CN-370000-HW680-DC015E.pdf

PDF 1 MB Posted

Attached to
Master Agreement FL|HW680|454e104ae8fbcb5641ac6acc30583968
Contract number
HW680
Issued by
Florida

About this file

Document Summary

This is a Task Assignment (TA) document entered into between the State of Florida Department of Environmental Protection (FDEP) and Arcadis U.S. Inc., pursuant to Contract Number HW680. The Task Assignment, numbered DC015E, pertains to environmental remediation and monitoring services at the former Miami Dry Cleaners site located at 8410 West Flagler Street in Miami-Dade County, Florida (ERIC_4372). The Department Project Manager is Theresa Pepe, and the Contractor's Project Manager is Gus Suarez.

Arcadis will conduct confirmatory soil sampling to verify remedial system effectiveness, perform annual groundwater monitoring from six monitor wells to ensure natural attenuation continues, and sample three monitor wells for PFAS compounds using FDEP's laboratory. All activities will be executed according to the December 10, 2024 Work Plan submitted by Arcadis. The Task Assignment total value is $19,842.82 on a fixed unit rate basis. Deliverables include an Annual Monitoring & Soil Sampling Report/IDW manifest/Project Management due by May 16, 2025 ($17,227.48), and PFAS sampling results due by March 31, 2025 ($2,615.34). The scope encompasses five subtasks: Project Management, Confirmatory Soil Sampling (seven soil samples), Annual Groundwater Monitoring (six wells), Reporting, and PFAS Sampling (three wells). Subcontractors for drilling and utility locate services were selected based on the lowest of three competitive bids. The Task Assignment was effective upon the last date signed by authorized representatives on December 17, 2024.

View the file

Other files

File Type Posted
CN-370000-HW680-DC001C.pdf PDF
CN-370000-HW680-DC002B.pdf PDF
CN-370000-HW680-DC003A.pdf PDF
CN-370000-HW680-DC004A.pdf PDF
CN-370000-HW680-DC004B.pdf PDF
CN-370000-HW680-DC004E.pdf PDF
CN-370000-HW680-DC007A.pdf PDF
CN-370000-HW680-DC008A.pdf PDF
CN-370000-HW680-DC008B.pdf PDF
CN-370000-HW680-DC010C.pdf PDF
CN-370000-HW680-DC011B.pdf PDF
CN-370000-HW680-DC013D.pdf PDF
CN-370000-HW680-DC013E.pdf PDF
CN-370000-HW680-DC013F.pdf PDF
CN-370000-HW680-DC014A.pdf PDF
CN-370000-HW680-DC014B.pdf PDF
CN-370000-HW680-DC014G.pdf PDF
CN-370000-HW680-DC014H.pdf PDF
CN-370000-HW680-DC015B.pdf PDF
CN-370000-HW680-DC015C.pdf PDF
CN-370000-HW680-DC015D.pdf PDF
CN-370000-HW680-DC016D.pdf PDF
CN-370000-HW680-DC016E.pdf PDF
CN-370000-HW680-DC018A.pdf PDF
CN-370000-HW680-DC019D.pdf PDF
CN-370000-HW680-DC01ACO2.pdf PDF
CN-370000-HW680-DC021C.pdf PDF
CN-370000-HW680-DC022D.pdf PDF
CN-370000-HW680-DC023A.pdf PDF
CN-370000-HW680-DC023C.pdf PDF
CN-370000-HW680-DC024C.pdf PDF
CN-370000-HW680-DC025B.pdf PDF
CN-370000-HW680-DC026A.pdf PDF
CN-370000-HW680-DC026C.pdf PDF
CN-370000-HW680-DC031C.pdf PDF
CN-370000-HW680-DC031D.pdf PDF
CN-370000-HW680-DC032A.pdf PDF
CN-370000-HW680-DC032B.pdf PDF
CN-370000-HW680-DC038A.pdf PDF
CN-370000-HW680-DC038C.pdf PDF
CN-370000-HW680-DC03BCO2.pdf PDF
CN-370000-HW680-DC040C.pdf PDF
CN-370000-HW680-DC040D.pdf PDF
CN-370000-HW680-DC041A.pdf PDF
CN-370000-HW680-DC042B.pdf PDF
CN-370000-HW680-DC052B.pdf PDF
CN-370000-HW680-DC053A.pdf PDF
CN-370000-HW680-DC05ACO1.pdf PDF
CN-370000-HW680-DC05ACO2.pdf PDF
CN-370000-HW680-DC05BCO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

HW680

DC015E July 25, 2025

Arcadis will conduct confirmatory soil sampling, and conduct annual groundwater monitoring including sampling for PFAS compounds from select wells at the site. All activities will be performed according to the December 10, 2024, Work Plan submitted by Arcadis.

Theresa Pepe 850-245-8966 Arcadis U.S. Inc.

Gus Suarez 813-205-4703

ERIC_4372

8410 West Flagler Street, Miami, Miami-Dade County

Miami Dry Cleaners

$ 19,842.82

$ 19,842.82

Scope of Work

Arcadis U.S. Inc.

Gus Suarez

Contract Manager

Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.

Date: 2024.12.17 15:34:11 -05'00'

Mubeen Darji

Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.

Date: 2024.12.17 14:57:39 -05'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Alesis A. Lambert Secretary

Memorandum

TO: Negotiation File Miami Dry Cleaners

FACID NO. 13-9501077; ERIC_4372

Miami, Miami-Dade County FROM: Theresa Pepe, Project Manager SUBJECT: Task Assignment DC015E (HW680) DATE: December 13, 2024

Arcadis U.S. Inc. will perform confirmatory soil sampling to verify the effectiveness of the remedial system. Arcadis will also conduct annual groundwater monitoring from select wells at the site. Groundwater monitoring will ensure that natural attenuation of contaminants continues to occur. Additionally, select wells will be sampled for PFAS compounds. All activities will be conducted in accordance with the December 10, 2024, Work Plan submitted by Doug McGlone of Arcadis.

The final task assignment total is $19,842.82. Arcadis may invoice according to the attached schedule.

Specific negotiated subtasks are as follows:

Subtask 1: Project Management Project Management is automatically calculated as a percentage of total labor.

Subtask 2: Confirmatory Soil Sampling FDEP obtained an access agreement from the property owner in August 2017. No changes in ownership have occurred since that date.

Arcadis will collect seven soil samples from various depths from previously contaminated locations. SPLP samples will be collected and run by the lab, if needed.

Confirmatory soil sampling is required before the site can be considered for closure.

FDEP’s geologist has approved the soil sampling scope of work.

Subcontractors for drilling and utility locate services were chosen based on the lowest of three bids.

Miami Dry Cleaners

ERIC_4372

Subtask 3: Annual Groundwater Monitoring Arcadis will sample six monitor wells for drycleaning solvents. IDW will be disposed of by a licensed waste hauler.

Subtask 4: Reporting Arcadis will submit a written report as the final deliverable including recommendations for additional actions as needed.

Subtask 5: PFAS sampling Arcadis will sample three monitor wells for PFAS compounds using FDEP’s laboratory in Tallahassee. The wells have been chosen based on prior PFAS results and FDEP’s new guidance/flow chart.

Hours and costs are comparable to past task assignments of similar scope.

FDEP COST ESTIMATE

Contractor: Arcadis, U.S., Inc.

Date: 12/10/24

Task #: SubTask 1 Project Management Site: Miami Dry Cleaner SubTask 2 Confirmatory Soil Sampling

Activity/Phase: Annual Monitoring SubTask 3 Groundwater Monitoring Project Manager: Doug McGlone SubTask 4 Reporting

SubTask 5 PFAS Sampling

Totals 1 2 3 4 5

Labor Rate Category

$70.09 Project Manager McGlone, Douglas (DMc) 7 7.0

$87.59 Principal Engineer Suarez, Gus (GS) 0 0 0 0 0

$70.09 Principal Scientist McGlone, Douglas (DMc) 11 4 2 4 1

$44.00 Project Scientist Salinas, Kendall (KS) 0 0 0 0 0

$44.00 Project Scientist Riley, Joel (JR) 52 14 13 16 9 $39.67 Drafter/Designer Oliva, Brian (BO) 7 0 0 5 2

$38.28 Project Assistant Cruz, Michele (MC) 11 2 3 4 2

$35.00 Document Technician Ballheim, Debra (DJB) 0 0 0 0 0

$31.20 Document Technician Embras, Susan (SRE) 0 0 0 0 0

Total Hours 88 7 20 18 29 14

Direct Labor $4,246.27 $488.51 $972.92 $827.02 $1,335.83 $621.99

Overhead 79.00% $3,354.56 $385.92 $768.61 $653.35 $1,055.31 $491.37

Gen & Admin 36.00% $1,528.66 $175.86 $350.25 $297.73 $480.90 $223.92

Fringe 37.10% $1,575.36 $181.24 $360.95 $306.82 $495.59 $230.76

Total Labor $10,704.85 $1,231.53 $2,452.73 $2,084.92 $3,367.63 $1,568.04

Travel

Vehicle Rental $360.00 $120.00 $120.00 $0.00 $120.00

Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00

Air Fare $0.00 $0.00 $0.00 $0.00 $0.00

Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00

Total Travel $360.00 $120.00 $120.00 $0.00 $120.00

Subcontractor (Equipment Procurement)

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00

Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00

Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement)

Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00

Drilling (Non-conventional) $2,550.00 $2,550.00 $0.00 $0.00 $0.00

Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00

Surveying $0.00 $0.00 $0.00 $0.00 $0.00

IDW Erwin $125.00 $0.00 $125.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00

Utility locate $795.00 $795.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $3,470.00 $3,345.00 $125.00 $0.00 $0.00

Handling Fee $347.00 $334.50 $12.50 $0.00 $0.00

Total Subcontractor Cost $3,817.00 $3,679.50 $137.50 $0.00 $0.00

Laboratory

Analytical Costs $1,810.00 $1,372.00 $438.00 $0.00 $0.00

Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00

Sample Shipping $300.00 $150.00 $150.00 $0.00 $0.00

Total Laboratory $2,110.00 $1,522.00 $588.00 $0.00 $0.00

Field Expenses

Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00

Expendables $120.00 $40.00 $40.00 $0.00 $40.00

Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Analytical related) $150.50 $77.00 $48.00 $0.00 $25.50

Equipment (IDW related) $100.00 $0.00 $100.00 $0.00 $0.00

Equipment (Other) $1,410.00 $0.00 $705.00 $0.00 $705.00

Total Field Expenses $1,780.50 $117.00 $893.00 $0.00 $770.50

Subtotal $18,772.35 $1,231.53 $7,891.23 $3,823.42 $3,367.63 $2,458.54

Completion Fee $1,070.47 $123.15 $245.27 $208.49 $336.76 $156.80

Total Estimated Cost $19,842.82 $1,354.68 $8,136.50 $4,031.91 $3,704.39 $2,615.34

REV: 02/03 CEF ARCADIS Page 1

SITE : Miami Dry Cleaner

SUBTASK 2: Confirmatory Soil Sampling

DATE: 12/10/24

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

(Subtask Title)

Principal (DMc) Access; technical analysis; oversight with field crew 4

Staff Scientist (JR) Prp for field work (1 hr), mob/demob (2 hr); oversee drilling; soil sample collection (10 hrs) , pack/ship (1 hrs) 14

Project Assistant (MC) Process field notes, sample tracking, data entry 2

TOTAL LABOR 20

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Per Day 0 $0.00 $0.00

Van/Truck $120.00 Per Day 1 $120.00 $120.00

TOTAL VEHICLE $120.00

PER DIEM STAFF RATE UNIT USEAGE

Meals

Category/Staff Rate Unit Usage Totals

$36.00 Per Day 0 $0.00

$36.00 Per Day 0 $0.00

Hotel

Category/Staff Rate Unit Usage Totals

$150.00 Per Day 0 $0.00

$150.00 Per Day 0 $0.00

Total Meal/Hotel: $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

Equipment Procurement

Name Equipment Rate Units Usage Totals

$2,000.00 Per Day 0 $0.00

Total Equip.: $0.00

Services Procurement

Name Purpose Rate Units Usage Totals

ETD Direct-push services $2,550.00 Lump Sum 1 $2,550.00

Blood hound Utility Locate / GPR Survey $795.00 Lump Sum 1 $795.00

Total Services: $3,345.00

TOTAL $3,345.00

LABORATORY COSTS

Analytical Costs

Parameter Method Media Rate Turn Around Total Samples Totals

VOC 8260 Soil $73.00 1.00 7 $511.00

SPLP Extraction 1311/1312 Soil $50.00 1.00 7 $350.00

VOC on SPLP extracted sample 8260 Aqueous $73.00 1.00 7 $511.00

TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $1,372.00

Rate Units Usage

Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 1 $150.00

Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00

Total Shipping: $150.00

TOTAL LAB $1,522.00

EQUIPMENT

Personal Protection

Item Rate Unit Usage Totals

Total PPE: $0.00

Expendables

Miscellaneous Expendables $40.00 Per Day 1 $40.00

Total Expendables: $40.00

Equipment Items Terra Cores $11.00 Each 7 $77.00

Total Equipment Items: $77.00

Equipment Kits

Total Equipment Kits: $0.00

Total Equipment Kits: $117.00

SUBTASK 3: Groundwater Monitoring

DATE: 12/10/24

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

(Subtask Title)

Principal (DMc) Technical analysis; oversight with field crew 2

Staff Scientist (JR) Prp for field work (1 hr), mob/demob (2 hr), round of water levels, purge & sample 6 wells (8 hrs), pack/ship, IDW stage (2 hrs) 13

Project Assistant (MC) Process field notes, sample tracking, data entry 3

Drafter/Designer (BO) Figures production for report

TOTAL LABOR 18

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Per Day 0 $0.00 $0.00

Van/Truck $120.00 Per Day 1 $120.00 $120.00

TOTAL VEHICLE $120.00

PER DIEM STAFF RATE UNIT USEAGE

Meals

Category/Staff Rate Unit Usage Totals

$36.00 Per Day 0 $0.00

$36.00 Per Day 0 $0.00

Hotel

Category/Staff Rate Unit Usage Totals

$150.00 Per Day 0 $0.00

$150.00 Per Day 0 $0.00

Total Meal/Hotel: $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

Equipment Procurement

Name Equipment Rate Units Usage Totals

$0.00 Per Day 1 $0.00

Total Equip.: $0.00

Services Procurement

Name Purpose Rate Units Usage Totals

Erwin IDW $125.00 Drum 1 $125.00

Handling Fee $0.00 Per Month 0 $0.00

Total Services: $125.00

TOTAL $125.00

LABORATORY COSTS

Analytical Costs

Parameter Method Media Rate Turn Around Total Samples Totals

VOC 8260 Aqueous $73.00 1.00 6 $438.00

TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $438.00

Rate Units Usage

Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 1 $150.00

Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00

Total Shipping: $150.00

TOTAL LAB $588.00

EQUIPMENT

Personal Protection

Item Rate Unit Usage Totals

Total PPE: $0.00

Expendables

Miscellaneous Expendables $40.00 Per Day 1 $40.00

Total Expendables: $40.00

Equipment Items

Tubing, Poly/HDPE $0.30 Per Foot 132 $39.60

Tubing, Silicon 3/16x3/8 $3.00 Per Foot 3 $9.00

55-gallon Drum $100.00 Each 1 $100.00

Total Equipment Items: $148.60

Equipment Kits

Shallow Groundwater Sampling Kit $290.00 Day 1 $290.00

Deep Groundwater Sampling Kit $415.00 Day 1 $415.00

Total Equipment Kits: $705.00

Total Equipment Kits: $893.60

SUBTASK 4: Reporting

DATE: 12/10/24

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

(Subtask Title)

Principal (DMc) Technical analysis; sign and seal report 4

Staff Scientist (JR) Data evaluation and report preparation 16

Project Assistant (MC) Process field notes, data entry, report assembly 4

Drafter/Designer (BO) Figures production for report 5

TOTAL LABOR 29

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Per Day 0 $0.00 $0.00

Van/Truck $120.00 Per Day 0 $0.00 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

Equipment Procurement

Name Equipment Rate Units Usage Totals

$0.00 Per Day 0 $0.00

Total Equip.: $0.00

Services Procurement

Name Purpose Rate Units Usage Totals

Total Services: $0.00

TOTAL $0.00

LABORATORY COSTS

Analytical Costs

Parameter Method Media Rate Turn Around Total Samples Totals

TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00

Rate Units Usage

Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00

Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00

Total Shipping: $0.00

TOTAL LAB $0.00

EQUIPMENT

Personal Protection

Item Rate Unit Usage Totals

Total PPE: $0.00

Expendables

Miscellaneous Expendables $40.00 Per Day 0 $0.00

Total Expendables: $0.00

Equipment Items

Total Equipment Items: $0.00

Equipment Kits

Total Equipment Kits: $0.00

TOTAL EQUIPMENT $0.00

SUBTASK 5: PFAS Sampling

DATE: 12/10/24

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

(Subtask Title)

Principal (DMc) Technical analysis 1

Staff Scientist (JR) Prp for field work (1 hr), mob/demob (2 hr), round of water levels, purge & sample 3 wells (4 hrs), pack/ship, IDW stage (2 hrs) 9

Project Assistant (MC) Process field notes, sample tracking, data entry 2

Drafter/Designer (BO) Figures production for report 2

TOTAL LABOR 14

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Per Day 0 $0.00 $0.00

Van/Truck $120.00 Per Day 1 $120.00 $120.00

TOTAL VEHICLE $120.00

PER DIEM STAFF RATE UNIT USEAGE

Meals

Category/Staff Rate Unit Usage Totals

$36.00 Per Day 0 $0.00

$36.00 Per Day 0 $0.00

Hotel

Category/Staff Rate Unit Usage Totals

$150.00 Per Day 0 $0.00

$150.00 Per Day 0 $0.00

Total Meal/Hotel: 0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

Equipment Procurement

Name Equipment Rate Units Usage Totals

$0.00 Per Day $0.00

Total Equip.: 0.00

Services Procurement

Name Purpose Rate Units Usage Totals

Handling Fee $0.00 Per Month $0.00

Total Services: 0.00

TOTAL $0.00

LABORATORY COSTS

Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals

TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: 0.00

Rate Units Usage

Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00

Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00

Total Shipping: 0.00

TOTAL LAB $0.00

EQUIPMENT

Personal Protection

Item Rate Unit Usage Totals

Total PPE: $0.00

Expendables

Miscellaneous Expendables $40.00 Per Day 1 $40.00

Total Expendables: $40.00

Equipment Items

Tubing, Poly/HDPE $0.30 Per Foot 65 $19.50

Tubing, Silicon 3/16x3/8 $3.00 Per Foot 2 $6.00

Total Equipment Items: $25.50

Equipment Kits

Shallow Groundwater Sampling Kit $290.00 Day 1 $290.00

Deep Groundwater Sampling Kit $415.00 Day 1 $415.00

Total Equipment Kits: $705.00

TOTAL EQUIPMENT 770.50

Use or disclosure of information contained on this sheet is subject to the restriction and disclaimer located on the signature page of this document.

arcadis.com C:\Users\pepe_t\Desktop\Miami DC 2024 Monitoring Proposal.docx

Page:

1/2

Theresa Pepe, Contract Manager Hazardous Waste Cleanup Section Florida Department of Environmental Protection Bob Martinez Center, MS 4520 2600 Blair Stone Road Tallahassee, Florida 32399-2400

Subject:

Proposal for Confirmatory Soil Sampling and Annual Groundwater Monitoring & Reporting Former Miami Dry Cleaner 8410 West Flagler Street, Miami, Florida Facility ID No. ERIC_4370

Dear Ms. Pepe:

Arcadis is pleased to provide the Florida Department of Environmental Protection (FDEP) this proposal for the former Miami Dry Cleaner, located in Miami, Miami- Dade County, Florida.

SCOPE OF WORK

The following sections provide a brief description of the tasks to be completed by Arcadis.

Task 1 – Project Management

This task includes project management activities associated with completion of Tasks 2 through 5.

Task 2 – Confirmatory Soil Sampling

To verify that previously impacted soils have been remediated, soil samples will be collected from SB002 @ 0-2’ and @ 2-4’, from SB003 @0-2’ and @2-4’, from SB011 @2-4’, and from SB013 @0-2’ and from 2-4’ (total of 7 soil samples).

Each soil sample will be analyzed for VOHs by EPA 8260 and placed on hold for potential SPLP analysis. Soil sample locations are shown in Figure 5.

Task 3 – Monitor Wells sampling – VOH

As requested, groundwater samples will be collected from six monitor wells (MW001, MW002, MW002I, MW004, MW005, and MW001D) for analysis of VOHs by EPA Method 8260 by an accredited laboratory. Water levels will be

ENVIRONMENT

Date:

December 1 , 2024

Contact:

Doug McGlone

Phone:

561.662.7978

Email:

Douglas.mcglone@arcadis.com

Our ref:

Aristocrat Monitoring 2024

This proposal and its contents shall not be duplicated, used or disclosed — in whole or in part — for any purpose other than to evaluate the proposal. This proposal is not intended to be binding or form the terms of a contract. The scope and price of this proposal will be superseded by the contract. If this proposal is accepted and a contract is awarded to Arcadis as a result of — or in connection with — the submission of this proposal, Arcadis and/or the client shall have the right to make appropriate revisions of its terms, including scope and price, for purposes of the contract. Further, client shall have the right to duplicate, use or disclose the data contained in this proposal only to the extent provided in the resulting contract.

arcadis.com C:\Users\pepe_t\Desktop\Miami DC 2024 Monitoring Proposal.docx

Annual Monitoring Proposal 13 December 2024

Page:

2/2 measured in the six wells for purposes of preparing a flow map. Purge water will be drummed for offsite disposal.

Task 4 – Reporting – VOH in Soils and Groundwater

A Confirmatory Soil Sampling / Annual Groundwater Monitoring Report documenting the sampling and results will be prepared and include conclusions and recommendations for future site work.

Task 5 – PFAS Sampling and Reporting

Wells MW002, MW003 and MW002I will also be sampled for PFAS by the FDEL laboratory. The PFAS results will be included in the annual monitoring report.

SCHEDULE

Arcadis will schedule field activities immediately upon receipt of the Task Assignment. Sampling is expected to occur in February 2025. The deliverable will be submitted within 60 days of completion of field work.

COST ESTIMATE

A Cost Estimate Form and Level of Effort (CEF-LOE) Form are attached for the above scope of work (Attachment 1).

CLOSING REMARKS

Arcadis appreciates the opportunity to assist the FDEP at this site. If you have any questions or wish to discuss this proposal, please do not hesitate to contact us.

Sincerely, Arcadis U.S., Inc.

Douglas J. McGlone, P.G.

Principal Geologist

Attachments:

CEF-LOE

EARTH TECH DRILLING

2703 NW 19TH STREET, POMPANO BEACH, FL 33069

954.974.2424 FAX:954.974.2423

Date: 11/19/2024

FAC ID#:

PROPOSED SCOPE OF WORK:

Unit Unit Rate Number of Units

Extended Price

Equipment Type: DPT Track Rig whole day $1,750.00 1 $1,750.00 half day $0.00 each $0.00 each $0.00 each $0.00 each $0.00 per well $0.00 daily roundtrip $575.00 1 $575.00 per crew / per night $0.00 each $80.00 0 $0.00 each $130.00 0 $0.00 each $85.00 0 $0.00 each $500.00 0 $0.00 each $75.00 3 $225.00 day $750.00 0 $0.00

TOTAL QUOTE PRICE $2,550.00

Notes:

Project No.: ___________________________

Date: 11/19/2024

(4) Hand Auger Borings to 4' inside dry cleaners

Shop Vac - Coredrill needed

Direct Push Daily Rate 1 - on-site day

Direct Push Half-Day Rate 1 - on-site half day

MAG Wells - 2" x ~6' w/ 5' .010" Screen

Auger Attachment, 4" Surface Casing

DIRECT PUSH TECHNOLOGY

Water Sample w/ HDPE Tubing

Signature and Title of Person Submitting Quote: Charles Bucher

Concrete Core & Patch

420M Geoprobe Dolly Rig - Upcharge

Days to Complete Scope of Work: 1 Day

Subcontract Company Name: EARTH TECH DRILLING. Inc.

Subcontract Mailing Address: 2703 NW 19th Street, Pompano Beach, FL 33069

ETD Policy: If pea gravel is encountered, borehole advancement is terminated. If client would like to continue borehole advancement, it is at the risk of the consultant, FDEP or property owner.

Decon / Decon Pit

Contractor Name: Arcadis - Doug McGlone - 561 662-7978

Site Name: Miami Dry Cleaners - 8410 W Flagler St - Miami, FL

(HAND CLEAR ALL LOCATIONS TO 5' or REFUSAL)

Permits - Install Well

MISCELLANEOUS

Patch holes with concrete

Mobilization

Per Diem

DOT Approved 55-gal Drum

Well Riser (includes all materials) 3/4" - 1" x 5'

Well Completion (includes 30 Min Dev. 8" B-D MH & locking well cap)

Pre-Packed PVC Well Screen (includes all materials) 3/4" - 1" x 5'

Monitoring Wells Sparge Wells Horizontal and Vertical Extraction Wells Geotechnical Drilling Direct Push

Preferred Drilling Solutions, Inc.

8820 66th St. North, Pinellas Park, FL 33782

Ph: 727-561-7477 Fax: 727-561-9028 www.pdsflorida.com

DIRECT PUSH TECHNOLOGY QUOTE FORM

Date: 11/26/24 FAC ID#:

Unit Unit Rate Number of Units

Extended Price whole day $1,975.00 1 1,975.00$ half day $1,575.00 -$ per foot $25.00 -$ each $110.00 -$ each $50.00 -$ each $35.00 -$ per well $150.00 -$ roundtrip $950.00 1 950.00$ per crew / per night $575.00 -$ each $75.00 -$ per day $150.00 1 150.00$ each -$

Decon Pad lump sum $350.00 -$ per day $100.00 -$ per day $100.00 1 100.00$

TOTAL QUOTE PRICE $3,175.00

Notes: 1. Includes saw cuts, development, standby time, and decon.

Project No.:

Subcontract Company Name: Preferred Drilling Solutions, Inc. (727) 561-7477

Subcontract Mailing Address: 8820 66th St, Pinellas Park, FL 33782

Signature and Title of Person Submitting Quote: ___________________________________Austin Bonacum, Estimator Date: 11/26/24

Days to Complete Scope of Work: 1

Daily Rate 1 - on-site day

Equipment Type: Geoprobe 8040DT, 3230DT, 7822DT, 6620DT, 6712DT

*Note: It is against PDS policy to drill in Pea Gravel. Borings in Pea Gravel will be terminated or can proceed solely at the risk of the consultant, DEP or Property Owner

Permits

Other (specify)

DOT Approved 55-gal Drum

Per Diem

Mobilization

DIRECT PUSH TECHNOLOGY

MISCELLANEOUS

Consumables (includes tubing, points, liners, concrete patch, asphalt patch, and grouting)

Well Completion (includes MH w/ cover, concrete pad, and locking well cap)

Well Riser (includes all materials) ID 1" 5' Length

Slotted PVC Well Screen (includes all materials) 5' Length Pack OD 3.5"

Pre-Packed Well Screen (includes all materials) ID 1" 5' Length Pack OD 3.5"

Steam Cleaner

Concrete Core Drill

Site Name and Location: Miami Dry Cleaner

Consultant Name: Arcadis U.S., Inc.

PROPOSED SCOPE OF WORK:

(4) Soil borings to 4', backfill and grout, restore grade

8410 West Flagler Street, Miami, Miami-Dade County, FL

Auger Attachment, 2" Well Install

Half-Day Rate 1 - on-site half day

PDS to supply concrete core drill and shop vac

ARCADIS 11/21/2024

7000 North Federal Hwy 196999 Boca Raton, Fl 33487

Project Name Commercial Site - Miami, Fl

Douglas McGlone Project Address 8410 West Flagler Street douglas.mcglone@arcadis.com Project City Miami 561-662-7978 Project State Fl

Project Zip 33144

Cascade Rep Contact Information

Scope of Work

Quantity Unit Sales Price Subtotal

1 Lump Sum 1,115.00$ 1,115.00$

1 Lump Sum 1,115.00$ 1,115.00$

1 Day 1,750.00$ 1,750.00$

1 Day 225.00$ 225.00$

1 Lump Sum 500.00$ 500.00$

4 Each 15.00$ 60.00$

Each 25.00$ -$

Pre-Tax Total

Tax Percentage

Taxes

Quote Total

Account Name Bid Date Address Quote Number

Quote Revision Date

Bill To Account

Contact Name Email Phone

Number

Prepared By Zachary Fordley, Project Manager Email zfordley@cascade-env.com

Cascade will provide a 66/78 series track mounted Geoprobe unit with an Operator to provide the following.

- Collect soils at Four locations to 4' BLG.

- Three (3) locations are inside the facility and will need to be concrete cored.

- All locations will be backfilled and patched to existing.

- This is NOT a prevailing wage site.

Description

$4,765.00

Mobilization

Demobilization

DPT Rig, Operator

Per diem

Core Drill & Shop Vac

Patch Chips - as needed

$4,765.00

ESTIMATE

Blood Hound 6500 Technology Center Dr.

Suite 200 Indianapolis, IN 46278

Email: BHI@bhug.com bhug.com Website:

Phone #: 888-858-9830 888-858-9829 Fax #:

From: Craig Fusaro To: McGlone, Douglas Subject: RE: Miami Dry Cleaner Boring Clearing Date: Tuesday, November 19, 2024 3:05:30 PM Attachments: image001.png

Arcadis Warning: Exercise caution with email messages from external sources such as this message. Always verify the sender and avoid clicking on links or scanning QR codes unless certain of their authenticity.

Hi Doug

Will $800 work again? If not let me know what works.

Thanks Craig

From: McGlone, Douglas <Douglas.McGlone@arcadis.com> Sent: Tuesday, November 19, 2024 3:01 PM To: Craig Fusaro <cfusaro@geoviewinc.com> Subject: Miami Dry Cleaner Boring Clearing

I need a quote to clear 4 drilling locations (SB002, SB003, SB011 and SB013) at the subject site (map attached). Three locations are inside through concrete and one is outside through grass. We have located and drilled at these locations before.

Thanks Douglas J. McGlone | Principal Geologist | douglas.mcglone@arcadis.com Arcadis | Arcadis U.S., Inc.

7000 North Federal Hwy. Boca Raton, Florida 33487 | USA T. +1 561 393 6555 | C. +1 561 662 7978

Connect with us! www.arcadis.com | LinkedIn | Twitter | Facebook

Be green, leave it on the screen.

This email and any files transmitted with it are the property of Arcadis and its affiliates. All rights, including without limitation copyright, are reserved. This email contains information that may be confidential and may also be privileged. It is for the exclusive use of the intended recipient(s). If you are not an intended recipient, please note that any form of distribution, copying or use of this communication or the information in it is strictly prohibited and may be unlawful. If you have received this communication in error, please return it to the sender and then delete the email and destroy any copies of it. While reasonable precautions have been taken to ensure that no software or viruses are present in our emails, we cannot guarantee that this email or any attachment is virus free or has not been intercepted or changed. Any opinions or other information in this email that do not relate to the official business of Arcadis are neither given nor endorsed by it.

SITE LINES PROPOSAL ACCEPTANCE

SIGNATURE PAGE

Site Lines Proposal Number: 01556p Proposal Date: November 20, 2024

Project Site: Miami Dry Cleaners Site – 8410 West Flagler Street, Miami, FL

Project Fee: $900.00

Payment Terms: [PAYABLE WITHIN 30-DAYS OF INVOICE]

INVOICE TO:

Client: ARCADIS Address: 1500 Gateway Blvd., Suite 200, Boynton Beach, FL 33426 Attention: Douglas J. McGlone, P.G.

Phone: 561-662-7978 Email: Douglas.McGlone@ARCADIS.com

Special Instructions:

In witness thereof, the parties hereto have made and executed this agreement

FOR [CLIENT] FOR SITE LINES LLC

Signature: Signature:

By: By: William L. Hardy II

Title: Title: President

Date Signed: Date Signed: November 20, 2024