This document package consists of a Task Assignment (TA) and a Task Assignment Change Order (TACO) between the State of Florida Department of Environmental Protection (FDEP) and WSP USA Inc. under Contract HW685. The task assignment was issued on December 18, 2023, with a completion date of March 29, 2024, for work to be performed at Concord Custom Cleaners #201, located at 1413 South Monroe Street in Tallahassee, Leon County, Florida. The project manager for FDEP is Patrick McGrane, and the contractor's project manager is Matt Crews of WSP USA Inc.

The task assignment authorizes WSP to conduct a file review to locate well permits for nine onsite monitoring wells at the Concord Custom Cleaners #201 facility. The original contract value was $4,591.94 on a fixed unit rate basis. TACO #1, dated January 5, 2024, reduced the total task assignment value to $4,471.94—a decrease of $120.00. This reduction resulted from the permit file review being conducted via telephone with the Northwest Florida Water Management District rather than requiring in-person travel to the district office in Havana. The cost savings were achieved by eliminating vehicle rental costs ($80.00) and miscellaneous field expendables ($40.00). The deliverable consists of Subtasks 1 and 2 (Project Management and File Review), with payment due upon submittal and FDEP approval of an email summary of findings including any located well permits, with a deadline of February 23, 2024.

View the file

Other files

File Type Posted
CN-370000-HW685-BF01C.pdf PDF
CN-370000-HW685-BF05ACO2.pdf PDF
CN-370000-HW685-BF05ACO3.pdf PDF
CN-370000-HW685-BF06A.pdf PDF
CN-370000-HW685-BF1ACO1.pdf PDF
CN-370000-HW685-BF6ACO1.pdf PDF
CN-370000-HW685-BIL01C.pdf PDF
CN-370000-HW685-BIL01CO1.pdf PDF
CN-370000-HW685-BIL03A.pdf PDF
CN-370000-HW685-BIL2ACO1.pdf PDF
CN-370000-HW685-BIL2CCO1.pdf.crdownload CRDOWNLOAD file
CN-370000-HW685-DC001A.pdf PDF
CN-370000-HW685-DC002G.pdf PDF
CN-370000-HW685-DC003A.pdf PDF
CN-370000-HW685-DC005C.pdf PDF
CN-370000-HW685-DC006B.pdf PDF
CN-370000-HW685-DC006C.pdf PDF
CN-370000-HW685-DC007C.pdf PDF
CN-370000-HW685-DC008A.pdf PDF
CN-370000-HW685-DC009B.pdf PDF
CN-370000-HW685-DC010A.pdf PDF
CN-370000-HW685-DC011A.pdf PDF
CN-370000-HW685-DC012C.pdf PDF
CN-370000-HW685-DC013A.pdf PDF
CN-370000-HW685-DC013C.pdf PDF
CN-370000-HW685-DC015B.pdf PDF
CN-370000-HW685-DC015C.pdf PDF
CN-370000-HW685-DC016A.pdf PDF
CN-370000-HW685-DC018A.pdf PDF
CN-370000-HW685-DC019B.pdf PDF
CN-370000-HW685-DC01ACO6.pdf PDF
CN-370000-HW685-DC01ACO8.pdf PDF
CN-370000-HW685-DC01ACO9.pdf PDF
CN-370000-HW685-DC020B.pdf PDF
CN-370000-HW685-DC022A.pdf PDF
CN-370000-HW685-DC022B.pdf PDF
CN-370000-HW685-DC022D.pdf PDF
CN-370000-HW685-DC023B.pdf PDF
CN-370000-HW685-DC023C.pdf PDF
CN-370000-HW685-DC027B.pdf PDF
CN-370000-HW685-DC027C.pdf PDF
CN-370000-HW685-DC029B.pdf PDF
CN-370000-HW685-DC029C.pdf PDF
CN-370000-HW685-DC02CCO1.pdf PDF
CN-370000-HW685-DC02FCO1.pdf PDF
CN-370000-HW685-DC031A.pdf PDF
CN-370000-HW685-DC031C.pdf PDF
CN-370000-HW685-DC032B.pdf PDF
CN-370000-HW685-DC035A.pdf PDF
CN-370000-HW685-DC037A.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number) Project Name:

4. ☐ There are no changes to the TA compensation.

☐ The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO ☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. ☐ There are no changes to the TA Expiration Date.

☐ The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. ☐ There are no changes to the Attachments.

☐ Attachment ___ is replaced with Attachment -____.

7. ☐ No Additional Changes.

☐ Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

DC002E 1

HW685

Patrick McGrane 850-245-8899 Contractor Contractor

Contractor Contractor

Contractor

WSP USA Inc.

Matt Crews 904-363-3430

ERIC_4867

Concord Custom Cleaners #201

✔ $ 4,471.94 $ 4,591.94

$ 4,471.94 $ 4,591.94 ✔ Completion

Completion 03/29/2024 03/29/2024 0

✔ 1 1

Digitally signed by jesse.brown@wsp.com DN: cn=jesse.brown@wsp.com Date: 2024.01.09 11:23:39 -05'00' jesse.brown@wsp.com

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2024.01.05 10:59:21 -05'00'

N/A

This Task Assignment Change Order authorizes a cost decrease due to the MW Permit File Review being performed over the phone.

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 01_18

Contract Number:

Task Assignment #:

Change Order #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

DC002E

HW685

$ 4,471.94

Subtask 1 & 2 – Project Management; File Review

Subtask 1 & 2 – Project Management; Submittal and FDEP approval of E-email summary of finding, including any located well permits

02/23/2024

$ 4,471.94

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

Memorandum

TO: Negotiation File

Concord Custom Cleaners #201 Tallahassee, Leon County

ERIC_4867

FROM: Patrick McGrane, Project Manager

SUBJECT: Negotiation Summary Task Assignment Change Order DC002E-1 (HW685)

DATE: Jan 5, 2024

This Change Order authorizes a total cost decrease due to the monitoring well permit File Review occurring over the phone, not in person at the Northwest Florida Water Management District office.

Further information is found in the January 4, 2023, change order email with Logan Chappell of WSP.

The previous cost total was $4,591.94. Total costs were decreased by $120.00 resulting in a new final cost total of $4,471.94. WSP may invoice according to the included schedule.

Specific negotiated subtasks are as follows:

Subtask 1:

Project Management is automatically calculated as a percentage of total labor in accordance with Contract HW685.

Subtask 2:

WSP labor performing Subtask 2 did not need to travel to the NWFWMD office. As a result, travel-related costs were removed.

FDEP COST ESTIMATEContractor: WSP USA Inc.

Date: 12/6/2023

Task #: DC002E SubTask 1 Project Management SubTask 6

Site: SubTask 2 File Review SubTask 7

Activity/Phase: Other SubTask 3 SubTask 8

Project Manager: Patrick McGrane SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$64.39 Project Manager (MC) 3 2.7 $0.00 Program Leader - X-14 0 0 0 0 0 0 0 0 0 0 $0.00 Practice Leader - X-13 0 0 0 0 0 0 0 0 0 0

$64.39 Senior Consultant - X-12 (MC) 16 16 0 0 0 0 0 0 0 0 $0.00 Senior Sci/Eng - X-11 0 0 0 0 0 0 0 0 0 0

$47.08 Senior Project Sci/Eng - P-10 (LC) 4 4 0 0 0 0 0 0 0 0 $0.00 Project Sci/Eng - P-9 0 0 0 0 0 0 0 0 0 0

$33.90 Staff Sci/Eng - P-8 (AS) 3 3 0 0 0 0 0 0 0 0 $0.00 Sci/Eng/Admin - P-7 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 26 2.7 23.0 0 0 0 0 0 0 0 0

Direct Labor $1,491.89 $171.63 $1,320.26 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 172.50% $2,573.51 $296.06 $2,277.45 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $4,065.40 $467.69 $3,597.71 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Concord Custom Cleaners No. 201

REV: 02/03 CEF GOLDER Page 1

FDEP COST ESTIMATEContractor: WSP USA Inc.

Task #: DC002E SubTask 1 Project Management SubTask 6

Site: SubTask 2 File Review SubTask 7

Activity/Phase: Other SubTask 3 SubTask 8

Project Manager: Patrick McGrane SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10

Concord Custom Cleaners No. 201

Travel Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $4,065.40 $467.69 $3,597.71 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $406.54 $46.77 $359.77 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $4,471.94 $514.46 $3,957.48 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF GOLDER Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Concord Custom Cleaners No. 201 SUBTASK 2: File Review

DATE: 12/6/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Consultant (M. Crews) 16

Senior Project Sci/Eng (L Chappell) 4

Staff Sci/Eng (A. Strayer) 3

TOTAL LABOR 23

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 per day 1 $80.00 Automobile $80.00 per day -1 ($80.00)

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE RATE UNIT USEAGE

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Miscellaneous Expendables $40.00 per day 1 $40.00 Miscellaneous Expendables $40.00 per day -1 ($40.00)

TOTAL EQUIPMENT $0.00

File review to locate well permits for nine onsite monitoring wells: CCCMW001, CCCMW002, CCCMW003, CCCMW005, CCCMW006, CCCMW007, CCCMW018, CCCDW001, and an unnamed monitoring well.

Retrieve and return hard copy files from WSP offsite file storage location.

File Review to locate permits with the Northwest Florida Water Management District office. Prepare and submit results of file review to FDEP.

FINAL --7/24/96

FDEP COST ESTI MATEContractor: WSP USA Inc.

Task #: DC002E SubTask 1 Project Management SubTask 6

Site: SubTask 2 File Review SubTask 7

Activity/Phase: Other SubTask 3 SubTask 8

Project Manager: Patrick McGrane SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$64.39 Project Manager (MC) 0 0.0 $0.00 Program Leader - X-14 0 0 0 0 0 0 0 0 0 0 $0.00 Practice Leader - X-13 0 0 0 0 0 0 0 0 0 0

$64.39 Senior Consultant - X-12 (MC) 0 0 0 0 0 0 0 0 0 0 $0.00 Senior Sci/Eng - X-11 0 0 0 0 0 0 0 0 0 0

$47.08 Senior Project Sci/Eng - P-10 (LC) 0 0 0 0 0 0 0 0 0 0 $0.00 Project Sci/Eng - P-9 0 0 0 0 0 0 0 0 0 0

$33.90 Staff Sci/Eng - P-8 (AS) 0 0 0 0 0 0 0 0 0 0 $0.00 Sci/Eng/Admin - P-7 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 0 0.0 0.0 0 0 0 0 0 0 0 0

Direct Labor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 172.50% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Task #: DC002E SubTask 1 Project Management SubTask 6

Site: SubTask 2 File Review SubTask 7

Activity/Phase: Other SubTask 3 SubTask 8

Project Manager: Patrick McGrane SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10

Concord Custom Cleaners No. 201

Travel Vehicle Rental ($80.00) ($80.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel ($80.00) ($80.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables ($40.00) ($40.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses ($40.00) ($40.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal ($120.00) $0.00 ($120.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost ($120.00) $0.00 ($120.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Concord Custom Cleaners No. 201 SUBTASK 2: File Review

DATE: 12/6/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Consultant (M. Crews) 0

Senior Project Sci/Eng (L Chappell) 0

Staff Sci/Eng (A. Strayer) 0

TOTAL LABOR 0

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 per day 0 $0.00 Automobile $80.00 per day -1 ($80.00)

TOTAL VEHICLE ($80.00)

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE RATE UNIT USEAGE

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Miscellaneous Expendables $40.00 per day 0 $0.00 Miscellaneous Expendables $40.00 per day -1 ($40.00)

TOTAL EQUIPMENT ($40.00)

File review to locate well permits for nine onsite monitoring wells: CCCMW001, CCCMW002, CCCMW003, CCCMW005, CCCMW006, CCCMW007, CCCMW018, CCCDW001, and an unnamed monitoring well.

Retrieve and return hard copy files from WSP offsite file storage location.

File Review to locate permits with the Northwest Florida Water Management District office. Prepare and submit results of file review to FDEP.

FINAL --7/24/96

Task #: DC002E SubTask 1 Project Management SubTask 6

Site: SubTask 2 File Review SubTask 7

Activity/Phase: Other SubTask 3 SubTask 8

Project Manager: Patrick McGrane SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$64.39 Project Manager (MC) 3 2.7 $0.00 Program Leader - X-14 0 0 0 0 0 0 0 0 0 0 $0.00 Practice Leader - X-13 0 0 0 0 0 0 0 0 0 0

$64.39 Senior Consultant - X-12 (MC) 16 16 0 0 0 0 0 0 0 0 $0.00 Senior Sci/Eng - X-11 0 0 0 0 0 0 0 0 0 0

$47.08 Senior Project Sci/Eng - P-10 (LC) 4 4 0 0 0 0 0 0 0 0 $0.00 Project Sci/Eng - P-9 0 0 0 0 0 0 0 0 0 0

$33.90 Staff Sci/Eng - P-8 (AS) 3 3 0 0 0 0 0 0 0 0 $0.00 Sci/Eng/Admin - P-7 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 26 2.7 23.0 0 0 0 0 0 0 0 0

Direct Labor $1,491.89 $171.63 $1,320.26 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 172.50% $2,573.51 $296.06 $2,277.45 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $4,065.40 $467.69 $3,597.71 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Task #: DC002E SubTask 1 Project Management SubTask 6

Site: SubTask 2 File Review SubTask 7

Activity/Phase: Other SubTask 3 SubTask 8

Project Manager: Patrick McGrane SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10

Concord Custom Cleaners No. 201

Travel Vehicle Rental $80.00 $80.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $80.00 $80.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $4,185.40 $467.69 $3,717.71 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $406.54 $46.77 $359.77 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $4,591.94 $514.46 $4,077.48 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

McGrane, Patrick

From: Chappell, Logan <Logan.Chappell@wsp.com> Sent: Thursday, January 4, 2024 12:57 PM To: McGrane, Patrick Cc: Crews, Matt Subject: DC002E TACO #1 Attachments: DELTA#1 - DC002E - Concord 201 File Review LOECEF.xlsx; ORIGINAL -DC002E - Concord 201 File

Review LOECEF.xlsx; TACO#1 - DC002E - Concord 201 File Review LOECEF.xlsx

Follow Up Flag: Follow up Flag Status: Flagged

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

Patrick, I forgot to menƟon this earlier, the original assignment had cost for me to drive to Havana and acquire permits from NWFWMD. I did not use the vehicle or misc. expenses. But instead called them over the phone and they assisted with the search of the permits remotely, which did take significantly longer than the original TA.

Let me know if the TACO aƩached is acceptable to the department.

Thanks, Logan

Logan Chappell, P.E.

Project Manager / Environmental Engineer

Email: Logan.Chappell@wsp.com Phone: +1 719-306-4640

WSP USA

325 John Knox Rd. Bldg F, Suite 140 Tallahassee, FL 32303 wsp.com

From: McGrane, Patrick <Patrick.McGrane@FloridaDEP.gov> Sent: Thursday, January 4, 2024 11:33 AM

To: Crews, Matt <matt.crews@wsp.com> Cc: Chappell, Logan <Logan.Chappell@wsp.com> Subject: Approval to Invoice DC002E ST 1 & 2

MaƩ, See aƩached approval to invoice for Subtasks 1 & 2 of TA DC002E Concord 201.

Thanks, Patrick McGrane Florida Department of Environmental ProtecƟon Waste Site Cleanup SecƟon Environmental Specialist II Patrick.McGrane@FloridaDEP.gov Office: 850-245-8899

NOTICE: This communication and any attachments ("this message") may contain information which is privileged, confidential, proprietary or otherwise subject to restricted disclosure under applicable law. This message is for the sole use of the intended recipient(s). Any unauthorized use, disclosure, viewing, copying, alteration, dissemination or distribution of, or reliance on, this message is strictly prohibited. If you have received this message in error, or you are not an authorized or intended recipient, please notify the sender immediately by replying to this message, delete this message and all copies from your e-mail system and destroy any printed copies.

-LAEmHhHzdJzBlTWfa4Hgs7pbKl

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

Additional signatures attached on separate page.

HW685

DC002E Completion March 29, 2024

This Task Assignment authorizes WSP to conduct a File Review for Concord Custom Cleaners #201 in accordance with the December 6, 2023 Scope of Work and Cost Estimate

Patrick McGrane 850-245-8766 Contractor WSP USA Inc. Contractor

Contractor Matt Crews Contractor 904-363-3430

ERIC_4867

1413 S Monroe Street Tallahassee, Leon County

Concord Custom Cleaners #201

Contractor Contractor

✔ $ 4,591.94

$ 4,591.94

Scope of Work

WSP USA Inc.

Contractor Matthew Crews

Environmental Engineer

12/18/2023

Crews, Matt (USMC700671) Digitally signed by Crews, Matt (USMC700671) Date: 2023.12.18 13:05:34 -05'00' Kelly Crain Digitally signed by Kelly Crain

Date: 2023.12.15 14:48:02 -05'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Subtask 1 & 2 – Project Management; File Review 02/23/2024

Subtask 1 & 2 – Project Management; Submittal and FDEP approval of E-email summary of finding, including any located well permits $ 4,591.94

$ 4,591.94