About this file
This document contains a material submittals schedule template for a federal construction project. The template requires contractors to provide information on required submittals such as shop drawings, samples, manufacturer data and warranties. Columns include due dates for initial submissions from the contractor, dates submissions are received and sent to the civil engineering team, return suspense dates, submittal numbers, and dates for approval or disapproval notifications to the contractor. Resubmittal numbers and final approval dates are also included.
The related federal contract opportunity is a solicitation to repair Building 561 at an Air Force base. Offerors must fill out an attached site visit document with names, places of birth, and ensure prime contractors are limited to two personnel. The solicitation and supporting documents provide relevant details for the repair work required.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions and Answers (2).pdf | ||
| Attachment 2 RFP APPENDIX A Repair B561 22July2020.pdf | ||
| Questions and Answers.pdf | ||
| Attachment 2_RFP APPENDIX _A Repair B561.pdf | ||
| Bldg. 561_Drawings.pdf | ||
| Attachment 1_SOW Repair B561_XLWU 20-8163.pdf | ||
| Attachment 12_RFP APPENDIX A Repair B561_XLWU 20 8163.pdf | ||
| Attachment 3_ APPENDIX B Title_XLWU 20-8163.pdf | ||
| Solicitation - FA481920R0016 -01.pdf | ||
| Solicitation - FA481920R0016.pdf | ||
| Attachment 04_Wage Determination.pdf | ||
| Site Visit Document - Fill in.xlsx | XLSX spreadsheet | |
| Attachment 10_General Financial Information.pdf | ||
| Attachment 08_AF3065.pdf | ||
| Attachment 09_Sample RFI.PDF | ||
| Attachment 02_Appendix A_Scope of Work.pdf | ||
| Attachment 07_AF 3064.pdf | ||
| Attachment 03_Appendix B_Supporting Documents.pdf | ||
| Attachment 06_AF Form 3000.pdf | ||
| Attachment 01_SOW Repair (Restore) Bldg 561.pdf | ||
| Attachment 11_Other Contract Requirements.pdf |
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Schedule
| Project Number: | |||
| [ enter here ] | Project Title: | ||
| [ enter here ] | Solicitation / Contract Number: |
[ enter here ]
| Line Number | (To be completed by Project Engineer) | (To be completed by Contract Administrator) | ||||||||||||||||||||
| Number of Copies Required | Remarks | |||||||||||||||||||||
| Item or Description of Item, Contract Reference, Type of Submittal | Certificate of Compliance | Shop Drawings | Samples | Color Selection | Manufacturer's Recommendation | Manufacturer's Warranty | Catalog Data | Operating Instructions | Schedules, Listings, Reports, Plans | Technical Data | Test Reports | Field Reports | Required Submission Date | Date Received in Contracting | Date to Civil Engineering | Return Suspense Date | Submittal Numbers | Date Contractor | ||||
| Notified | Contractor Resubmittal | Final Approval | ||||||||||||||||||||
| Approved | Disapproved | |||||||||||||||||||||
| 1 | ||||||||||||||||||||||
| 2 | ||||||||||||||||||||||
| 3 | ||||||||||||||||||||||
| 4 | ||||||||||||||||||||||
| 5 | ||||||||||||||||||||||
| 6 | ||||||||||||||||||||||
| 7 | ||||||||||||||||||||||
| 8 | ||||||||||||||||||||||
| 9 | ||||||||||||||||||||||
| 10 | ||||||||||||||||||||||
| 11 | ||||||||||||||||||||||
| 12 | ||||||||||||||||||||||
| 13 | ||||||||||||||||||||||
| 14 | ||||||||||||||||||||||
| 15 | ||||||||||||||||||||||
| 16 | ||||||||||||||||||||||
| 17 | ||||||||||||||||||||||
| 18 | ||||||||||||||||||||||
| 19 | ||||||||||||||||||||||
| 20 | ||||||||||||||||||||||
| 21 | ||||||||||||||||||||||
| 22 | ||||||||||||||||||||||
| 23 | ||||||||||||||||||||||
| 24 | ||||||||||||||||||||||
| 25 |
&L&"Verdana,Bold"&12Schedule of Material Submittals&C&12Print on Legal size paper ( 8 x 14 ).
&R&P of &N Enter the due date from the Contractor (MM/DD/YY) Enter the date received from the Contractor. (MM/DD/YY) Enter the date submittal was given to CE for review. (MM/DD/YY) Enter the date the submittal is due back from CE
(MM/DD/YY)
Enter the Submittal Number Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
Enter Resubmittal Number Enter the submittal final approval date
(MM/DD/YY)
File details come from the government source that posted it. Updated .