This is a Task Assignment (TA) under Contract Number HW685, issued by the Florida Department of Environmental Protection (FDEP) to WSP USA Inc. for groundwater sampling services at the Concord Custom Cleaners #201 facility located at 1413 South Monroe Street, Tallahassee, Leon County, Florida (DEP Facility ID: ERIC_4867). The Task Assignment is numbered DC002G with a completion date of August 29, 2025, and was executed on December 19, 2024. Patrick McGrane serves as the FDEP Project Manager, while Matt Crews represents WSP USA Inc. as the Contractor's Project Manager.
The scope of work authorizes WSP to conduct groundwater monitoring activities in accordance with the December 13, 2024 Scope of Work, Cost Estimate, and Bid Documentation. The work is divided into three subtasks: Subtask 1 (Project Management) costing $954.53 with deliverables due April 25, 2025; Subtask 2 (Groundwater Sampling Activities) costing $5,795.44 with deliverables due February 21, 2025, including field documentation, laboratory analytical reports for volatile organic compounds (VOCs), and waste manifests; and Subtask 3 (Reporting) costing $3,011.53 with a Groundwater Monitoring Report due March 28, 2025. The total Task Assignment value is $9,761.50 on a fixed unit rate basis, with 53 total labor hours. WSP will collect groundwater samples from four monitoring wells (CCCDW001, CCCMW001, CCCMW003, and CCCMW007) using low-flow sampling methods, conduct field parameter monitoring, arrange laboratory analysis for chlorinated VOCs using EPA Method 8260B, and manage investigation-derived waste disposal through subcontractor Erwin Remediation at $125.00 per drum for non-hazardous chlorinated solvent-impacted materials.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
Additional signatures attached on separate page.
HW685
DC002G Completion August 29, 2025
This Task Assignment authorizes WSP to conduct Groundwater Sampling at Concord Custom Cleaners #201 in accordance with the December 13, 2024 Scope of Work, Cost Estimate, and Bid Documentation.
Patrick McGrane 850-245-8899 Contractor WSP USA Inc. Contractor
Contractor Matt Crews Contractor 904-363-3430
ERIC_4867
1413 South Monroe Street, Tallahassee, Leon County
Concord Custom Cleaners #201
Contractor Contractor
✔ $ 9,761.50
$ 9,761.50
Scope of Work
WSP USA Inc.
Contractor Matthew Crews
Environmental Engineer
12/19/2024
Crews, Matt (USMC700671) Digitally signed by Crews, Matt (USMC700671) Date: 2024.12.19 09:24:04 -05'00'
Mubeen Darji
Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.
Date: 2024.12.19 08:43:38 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
BWC TAFORM 01/18
HW685
DC002G
Subtasks 1 & 3 - Project Management; Reporting
Subtask 2 - Groundwater Sampling Activities 02/21/2025
03/28/2025
Subtask 2 - Submittal and FDEP approval of email summary including field documentation, certified laboratory report for VOCs, and signed waste manifest
Subtasks 1 & 3 - Submittal and FDEP approval of the Groundwater Monitoring Report
$ 5,795.44
$ 3,966.06
$ 9,761.50
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette NNuñez
Lt. Governor
Alexis A. Lambert Secretary
Memorandum
TO: Negotiation File Concord Custom Cleaners #201
Tallahassee, Leon County
ERIC_4867
FROM: Patrick McGrane, Project Manager
SUBJECT: Negotiation Summary Task Assignment DC002G (HW685)
DATE: December 19, 2024
This Task Assignment authorizes WSP USA Inc. (WSP) to conduct groundwater monitoring at the
Concord Custom Cleaners #201 site. Only the wells that are specified in the included Scope of
Work are to be sampled. Work will begin following the execution of a site access agreement with the property owner and is to be performed as described in said site access agreement.
The total cost for this project is $9,761.50 with 53 total labor hours. All work is to be completed in accordance with the December 13, 2024, Scope of Work, Cost Estimate, and Bid
Documentation.
WSP may invoice according to the included schedule.
FDEP COST ESTIMATEContractor: WSP USA Inc.
Date: 12/13/2024
Task #: DC002G SubTask 1 Project Management SubTask 6
Site: SubTask 2 Groundwater Sampling Activities SubTask 7
Activity/Phase: Monitoring SubTask 3 Reporting SubTask 8
Project Manager: Patrick McGrane SubTask 4 SubTask 9
SubTask 5 SubTask 10
TTotals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$68.39 PProject Manager (MC) 5 4.7 $0.00 Program Leader - X-14 0 0 0 0 0 0 0 0 0 0 $0.00 Practice Leader - X-13 0 0 0 0 0 0 0 0 0 0
$68.39 Senior Consultant - X-12 (MC) 9 7 2 0 0 0 0 0 0 0 $49.42 Senior Sci/Eng - X-11 (LC) 25 11 14 0 0 0 0 0 0 0 $42.25 Senior Project Sci/Eng - P-10 (WM) 10 10 0 0 0 0 0 0 0 0
$0.00 Project Sci/Eng - P-9 0 0 0 0 0 0 0 0 0 0 $34.92 Staff Sci/Eng - P-8 (AS) 2 0 2 0 0 0 0 0 0 0
$0.00 Sci/Eng/Admin - P-7 0 0 0 0 0 0 0 0 0 0 $31.28 Staff Sci/Eng - P-8 (WM) 0 0 0 0 0 0 0 0 0 0 $53.09 Senior Sci/Eng - X-11 (BL) 2 0 2 0 0 0 0 0 0 0
$0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0
Total Hours 53 4.7 28.0 20 0 0 0 0 0 0 0
Direct Labor $2,767.97 $318.44 $1,444.85 $1,004.68 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 172.50% $4,774.75 $549.31 $2,492.37 $1,733.07 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $7,542.72 $867.75 $3,937.22 $2,737.75 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Concord Custom Cleaners No. 201
REV: 02/03 CEF GOLDER Page 1
FDEP COST ESTIMATEContractor: WSP USA Inc.
Date: 12/13/2024
Task #: DC002G SubTask 1 Project Management SubTask 6
Site: SubTask 2 Groundwater Sampling Activities SubTask 7
Activity/Phase: Monitoring SubTask 3 Reporting SubTask 8
Project Manager: Patrick McGrane SubTask 4 SubTask 9
SubTask 5 SubTask 10
TTotals 1 2 3 4 5 6 7 8 9 10
Concord Custom Cleaners No. 201
Travel Vehicle Rental $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $125.00 $125.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $125.00 $125.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $12.50 $12.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $137.50 $137.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $402.00 $402.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $150.00 $150.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $552.00 $552.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $515.00 $515.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $655.00 $655.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $9,007.22 $867.75 $5,401.72 $2,737.75 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $754.28 $86.78 $393.72 $273.78 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $9,761.50 $954.53 $5,795.44 $3,011.53 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF GOLDER Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Concord Custom Cleaners No. 201 SUBTASK 2: Groundwater Sampling Activities
DATE: 12/13/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Senior Consultant (M. Crews) 7
Senior Sci/Eng (L. Chappell) 11
Senior Project Sci/Eng (W. Mather) 10
TOTAL LABOR 28
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 per day 1 $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE RATE UNIT USEAGE
Erwin IDW T&D $125.00 per drum 1 $125.00
TOTAL $125.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
Groundwater Sampling Halocarbons Method 8260 $73.00 4 0 $292.00 PID/Hall-Series (Total VOCsMethod 8021 (IDW) $110.00 1 0 $110.00
Sample Shipping Large $150.00 1 $150.00
TOTAL LAB $552.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 per day 1 $40.00 Drum (new 55-gallon) $100.00 per drum 1 $100.00 Deep Groundwater Sampling Kit $415.00 per day 1 $415.00 Tubing, Poly/HDPE 1/2 x 5/8 $0.40 per foot 250 $100.00
TOTAL EQUIPMENT $655.00
Verification of property ownership prior to site access and HASP update (2 hours). Characterize IDW and prepare waste profile for transportation and disposal of IDW (2 hours). Prepare and submit field notes, sample forms, laboratory report in an email deliverable (3 hours).
Water levels and instrument calibration. Collect groundwater samples from four wells (CCCDW001, CCCMW001, CCCMW003, and CCCMW007) for chlorinated VOC analysis. IDW sampling and staging (10 hours).
Field event preparation (1 hour). Water levels and instrument calibration. Collect groundwater samples from four wells (CCCDW001, CCCMW001, CCCMW003, and CCCMW007) for chlorinated VOC analysis. IDW sampling and staging (10 hours).
FINAL --7/24/96
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Concord Custom Cleaners No. 201 SUBTASK 3: Reporting
DATE: 12/13/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Senior Consultant (M. Crews) 2
Senior Sci/Eng (L. Chappell) 14
Senior Sci/Eng (B. Lucero) CADD - Develop figures for Groundwater Monitoring Report 2
Staff Sci/Eng (A. Strayer) 2
TOTAL LABOR 20
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE RATE UNIT USEAGE
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
Prepare conclusions and recommendations for Groundwater Monitoring Report
Update data tables and prepare draft Groundwater Monitoring Report.
Reporting: report formatting, document production. Create pdf for OCULUS.
FINAL --7/24/96
WSP USA Inc.
9428 Baymeadows Road, Suite 400, Jacksonville, Florida 32256 USA
T: +1 904 363-3430 F: +1 904 363-3445 wsp.com
December 13, 2024 Proposal No. 2024US350454
Mr. Patrick McGrane Florida Department of Environmental Protection Division of Waste Management Waste Site Cleanup Section 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400
RE: COST PROPOSAL FOR GROUNDWATER SAMPLING
CONCORD CUSTOM CLEANERS #201
1413 S MONROE STREET
TALLAHASSEE, LEON COUNTY, FLORIDA
DEP FACILITY ID NUMBER: ERIC_4867
PROPOSED TASK ASSIGNMENT: DC002G
Dear Mr. McGrane:
WSP USA Inc. (WSP) is pleased to provide the Florida Department of Environmental Protection (DEP) with this cost proposal to complete groundwater sampling activities at the above-referenced site. This proposal includes a description of the proposed scope of services, level of effort sheets for each subtask, and a cost estimate form that summarizes the costs of the proposed services. The proposed scope of services is described below.
SUBTASK 1 – PROJECT MANAGEMENT
To facilitate project quality and satisfactory completion of the proposed scope of work, all aspects of this project will be overseen by an experienced project manager. The project manager will be responsible for the schedule, budget, invoicing, project activities, and communications with DEP and the field team. Project management will include coordination of field activities; resource allocation to confirm the work is conducted by qualified professionals in accordance with the project schedule; cost control and tracking of the budget status; and submittal of project invoices in accordance with DEP Waste Site Cleanup Section requirements. The project manager will oversee the work so that it is conducted in a manner that is consistent with the requirements of the DEP-approved task assignment.
SUBTASK 2 – GROUNDWATER SAMPLING ACTIVITIES
Groundwater Monitoring Following authorization to proceed, WSP will use the Leon County Property Appraiser’s website to verify that the current property owner has an executed Permission to Enter Property agreement with the DEP. WSP will then coordinate with the real property owner for access to complete the scope of work.
Mr. Patrick McGrane Proposal No. 2024US350454
Florida Department of Environmental Protection December 13, 2024
WSP will collect groundwater samples from four monitoring wells: CCCDW001, CCCMW001, CCCMW003, and CCCMW007. The attached Figure 2 shows the monitoring well locations.
Prior to groundwater sampling, depth-to-water measurements will be collected using an electronic water level indicator at each of the four monitoring wells to determine groundwater depth. During the sampling event, the locks and well caps will be inspected for damage or degradation and repaired or replaced, as necessary.
Groundwater samples will be collected from the wells in accordance with DEP Standard Operating Procedures (SOPs) for Field Activities (DEP SOP-001/01). Prior to collecting the groundwater sample, each well will be purged and field parameters including temperature, pH, specific conductance, dissolved oxygen, turbidity, and oxidation-reduction potential (ORP) will be monitored. Purge volumes and field parameters will be recorded on field data sheets, and the field monitoring equipment will be calibrated in accordance with the manufacturer’s recommended procedures.
Groundwater samples will be collected using low-flow sampling methods. The groundwater samples will be placed in laboratory-supplied containers, labeled with a unique identification number attached to the outside of the sample container, preserved on ice in a laboratory-provided cooler at a maximum temperature of four degrees Celsius, and delivered to a Florida Department of Health and National Environmental Laboratory Accreditation Program certified fixed-base laboratory, along with the completed chain-of-custody documentation. The laboratory will analyze the samples for chlorinated volatile organic compounds (VOCs) using EPA Method 8260B.
Investigation Derived Waste WSP will temporarily store the investigation-derived waste (IDW) purge water generated from the groundwater sampling event in a 55-gallon steel drum. A waste characterization sample will be collected from the IDW drum for analysis of total VOCs using EPA Method 8260. If the waste characterization sample is acceptable to the disposal subcontractor, the IDW drum will be picked up and transported to a facility for proper disposal. A non-hazardous waste manifest will be provided by the disposal subcontractor upon delivery to the disposal facility.
Interim Deliverable Upon completion of Subtask 2, an e-mail deliverable will be submitted and include copies of the field data sheets, equipment calibration forms, field notes, laboratory analytical report, laboratory chain-of-custody documentation, and non-hazardous waste manifest for the IDW transportation and disposal.
SUBTASK 3 – REPORTING
The Groundwater Monitoring Report will include a description of the sampling procedures, evaluation of the analytical results, comparison of current to historical data, tabulated summary of the current and historical analytical data, a site map showing the groundwater analytical results, water level elevation information in tables and figures, laboratory analytical data, conclusions, and recommendations.
HEALTH AND SAFETY
WSP will update the existing site-specific Health and Safety Plan for the fieldwork as needed. The work will be completed in accordance with WSP’s safety policies and procedures. At a minimum, WSP will wear safety glasses, high visibility safety vests, and steel-toed boots. A safety job briefing will be conducted prior to the start of work activities, and anytime the scope of work or site conditions change.
Mr. Patrick McGrane Proposal No. 2024US350454
Florida Department of Environmental Protection December 13, 2024
COST AND SCHEDULE
The estimated cost to complete the proposed scope of work is $9,761.50. WSP anticipates the monitoring event will take place in January 2025. The level of effort sheets and cost estimate form are included in Attachment A. The IDW disposal subcontractor quotes are included in Attachment B. The following table summarizes the proposed costs and deliverable schedule.
Task Proposed Cost Proposed Schedule/Deliverables
Subtask 1 – Project Management $ 954.53 April 25, 2025
Subtask 2 – Groundwater Sampling Activities
$ 5,795.44 February 21, 2025 (Field documentation, laboratory analytical report, and non-hazardous waste manifest via E-mail)
Subtask 3 – Reporting $ 3,011.53 March 28, 2025 (Groundwater Monitoring Report)
Total/Completion Date $9,761.50 May 23, 2025
WSP appreciates the opportunity to provide services to the DEP. Should you require additional information or clarifications, please contact us at (904) 363-3430.
Sincerely, WSP USA Inc.
Logan Chappell, PE Matthew C. Crews, PE Project Manager, Environmental Engineer Vice President, Environmental Engineer
LC/MCC/as
Attachments: Figure 2 – Site Layout Attachment A – Level of Effort Sheets and Cost Estimate Form Attachment B – Subcontractor Quotes
G:\Projects\DEP-WSCS\Projects\Tallahassee\Concord Custom Cleaners #201 (4867)\HW685\DC002G - Groundwater Sampling\Proposal\DC002G - Concord Custom Cleaners #201 GW Mon Proposal.docx
XXX
X
X X
X X X
O/H
O/H
O/H
O/H
O/H
O/H
O/H
O /H
O /H
O /H
O /H
O/H O/H O/H O/H O/H O/H O/H O/H O/H O/H O/H O/H O/H O/H O/H O/H O/H O/H
O/H O/H
O/H O/H
O/ O
CCCMW006
CCCMW002
CCCMW018
CCCMW001
CCCMW012
EXMW012
EXMW007
CCCMW007
CCCMW005
EXDW001
CCCDW001
VEW-4S VEW-4D
CCCMW003
VEW-3D
VEW-3S
VEW-6D
VEW-6SHEW-2HEW-1
VEW-5D
VEW-5S
O /H
O /H
O /H
O /H
O /H
O /H
O /H
O /H
O /H
O /H
O /H
O /H
O /H
O /H
VEW-7SVEW-7D
E HARRISON STREET
SO
U
TH
M
O N
R O
E
ST
SVE SYSTEM
2006 EXCAVATION AREA
(5ft-BGS)
2015 EXCAVATION AREA
(5ft-BGS)
FORMER CONCORD CUSTOM
CLEANERS No. 201
CANOPY
CANOPY
EXECUTIVE OFFICE SUPPLY
SOUTH MONROE
ENTERPRISE, LLC
HM WILLIAMS
PROPERTIES LTD
EXECUTIVE OFFICE SUPPLY, INC.
UNNAMED WELL
in
31404452
PHASE
4867-DC002C-A002
FIGURE
2022-12-05
BCL
MCC
MCC
JCB
SITE RESTORATION PLAN
CONCORD No 201
TALLAHASSEE, LEON COUNTY, FLORIDA
FL. DEPT. OF ENVIRONMENTAL PROTECTION
SITE LAYOUT
TITLE
PROJECT NO. REV.
PROJECT
CLIENT
CONSULTANT
PREPARED
DESIGNED
REVIEWED
APPROVED
YYYY-MM-DD
IF
T
H
IS
M
EA
SU
R
EM
EN
T D
O
ES
N O
T M
AT
C
H W
H
AT
IS
S
H O
W N
, T H
E
SH
EE
T
SI
ZE
H
AS
B
EE
N M
O D
IF
IE
D F
R O
M : A
N
SI
B
Pa th
\g ol de r.g ds
\c om pl ex da ta
\O ffi ce \J ac ks on vi lle \d ra fti ng \P ro je ct s\
FD
EP
\F D
EP
-D
C \3
2\
_4
7_ C on co rd
1\
_P R
O D
U C
TI
O
N \D
W G
Fi le
N am e:
7-
D C
2C
-A
2.
dw g
0 15 30
1. AERIAL IMAGE TAKEN FROM FDOT-APLUS, DATED JANUARY 18, 2018.
2. PROPERTY BOUNDARY TAKEN FROM FLORIDA DEPARTMENT OF
REVENUE.
3. BASEMAP SOURCE: BROWARD DAVIS & ASSOCIATES, INC., SURVEY
DATE:05.08.2019 & EARTH SYSTEMS, TITLED "SITE LAYOUT".
LEGEND
REFERENCE(S)
UPPER FLORIDAN AQUIFER WELL LOCATION
DEEPER FLORIDAN AQUIFER WELL LOCATION
UTILITY POLE
VAPOR EXTRACTION WELL LOCATION
HORIZONTAL VAPOR EXTRACTION WELL LOCATION
SVE SYSTEM CONVEYANCE PIPING TRENCH
PERCHED/SURFICIAL AQUIFER WELL LOCATION
O/H O/H EXISTING OVERHEAD UTILITY
NOTE(S)
1. ft-BGS = FEET BELOW GROUND SURFACE
2. SVE = SOIL VAPOR EXTRACTION
3. HEW = HORIZONTAL EXTRACTION WELL
4. VEW = VERTICAL EXTRACTION WELL
408 Ditmar Street Pensacola, FL 32503
To: Mr. Ralph Mongillo
WSP
9428 Baymeadows Road, Suite 400 Jacksonville, FL 32256
June 16, 2023
Re: Non-Hazardous Disposal of PFOS/PFAS Impacted Materials
Mr. Mongillo:
The price for the transportation and disposal (T&D) of non-hazardous soil, mud, and water is listed below:
For Non-Hazardous Chlorinated Solvent Impacted Materials:
Description Rate Unit T&D - Non-Haz Chlorinated Solvents Impacted Soil $ 125.00 Per Drum T&D - Non-Haz Chlorinated Solvents Impacted Mud/Water $ 125.00 Per Drum T&D - Non-Haz Chlorinated Solvents Impacted Water $ 95.00 Per Bucket
For Non-Hazardous PFAS/PFOS Impacted Materials:
Description Rate Unit Profile Fee (Charged once per site) $ 350.00 Per Site T&D - Non-Haz PFOS/PFAS Impacted Water (5-gallon bucket) $ 95.00 Per Bucket T&D - Non-Haz PFOS/PFAS Impacted Soil $ 195.00 Per Drum T&D - Non-Haz PFOS/PFAS Impacted Mud/Water $ 195.00 Per Drum
Please ensure that all drum lids are properly secured and that drums are on a level surface like the surrounding area (i.e., not on a pallet, etc.). A single False Mobilization fee will apply if our driver is not able to locate a drum on site or if we are unable to access the property due to a locked gate, etc. This quote is valid for 90 days.
Respectfully, Robert Donado Erwin Remediation, Inc.
Email: robert@erwinremediation.com p y
T&D - Non-Haz Chlorinated Solvents Impacted Mud/Water $ 125.00 Per Drum