CN-370000-HW680-DC004B.pdf
PDF 1 MB Posted
- Contract number
- HW680
- Issued by
- Florida
About this file
This document is a Task Assignment (TA) issued by the State of Florida Department of Environmental Protection (FDEP) to Arcadis U.S., Inc. for operation and maintenance activities at the Aristocrat Cleaners site located at 6745 Pembroke Road, Pembroke Pines, Broward County, Florida. The Task Assignment number is DC004B under Contract HW680, with an effective completion date of May 31, 2023. The project is managed by Theresa Pepe for FDEP and Gus Suarez for Arcadis U.S., Inc.
The contract encompasses six months of operation and maintenance (O&M) activities for a soil vapor extraction (SVE) system, including quarterly monitoring, vapor sampling, and reporting. The scope includes four subtasks: Project Management (calculated automatically as a percentage of total labor), Quarterly O&M and reporting for Year 4 Quarter 3 (October-December 2022), Quarterly O&M and reporting for Year 4 Quarter 4 (January-March 2023), and Utilities management. The total task assignment value is $17,049.39, consisting of a fixed unit rate of $15,249.39 and cost reimbursement of $1,800.00 for utilities. The cost reimbursement component is limited to utility invoices with an associated handling fee. Deliverables include a Year 4 Quarter 3 email update due January 27, 2023, three months of utility invoices due February 3, 2023, and a Year 4 Quarter 3 & 4 Semi-Annual O&M report due April 28, 2023, with additional utility invoices due May 5, 2023. Arcadis will invoice according to an attached schedule, and any actual utility costs exceeding the estimated $1,800.00 will be adjusted through change orders.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW680
DC004B Completion May 31, 2023
Arcadis will conduct six months of O&M activities at the site. Work will be performed according to the September 22, 2022, Work Plan submitted by Arcadis.
The payment of utility invoices is the only portion of this Task Assignment that is Cost Plus.
Theresa Pepe 850-245-8966 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Arcadis U.S. Inc.
Arcadis U.S. Inc.
Gus Suarez 813-205-4703
ERIC_4071
6745 Pembroke Rd, Pembroke Pines, Broward County
Aristocrat Cleaners
✔ $ 15,249.39 ✔ $ 1,800.00
$ 17,049.39
Scope of Work
Gus Suarez
Contract Manager
Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.
Date: 2022.10.04 10:42:27 -04'00' David Phillips Digitally signed by David Phillips
Date: 2022.10.04 09:27:16 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Year 4, Quarter 3 - O&M email update 01/27/2023
3 months Utility Invoices 02/03/2023
Year 4, Quarter 3 & 4 - Semi-Annual O&M report/Project Management 04/28/2023
3 months utility invoices 05/05/2023
FDEP approval of Year 4, Quarter 3 - O&M email update $ 6,115.77
FDEP approval of 3 months utility invoices Utilities (Cost Plus Fixed Fee) = not to exceed $900.00 Utilities Handling Fee = $60
$ 960.00
FDEP approval of Year 4, Quarter 3 & 4 - Semi-Annual O&M report/Project Management $ 9,013.62
FDEP approval of 3 months utility invoices Utilities (Cost Plus Fixed Fee)= not to exceed $900.00 Utilities Handling Fee = $60
$ 960.00
$ 17,049.39
HW680
DC004B
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: Negotiation File Aristocrat Cleaners
FACID NO. 06-9500381; ERIC_4071
Pembroke Pines, Broward County FROM: Theresa Pepe, Project Manager SUBJECT: Task Assignment DC004B (HW680) DATE: September 30, 2022
Task Assignment DC004B is for six months of O&M at Aristocrat Cleaners. The system will be bumped (two months off and one month on per quarter) with the goal of determining if system shutdown is appropriate. Vapor samples will be collected per WSCS engineer’s recommendation. Additional information is described in the September 22, 2022, Work Plan from Doug McGlone of Arcadis.
The final task assignment equals $17,049.39. Arcadis may invoice according to the attached schedule.
Specific negotiated subtasks are as follows:
Subtask 1: Project Management This subtask is calculated automatically based on a percentage of total labor.
Subtask 2: Quarterly O&M & Reporting An access agreement with the current real property owner was signed in August 2014.
Arcadis and FDEP confirmed that no changes in property ownership have occurred since that date.
This subtask provides costs for one quarter (October - December 2022) of O&M site visits including vapor sampling. One email update will be submitted to FDEP summarizing the above data.
Aristocrat Cleaners ERIC_4071
Subtask 3: Quarterly O&M & Reporting This subtask provides costs for one quarter (January - March 2023) of O&M site visits including vapor sampling. One Semi-annual report will be submitted to FDEP summarizing the above data.
Subtask 4: Utilities This subtask provides costs for six months of utilities and associated handling fees.
Arcadis will only invoice for actual charges and any remainder will be adjusted by change order.
FDEP COST ESTIMATE
Contractor: Arcadis, U.S., Inc.
Date: 9/23/2022
Task #: SubTask 1 Project Management
Site: Aristocrat Cleaners SubTask 2 Y4 Q3 O&M
Activity/Phase: O&M SubTask 3 Y4 Q4 O&M
Project Manager: Doug McGlone SubTask 4 Utilities
SubTask 5
Totals 1 2 3 4 5
Labor Rate Category
$65.11 Project Manager McGlone, Douglas (DMc) 7 6.7
$100.00 Principal Engineer Bedessem, Jim (JMB) 0 0 0 0 0
$65.43 Principal Scientist Burke, Brian (BRB) 0 0 0 0 0
$65.11 Principal Scientist McGlone, Douglas (DMc) 10 5 5 0 0
$44.00 Project Engineer Hays, Timothy (TH) 28 8 20 0 0
$39.34 Staff Scientist Riley, Joel (JR) 26 13 13 0 0
$39.67 Drafter/Designer Oliva, Brian (BO) 8 3 5 0 0
$35.81 Project Assistant McLemore, Michele (MMc) 4 2 2 0 0
Total Hours 83 7 31 45 0 0
Direct Labor $3,804.19 $437.65 $1,379.60 $1,986.94 $0.00 $0.00
Overhead 79.00% $3,005.30 $345.74 $1,089.88 $1,569.68 $0.00 $0.00
Gen & Admin 36.00% $1,369.51 $157.55 $496.66 $715.30 $0.00 $0.00
Fringe 37.10% $1,411.35 $162.37 $511.83 $737.15 $0.00 $0.00
Total Labor $9,590.35 $1,103.31 $3,477.97 $5,009.07 $0.00 $0.00
Travel
Vehicle Rental $480.00 $240.00 $240.00 $0.00 $0.00
Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00
Air Fare $0.00 $0.00 $0.00 $0.00 $0.00
Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00
Total Travel $480.00 $240.00 $240.00 $0.00 $0.00
Subcontractor (Equipment Procurement)
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00
Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00
Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement)
Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00
Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00
Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00
Surveying $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $1,800.00 $0.00 $0.00 $1,800.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $1,800.00 $0.00 $0.00 $1,800.00 $0.00
Handling Fee $120.00 $0.00 $0.00 $120.00 $0.00
Total Subcontractor Cost $1,920.00 $0.00 $0.00 $1,920.00 $0.00
Laboratory
Analytical Costs $2,400.00 $1,200.00 $1,200.00 $0.00 $0.00
Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00
Sample Shipping $600.00 $300.00 $300.00 $0.00 $0.00
Total Laboratory $3,000.00 $1,500.00 $1,500.00 $0.00 $0.00
Field Expenses
Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00
Expendables $160.00 $80.00 $80.00 $0.00 $0.00
Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Analytical related) $940.00 $470.00 $470.00 $0.00 $0.00
Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Other) -MAGS, recon, etc. $0.00 $0.00 $0.00 $0.00 $0.00
Total Field Expenses $1,100.00 $550.00 $550.00 $0.00 $0.00
Subtotal $16,090.35 $1,103.31 $5,767.97 $7,299.07 $1,920.00 $0.00
Completion Fee $959.04 $110.33 $347.80 $500.91 $0.00 $0.00
Total Estimated Cost $17,049.39 $1,213.64 $6,115.77 $7,799.98 $1,920.00 $0.00
REV: 02/03 CEF ARCADIS Page 1
SITE : Aristocrat Cleaners
SUBTASK 2: Y4 Q3 O&M
DATE: 9/23/2022
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Y4 Q3 O&M Pricipal / DMc Verification of property ownership; field event preparation, utilities 5 Staff Scientist / JR Prep for fieldwork (1 hr), mob/demob (2 hrs); 1 month O&M, vapor sampling (10 hrs) 13 Project Engineer (TH) Report results, system performance, prep email update 8 Project Asst - MMc Field notes processing, field support 2 Drafter/Designer (BO) Figure production for email update 3
TOTAL LABOR 31
VEHICLE TYPE RATE UNIT USEAGE
Van/Truck $120.00 Per Day 2 $240.00 $240.00
TOTAL VEHICLE $240.00
PER DIEM STAFF RATE UNIT USEAGE
Meals Staff Scientist / JR Category/Staff Rate Unit Usage Totals
$36.00 Per Day 0 $0.00 $36.00 Per Day 0 $0.00
Hotel Category/Staff Rate Unit Usage Totals
Staff Scientist / JR $150.00 Per Day 0 $0.00 $150.00 Per Day 0 $0.00
Total Meal/Hotel: $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Services Procurement
Name Purpose Rate Units Usage Totals Lump Sum $0.00
Enviroserve IDW $198.00 Drum 0 $0.00
Total Services: $0.00
TOTAL $0.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOC Soil Vapor TO-15 Vapor $200.00 1.00 6 $1,200.00 TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $1,200.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 2 $300.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $300.00
TOTAL LAB $1,500.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage Totals Total PPE: $0.00
Expendables Miscellaneous Expendables $40.00 Per Day 2 $80.00
Total Expendables: $80.00 Equipment ItemsTubing, Poly/HDPE $0.30 Per Foot 0 $0.00 PID (ppbRae) $110.00 Per Day 1 $110.0055-gallon Drum $100.00 Each 0 $0.00
Total Equipment Items: $110.00 Equipment KitsSoil Assessment Kit $175.00 Day 0 $0.00 Construction/O&M/Pilot Test Kit $360.00 Day 1 $360.00
Total Equipment Kits: $360.00
TOTAL EQUIPMENT $550.00
SUBTASK 3: Y4 Q4 O&M
DATE: 9/23/2022
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
PFAS Reporting Principal / DMc Verification of property ownership; field event preparation, utilities 5 Staff Scientist / JR Prep for fieldwork (1 hr), mob/demob (2 hrs); 1 month O&M, vapor sampling (10 hrs) 13 Project Engineer (TH) Report results, system performance, prep report 20 Drafter / BO Figures production for report 5 Project Asst - MMc Process field notes, submittals 2
TOTAL LABOR 45
VEHICLE TYPE RATE UNIT USEAGE
Van/Truck $120.00 Per Day 2 $240.00 $240.00
TOTAL VEHICLE $240.00
SUBCONTRACTOR COSTS
Services Procurement
Name Purpose Rate Units Usage Totals Drum $0.00
Total Services: $0.00
TOTAL $0.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOC Soil Vapor TO-15 Vapor $200.00 1.00 6 $1,200.00 TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $1,200.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 2 $300.00
Total Shipping: $300.00
TOTAL LAB $1,500.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage Totals Total PPE: $0.00
Expendables Miscellaneous Expendables $40.00 Per Day 2 $80.00
Total Expendables: $80.00 Equipment Items PID (ppbRae) $110.00 Per Day 1 $110.00
Total Equipment Items: $110.00 Equipment Kits Construction/O&M/Pilot Test Kit $360.00 Day 1 $360.00
Total Equipment Kits: $360.00
TOTAL EQUIPMENT $550.00
SUBTASK 4: Utilities
DATE: 9/23/2022
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
VOH Monitoring
Pricipal / DMc 0
Staff Scientist / JR Project Asst - MMc
TOTAL LABOR 0
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 0 $0.00 $0.00
Van/Truck $120.00 Per Day 0 $0.00 $0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
Meals
Category/Staff Rate Unit Usage Totals
$36.00 Per Day 0 $0.00
$36.00 Per Day 0 $0.00
Hotel
Category/Staff Rate Unit Usage Totals
$150.00 Per Day 0 $0.00
$150.00 Per Day 0 $0.00
Total Meal/Hotel: $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Equipment Procurement
Name Equipment Rate Units Usage Totals $0.00 Per Day 0 $0.00
Total Equip.: $0.00 Services Procurement
Name Purpose Rate Units Usage Totals NAME OF COMPANY Utilities -Telemetry $300.00 Per Month 6 $1,800.00
Handling Fee $20.00 Per Month 6 $120.00
Total Services: $1,920.00
TOTAL $1,920.00
LABORATORY COSTS
Analytical Costs
Parameter Method Media Rate Turn Around Total Samples Totals
Priority Pollutant Organics Full Suite Aqueous $735.00 1.00 0 $0.00
TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00
Rate Units Usage
Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00
Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $0.00
TOTAL LAB $0.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage Totals
Total PPE: $0.00
Expendables
Miscellaneous Expendables $40.00 Per Day 0 $0.00
Total Expendables: $0.00
Equipment ItemsTubing, Poly/HDPE $0.30 Per Foot 0 $0.00
Total Equipment Items: $0.00
Equipment KitsSite Reconnaissance Kit $150.00 Day 0 $0.00
Total Equipment Kits: $0.00
TOTAL EQUIPMENT $0.00
This proposal and its contents shall not be duplicated, used or disclosed — in whole or in part — for any purpose other than to evaluate the proposal. This proposal is not intended to be binding or form the terms of a contract. The scope and price of this proposal will be superseded by the contract. If this proposal is accepted and a contract is awarded to Arcadis as a result of — or in connection with — the submission of this proposal, Arcadis and/or the client shall have the right to make appropriate revisions of its terms, including scope and price, for purposes of the contract. Further, client shall have the right to duplicate, use or disclose the data contained in this proposal only to the extent provided in the resulting contract.
arcadis.com C:\Users\Pepe_T\Desktop\Aristocrat SVE 2022 OMM Proposal_20220209.docx
Page:
1/3
Ms. Theresa Pepe, Contract Manager Hazardous Waste Cleanup Section Florida Department of Environmental Protection Bob Martinez Center, MS 4520 2600 Blair Stone Road Tallahassee, Florida 32399-2400
Subject:
Proposal for Six Months of Operation and Maintenance Former Aristocrat Cleaners (ERIC_4071), 6745 Pembroke Road, Pembroke Pines, Florida
Dear Ms. Pepe:
Arcadis U.S., Inc. (Arcadis) is pleased to submit this proposal/cost estimate for the Former Aristocrat Cleaners Site, located in Pembroke Pines, Broward County, Florida. This proposal includes operation, maintenance and monitoring (OM&M) of the soil vapor extraction (SVE) system for six months (October 2022 - March 2023), vapor sampling, one semi-annual remedial action status report and one e-mail update. This proposal includes a description of the proposed scope of services, and an estimated cost and schedule for their completion.
TASK 1: PROJECT MANAGEMENT
As specified by FDEP, project management is calculated automatically in the CEF as the first subtask.
TASK 2 THROUGH TASK 3: GENERAL OM&M ACTIVITIES
In accordance with the approved ISRWP, the SVE system’s performance will be monitored monthly for six months (October 2022 – March 2023). The following will be performed during each monthly event when system is in operation:
• The ROI of the SVE system will be measured by sequentially isolating the
SVE wells and measuring the vacuum influence of the nearby SVE wells.
Additionally, depending on the seasonal variation in the groundwater table at the site, monitor well MW001 may be utilized to measure the ROI of the SVE wells.
ENVIRONMENTAL
Date:
September 22, 2022
Contact:
Doug McGlone
Phone:
561.662.7978
Email:
Douglas.mcglone@arcadis.com
Our ref:
30063270
Florida License Numbers
Engineering
Geology
GB564
Surveying
LB7062
• Vapor extraction flow rate and vacuums will be recorded using meters and gauges located within the system. Adjustments will be made as necessary to optimize system performance.
The extraction blower will be inspected and adjusted for proper operation, including periodic oil changes, grease, and filter replacement.
• The SVE system will be operated to minimize the capture and entrainment of groundwater.
• The system interlocking controls and fail-safe mechanisms will be inspected for proper operation
Recovered vapors from the SVE system will be monitored quarterly. The SVE vapor sample will be collected from system influent to calculate mass removal.
TASK 2: SVE SYSTEM OM&M YEAR 4 QUARTER 3 (OCTOBER THROUGH
DECEMBER 2022)
Task 2 consists of one monthly OM&M visit and quarterly reporting. The system will be shut down in October and remain off through November 2022. In early December 2022 the system will be restarted.
After approximately one month of operation (late December), vapor samples will be collected from the system influent and five individual SVE wells. Vapor samples will be collected in Summa™ canisters and analyzed for VOHs using EPA Method TO-15.
A quarterly email update consisting of tables and figures will be submitted to the FDEP following the December 2022 OM&M event.
TASK 3: SVE SYSTEM OM&M YEAR 4 QUARTER 4 (JANUARY THROUGH
MARCH 2023)
Task 3 consists of one monthly OM&M visit and semi-annual reporting. The system will be shut down during January and February 2023. The system will be restarted in early March 2023. After approximately one month of operation (late March 2023), vapor samples will be collected from the system influent and five individual SVE wells. Vapor samples will be collected in a Summa™ canisters and analyzed for VOHs using EPA Method TO-15 to calculate mass removal.
A Semi-Annual OM&M Report will be submitted at the completion of the quarter. The semi-annual report will include results and data analysis of the vapor monitoring events and recommendations to optimize system operation or terminate operation.
TASK 4: UTILITIES MANAGEMENT
This task will be used to manage and process FPL invoices for six months of system operation included in this proposal. Based upon prior FPL invoices, it is anticipated that the utility budget be estimated at
$400 per month. A monthly handing fee of $20 per month is also included. Actual utility costs will be invoiced, and any differences will be adjusted through Task Assignment Change Orders.
SCHEDULE
Arcadis will begin implementing the OM&M activities in October 2022 upon receipt of a Task Assignment (TA) from the FDEP. The following deliverables and estimated timeframe for completion are included below:
Deliverable Anticipated Submittal
Date
Year 4 Quarter 3 Email Update Late January 2023
Year 4 Quarter 3 & 4 Semi-Annual Remedial Action System Status Report Late April 2023
CLOSING REMARKS
Arcadis appreciates the opportunity to assist the FDEP at this site. If you have any questions or wish to discuss this proposal, please do not hesitate to contact us.
Sincerely, Arcadis U.S., Inc.
Doug McGlone, P.G.
Principal Scientist.
Enclosures:
CEF-LOE
| HW680_DC004B negsum.pdf |
| Subtask 1: Project Management |
| Subtask 2: Quarterly O&M & Reporting |
| Subtask 3: Quarterly O&M & Reporting |
| Subtask 4: Utilities |
| Aristocrat SVE 2022 OMM Proposal_20220209.pdf |
| task 1: Project Management |
| task 2 through task 3: General OM&M Activities |
| task 2: SVE System OM&M Year 4 Quarter 3 (October through December 2022) |
| task 3: SVE System OM&M Year 4 Quarter 4 (January through March 2023) |
| task 4: Utilities Management |
| Schedule |
| Closing Remarks |
File details come from the government source that posted it. Updated .