This document is a Task Assignment Change Order (TACO #8) issued by the State of Florida Department of Environmental Protection (FDEP) to WSP USA Inc. The change order amends Task Assignment DC001A under Contract HW685, with Patrick McGrane serving as the FDEP Project Manager and Matt Crews as the contractor's project manager. The contract involves work at multiple sites and is effective as of October 9, 2025.

The change order authorizes a cost increase of $1,155.92 to reconcile work approved under Work Change Directive #14, increasing the total Task Assignment value from $30,754.42 to $31,910.34. The work involves site activities and monitoring well abandonment, with deliverables due by December 27, 2027. The invoice schedule specifies two payment milestones: $30,754.42 upon submittal and FDEP approval of Work Change Directives #1-#13, and $1,155.92 upon submittal and FDEP approval of field documentation from WCD #14. The additional costs cover the abandonment of monitoring well MW-10 at the Alan Dry Cleaners site, including labor by senior project scientists, vehicle usage, and miscellaneous expendables. The completion date remains December 27, 2026, with no changes to other terms and conditions of the original Task Assignment.

View the file

Other files

File Type Posted
CN-370000-HW685-BF01A.pdf PDF
CN-370000-HW685-BF01CCO1.pdf PDF
CN-370000-HW685-BF02A.pdf PDF
CN-370000-HW685-BF05A.pdf PDF
CN-370000-HW685-BF05ACO1.pdf PDF
CN-370000-HW685-BF1BCO1.pdf PDF
CN-370000-HW685-BIL02C.pdf PDF
CN-370000-HW685-BIL1ACO4.pdf PDF
CN-370000-HW685-BIL2CCO1.pdf PDF
CN-370000-HW685-BIL3ACO1.pdf PDF
CN-370000-HW685-CSS01.pdf PDF
CN-370000-HW685-CSS2ACO2.pdf PDF
CN-370000-HW685-DC001C.pdf PDF
CN-370000-HW685-DC001E.pdf PDF
CN-370000-HW685-DC002B.pdf PDF
CN-370000-HW685-DC002C.pdf PDF
CN-370000-HW685-DC002E.pdf PDF
CN-370000-HW685-DC003C.pdf PDF
CN-370000-HW685-DC004A.pdf PDF
CN-370000-HW685-DC007A.pdf PDF
CN-370000-HW685-DC007B.pdf PDF
CN-370000-HW685-DC008B.pdf PDF
CN-370000-HW685-DC008D.pdf PDF
CN-370000-HW685-DC009A.pdf PDF
CN-370000-HW685-DC009D.pdf PDF
CN-370000-HW685-DC009E.pdf PDF
CN-370000-HW685-DC010C.pdf PDF
CN-370000-HW685-DC012A.pdf PDF
CN-370000-HW685-DC012D.pdf PDF
CN-370000-HW685-DC014B.pdf PDF
CN-370000-HW685-DC016D.pdf PDF
CN-370000-HW685-DC017A.pdf PDF
CN-370000-HW685-DC017B.pdf PDF
CN-370000-HW685-DC018B.pdf PDF
CN-370000-HW685-DC019A.pdf PDF
CN-370000-HW685-DC019C.pdf PDF
CN-370000-HW685-DC01ACO1.pdf PDF
CN-370000-HW685-DC01ECO1.pdf PDF
CN-370000-HW685-DC021A.pdf PDF
CN-370000-HW685-DC021B.pdf PDF
CN-370000-HW685-DC021C.pdf PDF
CN-370000-HW685-DC021E.pdf PDF
CN-370000-HW685-DC022C.pdf PDF
CN-370000-HW685-DC023A.pdf PDF
CN-370000-HW685-DC023D.pdf PDF
CN-370000-HW685-DC024C.pdf PDF
CN-370000-HW685-DC025A.pdf PDF
CN-370000-HW685-DC027D.pdf PDF
CN-370000-HW685-DC028A.pdf PDF
CN-370000-HW685-DC028D.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department) Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Name:

4. There are no changes to the TA compensation.

The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. There are no changes to the TA Expiration Date.

The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. There are no changes to the Attachments.

Attachment ___ is replaced with Attachment -____.

7. No Additional Changes.

Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

DC001A 8 HW685

Patrick McGrane 850-245-8899 WSP USA Inc.

Matt Crews 904-363-3430 Multiple

Multiple

$ 31,910.34 $ 30,754.42

$ 31,910.34 $ 30,754.42

12/27/2026 12/27/2026 0

1 1 8

WSP USA Inc.

Matthew Crews

Environmental Engineer

10/9/2025

Crews, Matt (USMC700671) Digitally signed by Crews, Matt (USMC700671) Date: 2025.10.09 09:12:04 -04'00'

Mubeen Darji

Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.

Date: 2025.10.08 15:45:18 -04'00'

N/A

This Change Order authorizes a cost increase to reconcile work authorized in Work Change Directive #14.

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number:

Task Assignment #:

Change Order #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

BWC TAFORM 01/18

Memorandum

TO: Negotiation File

FROM: Patrick McGrane, Project Manager

SUBJECT: Negotiation Summary Task Assignment Change Order DC001A-8 (HW685)

DATE: October 6, 2025

This Change Order authorizes a total cost increase to reconcile the work approved in WCD #1.

The previous cost total was $30,754.42. Total costs were increased by $1,155.92 resulting in a new final cost total of $31,910.34. WSP may invoice according to the included schedule.

Specific negotiated subtasks are as follows:

Subtask 2:

Work Change Directive #1 was authorized to abandon MW-10 following notification from the property owner on its condition. All costs associated with abandonment are reconciled in this change order.

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Multiple Sites SUBTASK 3: Well Abandonment

DATE: 10/3/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Project Sci/Eng (S. Sider) 2

Senior Project Sci/Eng (E. Marks) 3

TOTAL LABOR 5

VEHICLE TYPE RATE UNIT USEAGE

Truck (WCD #14) $120.00 Per Day 1 $120.00

TOTAL VEHICLE $120.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Miscellaneous Expendables (WCD #14 $40.00 Per Day 1 $40.00

TOTAL EQUIPMENT $40.00

WCD #14 - Verification of property ownership and Well ID and construction information. Email deliverable with description of work and photo log (2 hours).

WCD #14 - Round trip travel (1 hr), Field event preperation (1 hr), Abandon MW-10 manhole with concrete flush to existing grade (1 hr).

FINAL --7/24/96

Contract No. HW685

Additional work is not authorized without prior FDEP approval as indicated by an approved Work Change Directive Form or Task Assignment Change Order Form. It is the Contractor's responsibility to ensure that additional costs associated with this WCD are resolved by a Task Assignment Change Order (TACO) prior to the completion date of the original Task Assignment or subsequent TACOs completed prior to the execution date of this WCD. Failure to do so will result in a loss of reimbursement for work associated with this WCD.

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Work Change DirectiveForm

ATTACHMENT 6

Site Name: Site ID #:

Contract #:

Task Assignment #:

Contractor:

Work Change Directive #:

� Reason for Work Change Directive :

� Description of Work Change Directive :

� Attachments(if applicable, listdocuments supportingchange):

� Costs (if negotiated unitcosts, provide information below):

Maximum Estimated Increase in Task Amount:

AuthorizedContractorSignature:

AuthorizedFDEPSignature:

FDEP SupervisorApproval:

(if applicable)

Multiple Multiple

HW685 WSP USA Inc.

DC001A 14

WSP is requesting approval of this work change directive to cover costs associated with abandonment of the MW-10 manhole at the Alan Dry Cleaners site (ERIC_4399). WSP was contacted by the offsite property owner (Miami Gardens Holding LLC) that MW-10 has no manhole lid, and is a public safety hazard for pedestrians.

WSP will mobilize to the site from the Miami Gardens office, and abandon MW-10 manhole by filling with concrete flush to the existing grade. MW-10 was previously destroyed and replacement monitoring well MW-10R was installed in 2003. WSP will prepare photographic log and field documentation e-mail deliverable.

None

Subtask 1 - Project Management - 1.2 hrs (SS) Subtask 2 - Senior Sci/Eng (SS) - 2 hours Subtask 2 - Senior Sci/Eng (EM) - 5 hours Subtask 2 - 1 Day Truck ($120) and 1 Day Expendables ($40)

$ 1,750.00

Crews, Matt

(USMC700671)

Digitally signed by Crews, Matt

(USMC700671)

Date: 2025.02.06 10:25:20 -05'00'

Patrick McGrane Digitally signed by Patrick McGrane Date: 2025.02.07 08:58:33 -05'00'

Mubeen Darji, P.E.

Digitally signed by Mubeen Darji, P.E.

Date: 2025.02.10 12:00:10 -05'00'

File details come from the government source that posted it. Updated .