This document is an appendix to a solicitation for the repair and restoration of Building 561 at Tyndall Air Force Base in Florida. The scope of work includes replacing the roof, walls, windows, doors, and lighting with hurricane-resistant materials certified for high-velocity hurricane zones. Interior repairs comprise replacing ceiling tiles, flooring, and installing new HVAC, electrical, and plumbing systems. The vehicle exhaust system requires testing and possible replacement to provide explosion-proof ventilation. The estimated period of performance is 330 calendar days from notice to proceed. The contracting agency is the Department of the Air Force Air Combat Command.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions and Answers (2).pdf | ||
| Attachment 2 RFP APPENDIX A Repair B561 22July2020.pdf | ||
| Bldg. 561_Drawings.pdf | ||
| Questions and Answers.pdf | ||
| Attachment 12_RFP APPENDIX A Repair B561_XLWU 20 8163.pdf | ||
| Attachment 1_SOW Repair B561_XLWU 20-8163.pdf | ||
| Attachment 3_ APPENDIX B Title_XLWU 20-8163.pdf | ||
| Attachment 08_AF3065.pdf | ||
| Attachment 09_Sample RFI.PDF | ||
| Attachment 02_Appendix A_Scope of Work.pdf | ||
| Attachment 07_AF 3064.pdf | ||
| Attachment 05_AF Form 66.xls | XLS spreadsheet | |
| Attachment 04_Wage Determination.pdf | ||
| Site Visit Document - Fill in.xlsx | XLSX spreadsheet | |
| Attachment 10_General Financial Information.pdf | ||
| Attachment 03_Appendix B_Supporting Documents.pdf | ||
| Attachment 06_AF Form 3000.pdf | ||
| Attachment 01_SOW Repair (Restore) Bldg 561.pdf | ||
| Attachment 11_Other Contract Requirements.pdf | ||
| Solicitation - FA481920R0016 -01.pdf | ||
| Solicitation - FA481920R0016.pdf |
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4819-20-R-0016
Appendix - A
20 July 2020
APPENDIX - A
SCOPE OF WORK
For
REQUEST FOR PROPOSAL
EAST REGION
Repair B561
TYNDALL AFB FLORIDA
Project Number: XLWU 20-8163
Contents
1.0 SCOPE
1.1 PURPOSE
1.2 FIELD CHANGES: ........................................................................................ ERROR! BOOKMARK NOT DEFINED.
2.0 SUMMARY OF WORK
2.1 TASK 1.0
2.2 TASK 2.0 ...................................................................................................... ERROR! BOOKMARK NOT DEFINED.
3.0 POINTS OF CONTACT (POCS)
3.1 POCS WILL BE COORDINATED THROUGH THE CO
3.2 CONTRACTING OFFICER AUTHORITY:
3.3 PROJECT MANAGER (PM):
3.4 USER CONTACT ........................................................................................... ERROR! BOOKMARK NOT DEFINED.
3.5 BUILDING CONTACT ................................................................................... ERROR! BOOKMARK NOT DEFINED.
1.0 SCOPE
1.1 Purpose
A. The purpose of the Tyndall Air Force Base (TAFB) project XLWU 20-8163, Repair (Restore) Bldg. 561 is to repair hurricane damage and to bring the building and its supporting facilities into full compliance with current building codes, including the DoD Building Code, and the portion of the Florida Building Code that contains the High Velocity Hurricane Zone (HVHZ) provisions.
B. The scope of work is based on HVHZ FBC, section 1602.2 criteria for Miami
Dade County Risk Category III and IV Buildings and Structures meeting 186 mph. Based upon our AF Structural SME recommendations and in alignment with the SecAF directed Severe Weather Readiness Assessment recommendations, the
Tyndall PMO will use the UFC 3-301-01 and the following Tyndall design wind speeds based upon Risk Categories III-V. RC III 165 mph and RC IV 170 mph
(Risk categories are defined by UFC 03-301-01, Table 2-2).
C. All exterior building envelope materials such as, but not limited to windows, glazing, roofing systems, concrete masonry unit or metal panel walls, and doors shall have a current Miami-Dado Notice of Acceptance (N0A) and installed to
HVHZ standards that match the specified wind requirement. Our construction industry partners shall continue to have the option of submitting test results or drawings sealed by a Professional Engineer stating conformance with HVHZ standards in lieu of materials pre-approved by Miami-Dade County.
D. While we should always use our Unified Facilities Criteria as the basis for all our facilities designs, we will also integrate the best practices from the Florida
Building Code (FBC) High-Velocity Hurricane Zone (HVHZ) into this design guidance to further improve facility resiliency at Tyndall. Other details from the memorandum may apply as well.
E. A Risk Category III is applicable to buildings 561 since it is designated as Vehicle
Repair Center and must meet the requirements for a 165 mph wind speed.
F. This task order delivery method is Design-Build (D-B). Work on supporting facilities includes external building fixtures, building utilities within the Points of
Demarcation (POD) for privatized utilities, and work within the Administration /
Office Building. The Contractor shall be responsible for providing all labor, equipment, tools, materials, and services necessary to complete the project within the allotted timeframe.
G. This project has an estimated period of performance from Notification to Proceed
(NTP) through completion and turnover of the facility back to the Government for mission operations of 330 calendar days.
H. Implementation of work will not start until an approved 100% Design has been issued. Ordering of long lead items may be coordinated with CO.
I. The latest IFC is to be used for color selection to assure base uniformity. Match existing colors as close as possible. Lighter colors are encouraged. Colors will be approved for use on a per building basis.
1.2 Field Changes:
A. Field Changes: The Contractor and the Government may agree to perform a no cost field change. Field changes are made when the change appears to be mutually beneficial to all parties and would not require changing the negotiated items. All field changes must be approved by the CO prior to execution. Only the CO may authorize field changes or deviations from the SOW.
B. Surveys for asbestos, mold and lead paint should be conducted prior demolition or rehabilitation.
1.3 Requirements:
1.3.1 Exterior Windows, Curtain Walls, Storefronts, Doors, and Louvers Architectural
Design Criteria:
A. Approved products with test reports for use in the FBC HVHZ and their respective Florida Product Approval (FPA)that has been tested to the FBC standards of TAS 201, 202, and 203.
B. Blast resistant as per UCF 4-010-01(12 December 2018) DoD Minimum
Antiterrorism Standards for Buildings. The design criteria based on a secure site, existing building, and inhabited occupancy; the “Design Basis Threat” and “Level of Protection” as established by the Tyndall AFB Antiterrorism
Plan or unless otherwise as directed by the Contracting Officer.
C. Anodized, blue tinted low e windows and storefronts are to be used for window replacement.
D. Provide Stainless Steel 316 Hardware for resiliency.
1.3.2 HVHZ Windows and Storefronts Performance Requirements:
A. Wind loads: Provide storefront system; include anchorage, capable of withstanding wind load as indicated on the Structural Drawings. The design pressures are based on the FBC for the geographical location of Miami-Dade
County.
B. Air Infiltration: Test the specimen in accordance with ASTM E 283. Air infiltration rate shall not exceed 0.06 cubic foot per minute per square foot
(0.3 liter per second per square meter) at a static air pressure differential of
6.24 psf (300 Pa).
C. Water Resistance: Test the specimen in accordance with ASTM E 331. There shall be no leakage at a minimum static air pressure differential of 12 psf (575
Pa) as defined in AAMA 501.
D. Uniform Load: Apply a static air design load of 65 psf (3,112 Pa) in the positive and negative direction in accordance with ASTM E 330. There shall be no deflection in excess of L/180 of the span of any framing member. At a structural test load equal to 1.5 times the specified design load, no glass breakage or permanent set in the framing members in excess of 0.4% of their clear spans shall occur.
E. Windborne-debris-impact-resistance Performance: Test in accordance with
ASTM E 1886 and information in ASTM E 1996 and/or AAMA 506.
a. Large-missile Impact: For aluminum-framed systems located within 30 feet (9.1 meters [m]) of grade.
b. Small-missile Impact: For aluminum-framed systems located more than 30 feet (9.1 m) above grade.
F. Exterior glazing shall be large impact-rated in compliance with FBC Chapter
14; maximum glass sizes as per ASTM E1300; low thermal emissivity-type, insulated and tinted. Dry glazing gaskets are in accordance with ASTM C864 or ASTM C509 per FBC Chapter 14.
1.3.3 Lighting
A. The interior lighting replacements will be LED lights with a CRI 90 and a minimum of 4000K
B. The exterior lighting replacement will be LED lights with a CRI 80 minimum with amber light for turtle preservation
1.3.4 Carpeting
A. The requirements for the AF GSA carpeting program must be met for quality and pricing.
1.3.5 Exterior Hollow Metal Doors:
A. Doors shall be 14 gauge, heavy-duty, level 2, physical performance level B, model 2 with an R-10 insulated core.
B. Provide Stainless Steel 316 Hardware for resiliency.
1.3.6 Rollup Doors:
A. Doors shall be minimum of 20 Gauge aluminum with 24 gauge frames
B. Provide explosion proof motors and controls where hazardous vapors may be present.
1.3.7 ADA and ABA standards:
A. The building is not being brought up to ADA or ABA standards since the building is being demo’d
1.3.8 Fire Protection standards:
A. The building is not being brought up to meet current standards.
B. Any new additions must be installed per the current codes for the vehicle exhaust system to provide a safe work environment.
C. Replacement of the fire panel, mass notification, and antenna will remain the same.
1.3.9 General:
A. The contractor is to field verify all dimensions and actual layout. The awarded contract will assume the contractor has verified the dimensions and layout and additional quantities will be the bidder’s responsibility without a modification to the contract.
1.3.10 ACAD and pdf drawings:
A. Non as built available drawings in ACAD and pdf will be provided
2.0 Summary of Work
2.1 Task 1.0
A. Roof
1. Replace fascia, trim around front and back gabled roof edge.
2. Seal L channel both sides under existing roofing edge
3. Install gutter and downspouts on sides under the roof edge
4. Repair exterior leak into Office
B. Walls
1. Replace wall sheet metal above doors and around the building that is patched or has tape over holes.
2. Seal and paint exterior of the building ~ 82’ by 60’ building and mechanical room
3. Repair exterior leak into Office
C. Windows – (If the window is causing the leak then perform the following)
1. Seal or replace window in office
D. Doors
1. Replace rollup doors up to ~ 13’ by 20’ (up to 8) 20 gauge with 24 gauge accessories
2. Replace rollup door motors and controls (up to 8). One door may be serviceable
3. Replace store front and frame to the building
4. Repair or replace lock on left side exterior door facing store front door. The door will not unlock from the exterior.
5. Optional: Repair / Replace side door frame and door if the office leak is being caused by the door framing and seals.
E. Ceiling
1. Replace ceiling tiles and track in office with white tiles and tracks (grids)
2. Replace ceiling tiles and track in breakroom with white tiles and tracks (grids)
F. Lights – (If interior LED lights cannot be provided with explosion proof fixtures, then work with the contracting office to authorize other lighting.
1. Replace or install LED exit lights at bay exits with CRI 80 with amber lens for turtle preservation.
2. Replace bay lights with LED lights 90 CRI lights with a minimum 4000 K. (The existing lights are Class 1, Division 1 and 2, Group C and D).
3. Replace or install LED exit lights over the two exit doors
G. Office
1. Demo and mold remediate office
2. Replace walls in office with drywall
3. Replace insulation exterior walls as needed
4. Replace flooring with VCT if present
H. Bathroom – (The bathroom drawing calls for a urinal. The shower has replaced the uninal.)
1. Demo and mold remediate bathroom.
2. Install ceiling tiles with white tiles and tracks or drywall ceiling
3. Prep and paint ceiling if drywall is installed on ceiling
4. Prep and paint walls
5. Install new composite light colored partitions
6. Install new shower
7. Install Toilet and hardware
8. Install vanity, sink, and hardware
9. Install bathroom exhaust fan
10. Install bathroom accessories
11. The bathroom is not being brought up to ADA or ABA standards since the building is being demo’d.
I. Vehicle Exhaust System. (The vapor exhaust floor system is intermittent operation.
This may require a complete replacement of mechanical and explosion proof electrical equipment to provide a safe environment while working on explosive vapors. The lines in the floor may be plugged. The truck exhaust system is nonfunctional. A new 6” or larger exhaust trunk system is needed for commercial tanker trucks.)
1. Test , repair or replace vehicle floor vapor exhaust fan system
2. Install trunk line system to support vehicles running inside facility.
3. Anticipate fuels fumes to be 15 feet or higher when tanker lids are open.
J. Electrical
1. Explosion proof connections are required for any new electrical components where hazardous vapors may be encountered..
K. HVAC
1. Install a Trane 15 SEER Heat Pump Split System (208/230/1PH) sized to service the office, breakroom and bathroom.
2. A wall-hang application for AHU on wall may be used.
3. Provide ductwork to office, breakroom and bathroom to condition those areas.
4. Install new refrigerant line set and charge with R-410 to manufacturer's specs.
5. Install communication wire from AHU to CU.
6. Cover exposed line set and communication wire with line hide.
7. Place condensing unit on new composite pad.
8. Install new 20A electrical circuit in conduit from existing panel to condensing unit.
9. Install Disconnect at condensing unit.
10. Electrical modifications and final hookup w/ start-up.
11. Drain line modifications and hookup.
12. Apply Coastal Protection Package (Corrosion Grenade and Cal-Shield).
13. Include Wireless Thermostat Controller.
14. 5-year manufacturer's parts warranty.
15. 1-year warranty on materials, labor, and workmanship
16. Balance and test system upon installation.
L. Fire Protection
1. If the new exhaust system requires detection per code, then install detection and tie into fire protection panel.
2. 3rd party. Certification and testing is required for new fire protection tie ins.
3. The system is not being brought up to new requirements since the building is scheduled for demo.
3.0 POINTS OF CONTACT (POCs)
3.1 POCs will be coordinated through the CO.
3.2 Contracting Officer Authority:
A. CO, the term used herein, does not include any representative not acting within the scope of his/her authority. Notwithstanding any of the provisions of this contract, the CO shall be the only individual authorized to in any way amend or modify the terms of this contract.
3.3 Project Manager (PM):
A. Don Dotson
END OF DOCUMENT