This is a Task Assignment (TA) document between the State of Florida Department of Environmental Protection (FDEP) and Golder Associates USA Inc. The TA is entered into pursuant to Contract Number HW685 and is identified as Task Assignment DC001A. The document establishes the framework for critical response services at multiple waste site cleanup section sites, with Ben Grubbs serving as the FDEP Project Manager and Matt Crews as the Contractor's Project Manager.
The Task Assignment authorizes Golder Associates USA Inc. to address critical issues at Waste Site Cleanup Section sites on an as-needed basis in accordance with written requests from the Waste Site Cleanup Section. The compensation structure is based on a fixed unit rate of $2,500.00, representing the total TA value. The deliverable is documentation of completed site activities, due by December 27, 2026, with invoicing contingent upon submittal and FDEP approval of the documentation. The task assignment was effective January 7, 2022, and is scheduled for completion by December 27, 2026. No specific funding source information was provided in the documentation.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW685
DC001A Completion December 27, 2026
This Task Assignment authorizes Golder to address critical issues at Waste Site Cleanup Section sites on an as needed basis in accordance with a request from the Waste Site Cleanup Section.
Ben Grubbs 850-245-8992 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Golder Associates USA Inc.
Golder Associates USA Inc.
Matt Crews 904-363-3430 Multiple
Multiple
Multiple
$ 0.00 ✔ $ 2,500.00
$ 0.00
$ 2,500.00
Scope of Work
Donald Miller
Principal
January 7, 2022
Donald Miller Digitally signed by Donald Miller Date: 2022.01.07 13:12:07 -05'00' William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2022.01.07 10:54:10 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Documentation of Completed Site Activities 12/27/2026
Submittal and FDEP approval of Documentation of Completed Site Activities $ 2,500.00
$ 2,500.00
HW685
DC001A
Printed on recycled paper.
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
To: HW685 Contract Negotiation File Critical Response, Multiple Sites From: Ben Grubbs, Project Manager Date: January 7, 2022 Subject: Negotiation Summary
HW685 DC001A
This Task Assignment authorizes Golder to perform critical tasks at sites on an as needed basis in accordance with a request from the Waste Site Cleanup Section. The Section will request the services in writing and will identify the site or sites to be addressed.
The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost for this Task Assignment is $2,500.00.
Golder may invoice following the schedule established in the Deliverables and Invoice Schedule Attachment, which accompanies the Task Assignment Notification Form.
File details come from the government source that posted it. Updated .