This is a federal construction specification section for Building Enclosure Commissioning (BECx) at Portsmouth Naval Shipyard in Kittery, Maine, under SIOP 1740579, as amended on March 16, 2026. The specification establishes comprehensive requirements for validating and verifying that building envelope materials, components, assemblies, and systems are designed and installed to meet the Owner's Project Requirements (OPR) during both design and construction phases.
The specification mandates an independent third-party pressure test agency to conduct air tightness testing of the building envelope in accordance with ASTM E779 and ASTM E1827 standards. Key requirements include periodic field inspections of the continuous air barrier during construction, envelope surface area calculations, and performance verification testing with both positive and negative pressure tests at differential pressures between 40-85 Pa. The contractor must seal all penetrations through the air barrier and prepare detailed building envelope inspection checklists. Diagnostic testing is required using infrared thermography, fog tests, feel tests, and find tests to locate leaks; the thermographer must hold an active Level II Certification based on ANSI/ASNT CP-105 or CP-189 with at least two years of building science experience. Test equipment must include calibrated blower door fans and trailer-mounted fans (calibrated within five years), digital pressure gages accurate to within 1.0 percent or 0.15 Pa, and thermal imaging cameras with thermal sensitivity of ±0.18°F or less per ISO 6781-2. Submittals requiring Government approval include Building Enclosure Commissioning Specialist qualifications, the Preliminary and Final BECx Plans, thermal imaging camera specifications, test procedures, air leakage test reports, diagnostic test reports, and thermographer qualifications. The contractor must provide all testing materials and labor, coordinate with the Government's Commissioning Provider and Lead Cx Specialist, submit the Preliminary BECx Plan within 14 calendar days of the Commissioning Kickoff Meeting, and notify the Contracting Officer at least 10 working days before conducting pressure tests and 21 calendar days before envelope components are concealed. All testing must occur in favorable weather conditions (avoiding rain, snow, and high winds exceeding 10 mph), with final reports submitted within 14 days of test completion.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
B60: PRODUCTION FACILITY REPAIRS - SIOP 1740579
PORTSMOUTH NAVAL SHIPYARD, KITTERY, MAINE
SECTION 01 91 19
BUILDING ENCLOSURE COMMISSIONING
05/2023
PART 1 GENERAL
1.1 SUMMARY
Use this Section in conjunction with UFGS 01 91 00.15 22 TOTAL BUILDING COMMISSIONING. Building Enclosure Commissioning (BECx) is an essential part of overall Building Commissioning. The final BECx report is to be included as a part of the Cx Firm's submittal of the Final Commissioning Report as defined in 01 91 00.15 22 TOTAL BUILDING COMMISSIONING. This Section covers Building Envelope Commissioning for all six surfaces (4 walls, roof, and floor, for a rectangular shaped zone) of a building.
Additional Quality Control and testing requirements for specific components of the building envelope are described in the Division 03 thru 08 UFGS Sections of the project specifications.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referenced within the text by the basic designation only.
AMERICAN SOCIETY FOR NONDESTRUCTIVE TESTING (ASNT)
ANSI/ASNT CP-105 (2020) ASNT Standard Topical Outlines for Qualification of Nondestructive Testing Personnel
ANSI/ASNT CP-189 (2020) ASNT Standard for Qualification and Certification of Nondestructive Testing Personnel
ASNT SNT-TC-1A (2020) Recommended Practice for Personnel Qualification and Certification in Nondestructive Testing
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE 90.1 - IP (2019) Energy Standard for Buildings Except Low-Rise Residential Buildings
ASHRAE 202 (2024) Commissioning Process for Buildings and Systems
ASTM INTERNATIONAL (ASTM)
ASTM C1193 (2016) Standard Guide for Use of Joint Sealants
ASTM E779 (2019) Standard Test Method for Determining Air Leakage Rate by Fan Pressurization
SECTION 01 91 19 Page 1 jriley Typewritten Text
AMENDMENT 009, 03-16-2026
ASTM E783 (2002; R 2018) Standard Test Method for Field Measurement of Air Leakage Through Installed Exterior Windows and Doors
ASTM E1105 (2015; R 2023) Standard Test Method for Field Determination of Water Penetration of Installed Exterior Windows, Skylights, Doors, and Curtain Walls, by Uniform or Cyclic Static Air Pressure Difference
ASTM E1186 (2022) Standard Practices for Air Leakage Site Detection in Building Envelopes and Air Barrier Systems
ASTM E1258 (1988; R 2018) Standard Test Method for Airflow Calibration of Fan Pressurization Devices
ASTM E1827 (2022) Standard Test Methods for Determining Airtightness of Buildings Using an Orifice Blower Door
ASTM E2813 (2018) Standard Practice for Building Enclosure Commissioning
ASTM E2947 (2021) Standard Guide for Building Enclosure Commissioning
INTERNATIONAL ORGANIZATION FOR STANDARDIZATION (ISO)
ISO 6781 (1983) Thermal Insulation - Qualitative Detection of Thermal Irregularities in Building Envelopes - Infrared Method
ISO 6781-2 (2010) Performance of Buildings - Detection of Heat, Air, and Moisture Irregularities in Buildings by Infrared Methods - Part2: Equipment Requirements
ISO 6781-3 (2015) Performance of Buildings - Detection of Heat, Air, and Moisture Irregularities in Buildings by Infrared Methods - Part 3: Qualifications of Equipment Operators, Data Analysts, and Report Writers
1.3 DEFINITIONS
The definitions included here are specific to this Section. Refer to UFGS 01 91 00.15 22 TOTAL BUILDING COMMISSIONING for definitions that apply to both Sections. The following terms as they apply to this section:
1.3.1 Air Barrier Envelope
The components of building assemblies(roofs, walls, and floors) that separate the inside air from the outside air. The combination of air barrier assemblies and air barrier components, connected by air barrier accessories are designed to provide a continuous barrier to the movement of air through an environmental separator. A single building may have
SECTION 01 91 19 Page 2 more than one air barrier envelope enclosing multiple environmentally separated zones. The air barrier surface includes the top, bottom, and sides of the envelope. The term "air barrier envelope" is also known as "air barrier system" or simply "air barrier".
1.3.2 Air Leakage Rate
A measurement of air infiltration or exfiltration through the building envelope over time. The air leakage rate is the rate of air flow across the air barrier per unit surface area of the envelope at a defined differential pressure.
1.3.3 Basis of Design (BoD)
A document developed by the design team which includes technical concepts, assumptions, calculations, decisions, and product selections to support the Owner's Project Requirements (OPR).
1.3.4 Bias Pressure
Also known as zero flow pressure, baseline pressure, offset pressure or background pressure. With the envelope not artificially pressurized, bias is the differential pressure that always exists between the envelope that has been prepared (sealed) for the pressure test and the outdoors. Bias pressure is made up of two components, fixed static offset (usually due to stack effect or the HVAC system) and fluctuating pressure (usually due to wind or a moving elevator). Because of pressure fluctuations many bias pressure readings are recorded and averaged for use in the calculations.
1.3.5 Blower Door
Commonly used term for an apparatus used to pressurize and depressurize the space within the building envelope and quantify air leakage through the envelope. The blower door typically includes a door fan and an air resistant fabric or a series of hard panels that extends to cover and seal the door opening between the fan shroud and door frame. The door fan is a calibrated fan capable of measuring air flow and is usually placed in the opening of an exterior door. With the air barrier otherwise sealed, air produced by the door fan pressurizes or de-pressurizes the envelope, depending on the fan's orientation.
1.3.6 Building Envelope (or enclosure)
The materials, components, systems, and assemblies intended to provide an environmental separator between the interior and exterior or between interior spaces with different environment requirements. "Enclosure" is used interchangeably with "envelope".
1.3.7 Building Envelope Commissioning (BECx)
Technical service provided on behalf of the Government to provide a quality-focused process for enhancing the performance of the building envelope by validating the design phase and verifying during the construction phase that the performance of the building enclosure materials components, assemblies, and systems are designed and installed to meet the Owner's Project Requirements (OPR).
SECTION 01 91 19 Page 3
1.3.8 Building Envelope Commissioning Specialist (CxB)
An entity that functions as part of the overall Commissioning Team and is responsible for validating the design phase and verifying during the construction phase that the performance of the building enclosure materials, components, assemblies, and systems are designed and installed to meet the Owner's Project Requirements (OPR).
1.3.9 Construction Phase
The period of a project following the award of construction Contract to project completion.
1.3.10 Design Phase
The period of the project delivery process when a design supporting the Owner's Project Requirements is developed and translated into Contract Documents.
1.3.11 Environmental Separator
The parts of a building that separate the controlled interior environment from the uncontrolled exterior environment, or that separate spaces within a building that have dissimilar environments. The term "environmental separator" is also known as the "control layer".
1.3.12 Functional Performance Test (FPT)
A systematic process to verify that controls and other elements of the building project are capable of and configured to operate or perform as required. FPT's are written and observed by the Technical Cx Specialist and performed by the Verification and Testing Provider. Tests not written by the Technical Cx Specialists, but required and defined throughout this specification manual are not described as FPTs in UFGS 01 91 00.15 22
TOTAL BUILDING COMMISSIONING.
1.3.13 Pressure Test
A generic term for a test in which the building envelope or zone is either pressurized or de-pressurized with respect to the outdoors or other building zones.
1.3.14 Negative Pressure Test (Depressurization Test)
A test wherein air inside the envelope is drawn to the outdoors. This places the envelope at a lower (negative) pressure with respect to the outdoors.
1.3.15 Positive Pressure Test (Pressurization Test)
A test wherein outdoor air is pushed into the envelope. This air movement places the envelope at a higher (positive) pressure with respect to the outdoors.
1.3.16 Verification & Testing (V&T) Provider
An entity who completes the activities needed to implement verification and testing of the building's materials, components, assemblies, and systems, including testing described throughout this specification manual
SECTION 01 91 19 Page 4 and functional performance testing (FPT) activities to verify that elements of the building project meet contract document requirements.
1.4 COMMUNICATION WITH THE GOVERNMENT COMMISSIONING PROVIDER
For communication responsibilities, see Section 01 91 00.15 22 TOTAL
BUILDING COMMISSIONING.
1.5 COMMUNICATION WITH GOVERNMENT'S Cx and ACCEPTANCE TESTING
REPRESENTATIVES
The QC Manager must communicate directly with the Government Acceptance Testing Representatives, the government's Lead Cx Specialist (CxC), and Contracting Officer's Representative regarding Government acceptance testing activities. Inform the government's Lead Cx Specialist (CxC) andthe Contracting Officer's Representative when systems are ready for testing to be witnessed by the government's Cx Specialists and Government Acceptance Testing Representatives, and allow access to the construction site and system(s) to be tested.
1.6 ENCLOSURE COMPONENTS TO BE COMMISSIONED
1.6.1 Verification of the Installation of the Continuous Air Barrier
a. Conduct periodic field inspection of the continuous air barrier materials and assemblies, including all penetrations through the six sides of the air barrier, during construction while the continuous air barrier is still accessible for inspection and repair (after installation of all penetrations and wall cladding anchoring devices and before the installation of interior finishes) to verify and document compliance with the requirements. Conduct inspections at initial installation of each building envelope component and at in-progress construction intervals as stated in Part 3 section titled
BUILDING ENVELOPE INSPECTION AND TESTING.
b. Conduct Performance Verification Testing of the entire building envelope (systems, components, and assemblies) for air tightness in accordance with Part 3 section titled BUILDING ENVELOPE AIR TIGHTNESS
REQUIREMENT.
1.6.2 Inspection of Fenestration and Doors
a. Fenestration and Doors must be labeled and inspected to verify compliance with Building Envelope energy requirements, including applicable U-factors, Solar Heat Gain Coefficient (SHGC), Visible Transmittance (VT), and air leakage rates.
b. Inspect doors and windows for coordination with the insulating plane of the wall, continuity with the air/weather barrier, and flashing.
c. Inspect operation of doors, closers, and operating mechanisms for conformance with manufacturer's instructions.
d. Inspect seals and gaskets for fenestration and doors (including loading dock, sectional, and coiling doors) for proper installation and to verify that seals are in good condition and comply with ASHRAE 90.1 - IP maximum allowed leakage rates.
SECTION 01 91 19 Page 5
1.6.3 Inspection of Opaque Roof, Walls, and Floors
Opaque roof, above-grade and below-grade walls, and floors, must be subject to the following inspections during construction:
a. Use of ASHRAE 90.1 - IP -compliant materials and assemblies.
b. Insulation material meets design specifications and is continuous.
1.6.4 Fenestration Inspections
Conduct inspections of the following fenestration-related items during construction:
a. Skylights size and location in relation to the designed primary sidelighted area and secondary sidelighted area below.
b. Roof monitor size and location in relation to the designed primary sidelighted area and secondary sidelighted area below.
c. Dynamic glazing compliance with SHGC and U-factors, and testing of the operation for conformance with the manufacturer's instructions.
d. Permanent fenestration projections installation and performance in accordance with ASHRAE 90.1 - IP requirements and the Contract documents.
1.6.5 Loading Dock Weatherseal Inspections
Inspect loading dock weatherseals for proper installation and to verify the seals are in good condition.
1.6.6 Additional Building Enclosure Tests
Conduct the following building enclosure tests on mock-ups or early in the installation of the related building components:
Annex Envelop
1.7 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00.00 22 SUBMITTAL PROCEDURES (PWD ME):
SD-01 Preconstruction Submittals
Building Enclosure Commissioning Specialist Qualifications ; G
Building Enclosure Testing Work Plan ; G
PRELIMINARY BECx PLAN; G
SD-03 Product Data
Thermal Imaging Camera ; G
Test Equipment ; G
SECTION 01 91 19 Page 6
FINAL BECx PLAN ; G
SD-05 Design Data
Envelope Surface Area Calculations ; G
SD-06 Test Reports
Completed Building Envelope Inspection Checklists ; G
Pressure Test Procedures ; G
Air Leakage Test Report ; G
Diagnostic Test Report ; G
FINAL BECx REPORT
SD-07 Certificates
Pressure Test Agency
Thermographer Qualifications
Certificate of Readiness
SD-10 Operation and Maintenance Data
Training ; G
1.8 BUILDING ENCLOSURE TESTING WORK PLAN
For each building enclosure test to be performed, submit the following not later than 120 calendar days before start of testing work, steps to be taken by the lead test technician to accomplish the required testing.
a. Memorandum of test procedure.
(1) Proposed dates for conducting the tests.
(2) Submit detailed test procedures prior to the test. Provide a plan view showing proposed locations (personnel doors or other similar openings) to install equipment (such as blower doors or flexible ducts for trailer-mounted fans, if used).
(3) Submit detailed requirements for access to or pressurization of adjacent, occupied buildings or zones. Provide a plan view showing proposed locations (personnel doors or other similar openings) to install equipment (such as blower doors or flexible ducts for trailer-mounted fans, if used).
b. Test equipment to be used.
c. Scaffolding, scissor lifts, power, electrical extension cords, duct tape, plastic sheeting and other Contractor's support equipment required to perform all tests.
d. Other Contractor's support personnel who will be on site for testing.
SECTION 01 91 19 Page 7
1.9 ACCESSIBILITY REQUIREMENTS
Air barrier components, insulation, fenestration, and doors for commissioned systems must be made accessible for inspections. Contractor must make necessary modifications at Contractor's own expense if systems and enclosures are not accessible for inspections and testing. Assist commissioning team in testing and inspections by removing equipment covers, opening access panels, and other required activities that assist with visual oversight. Furnish ladders, flashlights, meters, gauges, or other inspection equipment as necessary.
1.10 SCHEDULING
Notify the Government's Lead Cx Specialist and the Contracting Officer a minimum 14 calendar days in advance of site visits and inspections by the roof system manufacturer technical representative for coordination with CxB and the Government Acceptance Testing Representative.
1.11 COORDINATION
Refer to Section 01 91 00.15 22 TOTAL BUILDING COMMISSIONING for requirements pertaining to coordination during the commissioning process.
Coordinate with the Commissioning Provider in accordance with Section 01 91 00.15 22 and in accordance with the Commissioning Plan to schedule inspections as required to support the commissioning process. Furnish additional information requested by the Commissioning Provider.
Coordinate scheduling of air barrier inspections and air barrier pressure testing with the commissioning team. Upload plans, reports, notes, and other documentation to the Commissioning Provider's web-based commissioning software, or as specified in the commissioning plan, as it is completed.
1.12 QUALITY CONTROL
1.12.1 Modification of References
Perform all pressure and diagnostic tests according to the referenced publications listed in paragraph REFERENCES and as modified by this section. Consider the advisory or recommended provisions, of the referred references, as mandatory.
1.12.2 Qualifications
1.12.2.1 Pressure Test Agency
Submit, no later than 15 calendar days after Contract award, information certifying that the pressure test agency is not affiliated with any other company participating in work on this Contract. The work of the test agency is limited to pressure testing the building envelope, performing a thermography test and fog test, and investigating, through various methods, the location of air leaks through the air barrier. See Part 3 paragraph PRESSURE TEST AGENCY for additional requirements. For thermographer qualifications, see paragraph THERMOGRAPHER QUALIFICATIONS.
Use the sample TEST AGENCY QUALIFICATIONS SHEET form (Appendix C), to submit the following information.
SECTION 01 91 19 Page 8
a. Verification of 2 years of experience as an agency in pressure testing commercial or industrial buildings.
b. List of at least ten commercial/industrial facilities with building envelopes that the agency has tested within the past 2 years. Include building name, address, and name of prime construction Contractor and Contractor's point-of-contact information.
c. Confirmation of 2 years of commercial and or industrial building pressure test experience for the lead pressure test technician and the thermographer in using the specified ASTM E779 or ASTM E1827 testing standard. References from five Contracting Officers for facilities where the lead test technician has supervised commercial and or industrial building pressure tests in the last 2 years.
d. Verification that the lead pressure test technician has been employed by a building pressure testing agency in the capacity of a lead pressure test technician for not less than 1 year.
1.12.2.2 Thermographer Qualifications
To perform an infrared diagnostic evaluation, use a lead thermographer who has at least an active Level II Certification that is based on the requirements in ANSI/ASNT CP-105 or ANSI/ASNT CP-189 and is in accordance with ASNT SNT-TC-1A . The course of study is to be specifically focused on infrared thermography for building science. The thermographer must have at least two years of building science thermography experience in IR testing commercial or industrial buildings. The thermographer must also have experience in building envelopes and building science in order to make effective recommendations to the Contractor should the envelope require additional sealing. Thermographic equipment operators, data analysts and report writers must comply with the requirements of ISO 6781-3 .
Submit the thermographer's certificate for approval. Submit a list of at least ten commercial/industrial buildings on which the thermographer has performed IR thermography in the past two years. The thermographer is to have a current active certification. Submit certification at least 60 days prior to thermography testing.
1.12.3 Test Reports
No later than 14 days after completion of the pressure test, submit electronic copies of an organized report. The report is to contain a table of contents, an executive summary, an introduction, a results section and a discussion of the results. Submit the air leakage test report as described in paragraph AIR LEAKAGE TEST REPORT. Submit a diagnostic test report as described in paragraph LOCATING LEAKS BY DIAGNOSTIC TESTING. The diagnostic test report is to include the Thermographic Investigation Report and the Fog Test Report.
Submit field data and completed report forms found in the appendices. Use the sample forms, Test Agency Qualification Sheet, Air Leakage Test Form and Air Leakage Test Results Form to summarize the tests for the appropriate building envelope. Submit both electronically populated and field hand filled-in forms.
Report Data. Include in the report the following information for all tests:
a. Date of issue
SECTION 01 91 19 Page 9
b. Project title and number
c. Name, address, and telephone number of testing agency
d. Dates and locations of samples and tests or inspections
e. Names of individuals making the inspection or test
f. Designation of the work and test method
g. Identification of product and specification section
h. Complete inspection or test data
i. Test results and an interpretation of test results
j. Comments or professional opinion on whether inspected or tested work complies with Contract document requirements
k. Recommendations on retesting
1.13 CLIMATE CONDITIONS SUITABLE FOR A PRESSURE TEST
As the test date approaches, monitor the weather forecast for the test site. Avoid testing on days forecast to experience high winds, rain, or snow. Monitor weather forecasts prior to shipping pressure test equipment to the site. Based on current and forecast weather conditions, the Contracting Officer's representative is to grant final approval for testing to occur.
1.13.1 Rain
For safety reasons, avoid testing during rain or if rain is anticipated during testing. If pneumatic hoses are installed and exposed to rain inspect the hose to ensure rainwater has not migrated into the hose ends.
Orient all exposed hose ends to keep them out of water puddles. Success in temporarily sealing outdoor ventilation components such as louvers and exhaust fans may also be compromised by rain. Don't seal roof-mounted ventilation components during times of potential lightning.
1.13.2 Wind
Because wind can skew pressure test results, test only on days and at times when winds are anticipated to be the calmest. Avoid pressure testing during gusty or high wind conditions. Avoid installing test fans on the windward side of the building if wind gusts during the test are anticipated to be greater than 10 miles per hour.
1.14 CERTIFICATE OF READINESS
Prior to scheduling the Commissioning Tests as required by this Section, submit Certificate of Readiness documentation in accordance with Section 01 91 00.15 22 TOTAL BUILDING COMMISSIONING for each enclosure-related system, certifying that inspections have been completed, open issues have been resolved, and the system is ready for the Commissioning Tests.
Documentation would include Building Envelope Inspection Checklists as required within this Section, as well as any inspections or test reports required within each enclosure-related technical specification section.
SECTION 01 91 19 Page 10
Additional Quality Control and testing requirements for specific components of the building enclosure are described in the Division 03 thru 08 UFGS Sections of the project specifications.
Submit the Certificate of Readiness for each system 20 working days prior to Commissioning Tests of that system. Do not schedule Commissioning Tests for a system until the Certificate of Readiness is approved by the Government. Do not schedule air tightness testing of the building envelope system until Certificates of Readiness and supporting documentation for enclosure-related systems have been submitted, reviewed and approved by the Government.
PART 2 PRODUCTS
2.1 TEST EQUIPMENT
Provide all equipment required to perform testing for the systems and components to be commissioned. Provide all testing equipment of sufficient quality and accuracy to test and measure system performance with the tolerances specified. Provide a sufficient quantity of two-way radios for each subcontractor.
Submit a signed and dated list of instruments to be used for testing, their application, manufacture, model, serial number, range of operation accuracy, and date of most recent calibration. Calibration data applicable to fan systems must be in accordance with ASTM E1258. Also list special equipment and proprietary tools specific to a piece of equipment required for testing.
2.2 PRESSURE TEST EQUIPMENT
Depending on site conditions and size of the envelope, the test may be conducted using blower door equipment and trailer-mounted fans. The testing agency is to supply sufficient quantity of blower equipment that will produce a minimum of 75 Pa differential pressure between the envelope and outdoors using the test methods described herein. Supplying additional blower test equipment to provide additional airflow capacity or to act as a backup is highly recommended.
2.2.1 Blower Door Fans and Trailer Mounted Fans
Each air flow measuring system including blower door fans and trailer mounted fans are to be calibrated within the last 5 years. Calibrated blower door fans and trailer mounted fans must measure accurately to within plus or minus 5 percent of the flow reading. Blower door equipment and trailer mounted fans are to be specifically designed to pressurize building envelopes. Each set of blower door equipment is to include fan(s), digital gage(s), door frame, door fabric or hard panels.
2.2.2 Digital Gages as Test Instruments
Use only digital gages as measuring instruments in the pressure test;
analog gages are not acceptable. The gauges must be accurate to within
1.0 percent of the pressure reading or 0.15 Pa, whichever is greater.
Each gage is to have been calibrated within two years of the test. The calibration is to be checked against a National Institute of Standards and Technology (NIST, formerly National Bureau of Standards) traceable standard.
SECTION 01 91 19 Page 11
2.3 THERMAL IMAGING CAMERA REQUIREMENTS
The thermal imaging camera used in the thermography test must have a thermal sensitivity (Noise Equivalent Temperature Difference.) of +/- 0.18 degrees F at 86 degrees F or less. Ensure the camera's operating spectral range falls between 2 and 15 micrometers. Ensure the camera's IR image viewing screen resolution measures at least 320x240 pixels. Ensure the camera has a means of recording thermal images seen on the camera viewing screen. The camera is to display output as individual still frame images that also can be downloaded and inserted into an electronic Thermographic Investigation Report. All thermographic equipment must comply with the requirements of ISO 6781-2 . Submit camera make and model, and catalog information that defines the camera thermal sensitivity for approval.
PART 3 EXECUTION
Coordinate with the COMMISSIONING TEAM and perform all Contractor and Equipment supplier activities and responsiblities defined in Section 01 91
00.15 22 TOTAL BUILDING COMMISSIONING and building envelope related specifications to accomplish building envelope commissioning in accordance with ASHRAE 202 and ASTM E2947 in addition to the requirements herein.
Follow ASTM E2947 except where it references ASTM E2813. All verification and testing work shall be documented and provided to the government's Cx Firm in sufficient detail to demonstrate compliance of the building envelope with the design intent as defined in the Contract documents.
3.1 MEETINGS
Attend all meetings in accordance with Section 01 91 00.15 22 TOTAL
BUILDING COMMISSIONING.
Provide timely updates on construction schedule changes so Commissioning Provider has scheduling information needed to execute commissioning process efficiently. Notify Contracting Officer of anticipated construction delays to commissioning activities not yet performed or not yet scheduled.
3.2 PRELIMINARY BECx PLAN
Submit the Preliminary BECx Plan no later than 14 calendar days after the Commissioning Kickoff Meeting. Submit the Preliminary BECx Plan for inclusion in the Interim Construction Phase Commissioning Plan as identified in Section 01 91 00.15 22 TOTAL BUILDING COMMISSIONING.
Coordinate the development of this plan with the commissioning plans required in Section 01 91 00.15 22 TOTAL BUILDING COMMISSIONING. Outline the commissioning process, commissioning team members and responsibilities, lines of communication, inspections, and documentation requirements for BECx. Identify the Commissioning Standards chosen for the project. Establish appropriate and quantifiable enclosure related performance metrics, test standards, and test methodology in accordance with referenced standards for inclusion in the Contract documents.
Provide a list of team members for systems to be commissioned with contact information, a list of tests as required to complete the scope of all commissioning and a copy of the project schedule as required by Section 01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULE for inclusion in the Preliminary BECx Plan.
The Preliminary BECx Plan must include, at a minimum, the following:
SECTION 01 91 19 Page 12
1. Required performance of commissioned equipment, systems, and assemblies, and results of all building envelope verification and testing.
2. Summary of compliance of the building and its components, assemblies, controls, and systems with requirements.
3. Issues and resolution logs, including itemization of deficiencies found during verification, testing, and commissioning that have not been corrected at the time of report preparation.
4. Deferred tests that cannot be performed at the time of report preparation.
5. Documentation of the training of operation personnel and building occupants on commissioned systems, and a plan for the completion of any deferred trainings not completed at the time of report preparation.
6. A plan for the completion of commissioning and training, including climatic and other conditions required for performance of the deferred tests.
3.3 FINAL BECx PLAN
Submit the Final BECx Plan directly to the Government's Lead Cx Specialist (CxC) for inclusion in the Cx Firm's submittal, the Construction Phase Interim Commissioning Plan, as identified in Section 01 91 00.15 22 TOTAL BUILDING COMMISSIONING. Outline the commissioning process, commissioning team members and responsibilities, lines of communication, and documentation requirements for BECx. Identify the Commissioning Standards chosen for the project. Identify enclosure related inspections, performance metrics, test standards, and test methodologies in accordance with referenced standards for inclusion in the commissioning process.
Provide a list of team members for systems to be commissioned with contact information, a list of tests as required by this Section as well as 07 27 10 BUILDING AIR BARRIER SYSTEM, and a copy of the project schedule as required by Section 01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULE for inclusion in the Final BECx Plan. Final BECx plan must be included in the Cx Firm's submittal of the Construction Phase Interim Commissioning Plan, and must be updated and included with the Cx Firm's submittal of the Construction Phase Final Commissioning Plan as identified in Section
01 91 00.15 22 TOTAL BUILDING COMMISSIONING.
3.4 CONSTRUCTION SUBMITTAL REVIEWS
Coordinate construction submittal document reviews for commissioned systems and assemblies with the CxC and CxB. The commissioning submittal review does not replace the designer of record (DoR) or Government submittal review, in accordance with Section 01 33 00.00 22 SUBMITTAL
PROCEDURES (PWD ME).
The CxB is responsible for identifying construction submittals to be provided by the Contractor for the commissioned systems and coordinating with the CxC. The CxB is responsible for evaluating construction submittals related to BECx for compliance with the Contract documents.
SECTION 01 91 19 Page 13
3.5 TEMPLATE BUILDING ENVELOPE INSPECTION CHECKLISTS
Use the Template Building Envelope Inspection Checklists prepared by the CxC to verify the building materials and construction maintain the required air tightness of the building envelope system.
The Building Envelope Compliance Documentation Form from ASHRAE 90.1 - IP User's Manual may be used as an example. The submitted checklist is not required to match the format of the form; however, the checklist must contain the same level of detail as shown on the mandatory provisions of the sample form.
3.6 BUILDING ENVELOPE INSPECTION AND TESTING
Demonstrate that all system components have been installed, that each building enclosure component operates, and that the systems operate and perform in accordance with Contract documents. Provide all materials, services, equipment, and labor required to perform the Building Envelope Inspections.
Coordinate site observation activities with the government's CxC and participate in periodic building envelope inspections with the technical Building Envelope commissioning specialists (CxB) using the approved Building Envelope Inspection Checklists to observe and document construction of the building envelope in-progress. Coordinate inspection requirements with Section 07 27 10 BUILDING AIR BARRIER SYSTEM and other Division 7 Specifications. Complete the checklists and indicate inspection and validation of each Building Envelope Inspection Checklist item by initials at the time they are inspected. Notify the Lead Commissioning Specialist (CxC) and Contracting Officer at least 21 calendar days before checklist items are concealed to ensure inspection items can be observed before construction progresses. Submit the initialed and Completed Building Envelope Inspection Checklists no later than 14 calendar days after completion of inspection of all checklist items. Notify the CxC at least 21 calendar days prior to the building envelope pressure tests and diagnostic tests specified in this Section.
3.6.1 Additional Building Enclosure Testing
Coordinate with specification Section 01 91 19 Building Envelope Commissioning.
a. Conduct air leakage testing of fenestration in accordance with
ASTM E783.
b. Conduct water penetration tests of fenestration in accordance with
ASTM E1105.
c. Conduct adhesion and cohesion tests of sealants in accordance with
ASTM C1193.
3.7 BUILDING ENCLOSURE AIR BARRIER PRESSURE TESTING
3.7.1 Pressure Test Agency
Employ an independent agency to conduct the pressure test on the building envelope in accordance with ASTM E779 and this specification section. The test agency is to be an independent third-party subcontractor, not an affiliated or subsidiary of the prime Contractor, subcontractors, or A/E
SECTION 01 91 19 Page 14 firm. The agency is to be regularly engaged in pressure testing of commercial/industrial building envelopes. If using blower door or trailer-mounted fans, the lead test technician must have at least two years of experience in using such equipment in building envelope pressurization tests. Formal training using pressure test equipment is highly recommended. Technicians using the building's air handling system for pressure testing are to have tested at least five commercial/industrial buildings within the past two years with each building having over 50,000 square feet of floor area. Submit the name, address, and floor areas of each of these five buildings for approval.
3.7.1.1 Field Work
The lead pressure test technician and thermographer are to be present at the project site while testing is performed and is to be responsible for conducting, supervising, and managing of their respective test work.
Management includes health and safety of test agency employees.
3.7.1.2 Reporting Work
The lead pressure test technician is to prepare, sign, and date the test agenda, equipment list, and submit a certified Air Leakage Test Report.
The thermographer is to prepare, sign, and date the test agenda, equipment list, and submit a certified Thermographic Investigation Report. The Contractor is to prepare a final report that identifies improvements that were made to the envelope to reduce air leaks , mitigate thermal bridging, eliminate moisture migration, repair insulation voids discovered during diagnostic tests. The Verification & Testing (V&T) providers must certify completion of required verification and testing and include a plan for the completion of any deferred testing, including climatic and other conditions required for performance of the deferred tests; include the results of the testing and verification activities in the completed verification and testing documentation. Jointly submit all reports.
3.7.2 Envelope Surface Area Calculation
The architectural air barrier boundary includes the floor, walls, and ceiling. After construction of the air barrier envelope is complete, field measure the envelope to ensure the physical measurements match the design drawings and the air barrier envelope surface area calculations are generated. If the calculation result is not within 10 percent of the defined air barrier boundary calculation result as indicated, submit the envelope surface area calculation and results for review. If the air barrier was defined during design but the air barrier envelope surface area was not calculated, calculate it during construction and submit the envelope surface area calculations and result for review.
3.7.3 Preparing The Building Envelope For The Pressure Test
3.7.3.1 Testing During Construction
The pressure test cannot be conducted until all components of the air barrier system have been installed. After all sealing as described herein has been completed, inspect the envelope to ensure it has been adequately prepared. During the pressure test, stop all ongoing construction within and neighboring the envelope which may impact the test or the air barrier integrity. The pressure test may be conducted before finishes that are not part of the air barrier envelope have been installed. For example, if suspended ceiling tile, interior gypsum board or cladding systems are not
SECTION 01 91 19 Page 15 part of the air barrier the test can be conducted before they are installed. Recommend testing prior to installing the finished ceilings and interior wall finishes within the envelope and immediately surrounding
it. The absence of finishes allows for inspection and diagnostic testing of the roof/wall interface and for implementation of repairs to the air barrier, if necessary to comply with the maximum allowed leakage.
3.7.3.2 Sealing the Air Barrier Envelope
The Contractor is to seal all penetrations through the air barrier.
Unavoidable penetrations due to electrical boxes or conduit, plumbing, and other assemblies that are not air-tight are to be made so by sealing the assembly and the interface between the assembly and the air barrier or by extending the air barrier over the assembly. Support the air barrier to withstand the maximum positive and negative air pressure to be placed on the building without displacement or damage, and transfer the load to the structure. Durably construct the air barrier to last the anticipated service life of the assembly and to withstand the maximum positive and negative pressures placed on it during pressure testing. Do not install lighting fixtures that are equipped with ventilation holes through the air barrier.
3.7.3.3 Sealing Plumbing
Prime all plumbing traps located within the envelope full of water.
3.7.3.4 Close and Lock Doors
Close and lock all doors and windows in the envelope perimeter. For doors not equipped with latching hardware, temporarily secure them in the closed position. Secure the doors in such a way that they remain fully closed even when the maximum anticipated differential air pressure produced during the test acts on them. Provide signage stating not to open the door and the time and duration of the test.
3.7.3.5 Hold Excluded Building Areas at the Outdoor Pressure Level
Keep building areas immediately surrounding but excluded from the test envelope at the outdoor pressure level during the pressure test. Maintain these areas at the outdoor pressure level by propping exterior doors open, opening windows and de-energizing all air moving devices in or serving these areas.
3.7.3.6 Maintain an Even Pressure within the Envelope
Ensure the pressure differences within the envelope are minimized by opening all internal air pathways including propping open all interior doors. Distribute test fans throughout the envelope as necessary to ensure the internal pressures are uniform (within 10 percent of the average differential pressure). Ideally, do not install suspended ceilings until after all pressure tests have been completed. If, however the envelope includes finished suspended ceiling spaces, temporarily remove approximately 5 percent of all ceiling tiles or a minimum of 1 tile from each isolated suspended ceiling space, whichever comprises the greatest surface area. Temporarily remove additional ceiling tiles during testing to allow for inspection and diagnostic testing of the ceiling/wall interface. An alternative to removing ceiling tiles is to measure the differential pressure between each isolated suspended ceiling space and the outdoors when the area below the suspended ceiling is maintained at a
SECTION 01 91 19 Page 16 differential pressure of 75 Pa with respect to the outdoors. If the suspended ceiling differential pressure measurement is within ten percent of the 75 Pa pressure below the suspended ceiling no ceiling tiles need to be removed.
3.7.3.7 Maintain Access to Mechanical and Electrical Rooms
Maintain access to mechanical rooms and electrical rooms associated with the envelope to allow for de-energizing ventilation equipment and resetting circuit breakers tripped by blower door equipment, if used.
3.7.3.8 Minimize Potential for Blowing Dust and Debris
Because high velocity air will be blown into and out of the envelope during the test, debris, including dust and litter, may become airborne.
Airborne debris may become trapped or entangled in test equipment, thereby skewing test results. Ensure areas within and surrounding the envelope are free of dust, litter and construction materials that are easily airborne. If pressurizing existing, occupied areas, provide adequate notice to building occupants of blowing dust and debris, and general disruption of normal activities during the test.
3.7.3.9 De-energize Air Moving Devices
De-energize all air moving devices serving the envelope to keep air within the envelope as still as reasonably achievable. De-energize all fans that deliver air to, exhaust air from, or recirculate air within the envelope.
Also, de-energize all fans serving areas adjacent to but excluded from the envelope.
3.7.3.10 Installing Blower Door Equipment in a Door Opening
Where blower door fans are used, before installing blower door equipment, select a door opening that does not restrict air flow into and out of the envelope and has at least 5 feet clear distance in front of and behind the door opening. Disconnect the door actuator and secure the door open to prevent it from being drawn into the fan-by-fan pressure. Avoid installing blower door equipment on the windward side of the building.
3.7.4 Building Envelope Air Tightness Requirement
For each building envelope, perform the Architectural Only test and if noted below, the Architectural Plus HVAC System test. The purpose of the pressure (air leakage) test is to determine final compliance with the airtightness requirement by demonstrating the performance of the continuous air barrier. An effective air barrier envelope minimizes infiltration and exfiltration through unintended air paths (leaks). The tests may be performed in any desired order.
3.7.4.1 Architectural Only Test
The test envelope is the architectural air barrier boundary as defined on the Contract drawings. This boundary includes connecting walls, roof and floor which comprise a complete, whole, and continuous three-dimensional envelope. Perform both a positive pressure test and a negative pressure test on this envelope, unless otherwise directed.
SECTION 01 91 19 Page 17
3.7.4.1.1 Test Goal
Input data from the test into the Air Leakage Rate by Fan Pressurization spreadsheet as described in paragraph CALCULATION PROGRAM via the Air Leakage Test Form. Compare output from the spreadsheet against the maximum allowable leakage defined in Section 07 27 10 BUILDING AIR BARRIER SYSTEM. The envelope passes the test if the leakage rate, as calculated using the spreadsheet, is equal to or lower than the Architectural Only leakage rate goal.
3.7.4.1.2 Preparing the Envelope for the Pressure Test - Seal All Openings through the Air Barrier
Temporarily close all perimeter windows, roof hatches and doors in the envelope perimeter except for those doors that are to remain open to accommodate blower door or trailer mounted fan test equipment installation. Seal, or isolate all other intentional openings, pathways, and fenestrations through the architectural envelope prior to pressure testing. Follow the Recommended Test Envelope Conditions identified in ASTM E1827, Table 1, for the Closed Envelope condition. These openings may include boiler flues, fuel-burning water heater flues, fuel-burning kitchen equipment, clothes dryer vents, fireplaces, wall or ceiling grilles, diffusers, and other similar openings. Before sealing flues, close their associated fuel valves and verify the associated pilot lights are extinguished. Prime all plumbing traps located within the envelope full of water. In lieu of applying tape or plastic, typical temporary sealing materials include tape and sheet plastic or a self-adhesive grille wrap. Use and apply tape and plastic in a manner that does not deface or remove paint or mar the finish of permanent surfaces. Be especially aware of residue that remains from tape applied to stainless steel surfaces such as kitchen hoods or rollup doors. For painted surfaces, use tape types that do not remove finish paint when the tape is removed. If paint is removed from the finished surface, repaint to match existing surfaces.
Secure dampers closed either manually or by using the building's HVAC system controls. Use the table below for further guidance in building preparation.
Building Component Envelope Condition
Air handling units, duct fans As found (open) or temporarily sealed as necessary
Dampers - intake, exhaust Physically closed or closed using control power or temporarily sealed
Diffusers, registers, grilles within the envelope
Temporarily sealed
Doors, personnel type, at the envelope perimeter
Secured closed
Doors, personnel type, within the envelope Secured (propped) open
Doors, roll-up type, at the envelope perimeter
Closed (no additional sealing)
Exhaust hoods Closed* and temporarily sealed
SECTION 01 91 19 Page 18
Building Component Envelope Condition
Pilot light and associated fuel valve Extinguished and closed, respectively
Vented combustion appliance Temporarily sealed *
Vented combustion appliance exhaust flue Off
Windows Secured closed
* If the building component has an associated manual or automatic damper, consider securing the damper closed in lieu of temporarily sealing.
3.7.4.2 Architectural Plus HVAC System Test
This test envelope includes the architectural air barrier boundary as defined on the Contract drawings plus all HVAC supply, return and exhaust systems that penetrate and terminate within said architectural air barrier boundary and that extends outward from said boundary. All associated ductwork, intake and exhaust dampers, and air moving devices, including air handling units and fans, are included in this test envelope even if they are physically located outside of the architectural air barrier boundary. The boundary extends to and includes the low leakage intake and exhaust dampers. Perform both a positive pressure test and a negative pressure test on this envelope, unless otherwise indicated.
3.7.4.2.1 Test Goal
Data from the test is to be input into the Air Leakage Rate by Fan Pressurization spreadsheet as described in paragraph CALCULATION PROGRAM via the Air Leakage Test Form. If both positive and negative pressure tests were performed, both data sets are to be input in the spreadsheet.
Compare output from the spreadsheet against the leakage rate goal. The envelope passes the test if the leakage rate, as calculated using the spreadsheet, is equal to or lower than the Architectural Plus HVAC System leakage rate goal.
3.7.4.2.2 Preparing the Building for the Pressure Test
In preparation for this test, de-energize all air moving devices within this envelope by putting their controls in the Unoccupied mode. This allows the building's HVAC controls to close all associated motorized intake, exhaust, and relief dampers. Make no other changes to the HVAC systems. Temporarily sealing diffusers, grilles, registers, kitchen hoods, exhaust hoods, fans, air handling units and all other HVAC system elements with tape or plastic sheeting or any other means is not allowed.
If the envelope includes a fireplace hearth do not seal it with tape and plastic. Use the table below for further guidance in building preparation.
Building Component Envelope Condition
Air handling units, duct fans As found (open)
SECTION 01 91 19 Page 19
Building Component Envelope Condition
Clothes dryer Off
Clothes dryer vents As found (no preparation)
Dampers - intake, exhaust As found (no preparation)
Diffusers, registers, grilles within the envelope
As found (open)
Doors, personnel type, at the envelope perimeter
Secured closed
Doors, personnel type, within the envelope Secured (propped) open
Doors, roll-up type, at the envelope perimeter
Closed (no preparation)
Exhaust hoods Closed
Fireplace hearth As found (open)
Kitchen hoods As found (open)
Pilot light and associated fuel valve Extinguished and closed, respectively
Vented combustion appliance Off
Vented combustion appliance exhaust flue As found (open)
Windows Secured closed
] 3.7.5 Conducting The Pressure Test
Notify the Contracting Officer at least ten(10) working days before conducting the pressure tests to provide the Government the opportunity to witness the tests and to monitor…
This is the start of the file's text. The full file is on GovTribe.