This is a Task Assignment Change Order (TACO No. 1) issued by the State of Florida Department of Environmental Protection under Contract HW685. The parties involved are the State of Florida Department of Environmental Protection (Department) and WSP USA Inc. (Contractor). The Department's Project Manager is Patrick McGrane (850-245-8899), and the Contractor's Project Manager is Matt Crews (904-363-3430). The project is located at 1413 South Monroe Street, Tallahassee, Leon County, and concerns Concord Custom Cleaners #201, with Project Number ERIC_4867.

This Change Order authorizes a no-cost 63-day time extension to the Task Assignment completion date, extending it from July 26, 2024 to September 27, 2024. The work involves WSP labor hours for project management and preparation of a Site Restoration Agreement between the FDEP and the property owner. The task assignment authorizes review and submission of an updated Permission to Enter Property. The total contract value remains unchanged at $6,010.74 as a fixed unit rate. Subtask 2's deliverable due date was extended from its original date to September 13, 2024 to account for unforeseen changes. The contractor may invoice upon submittal and FDEP approval of project management deliverables and meeting reviews related to the Site Restoration Agreement. The change order was effective as of July 25, 2024.

View the file

Other files

File Type Posted
CN-370000-HW685-BF01C.pdf PDF
CN-370000-HW685-BF05ACO2.pdf PDF
CN-370000-HW685-BF05ACO3.pdf PDF
CN-370000-HW685-BF06A.pdf PDF
CN-370000-HW685-BF1ACO1.pdf PDF
CN-370000-HW685-BF6ACO1.pdf PDF
CN-370000-HW685-BIL01C.pdf PDF
CN-370000-HW685-BIL01CO1.pdf PDF
CN-370000-HW685-BIL03A.pdf PDF
CN-370000-HW685-BIL2ACO1.pdf PDF
CN-370000-HW685-BIL2CCO1.pdf.crdownload CRDOWNLOAD file
CN-370000-HW685-DC001A.pdf PDF
CN-370000-HW685-DC002G.pdf PDF
CN-370000-HW685-DC003A.pdf PDF
CN-370000-HW685-DC005C.pdf PDF
CN-370000-HW685-DC006B.pdf PDF
CN-370000-HW685-DC006C.pdf PDF
CN-370000-HW685-DC007C.pdf PDF
CN-370000-HW685-DC008A.pdf PDF
CN-370000-HW685-DC009B.pdf PDF
CN-370000-HW685-DC010A.pdf PDF
CN-370000-HW685-DC011A.pdf PDF
CN-370000-HW685-DC012C.pdf PDF
CN-370000-HW685-DC013A.pdf PDF
CN-370000-HW685-DC013C.pdf PDF
CN-370000-HW685-DC015B.pdf PDF
CN-370000-HW685-DC015C.pdf PDF
CN-370000-HW685-DC016A.pdf PDF
CN-370000-HW685-DC018A.pdf PDF
CN-370000-HW685-DC019B.pdf PDF
CN-370000-HW685-DC01ACO6.pdf PDF
CN-370000-HW685-DC01ACO8.pdf PDF
CN-370000-HW685-DC01ACO9.pdf PDF
CN-370000-HW685-DC020B.pdf PDF
CN-370000-HW685-DC022A.pdf PDF
CN-370000-HW685-DC022B.pdf PDF
CN-370000-HW685-DC022D.pdf PDF
CN-370000-HW685-DC023B.pdf PDF
CN-370000-HW685-DC023C.pdf PDF
CN-370000-HW685-DC027B.pdf PDF
CN-370000-HW685-DC027C.pdf PDF
CN-370000-HW685-DC029B.pdf PDF
CN-370000-HW685-DC029C.pdf PDF
CN-370000-HW685-DC02CCO1.pdf PDF
CN-370000-HW685-DC031A.pdf PDF
CN-370000-HW685-DC031C.pdf PDF
CN-370000-HW685-DC032B.pdf PDF
CN-370000-HW685-DC035A.pdf PDF
CN-370000-HW685-DC037A.pdf PDF
CN-370000-HW685-DC038C.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department) Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Name:

4. There are no changes to the TA compensation.

The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. There are no changes to the TA Expiration Date.

The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. There are no changes to the Attachments.

Attachment ___ is replaced with Attachment -____.

7. No Additional Changes.

Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

DC002F 1 HW685

Patrick McGrane 850-245-8899 WSP USA Inc.

Matt Crews 904-363-3430

ERIC_4867

Concord Custom Cleaners #201

$ 6,010.74 $ 6,010.74

$ 6,010.74 $ 6,010.74

07/26/2024 09/27/2024 63

1 1 1

WSP USA Inc.

Matthew Crews

Environmental Engineer

7/25/2024

Crews, Matt (USMC700671) Digitally signed by Crews, Matt (USMC700671) Date: 2024.07.25 13:32:24 -04'00'

Mubeen Darji

Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.

Date: 2024.07.25 11:43:31 -04'00'

N/A

This Change Order authorizes a no cost 63-day time extension to allow for an extended timeline of the project.

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton

Secretary

Memorandum

TO: Negotiation File Concord Custom Cleaners #201 Tallahassee, Leon County

ERIC_4867

FROM: Patrick McGrane, Project Manager

SUBJECT: Negotiation Summary Task Assignment Change Order DC002F-1 (HW685)

DATE: July 24, 2024

This Change Order authorizes a no cost 63-day time extension to the Task Assignment completion date.

Subtask 2�s deliverable due date was also extended to account for any unforeseen changes. This change is necessary to allow WSP to continue assisting in the preparation of a Site Restoration Agreement between the FDEP and the property owner of Concord #201.

The final project cost remains $6,010.74. The Task Assignment completion date was extended from

7/26/2024 to 9/27/2024. Subtask 2�s deliverable due date was moved to 9/13/2024.

WSP may invoice according to the included schedule.

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor�st �s Project Manager: ontractor�s t�s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

HW685

DC002F Completion July 26, 2024

This Task Assignment authorizes WSP labor hours for the review and submission of an updated Permission to Enter Property for the Concord Custom Cleaners #201. All work is to be performed in accordance with the March 29, 2024 Scope of Work and Cost Estimate.

Patrick McGrane 850-245-8899 Contractor WSP USA Inc. Contractor

Contractor Matt Crews Contractor 904-363-3430

ERIC_4867

1413 South Monroe Street, Tallahassee, Leon County

Concord Custom Cleaners #201

Contractor Contractor

$ 6,010.74

$ 6,010.74

Scope of Work

WSP USA Inc.

Contractor

Matthew Crews

Environmental Engineer

4/9/2024

Crews, Matt (USMC700671) Digitally signed by Crews, Matt (USMC700671) Date: 2024.04.09 14:30:23 -04'00'

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2024.04.04 14:54:23 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Subtask 1 & 2 - Project Management; Site Access Agreement Preparation 05/10/2024

Subtask 1 & 2 - Project Management; Submittal and FDEP approval of Revised Site Access Agreement and Review from Meetings if needed $ 6,010.74

$ 6,010.74

HW685

DC002F