CN-370000-HW680-DC031C.pdf
PDF 593 KB Posted
- Contract number
- HW680
- Issued by
- Florida
About this file
This is a Task Assignment (TA) DC031C issued by the State of Florida Department of Environmental Protection (FDEP) to Arcadis U.S., Inc. for operation and maintenance (O&M) activities at the Rivergate Drycleaners site located at 1193 SE Port St. Lucie Boulevard, Port St. Lucie, St. Lucie County, Florida. The task assignment is issued pursuant to Contract Number HW680 and is effective through September 30, 2025. The Department Project Manager is Theresa Pepe (850-245-8966), and the Contractor's Project Manager is Gus Suarez (813-205-4703).
The task assignment requires Arcadis to conduct six months of O&M activities according to the February 20, 2025 Work Plan, including soil vapor extraction (SVE) system monitoring, quarterly vapor sampling, semi-annual and quarterly reporting, and utilities management. The total task assignment value is $26,268.87, comprised of a fixed unit rate of $23,568.87 for labor and services, and cost reimbursement of $2,700.00 for utilities. Payment is structured as follows: Quarter 1 consists of a semi-annual O&M report ($10,979.15) and three months of utilities with a $1,350.00 cost plus fixed fee and $60 handling fee ($1,410.00); Quarter 2 consists of a quarterly O&M email update and project management ($12,469.72) and three months of utilities ($1,410.00). The utilities portion is the only cost-plus component of the task assignment, with actual charges to be invoiced and any remainder adjusted at the end of the assignment. All work is subject to FDEP approval prior to invoice payment.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
Additional signatures attached on separate page.
HW680
DC031C Completion September 30, 2025
Arcadis will conduct six months of O&M activities at the site. Work will be performed according to the February 20, 2025, Work Plan submitted by Arcadis.
The payment of utility invoices is the only portion of this Task Assignment that is Cost Plus.
Theresa Pepe 850-245-8966 Contractor Arcadis U.S. Inc. Contractor
Contractor Gus Suarez Contractor 813-205-4703
ERIC_5413
1193 SE Port St. Lucie Blvd, Port St. Lucie, St. Lucie County
Rivergate Drycleaners
Contractor Contractor
✔ $ 23,568.87 ✔ $ 2,700.00
$ 26,268.87
Scope of Work
Arcadis U.S. Inc.
Contractor Gus Suarez
Contract Manager
Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.
Date: 2025.02.21 13:37:59 -05'00'
Mubeen Darji
Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.
Date: 2025.02.21 11:52:18 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Quarter 1 - Semi-Annual O&M report 05/30/2025
3 months Utility Invoices 05/30/2025
Quarter 2 - Quarterly O&M email update/Project Management 08/29/2025
3 months utility invoices 08/29/2025
FDEP approval of Quarter 1 - Semi-Annual O&M report $ 10,979.15
FDEP approval of 3 months utility invoices Utilities (Cost Plus Fixed Fee) = not to exceed $1,350.00 Utilities Handling Fee = $60
$ 1,410.00
FDEP approval of Quarter 2 - Quarterly O&M email update/Project Management $ 12,469.72
FDEP approval of 3 months utility invoices Utilities (Cost Plus Fixed Fee)= not to exceed $1,350.00 Utilities Handling Fee = $60
$ 1,410.00
$ 26,268.87
HW680
DC031C
FFLORIDA DEPARTMENT OF
EEnvironmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
SShawn Hamilton Secretary
Memorandum
TO: Negotiation File Rivergate Drycleaners
FACID NO. 56-9501255; ERIC_5413
Port St. Lucie, St. Lucie County FROM: Theresa Pepe, Project Manager SUBJECT: Task Assignment DC031C (HW680) DATE: February 20, 2025
Task Assignment DC031C is for six months of O&M activities at Rivergate Drycleaners.
Additional information is described in the February 20, 2025, Work Plan from Doug McGlone of Arcadis.
The final task assignment equals $26,268.87. Arcadis may invoice according to the attached schedule.
Specific negotiated subtasks are as follows:
Subtask 1: Project Management This subtask is calculated automatically based on a percentage of total labor.
Subtask 2: Quarterly O&M & Reporting A signed access form was obtained from the current property owner in December 2019.
This subtask provides costs for one quarter of O&M including vapor sampling. A semi-annual report will be submitted to FDEP summarizing the above data.
Subtask 3: Quarterly O&M & Reporting This subtask provides costs for one quarter of O&M including vapor sampling. An email update will be submitted to FDEP summarizing the above data.
Subtask 4: Utilities This subtask provides costs for six months of utilities and associated handling fees.
Arcadis will only invoice for actual charges and any remainder will be adjusted at the end of the Task Assignment.
FDEP COST ESTIMATE
Contractor: Arcadis, U.S., Inc.
Date: 2/20/2025
Task #: SubTask 1 Project Management
Site: Rivergate Dry Cleaners SubTask 2 Y1 Q2 O&M
Activity/Phase: O&M SubTask 3 Y1 Q3 O&M
Project Manager: Doug McGlone SubTask 4 Utilities
SubTask 5
TTotals 1 2 3 4 5 Labor Rate Category
$70.09 Project Manager McGlone, Douglas (DMc) 11 11.2 $100.00 Principal Engineer Bedessem, Jim (JMB) 0 0 0 0 0
$70.09 Principal Scientist McGlone, Douglas (DMc) 11 6 5 0 0 $50.00 Project Engineer Hays, Timothy (TH) 28 15 13 0 0 $44.00 Staff Scientist Riley, Joel (JR) 74 37 37 0 0 $39.67 Drafter/Designer Oliva, Brian (BO) 10 6 4 0 0 $38.28 Project Assistant McLemore, Michele (MMc) 6 3 3 0 0
Total Hours 140 11 67 62 0 0
Direct Labor $6,840.31 $786.94 $3,151.40 $2,901.97 $0.00 $0.00
Overhead 79.00% $5,403.85 $621.68 $2,489.61 $2,292.56 $0.00 $0.00 Gen & Admin 36.00% $2,462.51 $283.30 $1,134.50 $1,044.71 $0.00 $0.00 Fringe 37.10% $2,537.75 $291.95 $1,169.17 $1,076.63 $0.00 $0.00 Total Labor $17,244.42 $1,983.87 $7,944.68 $7,315.87 $0.00 $0.00
Travel Vehicle Rental $720.00 $360.00 $360.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $720.00 $360.00 $360.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $2,700.00 $0.00 $0.00 $2,700.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $2,700.00 $0.00 $0.00 $2,700.00 $0.00 Handling Fee $120.00 $0.00 $0.00 $120.00 $0.00 Total Subcontractor Cost $2,820.00 $0.00 $0.00 $2,820.00 $0.00
Laboratory Analytical Costs $400.00 $200.00 $200.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $300.00 $150.00 $150.00 $0.00 $0.00 Total Laboratory $700.00 $350.00 $350.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $240.00 $120.00 $120.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $660.00 $330.00 $330.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) -MAGS, recon, etc. $2,160.00 $1,080.00 $1,080.00 $0.00 $0.00 Total Field Expenses $3,060.00 $1,530.00 $1,530.00 $0.00 $0.00
Subtotal $24,544.42 $1,983.87 $10,184.68 $9,555.87 $2,820.00 $0.00 Completion Fee $1,724.45 $198.39 $794.47 $731.59 $0.00 $0.00
Total Estimated Cost $26,268.87 $2,182.26 $10,979.15 $10,287.46 $2,820.00 $0.00
REV: 02/03 CEF ARCADIS Page 1
SITE : Rivergate Dry Cleaners
SUBTASK 2: Y1 Q2 O&M
DATE: 2/20/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Y1 Q2 O&M Pricipal / DMc Verification of property ownership; field event preparation, utilities 6 Staff Scientist / JR Prep for fieldwork (1 hr), mob/demob (2 hrs x 3); 3 months O&M, vapor sampling (30 hrs) 37 Project Engineer (TH) Report results, system performance, report prep/submittal 15 Project Asst - MMc Field notes processing, field support 3 Drafter/Designer (BO) Figure production for email update 6
TOTAL LABOR 67
VEHICLE TYPE RATE UNIT USEAGE
Van/Truck $120.00 Per Day 3 $360.00 $360.00
TOTAL VEHICLE $360.00
PER DIEM STAFF RATE UNIT USEAGE
Meals Staff Scientist / JR Category/Staff Rate Unit Usage Totals
$36.00 Per Day 0 $0.00 $36.00 Per Day 0 $0.00
Hotel Category/Staff Rate Unit Usage Totals
Staff Scientist / JR $150.00 Per Day 0 $0.00 $150.00 Per Day 0 $0.00
Total Meal/Hotel: $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Services Procurement
Name Purpose Rate Units Usage Totals Lump Sum $0.00
Enviroserve IDW $198.00 Drum 0 $0.00
Total Services: $0.00
TOTAL $0.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOC Soil Vapor TO-15 Vapor $200.00 1.00 1 $200.00 TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $200.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 1 $150.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $150.00
TOTAL LAB $350.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage Totals Total PPE: $0.00
Expendables Miscellaneous Expendables $40.00 Per Day 3 $120.00
Total Expendables: $120.00 Equipment Items PID (ppbRae) $110.00 Per Day 3 $330.00
Total Equipment Items: $330.00 Equipment Kits Construction/O&M/Pilot Test Kit $360.00 Day 3 $1,080.00
Total Equipment Kits: $1,080.00
TOTAL EQUIPMENT $1,530.00
SITE : Rivergate Dry Cleaners
SUBTASK 3: Y1 Q3 O&M
DATE: 2/20/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
PFAS Reporting Principal / DMc Verification of property ownership; field event preparation, utilities 5 Staff Scientist / JR Prep for fieldwork (1 hr), mob/demob (2 hrs x 3); 3 months O&M, vapor sampling (30 hrs) 37 Project Engineer (TH) Report results, system performance, prep email 13 Drafter / BO Figures production for O&M update 4 Project Asst - MMc Process field notes, submittals 3
TOTAL LABOR 62
VEHICLE TYPE RATE UNIT USEAGE
Van/Truck $120.00 Per Day 3 $360.00 $360.00
TOTAL VEHICLE $360.00
SUBCONTRACTOR COSTS
Services Procurement
Name Purpose Rate Units Usage Totals Drum $0.00
Total Services: $0.00
TOTAL $0.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOC Soil Vapor TO-15 Vapor $200.00 1.00 1 $200.00 TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $200.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 1 $150.00
Total Shipping: $150.00
TOTAL LAB $350.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage Totals Total PPE: $0.00
Expendables Miscellaneous Expendables $40.00 Per Day 3 $120.00
Total Expendables: $120.00 Equipment Items PID (ppbRae) $110.00 Per Day 3 $330.00
Total Equipment Items: $330.00 Equipment Kits Construction/O&M/Pilot Test Kit $360.00 Day 3 $1,080.00
Total Equipment Kits: $1,080.00
TOTAL EQUIPMENT $1,530.00
SITE : Rivergate SUBTASK 4: Utilities
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
VOH Monitoring Pricipal / DMc 0
Staff Scientist / JR Project Asst - MMc
TOTAL LABOR 0
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 0 $0.00 $0.00
Van/Truck $120.00 Per Day 0 $0.00 $0.00
TOTAL VEHICLE $0.00
SUBCONTRACTOR COSTS
Equipment Procurement
Name Equipment Rate Units Usage Totals $0.00 Per Day 0 $0.00
Total Equip.: $0.00 Services Procurement
Name Purpose Rate Units Usage Totals NAME OF COMPANY Utilities -Telemetry $450.00 Per Month 6 $2,700.00
Handling Fee $20.00 Per Month 6 $120.00
Total Services: $2,820.00
TOTAL $2,820.00
LABORATORY COSTS
Analytical Costs
TOTAL LAB $0.00
EQUIPMENT
Personal Protection
TOTAL EQUIPMENT $0.00
This proposal and its contents shall not be duplicated, used or disclosed — in whole or in part — for any purpose other than to evaluate the proposal. This proposal is not intended to be binding or form the terms of a contract. The scope and price of this proposal will be superseded by the contract. If this proposal is accepted and a contract is awarded to Arcadis as a result of — or in connection with — the submission of this proposal, Arcadis and/or the client shall have the right to make appropriate revisions of its terms, including scope and price, for purposes of the contract. Further, client shall have the right to duplicate, use or disclose the data contained in this proposal only to the extent provided in the resulting contract.
arcadis.com C:\Users\pepe_t\Desktop\Rivergate SVE 2025 OMM Proposal_022025.docx
Page:
1/3
Ms. Theresa Pepe, Contract Manager Hazardous Waste Cleanup Section Florida Department of Environmental Protection Bob Martinez Center, MS 4520 2600 Blair Stone Road Tallahassee, Florida 32399-2400
Subject:
Proposal for Six Months of Operation and Maintenance Rivergate Dry Cleaner (ERIC_5413), 1193 SE Port Saint Lucie Blvd, Port Saint Lucie, Florida
Dear Ms. Pepe:
Arcadis U.S., Inc. (Arcadis) is pleased to submit this proposal/cost estimate for the Rivergate Dry Cleaner Site, located in Port Saint Lucie, Saint Lucie County, Florida. This proposal includes operation, maintenance and monitoring (OM&M) of the soil vapor extraction (SVE) system for six months (February 2025 – July 2025), vapor sampling, one semi-annual remedial action status report and one e-mail update. This proposal includes a description of the proposed scope of services, and an estimated cost and schedule for their completion.
TASK 1: PROJECT MANAGEMENT
As specified by FDEP, project management is calculated automatically in the CEF as the first subtask.
TASK 2 THROUGH TASK 3: GENERAL OM&M ACTIVITIES
In accordance with the approved ISRWP, the SVE system’s performance will be monitored monthly for six months (February 2025 – July 2025). The following will be performed during each monthly event:
The ROI of the SVE system will be measured by sequentially isolating the
SVE wells and measuring the vacuum influence of the nearby SVE or monitor wells.
Vapor extraction flow rate and vacuums will be recorded using meters and gauges located within the system. Adjustments will be made as necessary to optimize system performance.
ENVIRONMENTAL
Date:
February 20, 2025
Contact:
Doug McGlone
Phone:
561.662.7978
Email:
Douglas.mcglone@arcadis.com
Our ref:
30200784
Florida License Numbers
Engineering
Geology
GB564
Surveying
LB7062
The extraction blower will be inspected and adjusted for proper operation, including periodic oil changes, grease, and filter replacement.
The SVE system will be operated to minimize the capture and entrainment of groundwater.
The system interlocking controls and fail-safe mechanisms will be inspected for proper operation
Recovered vapors from the SVE system will be monitored quarterly. The SVE vapor sample will be collected from system influent to calculate mass removal.
TASK 2: SVE SYSTEM OM&M YEAR 1 QUARTER 2 (FEBRUARY THROUGH
APRIL 2025)
Task 2 consists of system monthly OM&M visits for one quarter and semi-annual reporting. The SVE vapor sample will be collected from system influent to calculate mass removal.
A Semi-Annual OM&M Report will be submitted at the completion of the quarter and include six months of system operational data (i.e., November 2024 through April 2025). The semi-annual report will include results and data analysis of the vapor monitoring events and recommendations to optimize system operation.
TASK 3: SVE SYSTEM OM&M YEAR 1 QUARTER 3 (MAY THROUGH JULY
2025)
Task 3 consists of system monthly OM&M visits for one quarter and quarterly reporting. A vapor sample will be collected from the influent sample port in a Summa™ canister and analyzed for VOHs using EPA Method TO-15 to calculate mass removal.
A Quarterly email update consisting of tables and figures will be submitted to the FDEP following the July 2025 OM&M event.
TASK 4: UTILITIES MANAGEMENT
This task will be used to manage and process FPL invoices for six months of system operation included in this proposal. Based upon prior FPL invoices, it is anticipated that the utility budget be estimated at $450 per month. A monthly handing fee of $20 per month is also included. Actual utility costs will be invoiced, and any differences will be adjusted through Task Assignment Change Orders.
SCHEDULE
Arcadis will begin implementing the OM&M activities in February 2025 upon receipt of a Task Assignment (TA) from the FDEP. The following deliverables and estimated timeframe for completion are included below:
Deliverable Anticipated Submittal
Date
Year 1 Quarter 1 & 2 Semi-Annual Remedial Action System Status Report May 2025
Year 1 Quarter 3 Email Update August 2025
CLOSING REMARKS
Arcadis appreciates the opportunity to assist the FDEP at this site. If you have any questions or wish to discuss this proposal, please do not hesitate to contact us.
Sincerely, Arcadis U.S., Inc.
Doug McGlone, P.G.
Principal Scientist.
Enclosures:
CEF-LOE
File details come from the government source that posted it. Updated .