This Task Assignment (TA) Number DC015D is executed between the State of Florida Department of Environmental Protection (FDEP) and Arcadis U.S., Inc., a environmental consulting firm. The contract is issued under the underlying Contract Number HW680 and addresses Operation and Maintenance (O&M) activities at the Miami Dry Cleaners facility located at 8410 West Flagler Street, Miami-Dade County, Florida (ERIC_4372). The task assignment is effective through June 28, 2024, with Theresa Pepe serving as the FDEP Project Manager and Gus Suarez representing Arcadis as the Contract Manager.
Arcadis will conduct six months of O&M activities for a soil vapor extraction (SVE) system from November 2023 through April 2024, including monthly site visits, vapor sampling for volatile organic compounds using EPA Method TO-15, system inspections and maintenance, and reporting. The total TA value is $26,062.62, comprised of a fixed unit rate of $23,662.62 and cost reimbursement of $2,400.00 for utilities. The contract includes four subtasks: Project Management (calculated as a percentage of total labor), Quarterly O&M and Reporting for Quarter 1 ($9,093.67), Quarterly O&M and Reporting for Quarter 2 ($14,448.95), and Utilities Management with a cost-plus arrangement not to exceed $1,200.00 per three-month period plus a $60 handling fee. The only portion structured as cost-plus is utility invoices, with all other services on a fixed rate basis. Deliverables include a semi-annual O&M report, quarterly email updates, and processed utility invoices, with invoicing contingent upon FDEP approval of corresponding deliverables.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW680
DC015D Completion June 28, 2024
Arcadis will conduct six months of O&M activities at the site. Work will be performed according to the October 2, 2023, Work Plan submitted by Arcadis.
The payment of utility invoices is the only portion of this Task Assignment that is Cost Plus.
Theresa Pepe 850-245-8966 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Arcadis U.S. Inc.
Arcadis U.S. Inc.
Gus Suarez 813-205-4703
ERIC_4372
8410 West Flagler Street, Miami, Miami-Dade County
Miami Dry Cleaners
✔ $ 23,662.62 ✔ $ 2,400.00
$ 26,062.62
Scope of Work
Gus Suarez
Contract Manager
Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.
Date: 2023.11.01 15:32:18 -04'00'
Kelly Crain
Kelly Crain Digitally signed by Kelly Crain Date: 2023.11.01 14:52:24 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Semi-Annual O&M report 03/01/2024
3 months Utility Invoices 03/15/2024
Quarterly O&M email update/Project Management 06/03/2024
3 months utility invoices 06/14/2024
FDEP approval of Semi-Annual O&M report $ 9,093.67
FDEP approval of 3 months utility invoices Utilities (Cost Plus Fixed Fee) = not to exceed $1,200.00 Utilities Handling Fee = $60
$ 1,260.00
FDEP approval of Quarterly O&M email update/Project Management $ 14,448.95
FDEP approval of 3 months utility invoices Utilities (Cost Plus Fixed Fee)= not to exceed $1,200.00 Utilities Handling Fee = $60
$ 1,260.00
$ 26,062.62
HW680
DC015D
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: Negotiation File Miami Dry Cleaners Facility ID No. 13-9501077; ERIC_4372 Miami, Miami-Dade County FROM: Theresa C. Pepe, Project Manager SUBJECT: Task Assignment DC015D (HW680) DATE: October 31, 2023
Task Assignment DC015D is for six months of O&M activities at Miami Dry Cleaners.
Additional information is described in the October 2, 2023, Work Plan from Doug McGlone of Arcadis.
The final task assignment equals $26,062.62. Arcadis may invoice according to the attached schedule.
Specific negotiated subtasks are as follows:
Subtask 1: Project Management This subtask is calculated automatically based on a percentage of total labor.
Subtask 2: Quarterly O&M & Reporting A site access form was obtained from the owner in August 2017. There has been no change in ownership since this time.
This subtask provides costs for one quarter (November 2023 – January 2024) of monthly O&M site visits including vapor sampling. A Semi-annual report will be submitted to FDEP summarizing the above data.
Subtask 3: Quarterly O&M & Reporting This subtask provides costs for one quarter (February – April 2024) of monthly O&M site visits including vapor sampling. An email update will be submitted to FDEP summarizing the above data.
Miami Dry Cleaners
ERIC_4372
Subtask 4: Utilities This subtask provides costs for six months of utilities and associated handling fees.
Arcadis will only invoice for actual charges and any remainder will be adjusted at the end of the Task Assignment.
FDEP COST ESTIMATEContractor: Arcadis, U.S., Inc.
Date: 10/2/2023
Task #: SubTask 1 Project Management Site: Miami Dry Cleaner SubTask 2 Quarter1 O&M
Activity/Phase: O&M SubTask 3 Quarter 2 O&M Project Manager: Doug McGlone SubTask 4 Utilities
SubTask 5
Totals 1 2 3 4 5 Labor Rate Category
$67.07 Project Manager McGlone, Douglas (DMc) 10 10.4$100.00 Principal Engineer Bedessem, Jim (JMB) 0 0 0 0 0 $67.07 Principal Scientist McGlone, Douglas (DMc) 8 4 4 0 0 $44.00 Project Engineer Hays, Timothy (TH) 29 14 15 0 0 $39.34 Staff Scientist Riley, Joel (JR) 72 24 48 0 0 $39.67 Drafter/Designer Oliva, Brian (BO) 10 4 6 0 0 $37.25 Project Assistant Cruz, Michele (MC) 8 4 4 0 0
Total Hours 137 10 50 77 0 0
Direct Labor $6,033.91 $694.17 $2,136.12 $3,203.62 $0.00 $0.00
Overhead 79.00% $4,766.78 $548.39 $1,687.53 $2,530.86 $0.00 $0.00 Gen & Admin 36.00% $2,172.20 $249.90 $769.00 $1,153.30 $0.00 $0.00 Fringe 37.10% $2,238.58 $257.54 $792.50 $1,188.54 $0.00 $0.00 Total Labor $15,211.47 $1,750.00 $5,385.15 $8,076.32 $0.00 $0.00
Travel Vehicle Rental $720.00 $240.00 $480.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $720.00 $240.00 $480.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Telemetry $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 IDW EnviroServe $0.00 $0.00 $0.00 $0.00 $0.00 Utilities $2,400.00 $0.00 $0.00 $2,400.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $2,400.00 $0.00 $0.00 $2,400.00 $0.00 Handling Fee $120.00 $0.00 $0.00 $120.00 $0.00 Total Subcontractor Cost $2,520.00 $0.00 $0.00 $2,520.00 $0.00
Laboratory Analytical Costs $4,800.00 $2,400.00 $2,400.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $600.00 $300.00 $300.00 $0.00 $0.00 Total Laboratory $5,400.00 $2,700.00 $2,700.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $240.00 $80.00 $160.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $450.00 $150.00 $300.00 $0.00 $0.00 Total Field Expenses $690.00 $230.00 $460.00 $0.00 $0.00
Subtotal $24,541.47 $1,750.00 $8,555.15 $11,716.32 $2,520.00 $0.00 Completion Fee $1,521.15 $175.00 $538.52 $807.63 $0.00 $0.00
Total Estimated Cost $26,062.62 $1,925.00 $9,093.67 $12,523.95 $2,520.00 $0.00
REV: 02/03 CEF ARCADIS Page 1
SITE : Miami Dry Cleaner SUBTASK 2: Quarter1 O&M
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
(Subtask Title) Principal (DMc) PG analysis of data, report and email update 4 Project Engineer (TH) System performance / data trends, report prep/submittal 14 Staff Scientist (JR) Mob (2hrs x 2), month 2 O&M visits (20 hrs), vapor sampling events 24 Staff Scientist (JR) Project Asst (MMc) Process field notes, sample tracking, data entry, report assembly 4 Drafter/Designer(BO) Figures production for email update 4
TOTAL LABOR 50
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 0 $0.00 $0.00 Van/Truck $120.00 Per Day 2 $240.00 $240.00
TOTAL VEHICLE $240.00
PER DIEM STAFF RATE UNIT USEAGE
Meals Category/Staff Rate Unit Usage Totals
$36.00 Per Day 0 $0.00 $36.00 Per Day 0 $0.00
Hotel Category/Staff Rate Unit Usage Totals
$150.00 Per Day 0 $0.00 $150.00 Per Day 0 $0.00
Total Meal/Hotel: $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Equipment Procurement
Name Equipment Rate Units Usage Totals Per Day $0.00
Total Equip.: $0.00 Services Procurement
Name Purpose Rate Units Usage Totals Handling Fee $0.00 Per Month 0 $0.00
Total Services: $0.00
TOTAL $0.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOC TO-15 Vapor $200.00 1.00 12 $2,400.00VOC 8260 Aqueous $150.00 1.00 0 $0.00 TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $2,400.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 2 $300.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $300.00
TOTAL LAB $2,700.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage TotalsPPE Level D $35.00 Per Man Day 0 $0.00 Total PPE: $0.00
Expendables Miscellaneous Expendables $40.00 Per Day 2 $80.00
Total Expendables: $80.00 Equipment Items
Total Equipment Items: $0.00 Equipment KitsSite Reconnaissance Kit $150.00 Day 0 $0.00 Construction/O&M Supplies $75.00 Day 2 $150.00
Total Equipment Kits: $150.00
TOTAL EQUIPMENT $230.00
SUBTASK 3: Quarter 2 O&M
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
(Subtask Title) Principal (DMc) PG analysis of data, report, owner/operator discussions/access, utilities 4
Project Engineer (TH) System performance / data trends, report prep/submittal 15
Staff Scientist (JR) Mob (2hrs x 4), 4 O&M visits (40 hrs), vapor sampling events 48
Project Asst (MMc) Process field notes, sample tracking, data entry, report assembly 4
Drafter/Designer(BO) Figures prodution for O&M report 6
TOTAL LABOR 77
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 0 $0.00 $0.00
Van/Truck $120.00 Per Day 4 $480.00 $480.00
TOTAL VEHICLE $480.00
PER DIEM STAFF RATE UNIT USEAGE
Meals Category/Staff Rate Unit Usage Totals
$36.00 Per Day 0 $0.00
$36.00 Per Day 0 $0.00
Hotel Category/Staff Rate Unit Usage Totals
$150.00 Per Day 0 $0.00
$150.00 Per Day 0 $0.00
Total Meal/Hotel: $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Equipment Procurement
Name Equipment Rate Units Usage Totals $0.00 Per Day 1 $0.00
Total Equip.: $0.00 Services Procurement
Name Purpose Rate Units Usage Totals Handling Fee $0.00 Per Month 0 $0.00
Total Services: $0.00
TOTAL $0.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOC TO-15 Vapor $200.00 1.00 12 $2,400.00TRPH FL PRO Soil $88.00 1.00 0 $0.00
TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $2,400.00 Rate Units Usage
Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 2 $300.00
Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $300.00
TOTAL LAB $2,700.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage TotalsPPE Level D $35.00 Per Man Day 0 $0.00
Total PPE: $0.00 Expendables Miscellaneous Expendables $40.00 Per Day 4 $160.00
Total Expendables: $160.00 Equipment ItemsPID/FID Combo or FID $125.00 Per Day 0 $0.00
Total Equipment Items: $0.00 Equipment Kits
Construction/O&M Supplies $75.00 Day 4 $300.00Soil Sampling Kit (through concrete) $235.00 Day 0 $0.00
Total Equipment Kits: $300.00
TOTAL EQUIPMENT $460.00
SUBTASK 4: Utilities
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
(Subtask Title) Principal (DMc)
Project Engineer (TH)
Staff Scientist (JR)
Staff Scientist (JR)
Project Asst (MMc)
Drafter/Designer(BO)
TOTAL LABOR 0
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 0 $0.00 $0.00
Van/Truck $120.00 Per Day 0 $0.00 $0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
Meals Category/Staff Rate Unit Usage Totals
$36.00 Per Day 0 $0.00
$36.00 Per Day 0 $0.00
Hotel Category/Staff Rate Unit Usage Totals
$150.00 Per Day 0 $0.00
$150.00 Per Day 0 $0.00
Total Meal/Hotel: $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Equipment Procurement
Name Equipment Rate Units Usage Totals $0.00 Per Day 0 $0.00
Total Equip.: $0.00 Services Procurement
Name Purpose Rate Units Usage TotalsNAME OF COMPANY Direct-push services $0.00 Lump Sum 0 $0.00 NAME OF COMPANY Utilities -Telemetry $400.00 Per Month 6 $2,400.00
Handling Fee $20.00 Per Month 6 $120.00
Total Services: $2,520.00
TOTAL $2,520.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples TotalsVOC TO-15 Vapor $200.00 1.00 0 $0.00
TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00 Rate Units Usage
Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00
Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $0.00
TOTAL LAB $0.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage TotalsPPE Level D $35.00 Per Man Day 0 $0.00
Total PPE: $0.00 Expendables Miscellaneous Expendables $40.00 Per Day 0 $0.00
Total Expendables: $0.00 Equipment ItemsPID/FID Combo or FID $125.00 Per Day 0 $0.00
Total Equipment Items: $0.00 Equipment KitsSite Reconnaissance Kit $150.00 Day 0 $0.00
Total Equipment Kits: $0.00
TOTAL EQUIPMENT $0.00
Use or disclosure of information contained on this sheet is subject to the restriction and disclaimer located on the signature page of this document.
Arcadis U.S., Inc.
1500 Gateway Boulevard Suite 200 Boynton Beach Florida 33426 Phone: 561 697 7000 Fax: 561 369 4731 www.arcadis.com
FL Engineering License #7917 FL Geology License #GB564 FL Surveying License #LB7062
1/4
Ms. Theresa Pepe Contract Manager Florida Department of Environmental Protection Bob Martinez Center, MS 4520 2600 Blair Stone Road Tallahassee, Florida 32399-2400
Date: October 2, 2023 Our Ref: 30181206 Subject: Proposal for Six Months of Operation and Maintenance Maimi Dry Cleaner (ERIC_4370), 8410 West Flagler Street, Florida
Dear Ms. Pepe, Arcadis U.S., Inc. (Arcadis) is pleased to submit this proposal/cost estimate for the Miami Dry Cleaner Site, located in Miami, Miami-Dade County, Florida. This proposal includes operation, maintenance and monitoring (OM&M) of the soil vapor extraction (SVE) system for six months (November 2023 – April 2024), vapor sampling, one semi-annual remedial action status report and one e-mail update. This proposal includes a description of the proposed scope of services, and an estimated cost and schedule for their completion. Based upon recent vapor concentrations at Miami DC, pulsing of the system is proposed to determine vapor rebound. The CEF is included as Attachment 1.
TASK 1: PROJECT MANAGEMENT
As specified by FDEP, project management is calculated automatically in the CEF as the first subtask.
TASK 2 THROUGH TASK 5: GENERAL OM&M ACTIVITES
The SVE system’s performance will be monitored monthly for six months (November 2023 – April 2024). The following will be performed during each monthly event:
• The ROI of the SVE system will be measured by sequentially isolating the SVE wells and measuring the vacuum influence of the nearby SVE or monitor wells.
• Vapor extraction flow rate and vacuums will be recorded using meters and gauges located within the system.
Adjustments will be made as necessary to optimize system performance.
The extraction blower will be inspected and adjusted for proper operation, including periodic oil changes, grease, and filter replacement.
• The SVE system will be operated to minimize the capture and entrainment of groundwater.
FDEP
October 2, 2023
Use or disclosure of information contained on this sheet is subject to the restriction and disclaimer located on the signature page of this document. 2/4
• The system interlocking controls and fail-safe mechanisms will be inspected for proper operation.
• During each OM&M visit the SVE wells will be evaluated for mass recovery. Each SVE well will be operated for a minimum of 30 minutes prior to PID reading collection. The three wells with the highest PID reading will be left in operation each month in an effort to increase mass recovery.
Recovered vapors from the SVE system will be monitored monthly, when in operation. SVE vapor samples will be collected from the system influent during each site visit to calculate mass removal and for vapor rebound.
TASK 2: SVE SYSTEM OM&M QUARTER 1 (NOVEMBER 2023 THROUGH JANUARY
2024) Task 2 consists of system monthly OM&M visits for one quarter and semi-annual reporting. The proposed vapor sampling will be sampled for volatile organic compounds (VOCs) for EPA Method TO-15. A summary table for the quarter is included below:
Month Site Visits Samples
November 2023 0-System Off None
December 2023 2-Restart & O&M 12 total samples (Influent, SVE-1 thru SVE-5 – Restart and
O&M)
January 2024 0-System Off None
• The system will remain off in November 2023 and January 2024.
• Two site visits will be conducted in December, the first to restart/balance the system and the second to perform an O&M event.
A Semi-Annual OM&M Report update will be submitted to the FDEP following the January 2024 site visit and include six months of system operational data (August 2023 through January 2024).. The semi-annual report will include results and data analysis of the vapor monitoring events and recommendations to optimize system operation.
TASK 3: SVE SYSTEM OM&M QUARTER 2 (FEBRUARY THROUGH APRIL 2024)
Task 3 consists of system monthly OM&M visits for one quarter and quarterly reporting. The proposed vapor sampling will be sampled for volatile organic compounds (VOCs) for EPA Method TO-15. A summary table for the quarter is included below:
Month Site Visits Samples
February 2024 2-Restart & O&M 6 total samples (Influent, two wells with highest vapor concentrations from Task 2 -Restart and O&M)
March 2024 0-System Off None
October 2, 2023
Use or disclosure of information contained on this sheet is subject to the restriction and disclaimer located on the signature page of this document. 3/4
April 2024 2-Restart & O&M 6 total samples (Influent, two wells with highest vapor concentration from Task 2 -Restart and O&M)
• The system will remain off in March 2024.
• Two site visits will be conducted in February and April, the first to restart/balance the system and the second to perform an O&M event and shutdown the system.
A Quarterly email update consisting of tables and figures will be submitted at the completion of the quarter (i.e., February through April 2024).
TASK 4: UTILITIES MANAGEMENT
This task will be used to manage and process FPL invoices for six months of system operation included in this proposal. Based upon prior FPL invoices, it is anticipated that the utility budget be estimated at $400 per month.
A monthly handing fee of $20 per month is also included. Actual utility costs will be invoiced, and any differences will be adjusted through Task Assignment Change Orders.
SCHEDULE
Arcadis will begin implementing the OM&M activities in November 2023 upon receipt of a Task Assignment (TA) from the FDEP. The following deliverables and estimated timeframe for completion are included below:
Deliverable Anticipated Submittal Date
Semi-Annual Remedial Action Status Report March 2024
Quarter 2 Email Update June 2024
October 2, 2023
This proposal and its contents shall not be duplicated, used or disclosed — in whole or in part — for any purpose other than to evaluate the proposal. This proposal is not intended to be binding or form the terms of a contract. The scope and price of this proposal will be superseded by the contract. If this proposal is accepted and a contract is awarded to Arcadis as a result of — or in connection with — the submission of this proposal, Arcadis and/or the client shall have the right to make appropriate revisions of its terms, including scope and price, for purposes of the contract. Further, client shall have the right to duplicate, use or disclose the data contained in this proposal only to the extent provided in the resulting contract.
www.arcadis.com Miami DC - 6 Month OMM Proposal - 092523
4/4
CLOSING REMARKS
Arcadis appreciates the opportunity to assist the FDEP at this site. If you have any questions or wish to discuss this proposal, please do not hesitate to contact us.
Sincerely, Arcadis U.S., Inc.
Doug McGlone, P.G.
Principal Scientist
Email: douglas.mcglone@arcadis.com Mobile: 561.662.7978
CC. File
Enclosures:
Attachment 1 – CEF LOE
| HW680_DC015D negsum.pdf |
| Subtask 1: Project Management |
| Subtask 2: Quarterly O&M & Reporting |
| Subtask 3: Quarterly O&M & Reporting |
| Subtask 4: Utilities |
| Miami DC - 6 Month OMM Proposal - 092523.pdf |
| TASK 1: PROJECT MANAGEMENT |
| TASK 2 THROUGH TASK 5: GENERAL OM&M ACTIVITES |
| TASK 2: SVE SYSTEM OM&M QUARTER 1 (NOVEMBER 2023 THROUGH JANUARY 2024) |
| TASK 3: SVE SYSTEM OM&M QUARTER 2 (FEBRUARY THROUGH APRIL 2024) |
| TASK 4: UTILITIES MANAGEMENT |
| SCHEDULE |
| CLOSING REMARKS |