About this file

This document is a Task Assignment Change Order (TACO) issued by the State of Florida Department of Environmental Protection (FDEP) to amend an existing task assignment with Arcadis U.S. Inc. The change order extends the completion date for groundwater monitoring and PFAS sampling work at the Dry Cleaning Depot facility (ERIC_4160) located at 3470 W Broward Boulevard, Fort Lauderdale, Broward County. The work is performed under Contract Number HW680, with Theresa Pepe serving as FDEP's project manager and Gus Suarez as Arcadis's contract manager.

The task assignment maintains a fixed unit rate total value of $22,286.41 with no cost changes. The original completion date of June 6, 2025, is extended by 42 days to July 18, 2025, due to FDEP laboratory scheduling constraints for PFAS analysis. The deliverables include an Annual Monitoring Report with IDW manifest and project management ($19,460.35) due by May 16, 2025, and PFAS sampling ($2,826.06) due by April 18, 2025. Invoice payment is contingent upon FDEP approval of each deliverable. The change order was executed on January 28-29, 2025, and incorporates an updated Scope of Work attachment reflecting the extended timeline.

View the file

Other files

File Type Posted
CN-370000-HW680-DC001C.pdf PDF
CN-370000-HW680-DC002B.pdf PDF
CN-370000-HW680-DC003A.pdf PDF
CN-370000-HW680-DC004A.pdf PDF
CN-370000-HW680-DC004B.pdf PDF
CN-370000-HW680-DC004E.pdf PDF
CN-370000-HW680-DC007A.pdf PDF
CN-370000-HW680-DC008A.pdf PDF
CN-370000-HW680-DC008B.pdf PDF
CN-370000-HW680-DC010C.pdf PDF
CN-370000-HW680-DC011B.pdf PDF
CN-370000-HW680-DC013D.pdf PDF
CN-370000-HW680-DC013E.pdf PDF
CN-370000-HW680-DC013F.pdf PDF
CN-370000-HW680-DC014A.pdf PDF
CN-370000-HW680-DC014B.pdf PDF
CN-370000-HW680-DC014G.pdf PDF
CN-370000-HW680-DC014H.pdf PDF
CN-370000-HW680-DC015B.pdf PDF
CN-370000-HW680-DC015C.pdf PDF
CN-370000-HW680-DC015D.pdf PDF
CN-370000-HW680-DC015E.pdf PDF
CN-370000-HW680-DC016D.pdf PDF
CN-370000-HW680-DC016E.pdf PDF
CN-370000-HW680-DC018A.pdf PDF
CN-370000-HW680-DC019D.pdf PDF
CN-370000-HW680-DC01ACO2.pdf PDF
CN-370000-HW680-DC021C.pdf PDF
CN-370000-HW680-DC022D.pdf PDF
CN-370000-HW680-DC023A.pdf PDF
CN-370000-HW680-DC023C.pdf PDF
CN-370000-HW680-DC024C.pdf PDF
CN-370000-HW680-DC025B.pdf PDF
CN-370000-HW680-DC026A.pdf PDF
CN-370000-HW680-DC026C.pdf PDF
CN-370000-HW680-DC031C.pdf PDF
CN-370000-HW680-DC031D.pdf PDF
CN-370000-HW680-DC032A.pdf PDF
CN-370000-HW680-DC032B.pdf PDF
CN-370000-HW680-DC038A.pdf PDF
CN-370000-HW680-DC038C.pdf PDF
CN-370000-HW680-DC03BCO2.pdf PDF
CN-370000-HW680-DC040C.pdf PDF
CN-370000-HW680-DC040D.pdf PDF
CN-370000-HW680-DC041A.pdf PDF
CN-370000-HW680-DC042B.pdf PDF
CN-370000-HW680-DC052B.pdf PDF
CN-370000-HW680-DC053A.pdf PDF
CN-370000-HW680-DC05ACO1.pdf PDF
CN-370000-HW680-DC05ACO2.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Name:

4. There are no changes to the TA compensation.

The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. There are no changes to the TA Expiration Date.

The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. There are no changes to the Attachments.

Attachment ___ is replaced with Attachment -____.

7. No Additional Changes.

Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

Additional signatures attached on separate page.

DC014F 1 HW680

A time extension of 42 days is added due to FDEP lab schedule.

Theresa Pepe 850-245-8966 Contractor Arcadis U.S. Inc. Contractor

Contractor Gus Suarez Contractor 813-205-4703

ERIC_4160

Dry Cleaning Depot

✔ $ 22,286.41 $ 22,286.41

$ 22,286.41 $ 22,286.41 Completion

✔ Completion 06/06/2025 07/18/2025 42

✔ 1 1 1

Arcadis U.S. Inc.

Contractor Gus Suarez

Contract Manager

Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.

Date: 2025.01.29 10:31:44 -05'00'

Mubeen Darji

Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.

Date: 2025.01.28 16:12:10 -05'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

HW680

DC014F

$ 22,286.41

Annual Monitoring Report/IDW manifest/Project Management

PFAS sampling

FDEP approval of Annual Monitoring Report/IDW manifest/Project Management

FDEP approval of PFAS sampling

05/16/2025

04/18/2025

$ 2,826.06

$ 19,460.35

FFLORIDA DEPARTMENT OF

EEnvironmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette NNuñez Lt. Governor

Alexis A. Lambert Secretary

Memorandum TO: Negotiation File

Dry Cleaning Depot Facility ID No. 06-9502029; ERIC_4160 Fort Lauderdale, Broward County

FROM: Theresa C. Pepe, Project Manager SUBJECT: Task Assignment Change Order DC014F-1 (HW680) DATE: January 28, 2025

The FDEP lab is booked through February for PFAS analysis (see attached change order memo).

Therefore, Arcadis requested a 30-day extension to complete the tasked sampling. The FDEP project manager extended the date by days due to the Independence Day holiday.

This change order adds thirty-five days to the completion date. There is no cost change to the task assignment. Arcadis may invoice according to the attached schedule.

From: McGlone, Douglas To: Pepe, Theresa Cc: Tran, Thuy-Minh Subject: FW: Sample Order Kit Request for PFAS GW Samples (Dry Cleaning Depot - ERIC_4160) - Groundwater

Monitoring Date: Monday, January 27, 2025 9:30:20 AM Attachments: image001.png image002.png image003.png image004.png image005.png image007.png HW680_DC014F.pdf

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

Theresa, We are requesting a 30 day time extension for DC Depot due to FDEP lab schedule. See below.

Thanks

Douglas J. McGlone | Principal Geologist | douglas.mcglone@arcadis.com Arcadis | Arcadis U.S., Inc.

7000 North Federal Hwy. Boca Raton, Florida 33487 | USA T. +1 561 393 6555 | C. +1 561 662 7978 Connect with us! www.arcadis.com | LinkedIn | Twitter | Facebook

Be green, leave it on the screen.

From: Tran, Thuy-Minh <thuyminh.tran@arcadis.com> Sent: Monday, January 27, 2025 8:50 AM To: McGlone, Douglas <Douglas.McGlone@arcadis.com> Subject: RE: Sample Order Kit Request for PFAS GW Samples (Dry Cleaning Depot - ERIC_4160) - Groundwater Monitoring

Hi Doug, I assume March is okay since it has to be. The due dates for this one is the reporting 3/21/25 and PFAS sampling 2/28/25. Can you ask for an extension?

Thank you, Thuy-Minh

Ms. Thuy-Minh Tran EI Staff Environmental Engineer Arcadis U.S., Inc.

1200 Riverplace Boulevard, Suite 425 | Jacksonville, FL | 32207 | USA T +1 904 493 8582 | C +1 904 742 8914 www.arcadis.com

From: Ayres, Joshua <Joshua.Ayres@FloridaDEP.gov> Sent: Monday, January 27, 2025 8:46 AM To: Tran, Thuy-Minh <thuyminh.tran@arcadis.com> Cc: Fox, Brian <Brian.Fox@arcadis.com>; McGlone, Douglas <Douglas.McGlone@arcadis.com> Subject: RE: Sample Order Kit Request for PFAS GW Samples (Dry Cleaning Depot - ERIC_4160) - Groundwater Monitoring

Arcadis Warning: Exercise caution with email messages from external sources such as this message. Always verify the sender and avoid clicking on links or scanning QR codes unless certain of their authenticity.

Thuy-Minh, The PFAS lab is already at capacity for February, the earliest I can schedule this RQ is March.

Please let me know if March will work.

JOSHUA AYRES

Florida Department of Environmental Protection Services Support Program / Laboratories Environmental Administrator Joshua.Ayres@FloridaDep.gov Office: 850.245.8206

From: Tran, Thuy-Minh <thuyminh.tran@arcadis.com> Sent: Friday, January 24, 2025 4:36 PM To: Ayres, Joshua <Joshua.Ayres@FloridaDEP.gov> Cc: Fox, Brian <Brian.Fox@arcadis.com>; McGlone, Douglas <Douglas.McGlone@arcadis.com> Subject: Sample Order Kit Request for PFAS GW Samples (Dry Cleaning Depot - ERIC_4160) - Groundwater Monitoring

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

Additional signatures attached on separate page.

HW680

DC014F Completion June 6, 2025

Arcadis will conduct groundwater monitoring including sampling for PFAS from select wells at the site. All activities will be performed according to the October 17, 2024, Work Plan submitted by Arcadis.

Theresa Pepe 850-245-8966 Contractor Arcadis U.S. Inc. Contractor

Contractor Gus Suarez Contractor 813-205-4703

ERIC_4160

3470 W Broward Blvd, Ft. Lauderdale, Broward County

Dry Cleaning Depot

Contractor Contractor

✔ $ 22,286.41

$ 22,286.41

Scope of Work

Arcadis U.S. Inc.

Contractor Gus Suarez

Contract Manager

Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.

Date: 2024.10.23 09:35:05 -04'00'

Mubeen Darji

Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.

Date: 2024.10.23 08:44:21 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Annual Monitoring Report/IDW manifest/Project Management 03/21/2025

PFAS sampling 02/28/2025

FDEP approval of Annual Monitoring Report/IDW manifest/Project Management $ 19,460.35

FDEP approval of PFAS sampling $ 2,826.06

$ 22,286.41