This is a Task Assignment (TA) document between the State of Florida Department of Environmental Protection (FDEP) and WSP USA Inc., executed under Contract Number HW685 for groundwater monitoring activities at the Swift Cleaners Inc. Beaches Site (Third Street Cleaners) located at 1029 N. 3rd Street, Jacksonville Beach, Duval County, Florida. The project site is identified as ERIC_4583. The Department Project Manager is Opeyemi Kehinde (850-245-8887), and the Contractor's Project Manager is Matt Crews (904-363-3430). The TA was signed on June 20-22, 2023, with an effective completion date of November 30, 2023.
The contract authorizes WSP to conduct groundwater monitoring activities in accordance with the June 15, 2023 Scope of Work, Cost Estimate, and Bid Documentation, structured in three subtasks: Project Management, Annual Groundwater Monitoring with Investigation-Derived Waste (IDW) treatment, and Reporting. The work includes groundwater sampling from 13 monitoring wells, field documentation, laboratory analytical testing for chlorinated volatile organic compounds (VOCs) using EPA Method 8260B, and preparation of an Annual Groundwater Monitoring Report. The total Task Assignment value is $9,909.37 on a fixed unit rate basis, with costs distributed as follows: Subtask 1 (Project Management) $908.57, Subtask 2 (Annual Groundwater Monitoring) $5,326.52, and Subtask 3 (Reporting) $3,674.28. Deliverables include field documentation and laboratory analytical reports due August 18, 2023, and the final Annual Groundwater Monitoring Report due October 27, 2023. IDW disposal costs were procured through competitive bidding, with Erwin Remediation selected as the lowest responsive bidder at $545.00 for transportation and disposal services.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW685
DC029B Completion November 30, 2023
This Task Assignment authorizes WSP to conduct groundwater monitoring activities in accordance with the June 15, 2023 Scope of Work, Cost Estimate, and Bid Documentation.
Opeyemi Kehinde 850-245-8887 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
WSP USA Inc.
WSP USA Inc.
Matt Crews 904-363-3430
ERIC_4583
1029 N. 3rd Street, Jacksonville Beach, Duval County
Swift Cleaners Inc. Beaches Site (Third Street Cleaners)
✔ $ 9,909.37
$ 9,909.37
Scope of Work
Donald Miller
Senior Vice President
Donald Miller Digitally signed by Donald Miller Date: 2023.06.22 10:10:15 -04'00' Kelly Crain Digitally signed by Kelly Crain
Date: 2023.06.20 11:35:34 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Subtask 2 – Field documentation and laboratory analytical report 08/18/2023
Subtasks 1 & 3: Reporting; Project Management 10/27/2023
Subtask 2: Submittal and FDEP approval of E-mail summary with Field documentation and laboratory analytical report $ 5,326.52
Subtask 1 & 3: Submittal and FDEP approval of E-mail summary with the Annual Groundwater Monitoring Report $ 4,582.85
$ 9,909.37
HW685
DC029B
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
To:
From:
Date:
HW685 Contract Negotiation File Swift Cleaners Inc., Duval County, ERIC_ 4583
Kehinde Opeyemi, Project Manager June 19, 2023
Subject: Negotiation Summary
HW685_DC029B
This Task Assignment authorizes WSP to conduct groundwater monitoring activities in accordance with the June 15, 2023, Scope of Work, Cost Estimate, and Bid Documentation.
Subtask 1: Project Management An automatic calculation based upon total direct labor hours determines the labor hours within this subtask.
Subtask 2: Annual Groundwater Monitoring WSP will collect groundwater samples from monitoring wells (MW002, MW005, MW004, MW007, MW006, and MW013) for chlorinated volatile organic compounds (VOCs) by EPA Method 8260B. Prior to groundwater sampling, depth-to-water measurements will be collected using an electronic water level indicator at monitoring wells MW001, MW003, MW008, MW009, MW010, MW011, and MW012 along with the monitoring wells that will be sampled to determine groundwater flow direction. Investigation-derived waste (IDW) will be temporarily stored in a 55-gallon drum. WSP requested bids for IDW drum treatment and disposal from Erwin, US Ecology, and HEPACO. Erwin was selected as the lowest responsive and responsible bidder.
Subtask 3: Reporting WSP will submit the Annual Groundwater Monitoring Report deliverable to FDEP.
WSP and the FDEP confirmed on June 19, 2023, that an Access Agreement with the current real property owner of the Aloha Cleaners (ERIC_4583) site has been executed.
The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost for this Task Assignment is $9,909.37 with 56 labor hours.
The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost for this Task Assignment is $23,386.91 with 115 labor hours. Printed on recycled paper.
FDEP COST ESTIMATEContractor: WSP USA Inc.
Date: 6/15/2023
Task #: DC029B SubTask 1 Project Management SubTask 6
Site: Swift Beaches SubTask 2 Annual GW Monitoring SubTask 7
Activity/Phase: Assessment SubTask 3 Reporting SubTask 8
Project Manager: Opeyemi Kehinde SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$53.28 Project Manager (RFM) 6 5.7 $0.00 Program Leader - X-14 0 0 0 0 0 0 0 0 0 0
$68.75 Practice Leader - X-13 (JB) 2 0 2 0 0 0 0 0 0 0 $0.00 Senior Consultant - X-12 0 0 0 0 0 0 0 0 0 0
$53.28 Senior Sci/Eng - X-11 (RFM) 23 7 16 0 0 0 0 0 0 0 $42.00 Senior Project Sci/Eng - P-10 (BL) 4 0 4 0 0 0 0 0 0 0
$0.00 Project Sci/Eng - P-10 0 0 0.0 0 0 0 0 0 0 0 $39.00 Staff Sci/Eng - P-8 (LS) 10 10.0 0 0 0 0 0 0 0 0 $38.10 Project Sci/Eng - P-9 (SN) 9 9.0 0 0 0 0 0 0 0 0 $33.90 Staff Sci/Eng - P-8 (AS) 2 0 2 0 0 0 0 0 0 0
$0.00 Sci/Eng/Admin - P-7 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0
Total Hours 56 5.7 26.0 24.0 0 0 0 0 0 0 0
Direct Labor $2,634.75 $303.11 $1,105.86 $1,225.78 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 172.50% $4,544.94 $522.86 $1,907.61 $2,114.47 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $7,179.69 $825.97 $3,013.47 $3,340.25 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF GOLDER Page 1
FDEP COST ESTIMATEContractor: WSP USA Inc.
Date: 6/15/2023
Task #: DC029B SubTask 1 Project Management SubTask 6
Site: Swift Beaches SubTask 2 Annual GW Monitoring SubTask 7
Activity/Phase: Assessment SubTask 3 Reporting SubTask 8
Project Manager: Opeyemi Kehinde SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Travel
Vehicle Rental $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $545.00 $545.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utility Location $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $545.00 $545.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $54.50 $54.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $599.50 $599.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $548.00 $548.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $220.00 $220.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $768.00 $768.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $384.20 $384.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $524.20 $524.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $9,191.39 $825.97 $5,025.17 $3,340.25 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $717.98 $82.60 $301.35 $334.03 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $9,909.37 $908.57 $5,326.52 $3,674.28 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF GOLDER Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Swift Beaches SUBTASK 2: Annual GW Monitoring
DATE: 6/15/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Senior Sci/Eng (R Mongillo) 7
Staff Sci/Eng L. Swindle) 10
Project Sci/Eng (N. Scott) 9
TOTAL LABOR 26
VEHICLE TYPE RATE UNIT USEAGE
Truck (GW sampling $120.00 Per Day 1 $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
Per Diem Staff Sci/Eng (L. Swindel) $36.00 Per Day 0 $0.00 Per Diem Project Sci/Eng ( S. Neal) $36.00 Per Day 0 $0.00
Hotel Staff Sci/Eng (L. Swindel) $89.00 Per Day 0 $0.00 Hotel Project Sci/Eng ( S. Neal) $89.00 Per Day 0 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Erwin Profile Fee $350.00 LS 1 $350.00 Erwin T&D - Non-Haz PFOS/PFAS Water $195.00 per drum 1 $195.00
TOTAL $545.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
Chlorinated VOCs - EPA Method 8260B
Total VOHs EPA Method 8260B $73.00 6 $438.00
Total VOCs EPA Method 8260B $110.00 1 $110.00
Sample Shipping Small $110.00 2 $220.00
TOTAL LAB $768.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Miscellaneous Expendables $40.00 Per Day 1 $40.00 Shallow Groundwater Sampling Kit $290.00 Per Day 1 $290.00 Tubing, Poly HDPE $0.30 Per Foot 254 $76.20 Tubing, Silicon 3/16 x 3/8 $3.00 Per Foot 6 $18.00 Drum, 55-gallon $100.00 Per Drum 1 $100.00
TOTAL EQUIPMENT $524.20
Round trip travel (1 hour). Field event preparation (1 hr). Instrument calibration, groundwater measure water levels from 13 wells, measure field parameters, collect samples from 6 wells: two shallow zone monitoring wells (MW002 and MW005); two intermediate zone monitoring wells (MW004 and MW007); and two deep zone monitoring wells (MW006 and MW013) analyze for chlorinated VOCs by EPA Method 8260B and manage IDW (8 hours). .
Verification of property ownership with property access forms (onsite and offsite) prior to groundwater sampling (1 hour). Characterize IDW and prepare waste profile for transportation and disposal of IDW (3 hours). Prepare and submit email summary with field documentation of groundwater and certified laboratory report (3 hours).
Round trip travel (1 hour). Instrument calibration, groundwater measure water levels from 13 wells, measure field parameters, collect samples from 6 wells: two shallow zone monitoring wells (MW002 and MW005); two intermediate zone monitoring wells (MW004 and MW007); and two deep zone monitoring wells (MW006 and MW013) analyze for chlorinated VOCs by EPA Method 8260B and manage IDW (8 hours). .
Contact property owner offsite property owners, and DEP scheduling field work, collect and depth to water measurements from 13 wells and groundwater samples from 6 existing monitoring wells for chlorinated VOC analysis and IDW characterization and waste profile for transportation and disposal.
FINAL --7/24/96
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Swift Beaches SUBTASK 3: Reporting
DATE: 6/15/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Practice Leader (J. Brown) 2
Senior Sci/Eng (R Mongillo) 16
Senior Project Sci/Eng (B. Lucero) 4
Staff Sci/Eng (A. Strayer) 2
TOTAL LABOR 24
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
Reporting: Updating tables document production, binding and shipping. Create pdf for OCULUS.
Develop conclusions and recommendations and prepare final Annual Monitoring Report.
Preparation of draft Annual Monitoring Report
CADD Update Figures (three groundwater flow and three CVOC detections)
FINAL --7/24/96
US Ecology* HEPACO T&D Non Haz Soil - VOCs per drum 0 $110.00 $0.00 T&D Non Haz Mud/water - VOCs per drum 0 $110.00 $0.00 False Mobilization (no drum found) 0 $85.00 $0.00 PFAS Profile Fee (1 per site) 1 $350.00 $350.00 T&D Non Haz Soil - PFAS/PFOS per drum 0 $195.00 $0.00 T&D Non Haz Mud/water -PFAS/PFOS per drum 1 $195.00 $195.00 Disposal Non Haz Soil - VOCs per drum 0 $150.00 $0.00 Disposal Non Haz Mud/water - VOCs per drum 0 $150.00 $0.00 PFAS Profile Fee (1 per site) 1 $95.00 $95.00 Disposal Non Haz Soil - PFAS/PFOS 0 $650.00 $0.00 Disposal Non Haz Mud/water -PFAS/PFOS 1 $650.00 $650.00 Approval Fee (per site) 1 $750.00 $750.00 Non Haz Solification Waste Profile fee 0 $50.00 $0.00 Non Haz Solids Disposal (per drum) 0 $185.00 $0.00 Non Haz Sludge Disposal 0 $185.00 $0.00 PFAS Waste 55 gal drum emelle AL 1 $810.00 $810.00 Truck with lift gate and driver 4 $145.00 $580.00 non haz liquids disposal (per drum) 0 $141.75 $0.00 55 gallon reconditioned drum 0 $134.63 $0.00 LTL fees (less than 15 drums 1 $150.00 $150.00 Energy security recovery fee 15% 1 $231.00 $231.00
Total Cost $545.00 $1,495.00 * $1,771.00
Notes* Transportation costs will be calculated based on pickups at various sites and waste stream volume
IDW SUBCONTRACTOR COST ESTIMATES FOR PFAS MATERIAL
Erwin
Summary of IDW Subcontractors Costs 2023_4_11 PFAS Page 1 of 1
WSP USA Inc.
9428 Baymeadows Road, Suite 400, Jacksonville, Florida 32256 USA
T: +1 904 363-3430 F: +1 904 363-3445 wsp.com
June 15, 2023 Proposal No. 202208346
Mr. Opeyemi Kehinde Florida Department of Environmental Protection Division of Waste Management Drycleaning Solvent Cleanup Program 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400
RE: COST PROPOSAL FOR THE SWIFT CLEANERS INC. BEACHES SITE (3RD STREET CLEANERS)
2023 ANNUAL GROUNDWATER MONITORING
1029 N. 3RD STREET
JACKSONVILLE BEACH, DUVAL COUNTY, FLORIDA
DEP FACILITY ID NUMBER: ERIC_4583
PROPOSED TASK ASSIGNMENT: HW685_DC029B
Dear Mr. Kehinde
WSP USA Inc. (WSP) formerly Golder Associates USA Inc. is pleased to provide the Florida Department of Environmental Protection (DEP) with this cost proposal for annual groundwater monitoring at the above-referenced site. This proposal includes a description of the proposed scope of services, level of effort sheets for each subtask, and a cost estimate form that summarizes the costs of the proposed services. The scope of work is based on the recommendations WSP presented in 2022 annual groundwater monitoring report for the site, dated November 10, 2022. The proposed scope of services is described below.
SUBTASK 1 – PROJECT MANAGEMENT
To facilitate project quality and satisfactory completion of the proposed scope of work, all aspects of this project will be overseen by an experienced project manager. The project manager will be responsible for the schedule, budget, invoicing, project activities, and communications with DEP and the field team. Project management will include coordination of field activities; resource allocation to confirm the work is conducted by qualified professionals in accordance with the project schedule; cost control and tracking of the budget status; and submittal of project invoices in accordance with DEP Drycleaning Solvent Cleanup Program requirements. The project manager will oversee the work so that it is conducted in a manner that is consistent with the requirements of the DEP-approved task assignment.
SUBTASK 2 – ANNUAL GROUNDWATER MONITORING AND IDW TREATMENT
WSP will collect groundwater samples from 13 monitoring wells: two shallow zone monitoring wells (MW002 and MW005); two intermediate zone monitoring wells (MW004 and MW007); and two deep zone monitoring wells (MW006 and MW013) for chlorinated volatile organic compounds (VOCs) by EPA Method 8260B. Figures 6, 7, Mr. Opeyemi Kehinde Proposal No. 202208346
Florida Department of Environmental Protection June 15, 2023 and 8 from the previous sampling event completed in 2022 showing chlorinated VOC results for the three zones of the surficial aquifers, are attached.
Prior to groundwater sampling, depth-to-water measurements will be collected using an electronic water level indicator at monitoring wells MW001, MW003, MW008, MW009, MW010, MW011, and MW012 along with the monitoring wells that will be sampled to determine groundwater flow direction. During the sampling event, the locks and well caps will be inspected for damage or degradation and repaired or replaced, as necessary.
Groundwater samples will be collected from the wells in accordance with DEP Standard Operating Procedures (SOPs) for Field Activities (DEP SOP-001/01). Prior to collecting the groundwater sample, each well will be purged and field parameters including temperature, pH, specific conductance, dissolved oxygen, turbidity, and oxidation-reduction potential will be monitored. Purge volumes and field parameters will be recorded on field data sheets, and the field monitoring equipment will be calibrated in accordance with the manufacturer’s recommended procedures.
Groundwater samples will be collected using low flow sampling methods. The groundwater samples will be placed in laboratory-supplied containers, labeled with a unique identification number attached to the outside of the sample container, preserved on ice in a laboratory-provided cooler at a maximum temperature of four degrees Celsius, and delivered to a Florida Department of Health and National Environmental Laboratory Accreditation Program certified fixed-base laboratory along with the completed chain-of-custody documentation to be analyzed for chlorinated VOCs using EPA Method 8260B. Upon receipt of the laboratory analytical results, WSP will evaluate the constituent concentrations to determine if off-site notification is required.
WSP will temporarily store the investigation derived waste (IDW) purge water generated from the groundwater sampling event in a 55-gallon steel drum(s). A waste characterization sample will be collected from the IDW drum(s) for analysis of total VOCs using EPA Method 8260. A waste profile will be completed using the chlorinated VOC results and PFAS results from a previous sampling event. If the waste characterization samples are acceptable to the disposal subcontractor, the IDW drum(s) will be picked up and transported to a facility for proper disposal. A non-hazardous waste manifest will be provided by the disposal subcontractor upon delivery to the disposal facility.
Upon completion of Subtask 2, an e-mail deliverable will be submitted and include copies of the field data sheets, equipment calibration forms, field notes, laboratory analytical report, and laboratory chain-of-custody documentation.
SUBTASK 3 – REPORTING
The annual groundwater monitoring report will include a description of the sampling procedures, evaluation of the analytical results, comparison of current to historical data, tabulated summary of the current and historical analytical data, a site map showing the groundwater analytical results, water level elevation information in tables and figures, laboratory analytical data, conclusions, and recommendations. Additionally, WSP will forward the Automated Data Processing Tool (ADaPT) data deliverables for the groundwater sampling event provided by the laboratory.
HEALTH AND SAFETY
WSP will update the existing site-specific Health and Safety Plan for the field work. The work will be completed in accordance with WSP’s safety policies and procedures. At a minimum, WSP will wear safety glasses, high visibility safety vests, and steel-toed boots. A safety job briefing will be conducted prior to the start of work activities, and anytime the scope of work or site conditions change.
Mr. Opeyemi Kehinde Proposal No. 202208346
Florida Department of Environmental Protection June 15, 2023
COST AND SCHEDULE
The estimated cost to complete the proposed scope of work is $9,909.37. WSP anticipates the monitoring event will take place in late July to early August 2023. The LOE/CEF sheets and Disposal subcontractor IDW quotes are included in Attachment A. The following table summarizes the proposed costs and deliverable schedule.
Task Proposed Cost Proposed Schedule/Deliverables
Subtask 1 – Project Management $ 908.57 October 27, 2023
Subtask 2 – Annual Groundwater Monitoring
$5,326.52 August 18, 2023 (Field documentation and laboratory analytical report via E-mail)
Subtask 3 – Reporting $3,674.28 September 22, 2023 (Annual Groundwater Monitoring Report)
Total/Completion Date $9,909.37 November 30, 2023
WSP appreciates the opportunity to provide services under the Drycleaning Solvent Cleanup Program. Should you require additional information or clarifications, please contact us at (904) 363-3430.
Sincerely, WSP USA Inc.
Ralph F. Mongillo, Jr., PG Jesse C. Brown, PE Lead Consultant / Senior Geologist Vice President, Environmental Engineer
RFM/JCB/as
Attachments: Figure 6 – Groundwater Analytical Results Shallow Zone (5-10 feet bgs) Figure 7 – Groundwater Analytical Results Intermediate Zone (22-32 feet bgs) Figure 8 – Groundwater Analytical Results Deep Zone (45-55 feet bgs)
Attachment A – Level of Effort Sheets and Cost Estimate Form and Subcontractor Quotes
G:\Projects\DEP-Drycleaning\Projects\Jax\Swift Cleaners Inc - Beaches\HW685\DC029B - 2023 Annual Monitoring\HW685 2023 Swift Beaches GW Monitoring proposal - ERIC_4583.docx