This document is a Task Assignment Change Order (TACO #1) issued by the State of Florida Department of Environmental Protection (FDEP) to WSP USA Inc. under Contract Number HW685. The change order amends Task Assignment BIL01B for site assessment and permitting activities at the Pelican Harbor Seabird Station located at 399 NE 82nd Terrace, Miami, Miami-Dade County. The project is identified as ERIC_18138. Department Project Manager Megan Johnson and Contractor Project Manager Brandon Poiencot, PE are the designated points of contact.
The change order extends the Task Assignment completion date from March 9, 2024 to July 7, 2024, a total extension of 120 days. The extension was necessitated by delays in Department of Environmental Resources Management (DERM) approval of the Soil Sampling Plan and the requirement for City of Miami right-of-way permits prior to field sampling activities. The total contract value remains unchanged at $39,711.30, consisting of $36,291.30 in fixed unit rate costs and $3,420.00 in cost reimbursement for NPDES and Certificate Fees. The primary deliverable comprises field documentation, laboratory analytical reports, tables, and figures, with the revised due date of June 3, 2024. All other terms and conditions of the original Task Assignment remain in effect.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O.
Object Code
Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/17/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:
1. TA Number: TACO Number: Contract Number:
TACO Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department’s Project Manager: Department’s Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Name:
4. There are no changes to the TA compensation.
The compensation of the TA is changed to the amounts indicated below:
Amended Price Price Prior to TACO
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
There are no changes to the TA Expiration Date.
The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).
6. There are no changes to the Attachments.
Attachment ___ is replaced with Attachment -____.
7. No Additional Changes.
Additional Changes:
8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.
IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department
Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature)
Date:
Additional signatures attached on separate page.
BIL01B 1 HW685
Megan Johnson 850.245.899 WSP USA Inc.
Brandon Poiencot, PE 904.363.3430
ERIC_18138
Pelican Harbor Seabird Station
$ 0.00 $ 0.00
03/09/2024 07/07/2024 120
1 1 1
WSP USA Inc.
Matthew Crews, PE
Environmental Engineer
3/7/2024
Crews, Matt (USMC700671) Digitally signed by Crews, Matt (USMC700671) Date: 2024.03.07 08:24:05 -05'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2024.03.06 15:40:10 -05'00'
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: WSP USA Inc., HW685 Contract File
FROM: Megan Johnson, Contract Manager
DATE: March 6, 2024
SUBJECT: Negotiation Summary – BIL22 Task Assignment (TA) Change Order #1 – TA BIL01BC1 Pelican Harbor Seabird Station – Site ID # ERIC_18138 Site Assessment and Permitting activities
This Task Assignment Change Order (TACO) extends the Task Assignment completion date and the interim and final deliverable due dates. Specific changes are detailed below:
FDEP and the contractor agreed on a time extension for the final deliverable due to a delay in DERM approving the Soil Sampling Plan and requiring City of Miami right of way permits prior to sampling.
There is no change to the original cost of $39,711.30.
From: Poiencot, Brandon To: Johnson, Megan R; Brown, Jesse Cc: Crews, Matt Subject: RE: Pelican Harbor assessment work Date: Thursday, February 15, 2024 2:30:20 PM Attachments: image001.png image002.png
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Megan, Yes, that would be good. Thank you!
Brandon K. Poiencot, PE Lead Consultant Environmental Engineer
T+ 1 904-363-3430 M+ 1 904-312-4347
From: Johnson, Megan R <Megan.R.Johnson@FloridaDEP.gov> Sent: Thursday, February 15, 2024 2:28 PM To: Poiencot, Brandon <brandon.poiencot@wsp.com>; Brown, Jesse <jesse.brown@wsp.com> Cc: Crews, Matt <matt.crews@wsp.com> Subject: RE: Pelican Harbor assessment work
Hey Brandon, That sounds good, I appreciate the update. Would you all be ok with us bumping out the deliverable and TA completion dates with a time extension TACO?
Thanks, Megan
From: Poiencot, Brandon <brandon.poiencot@wsp.com> Sent: Thursday, February 15, 2024 2:12 PM To: Johnson, Megan R <Megan.R.Johnson@FloridaDEP.gov>; Brown, Jesse <jesse.brown@wsp.com> Cc: Crews, Matt <matt.crews@wsp.com> Subject: RE: Pelican Harbor assessment work
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Hey Megan, DERM is requiring an approved Soil Sampling Plan in addition to a City of Miami R/W permit before we can sample. We are currently working on the R/W permit and hope to have a draft sampling plan ready for review in the next week or two. I’m unsure as to how long DERM will take to approve the sampling plan.
On another note, we had an onsite meeting yesterday with Pelican Harbor, some of their subcontractors, and a City of Miami planning department official to discuss the ISR Work Plan and the requirements for the City of Miami Certificate to Dig. I plan to send out a summary email of that meeting, which I will copy you on. The Certificate to Dig is our last hurdle before we can finally mobilize and start moving dirt.
Feel free to contact me with any questions or comments. I will get that summary email out later today.
Thanks, Brandon K. Poiencot, PE Lead Consultant Environmental Engineer
T+ 1 904-363-3430 M+ 1 904-312-4347
From: Johnson, Megan R <Megan.R.Johnson@FloridaDEP.gov> Sent: Thursday, February 15, 2024 1:57 PM To: Brown, Jesse <jesse.brown@wsp.com>; Poiencot, Brandon <brandon.poiencot@wsp.com> Cc: Crews, Matt <matt.crews@wsp.com> Subject: Pelican Harbor assessment work
Hey guys, I’m just checking in on the assessment work that was to be done at the Pelican Harbor site, see attached Task Assignment BIL01B. The deliverable (field documentation, etc.) is due February 26, 2024, and with the TA expiration of March 9, 2024, I just didn’t want time to get away from us and that TA to expire. Let me know where y’all are when you get a chance.
Thanks so much, Megan
Megan R. Johnson Environmental Consultant Brownfields and CERCLA Site Screening Section Florida Department of Environmental Protection 2600 Blair Stone Road, MS 4535 Tallahassee, FL 32399
Megan.R.Johnson@floridadep.gov Office:
Dep Customer Survey
NOTICE: This communication and any attachments ("this message") may contain information which is privileged, confidential, proprietary or otherwise subject to restricted disclosure under applicable law. This message is for the sole use of the intended recipient(s). Any unauthorized use, disclosure, viewing, copying, alteration, dissemination or distribution of, or reliance on, this message is strictly prohibited. If you have received this message in error, or you are not an authorized or intended recipient, please notify the sender immediately by replying to this message, delete this message and all copies from your e-mail system and destroy any printed copies.
-LAEmHhHzdJzBlTWfa4Hgs7pbKl
Dep Customer Survey
Funding Information:
Org. Code E.O.
Object Code
Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor�st �s Project Manager: ontractor�s t�s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department
Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature)
Date:
Additional signatures attached on separate page.
HW685
BIL01B Completion March 9, 2024
The Department approves this Task Assignment (TA), based upon the Cost Proposal and Level of Effort (CP/LOE), for Site Assessment and Permitting activities at the below project site, submitted to the Department on December 18, 2023, by WSP USA Inc.
Megan Johnson 850.245.8994 Contractor WSP USA Inc. Contractor
Contractor Brandon Poiencot, PE Contractor 904.363.3430
ERIC_18138
399 NE 82nd Terrace, Miami, Miami-Dade County
Pelican Harbor Seabird Station
Contractor Contractor
$ 36,291.30
$ 3,420.00
$ 39,711.30
Scope of Work
WSP USA Inc.
Contractor
Matthew Crews, PE
Environmental Engineer
12/20/2023
Crews, Matt (USMC700671) Digitally signed by Crews, Matt (USMC700671) Date: 2023.12.20 15:31:37 -05'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2023.12.19 15:43:43 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Field documentation, laboratory analytical reports, tables, and figures.
02/26/2024
Department approval of Project Management and field documentation, laboratory analytical report, tables, and figures (Subtasks 1 and 2) NPDES and Certificate Fees (Cost Reimbursement) not to exceed $3,420.00
$ 39,711.30
$ 39,711.30
HW685
BIL01B