

Atlantic Drilling 2"X5' dia 0.010" slot screen $38.20 per 5 foot 7 $267.40 Supply 2" Riser - for adjustments $23.45 per 5 foot 2 $46.90

2" Male FT Point $8.30 per cap 12 $99.60 Water tight sealable 2" cap $5.75 per cap 12 $69.00 20/30 sand $5.90 per bag 8 $47.20 6" Steel Manhole $27.00 per manhole 12 $324.00 Portland cement $9.00 per 47 lb bag 2 $18.00 Concrete mix $6.40 per 47 lb bag 3 $19.20 7.5% sales Tax $66.85 LS 1 $66.85

Subtotal $958.15

Erwin IDW T&D 1 soil/ 1 liquid $110.00 per drum 2 $220.00

Geotek Utility location $750.00 LS 1 $750.00

TOTAL $2,886.30

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

Chlorinated VOCs - EPA Method 8260B

VOCs (Soil Vapor) TO-15 $200.00 7 $1,400.00

TCLP VOCs - Soil IDW 1311/8260 $210.00 1 $210.00 TCLP RCRA Metals - Soil IDW 1311/6010/7470 $135.00 1 $135.00

CVOCs - Primary Soil samples 8260 $73.00 24 $1,752.00

SPLP Extraction - Split Soil Samples 1311/1312 $55.00 0 $0.00 CVOCs - Split Soil samples 8260 $73.00 0 $0.00

Sample Shipping - Soil Large $150.00 2 $300.00 Sample Shipping - Soil vapor Large $150.00 1 $150.00

TOTAL LAB $3,947.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Miscellaneous Expendables $40.00 Per Day 3 $120.00 Construction/O&M Supplies $75.00 Per Day 2 $150.00 MAGS Investigation Kit $500.00 Per Day 1 $500.00 Tedlar Bag $20.00 Each 4 $80.00 PCE detector tubes (Low range) $240.00 Package of 10 1 $240.00 PCE detector tubes (High range) $90.00 Package of 10 1 $90.00 Encore Sampler for SPLP Samples $16.00 Per Sample 24 $384.00 Soil Sampling Kit (through concrete) $235.00 Per Day 2 $470.00 Drum $100.00 Per Drum 2 $200.00

TOTAL EQUIPMENT $2,234.00

Real-time MAGS calculations to evaluate estimated ROI, pore volume, and testing run time (6 hours).

Verification of property ownership (1 hour). Prepare and submit e-mail deliverable with field documentation and laboratory analytical report (4 hours).

Round trip travel (7 hours). Field preparation (1 hour). Soil sampling & MAGS well and VMP installations (10 hours per day x 2 days = 20 hours). MAGS investigation (10 hours per day x 1 day = 10 hours).

Round trip travel (7 hours). Soil sampling & MAGS well and VMP installations (10 hours per day x 2 days = 20 hours). MAGS investigation (10 hours per day x 1 day = 10 hours).

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : AR-Pats Dry Cleaning Inc.

SUBTASK 3: Reporting

DATE: 3/27/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Practice Leader (J. Brown) 3

Senior Sci/Eng (R. Mongillo) 12

Senior Consultant (M. Crews) MAGS evaluation and report documentation 20

Senior Project Sci/Eng (B. Lucero) 4

Staff Sci/Eng (A. Strayer) 2

TOTAL LABOR 41

VEHICLE TYPE RATE UNIT USEAGE

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT $0.00

Preparation of draft Supplemental Site Assessment Report

Develop conclusions and recommendations and prepare final Supplemental Site Assessment Report

Reporting: Document Production

CADD: Prepare report figures

FINAL --7/24/96

ERWIN US Ecology* HEPACO T&D Non Haz Soil - VOCs per drum 1 $110.00 $110.00 T&D Non Haz Mud/water - VOCs per drum 1 $110.00 $110.00 False Mobilization (no drum found) 0 $85.00 $0.00 PFAS Profile Fee (1 per site) 0 $350.00 $0.00 T&D Non Haz Soil - PFAS/PFOS per drum 0 $130.00 $0.00 T&D Non Haz Mud/water -PFAS/PFOS per drum 0 $140.00 $0.00 Disposal Non Haz Soil - VOCs per drum 1 $150.00 $150.00 Disposal Non Haz Mud/water - VOCs per drum 1 $150.00 $150.00 PFAS Profile Fee (1 per site) 0 $95.00 $0.00 Disposal Non Haz Soil - PFAS/PFOS 0 $650.00 $0.00 Disposal Non Haz Mud/water -PFAS/PFOS 0 $650.00 $0.00 Approval Fee (per site) 0 $750.00 $0.00 Disposal Non Haz Mud/water - VOCs per drum 1 $141.75 $141.75 Disposal Non Haz Soil - VOCs per drum 1 $185.00 $185.00 Waste Profile Fee (1 per media) 1 $110.00 $110.00 Technician per hr 0 $60.56 $0.00 Driver per hr 2 $69.60 $139.20 55 gallon reconditioned drum 0 $95.12 $0.00 55 gallon reconditioned drum 0 $134.63 $0.00 Flat Bed with lift gate per hr 2 $76.32 $152.64 Energy security recovery fee 15% 1 $109.29 $109.29

Total Cost $220.00 $300.00 * $837.88

IDW SUBCONTRACTOR COST ESTIMATES

Summary of IDW Subcontractors Costs Page 1 of 1

408 Ditmar Street

Pensacola, FL 32503

ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562

(850) 292-6511

To: Mr. Ralph Mongillo

WSP USA Inc.

9428 Baymeadows Road, Suite 400

Jacksonville, FL 32256 USA

January 4, 2023

Re: Non-Hazardous Drum Disposal

Mr. Mongillo:

The price for the transportation and disposal (T&D) of drums of non-hazardous soil, mud and water is listed below.

Non-Hazardous Chlorinated Solvents, Petroleum and Metals:

Description Rate Unit

T&D - Non-Haz Soil $ 110.00 Per Drum

T&D - Non-Haz Mud/Water $ 110.00 Per Drum

False Mobilization (No Drum Found) $ 85.00 Per Stop

The prices listed are all inclusive without any additional fees or charges (fuel surcharge, low volume stop fee etc.) and are valid for all regions in the State of Florida except for the Florida Keys.

Pricing for sites located in the Florida Keys will be bid on a case-by-case basis dependent on the volume of drums and the location.

Respectfully, Jonathan Erwin

Erwin Remediation, Inc.

Email: ErwinRemediation@Gmail.com

Office: (850) 292-6511 mailto:Remediation@Gmail.com

408 Ditmar Street

Pensacola, FL 32503

ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562

(850) 292-6511

To: Mr. Ralph Mongillo

9428 Baymeadows Road, Suite 400

Jacksonville, FL 32256 USA

January 9, 2023

Re: Non-Hazardous Drum Disposal of PFOS/PFAS Impacted Materials

Mr. Mongillo:

The price for the transportation and disposal (T&D) of drums of non-hazardous PFOS/PFAS soil, mud and water located in the State of Florida is listed below.

Description Rate Unit

Profile Fee (Charged once per site) $ 350.00 Per Site

T&D - Non-Haz PFOS/PFAS Impacted Soil $ 130.00 Per Drum

T&D - Non-Haz PFOS/PFAS Impacted Mud/Water $ 140.00 Per Drum

False Mobilization (No Drum Found) $ 85.00 Per Stop

The prices listed are all inclusive without any additional fees or charges (fuel surcharge, low volume stop fee etc.) and are valid for all regions in the State of Florida except for the Florida Keys. Pricing for sites located in the Florida Keys will be bid on a case-by-case basis dependent on the volume of drums and the location.

Respectfully, Jonathan Erwin

Erwin Remediation, Inc.

Email: ErwinRemediation@Gmail.com

Office: (850) 292-6511 mailto:Remediation@Gmail.com

From: Jason Boltus To: Crews, Matt Cc: Mongillo, Ralph; Jon Ramsier Subject: RE: Rate Sheet for Drum Pickups Date: Wednesday, February 8, 2023 11:34:02 AM Attachments: image002.png image003.png

Good Morning Matt, US Ecology can provide disposal options (solid/liquid) based on the analytical confirming Non-Reg Disposal at $150.00/Drum. The PFAs containing material would be priced at $650/Drum to a Subtitle C Landfill. The PFAs also would carry a $750 subtitle C State Approval fee. Each Wastestream profiled would carry a $95.00 profiling fee to that designated facility. Hope that helps and if there is anything else you need don’t hesitate to reach out.

Transportation we can discussed based on location of the various job sites and wastestream volume.

Thank you, Jason Boltus

Branch Manager 7202 E. 8th Avenue Tampa, FL 33619 E: Jason.Boltus@usecology.com P: (315) 256-2688 C: (315) 802-3164 Emergency Response: 800.839.3975

From: Crews, Matt <matt.crews@wsp.com> Sent: Wednesday, February 8, 2023 8:45 AM To: Jason Boltus <Jason.Boltus@usecology.com> Cc: Mongillo, Ralph <ralph.mongillo@wsp.com> Subject: RE: Rate Sheet for Drum Pickups

This email came from an external source, please take caution when interacting with it.

Thanks, Jason. The material would be located at sites across the state of Florida. We understand that transportation costs depend on location. We have had other companies provide transportation rates based on a range of distances from the disposal facility.

Matthew Crews, P.E.

Assistant Vice President, Environmental Engineer mailto:Jason.Boltus@usecology.com mailto:matt.crews@wsp.com mailto:ralph.mongillo@wsp.com mailto:Jon.Ramsier@usecology.com https://www.wsp.com/

T+ 1 904-363-3430 M+ 1 904-327-8420

9428 Baymeadows Road, Suite 400 Jacksonville, Florida, USA 32256 wsp.com

From: Jason Boltus <Jason.Boltus@usecology.com> Sent: Wednesday, February 8, 2023 6:19 AM To: Crews, Matt <matt.crews@wsp.com> Cc: Mongillo, Ralph <ralph.mongillo@wsp.com> Subject: RE: Rate Sheet for Drum Pickups

Good Morning Matt, Yes I will work up a rate sheet for Transportation and Disposal of 55 gallon drums of Solids/Liquids based on contaminants listed below.

Where would the material be located?

Thank you, Branch Manager 7202 E. 8th Avenue Tampa, FL 33619 E: Jason.Boltus@usecology.com P: (315) 256-2688 C: (315) 802-3164 Emergency Response: 800.839.3975

From: Crews, Matt <matt.crews@wsp.com> Sent: Friday, February 3, 2023 10:03 AM To: Jason Boltus <Jason.Boltus@usecology.com> Cc: Mongillo, Ralph <ralph.mongillo@wsp.com> Subject: Rate Sheet for Drum Pickups

CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe.

This email came from an external source, please take caution when interacting with it.

mailto:Jason.Boltus@usecology.com mailto:matt.crews@wsp.com mailto:ralph.mongillo@wsp.com mailto:Jason.Boltus@usecology.com mailto:matt.crews@wsp.com mailto:Jason.Boltus@usecology.com mailto:ralph.mongillo@wsp.com

Jason, We have a contract with the FDEP Waste Cleanup Program and would like to know if you can provide a general rate sheet to us for transportation and disposal of soils and liquids generated during our projects. For this rate sheet, please assume that the waste is non-hazardous and stored in 55-gallon steel drums. Our most common contaminants of concern are chlorinated volatile organic compounds, PFAS, and metals. Please let us know if you can help.

Thanks, Matt

Matthew Crews, P.E.

Assistant Vice President, Environmental Engineer

T+ 1 904-363-3430

M+ 1 904-327-8420

9428 Baymeadows Road, Suite 400 Jacksonville, Florida, USA 32256 wsp.com

NOTICE: This communication and any attachments ("this message") may contain information which is privileged, confidential, proprietary or otherwise subject to restricted disclosure under applicable law. This message is for the sole use of the intended recipient(s). Any unauthorized use, disclosure, viewing, copying, alteration, dissemination or distribution of, or reliance on, this message is strictly prohibited. If you have received this message in error, or you are not an authorized or intended recipient, please notify the sender immediately by replying to this message, delete this message and all copies from your e-mail system and destroy any printed copies.

-LAEmHhHzdJzBlTWfa4Hgs7pbKl

02/03/2023

Ralph Mongillo

WSO USA

9428 Baymeadows Rd Ste 400

Jacksonville,, FL, 32256 ralph.mongillo@wsp.com

19046108761

Subject: Non Hazardous Waste Drums

Quote Number: QT-2040

Dear Ralph, Thank you for the opportunity to provide this proposal for the waste management of 55 gallon drums located at Multiple Site Locations. I have created a rate quote based on your description of needs. I have also included our standard rate sheet of other needs and services.

HEPACO is the premier environmental contractor with coverage from 45 offices. We specialize in emergency response, industrial services, remediation, and waste services. HEPACO serves a multitude of customers including transportation companies, energy companies, environmental consultants, industrial facilities, terminals, environmental service companies, general contractors, property owners, and many other public and private-sector clients.

HEPACO, with its well-rounded and cross-trained staff, can effectively and efficiently complete this project and appreciates the opportunity. We stand firmly behind our work and always strives to deliver exceptional value and a high level of service at reasonable pricing.

Scope of Work

HEPACO will provide the following:

Transport 55 gallon drums of non regulated solids and liquids

Disposal of non hazardous solids and liquids

Assumptions

HEPACO assumes the following:

All work will be completed in one mobilization unless otherwise noted

If groundwater is encountered, additional costs for transportation, disposal, management, and/or containment will apply accordingly to the HEPACO Time and Materials Rate Sheet.

Costs do not include any required permitting unless otherwise noted

Costs do not include any surgical excavation around utilities, surface and/or subsurface structures

(it is assumed utilities are not present)

Client will provide any required sampling/analysis, technical reports, surveying, compaction testing and/or private utility locating services unless otherwise noted

All disposal costs are based on final profile approval and waste acceptance by the disposal facility

Client is responsible for any additional cost associated with non-conforming waste as determined by the disposal facility

Field crew will be on-site working eight (8) hours per day M-F with no weekend or holiday work unless otherwise noted

Customer is responsible for disposal costs unless otherwise noted

Quantities are speculative. With the exception of minimums, all billing will be based on actual quantities.

Price

A pricing itemization is provided in Attachment A.

HEPACO Basic Conditions:

All projects require a two (2) week notice to proceed. HEPACO will make every effort possible to meet all our client’s requests; however, HEPACO cannot guarantee a project start date with less than two (2) weeks’ notice to proceed.

This proposal is contingent upon credit approval and valid for thirty days

For any additional work beyond the original scope of work, time and material rates will apply.

Except for minimums, billing will be based on actual quantities at unit costs (see Attachment A).

A four (4)-hour minimum will apply to all unit costs quoted by the hour

Unit costs quoted by the day will be billed at the full day rate for any work on site. There will be no partial billing for partial workdays.

Unit costs quoted by the day apply up to eight hours per day. After eight hours per day, the day rate will be pro-rated for additional hours.

Unit costs are based on a non-union work force, no prevailing wages, no overtime work, and no performance bond.

Additional costs related to unexpected, concealed, or unknown conditions or any delays at the project site shall be incurred by customer.

HEPACO will not be held responsible if underground or above ground structures, cables, conduits, site features, property, materials, or equipment are destroyed, damaged, or rendered inoperable during the project.

Pricing is based on the national average for Diesel Fuel at the time of proposal submittal. The index will be reviewed during the start of the field work and additional costs will be billed if applicable. For reference, the link to current and historic fuel pricing is located at https://www.eia.gov/petroleum/gasdiesel/

Pricing includes HEPACO’s standard insurance coverage. Adding additional insured or increased coverages will be at additional cost and will be quoted on a case-by-case basis.

Again, thank you for the opportunity and we look forward to completing this project.

Sincerely, Kevin Hamilton

Kevin Hamilton

HEPACO Territory Account Manager

Subject: Non Hazardous Waste Drums

Quote Number: QT-2040

By signing below the customer acknowledges that they have received, reviewed, and agree to the HEPACO

Proposal

Owner or Owner Agent:

Signature:

Date of Acceptance:

Print Name

Owner or Owner Agent

ATTACHMENT A

PRICING ITEMIZATION TABLE

PRICING ITEMIZATION TABLE

FEES

Fee Calculated As Total Dollar Amount

Energy, Security and Recovery Fee Percentage of Total $130.95

Estimated Total Quote Cost: $1,003.93

Item Name or Description Estimated Quantity Unit Cost Units of Measure Total Line-Item Cost

NON-HAZ LIQUIDS DISPOSAL (PER

DRUM) 1 $141.75 DRUM $141.75

NON-HAZ SOLIDS DISPOSAL (PER

DRUM) 1 $185.00 DRUM $185.00

WASTE PROFILE FEE 1 $110.00 EACH $110.00

TECHNICIAN 1 $60.56 HOUR $60.56

TRUCK DRIVER 1 $69.60 HOUR $69.60

17H/E 55 GALLON - RECONDITIONED

DRUMS 1 $95.12 EACH $95.12

17H/E 55 GALLON DRUMS 1 $134.63 EACH $134.63

FLATBED W/LIFT GATE 1 $76.32 HOUR $76.32

9428 Baymeadows Road, Suite 400, Jacksonville, Florida 32256 USA

T: +1 904 363-3430 F: +1 904 363-3445

WSP.com

March 27, 2023 Proposal No. 202208346

Ms. Ginger Shirah Florida Department of Environment Protection Division of Waste Management Waste Site Cleanup Section 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400

RE: PROPOSAL FOR SUPPLEMENTAL SITE ASSESSMENT

MODIFIED ACTIVE GAS SAMPLING INVESTIGATION

AR-PAT’S DRY CLEANING INC.

SEBASTIAN, INDIAN RIVER COUNTY, FLORIDA

FACILITY ID NUMBER: ERIC_4805

PROPOSED TASK ASSIGNMENT: HW685_DC008C

Dear Ms. Shirah:

WSP USA Inc. (WSP) is pleased to provide the Florida Department of Environmental Protection (DEP) with this cost proposal for completing Supplemental Site Assessment activities at the above-referenced site. This proposal includes a description of the proposed scope of services, level of effort sheets for each subtask, and a cost estimate form that summarizes the costs of the proposed services. The scope of work is based on the recommendations accepted by the DEP in the review of the 2022 Annual Groundwater Monitoring Report, dated January 24, 2023.

The proposed MAGS well locations were reviewed and approved by the DEP in a January 5, 2023 email.

SUBTASK 1 – PROJECT MANAGEMENT

To facilitate project quality and satisfactory completion of the proposed scope of work, all aspects of this project will be overseen by an experienced project manager. The project manager will be responsible for the schedule, budget, invoicing, project activities, and communications with DEP. Project management will include coordination of field activities; resource allocation to confirm the work is conducted by qualified professionals in accordance with the project schedule; cost control and tracking of the budget status; and submission of project invoices in accordance with DEP Waste Cleanup Program requirements. The project manager will be responsible for seeing that the work is conducted in a manner that is consistent with the requirements of the DEP-approved task assignment.

Ms. Ginger Shirah Proposal No. 202208346

Florida Department of Environment Protection March 27, 2023

SUBTASK 2 – SOIL SAMPLING, MAGS WELL INSTALLATION, AND MAGS

INVESTIGATION

Utility Location Following authorization to proceed, WSP will coordinate with the real property owner for access to complete the scope of work. WSP will obtain the applicable local, county, and state-required permits before implementing the proposed scope of work. The location of underground utilities will be identified and marked. Sunshine State One Call, a utility location service provider, will be contacted at least three working days (72 hours) before any subsurface work begins. Given that work will be conducted on private property, Sunshine State One Call might not be able to provide details regarding specific utilities in the area where assessment activities will be conducted. Therefore, WSP will use a private utility location company to locate and map shallow subsurface anomalies present within the proposed assessment areas.

Soil Sampling WSP will core through the concrete parking areas and concrete slab inside the building and advance soil borings at seven (7) proposed modified active gas sampling (MAGS) well locations and five (5) proposed vacuum monitoring point (VMP) locations. At each location, WSP will use a stainless-steel hand auger to collect discrete soil samples from the 0 to 0.5 feet below ground surface (bgs) and 0.5 to 2.0 feet bgs depth intervals. WSP will collect a primary soil sample from the bottom of each depth interval (0.5 feet bgs and 2.0 feet bgs). WSP will also collect a split soil sample using a 25-gram EnCore sampler. The split samples will be placed on hold pending a review of the primary sample results. Based on previous assessment data, WSP anticipates a depth-to-groundwater of 3 to 3.5 feet bgs.

The proposed MAGS well and VMP locations are shown on the attached Figure 1.

Soil samples will be collected from the wells in accordance with DEP Standard Operating Procedures (SOPs) for Field Activities (DEP SOP-001/01), dated January 2017 (effective April 16, 2018). WSP will place the soil samples on ice and ship the coolers to a Florida Department of Health and National Environmental Laboratory Accreditation Program-certified fixed-based laboratory, along with the completed chain of custody documentation. The laboratory will analyze the primary samples for chlorinated volatile organic compounds (VOCs) using EPA Method 8260B.

If the results exceed a DEP Soil Cleanup Target Level for leachability, based on groundwater criteria, for any constituent, WSP will request DEP approval to analyze the split samples using the Synthetic Precipitation Leaching Procedure (SPLP), if necessary. The cost for the SPLP extraction and subsequent chlorinated VOC analysis is not included in this proposal and a Work Change Directive will be completed if this testing is necessary after consulting with the DEP. WSP will collect up to 24 soil samples (two at each boring location) for laboratory analysis using standard turnaround time.

MAGS Well Installation WSP will convert the 12 soil borings into seven (7) MAGS wells (MAG001 through MAG007) and five (5) VMP wells (VMP001 through VMP005) for subsequent use during the MAGS investigation. WSP has assumed a 20-foot vacuum radius of influence (ROI) for the purposes of MAGS well and VMP spacing.

The MAGS wells and VMPs will be constructed of 2-inch diameter, Schedule 40 PVC with 0.010-inch machine-slotted screens. The bottom of the well screen will be set approximately 1 foot above the water table. Based on an anticipated depth-to-groundwater of 3 to 3.5 feet bgs, WSP has assumed the MAGS wells and VMPs will be screened from 1.0 to 2.5 feet bgs for cost estimating purposes.

Following installation of the MAGS wells and VMPs, WSP will fill the annular space in the borehole with 20/30 grade silica sand to a level approximately 0.5 feet above the top of the well screen. WSP will then add a layer of bentonite grout to the surface to create a seal. Each of the risers will be cut just below final grade and capped with a water-tight expandable locking plug. The MAGS wells and VMPs will be housed within a steel manhole cover and completed at the surface within a flush-mounted concrete pad.

WSP estimates two days for a two-person field crew to complete soil sampling and MAGS well and VMP installation activities.

MAGS Investigation WSP will complete the MAGS investigation to evaluate the presence and locations of potential source areas and to identify locations and analyses for additional discrete soil sampling. The results may also be used for a full-scale soil vapor extraction system design, if warranted. The site is an active drycleaner (PERC free); therefore, the testing will be conducted when the drycleaner is not busy. The facility removed the last dry cleaning machine using PERC and replaced it with a Miele Washing Machine (PERC free) in November 2022. WSP will use the newly installed seven MAGS wells and five VMP wells during the investigation.

The MAGS investigation will involve fitting a regenerative blower (Fuji Electric Model VFC508P-2T, 2.5 hp, single phase) to a MAGS well to extract soil vapor from vadose zone soil. WSP will analyze the extracted soil vapor using an OVA-PID and/or Draeger colorimetric detector tubes. The blower will be capable of a flow rate of 154 standard cubic feet per minute at a vacuum of 80 inches of water (inches H20) under ideal conditions. A portable generator will supply power to the blower. The connection between the MAGS wellhead and blower will be made using 2-inch diameter vacuum-rated flexible PVC tubing and Schedule 40 PVC pipe. Vacuum gauges, a flowmeter, filter, and sample ports will be installed in line.

WSP will test each of the MAGS wells for an estimated 30 minutes to one hour. At a minimum of one location, WSP will perform step-increase vacuum tests, which will consist of a low, medium, and high vacuum setting. WSP will measure subsurface vacuum pressure at varying distances from the primary extraction points using nearby MAGS wells and VMPs to evaluate subsurface flow characteristics. This data will be used to estimate the effective field ROI, soil permeability, hydraulic conductivity, pore volume, and purge time. The project engineer will perform calculations during the field event to confirm the time required to evaluate one pore volume of soil vapor based on the measured ROI and actual vapor flow rate. Based on these calculations, the time that vapor is extracted at each MAGS well will be adjusted accordingly. An OVA-PID and colorimetric detector tubes will be used to monitor soil vapor extracted from the MAGS sampling point.

Near the end of the MAGS extraction at each location, one soil vapor sample will be collected to provide a general assessment of the types and concentrations of remaining chlorinated VOCs in soil. The samples will be collected in Summa Canisters (Tedlar bags if Summa Canisters are not available) and submitted to a fixed-base laboratory for VOC analysis using EPA Method TO-15.

WSP estimates one day for a two-person field crew to complete the MAGS investigation.

Investigation Derived Waste WSP will temporarily store the investigation-derived waste (IDW) soil cuttings from the hand auger borings in a 55-gallon steel drum(s). A waste characterization sample will be collected from the IDW drum(s) for analysis of total VOCs using EPA Method 8260. If the waste characterization sample is nonhazardous and acceptable to the disposal subcontractor, the IDW drum(s) will be picked up and transported to a facility for proper disposal. A non-hazardous waste manifest will be provided by the disposal subcontractor upon delivery to the disposal facility.

For cost estimating purposes, WSP has included containerization, characterization sampling, and disposal of one 55-gallon drum of non-hazardous soil and liquid (decontamination water).

Interim Deliverable for Subtask 2 Upon completion of Subtask 2, an e-mail deliverable will be submitted and include copies of the field data sheets, equipment calibration forms, field notes, laboratory analytical report, laboratory chain-of-custody documentation, and non-hazardous waste manifest.

SUBTASK 3 – REPORTING

Upon completion of field activities, WSP will prepare a Supplemental Site Assessment report documenting the soil sampling and MAGS investigation results. The report will include a description of the field investigation and sampling procedures, evaluation of the analytical results, tabulated summary of the current and historical soil analytical data, MAGS results, tables, figures, conclusions, and recommendations.

HEALTH AND SAFETY

WSP will update the existing site-specific Health and Safety Plan for the field work. The work will be completed in accordance with WSP’s safety policies and procedures. At a minimum, WSP will wear safety glasses, high visibility safety vests, and steel-toed boots. A safety job briefing will be conducted prior to the start of work activities, and anytime the scope of work or site conditions change.

COST AND SCHEDULE

The estimated cost to complete the proposed scope of work is $28,621.08. WSP anticipates completing the field work in May 2023. The LOE/CEF sheets are included in Attachment A and the subcontractor bids are included in Attachment B. The following table summarizes the proposed costs and deliverable schedule.

Task Proposed Cost Proposed Schedule and Deliverables

Subtask 1: Project Management $ 2,213.23 September 30, 2023

Subtask 2: Soil Sampling, MAGS Well Installation, and MAGS Investigation

$19,527.14 July 15, 2023 (Field documentation, non-hazardous waste manifest, and laboratory report submittal via email submittal)

Subtask 3: Reporting $ 7,101.71 August 15, 2023 (Supplemental Site Assessment Report)

Total/Completion Date $28,842.08 October 31, 2023

WSP appreciates the opportunity to provide services to the DEP Waste Cleanup Program. Should you require additional information or clarifications, please contact us at 904 363-3430.

Sincerely, Ralph F. Mongillo, Jr. PG Matthew C. Crews, PE Lead Consultant / Senior Geologist Assistant Vice President, Environmental Engineer

RFM/MCC/as

Attachments: Figure 1 Proposed MAGS and VPM Well Locations

Attachment A Level of Effort Sheets/Cost Estimate Form Attachment B Subcontractor Bids

G:\Projects\DEP-Drycleaning\Projects\Sebastian\Ar-Pats Dry Cleaners\HW685\DC008C - MAGS\Proposal\DC008C - Supplemental Assessment (MAGS) Proposal_ERIC_4805.docx

File details come from the government source that posted it. Updated .