CN-370000-HW680-DC14BCO9.pdf
PDF 4 MB Posted
- Contract number
- HW680
- Issued by
- Florida
About this file
Document Summary
This document comprises two Task Assignment Change Orders (TACO #8 and TACO #9) issued by the State of Florida Department of Environmental Protection (FDEP) to Arcadis U.S. Inc. for work at the Dry Cleaning Depot facility (ERIC_4160) in Fort Lauderdale, Broward County, Florida under Contract Number HW680. The project is managed by FDEP Project Manager Theresa Pepe and Arcadis Contract Manager Gus Suarez.
TACO #8, effective April 11, 2024, updated subcontractor costs for downgradient well installations and extended the task completion date from June 7, 2024 to September 5, 2024, adding 90 days to the schedule. The total task assignment value increased from $48,127.18 to $49,426.28. TACO #9, effective April 29, 2024, authorized an additional utility locate for downgradient well installations due to underground utilities discovered at the original drilling location. This change order increased costs by $1,966.13, resulting in a new total of $51,392.39 with no additional time extension. The cost increase was attributed to acquiring GeoView, Inc. as a subcontractor to perform the utility locate at $900.00, with 4 hours of principal-level oversight at $120.00 in vehicle costs and $40.00 in miscellaneous expendables. The invoice schedule itemizes costs across multiple deliverables including site access negotiations ($4,053.01), monitor well installation and sampling ($31,299.10), monitoring and project management ($5,501.89 under TACO #9), ROW permit and access ($8,666.16), and the additional utility locate ($1,872.23 under TACO #9).
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O.
Object Code
Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/17/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:
1. TA Number: TACO Number: Contract Number:
TACO Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department’s Project Manager: Department’s Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Name:
4. There are no changes to the TA compensation.
The compensation of the TA is changed to the amounts indicated below:
Amended Price Price Prior to TACO
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. There are no changes to the TA Expiration Date.
The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).
6. There are no changes to the Attachments.
Attachment ___ is replaced with Attachment -____.
7. No Additional Changes.
Additional Changes:
8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.
IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department
Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature)
Date:
Additional signatures attached on separate page.
DC014B 9 HW680
This change order authorizes an additional utility locate for downgradient well installations.
Theresa Pepe 850-245-8966 Arcadis U.S. Inc.
Gus Suarez 813-205-4703
ERIC_4160
Dry Cleaning Depot
$ 51,392.39 $ 49,426.28
$ 51,392.39 $ 49,426.28
09/05/2024 09/05/2024 0
1 1 9
Arcadis U.S. Inc.
Gus Suarez
Contract Manager
Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.
Date: 2024.04.29 09:24:21 -04'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2024.04.29 09:10:23 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: Negotiation File Dry Cleaning Depot Facility ID No. 06-9502029; ERIC_4160 Fort Lauderdale, Broward County FROM: Theresa C. Pepe, Project Manager SUBJECT: Task Assignment Change Order DC014B-9 (HW680) DATE: April 26, 2024
The original proposed drilling location was discovered to contain numerous underground utilities. An alternate location still within the permit area seems suitable but another utility locate event is required before drilling can safely commence. Further information is found in the April 25, 2024, change order memo from Doug McGlone of Arcadis.
The original total was $49,426.28. Costs are increased by $1,966.13 (rounding error of - 0.02) resulting in a new total of $51,392.39. There is no time change to the task assignment. Arcadis may invoice according to the attached schedule.
Specific negotiated subtasks are as follows:
Subtask 6: Right of Way TACO 2 Geo View is the subcontractor that has been acquired to do the utility locate. They are familiar with the area and are immediately available. No other bids were obtained since the work is urgent in order to accommodate the driller’s schedule.
FDEP COST ESTIMATE
REV: 02/03 CEF ARCADIS Page 1
SITE :
SUBTASK 6: ROW TACO 2
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
(Subtask Title)
Principal (DMc) 4 hrs to oversee private utility locate for offsite property within approved City ROW permit area and approved MOT area 4
Senior Sci 0
Staff Sci 0
Technician 0
TOTAL LABOR 4
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 0 $0.00 $0.00
Van/Truck $120.00 Per Day 1 $120.00 $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
Meals
Category/Staff Rate Unit Usage Totals
$36.00 Per Day 0 $0.00
$36.00 Per Day 0 $0.00
Hotel
Category/Staff Rate Unit Usage Totals
$150.00 Per Day 0 $0.00
$150.00 Per Day 0 $0.00
Total Meal/Hotel: $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Equipment Procurement
Name Equipment Rate Units Usage Totals
$0.00 Per Day 1 $0.00
Total Equip.: $0.00
Services Procurement
Name Purpose Rate Units Usage Totals
Geoview Utility Locate / GPR Survey $900.00 Lump Sum 1 $900.00
Handling Fee $0.00 Per Month 0 $0.00
Total Services: $900.00
TOTAL $900.00
LABORATORY COSTS
Analytical Costs
Parameter Method Media Rate Turn Around Total Samples Totals
TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00
Rate Units Usage
Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00
Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $0.00
TOTAL LAB $0.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage Totals
Total PPE: $0.00
Expendables
Miscellaneous Expendables $40.00 Per Day 1 $40.00
Total Expendables: $40.00
Equipment Items
Total Equipment Items: $0.00
Equipment Kits
Total Equipment Kits: $0.00
TOTAL EQUIPMENT $40.00
SUBTASK 6: ROW TACO 2
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
(Subtask Title)
Principal (DMc) 4 hrs to oversee private utility locate for offsite property within approved City ROW permit area and approved MOT area 4
Senior Sci 0
Staff Sci 0
Technician 0
TOTAL LABOR 4
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 0 $0.00 $0.00
Van/Truck $120.00 Per Day 1 $120.00 $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
Meals
Category/Staff Rate Unit Usage Totals
$36.00 Per Day 0 $0.00
$36.00 Per Day 0 $0.00
Hotel
Category/Staff Rate Unit Usage Totals
$150.00 Per Day 0 $0.00
$150.00 Per Day 0 $0.00
Total Meal/Hotel: $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Equipment Procurement
Name Equipment Rate Units Usage Totals
$0.00 Per Day 1 $0.00
Total Equip.: $0.00
Services Procurement
Name Purpose Rate Units Usage Totals
Geoview Utility Locate / GPR Survey $900.00 Lump Sum 1 $900.00
Handling Fee $0.00 Per Month 0 $0.00
Total Services: $900.00
TOTAL $900.00
LABORATORY COSTS
Analytical Costs
Parameter Method Media Rate Turn Around Total Samples Totals
TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00
Rate Units Usage
Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00
Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $0.00
TOTAL LAB $0.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage Totals
Total PPE: $0.00
Expendables
Miscellaneous Expendables $40.00 Per Day 1 $40.00
Total Expendables: $40.00
Equipment Items
Total Equipment Items: $0.00
Equipment Kits
SITE : Dry Clean Depot SUBTASK 2: Supplemental Assessment
DATE: 4/9/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Supplemental Assessment Pricipal / DMc Property ownership verification and offsite access negotiations (6 hrs), 6 Staff Scientist / JR Prep for fieldwork (1 hr), mob/demob (2 hrs); oversee well installations (30 hrs) 33 Staff Scientist / JR Prep for fieldwork (1 hr), mob/demob (2 hrs); sample 4 wells (4 hrs), survey TOCs (2 hrs), pack/ship (1 hr) 10 Project Asst - MMc Field support 4
TOTAL LABOR 53
VEHICLE TYPE RATE UNIT USEAGE
Van/Truck $120.00 Per Day 4 $480.00 $480.00
TOTAL VEHICLE $480.00
PER DIEM STAFF RATE UNIT USEAGE
Meals Staff Scientist / JR Category/Staff Rate Unit Usage Totals
$36.00 Per Day 0 $0.00 $36.00 Per Day 0 $0.00
Hotel Category/Staff Rate Unit Usage Totals
Staff Scientist / JR $150.00 Per Day 0 $0.00 $150.00 Per Day 0 $0.00
Total Meal/Hotel: $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Services Procurement
Name Purpose Rate Units Usage Totals Lump Sum $0.00
Erwin IDW $125.00 Drum 8 $1,000.00 Earth Tech Drilling Well Installations $22,905.00 Lump Sum 1 $22,905.00
Total Services: $23,905.00
TOTAL $23,905.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOC (Halocarbons Only) 8260 Aqueous $73.00 1.00 4 $292.00 Methane, ethane, ethene RSK175 Aquesus $180.00 1.00 0 $0.00 Total organic carbon EPA 9060 Aquesous $30.00 1.00 0 $0.00 Total dissolved solids SM 2540 Aqueous $16.00 1.00 0 $0.00 TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $292.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 1 $110.00
Total Shipping: $110.00
TOTAL LAB $402.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage Totals Total PPE: $0.00
Expendables Miscellaneous Expendables $40.00 Per Day 4 $160.00
Total Expendables: $160.00 Equipment Items Tubing, Poly/HDPE $0.30 Per Foot 350 $105.00 Tubing, Silicon 3/16x3/8 $3.00 Per Foot 4 $12.00 55-gallon Drum $100.00 Each 1 $100.00
Total Equipment Items: $217.00 Equipment Kits Monitor Well Installation Kit $325.00 Day 1 $325.00 Deep Groundwater Sampling Kit $415.00 Day 1 $415.00
Total Equipment Kits: $740.00
TOTAL EQUIPMENT $1,117.00
SITE : Dry Clean Depot SUBTASK 3: Reporting
DATE: 8/31/2022
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Data Evaluation and Letter Report Principal / DMc Prepare and submit field notes, sample forms, lab report and deliverable to FDEP 4 Staff Scientist / JR Data evaluation and preparation of deliverable 16 Drafter / BO Figures production for report 5 Project Asst - MMc Process field notes, submittals 4
TOTAL LABOR 29
VEHICLE TYPE RATE UNIT USEAGE
Van/Truck $120.00 Per Day 0 $0.00 $0.00
TOTAL VEHICLE $0.00
SUBCONTRACTOR COSTS
Services Procurement
Name Purpose Rate Units Usage Totals Drum $0.00
Total Services: $0.00
TOTAL $0.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOC (Halocarbons Only) 8260 Aqueous $73.00 1.00 0 $0.00 TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00
Total Shipping: $0.00
TOTAL LAB $0.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage Totals Total PPE: $0.00
Expendables Miscellaneous Expendables $40.00 Per Day 0 $0.00
Total Expendables: $0.00 Equipment Items Tubing, Poly/HDPE $0.30 Per Foot 0 $0.00
Total Equipment Items: $0.00 Equipment Kits Deep Groundwater Sampling Kit $415.00 Day 0 $0.00
TOTAL EQUIPMENT $0.00
SUBTASK 4:
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
(Subtask Title)
Principal / DMc Share analytical results with FDEP 1
Senior Sci 0
Staff Scientist / JR Mob/demob (1 hr), collect upt to three potable water samples for analysis (3 hr) , pack/ship samples (1 hr) 5
Technician 0
TOTAL LABOR 6
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 0 $0.00 $0.00
Van/Truck $120.00 Per Day 1 $120.00 $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
Meals
Category/Staff Rate Unit Usage Totals
$36.00 Per Day 0 $0.00
$36.00 Per Day 0 $0.00
Hotel
Category/Staff Rate Unit Usage Totals
$150.00 Per Day 0 $0.00
$150.00 Per Day 0 $0.00
Total Meal/Hotel: $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Equipment Procurement
Name Equipment Rate Units Usage Totals $0.00 Per Day 0 $0.00
Total Equip.: $0.00 Services Procurement
Name Purpose Rate Units Usage Totals
Handling Fee $0.00 Per Month 0 $0.00
Total Services: $0.00
TOTAL $0.00
LABORATORY COSTS
Analytical Costs
Parameter Method Media Rate Turn Around Total Samples Totals VOC 8260 Aqueous $150.00 1.00 0 $0.00
TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00
Rate Units Usage
Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00
Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $0.00
TOTAL LAB $0.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage Totals
Total PPE: $0.00
Expendables
Miscellaneous Expendables $40.00 Per Day 1 $40.00
Total Expendables: $40.00
Equipment Items
Total Equipment Items: $0.00
Equipment Kits
SUBTASK 5:
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
(Subtask Title)
Pricipal / DMc 0
Senior Sci 0
Staff Scientist / JR 2 mobilizations, church negotiations (8 hrs), City of Lauderhill registration and ROW permit negotiations (38 hrs) 46
Project Asst - MMc 0
TOTAL LABOR 46
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 0 $0.00 $0.00
Van/Truck $120.00 Per Day 2 $240.00 $240.00
TOTAL VEHICLE $240.00
PER DIEM STAFF RATE UNIT USEAGE
Meals
Category/Staff Rate Unit Usage Totals
$36.00 Per Day 0 $0.00
$36.00 Per Day 0 $0.00
Hotel
Category/Staff Rate Unit Usage Totals
$150.00 Per Day 0 $0.00
$150.00 Per Day 0 $0.00
Total Meal/Hotel: $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Equipment Procurement
Name Equipment Rate Units Usage Totals Bob's Barricades MOT Plan $861.81 Per Day 1 $861.81
Total Equip.: $861.81 Services Procurement
Name Purpose Rate Units Usage Totals
Site Lines Utility Locate / GPR Survey $800.00 Lump Sum 1 $800.00
$0.00 Lump Sum 0 $0.00 City of Lauderhill ROW Permit ROW Permit $1,579.85 Lump Sum 1 $1,579.85
Total Services: $2,379.85
TOTAL $3,241.66
LABORATORY COSTS
Analytical Costs
Parameter Method Media Rate Turn Around Total Samples Totals
TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00
Rate Units Usage
Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00
Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $0.00
TOTAL LAB $0.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage Totals
Total PPE: $0.00
Expendables
Miscellaneous Expendables $40.00 Per Day 0 $0.00
Total Expendables: $0.00
Equipment Items
Total Equipment Items: $0.00
Equipment Kits
TOTAL EQUIPMENT $0.00
From: McGlone, Douglas To: Pepe, Theresa Subject: DC Depot Offsite Wells Date: Thursday, April 25, 2024 9:41:13 AM Attachments: image001.png image002.png image003.png image004.png image005.png image006.png BCPA Parcel N of Church ROW.pdf BCPA ROW N of Church_DC Depot.pdf
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Theresa, On Tuesday I went down and oversaw the private utility locate for the offsite wells. The proposed are specified for the well is full of utilities (see JPG) and we can’t drill there. The good news is the ROW extends further north and expands to the east (see attached BCPA ROW N od Church). I think we can find a location north of our original location and still be within ROW and still make use of the permit and required MOT. What I think we need to do is another utility locate in the mulch area to the north and south of the bench. I will call you to discuss.
Douglas J. McGlone PG Principal Geologist Arcadis U.S., Inc.
1500 Gateway Blvd., Suite 200 | Boynton Beach, Florida | 33426 | USA M. +1 561.662.7978 www.arcadis.com
Professional Geologist / PG-FL 2405
This email and any files transmitted with it are the property of Arcadis and its affiliates. All rights, including without limitation copyright, are reserved. This email contains information that may be confidential and may also be privileged. It is for the exclusive use of the intended recipient(s). If you are not an intended recipient, please note that any form of distribution, copying or use of this communication or the information in it is strictly prohibited and may be unlawful. If you have received this communication in error, please return it to the sender and then delete the email and destroy any copies of it. While reasonable precautions have been taken to ensure that no software or viruses are present in our emails, we cannot guarantee that this email or any attachment is virus free or has not been intercepted or changed. Any opinions or other information in this email that do not relate to the official business of Arcadis are neither given nor endorsed by it.
From: Craig Fusaro To: McGlone, Douglas; Mike Wightman Cc: Hernandez, Christopher Subject: RE: Dry Clean Depot Date: Thursday, April 25, 2024 2:13:45 PM Attachments: image011.png image013.png image014.png image015.png image016.png image001.png image002.png image004.png image005.png
Arcadis Warning: Exercise caution with email messages from external sources such as this message. Always verify the sender and avoid clicking on links or scanning QR codes unless certain of their authenticity.
Hi Doug
Nice speaking with you. The cost to revisit the site will be $900. I can be at the site late Monday morning and will contact you in the morning to set up a more exact meet time.
Thanks
Craig A. Fusaro Geophysicist |Business Development Manager Southeast Florida Branch Manager Boca Raton, Florida Office: 561-430-5296 Cell: 727-479-6338
GeoView, Inc.
St. Petersburg – Jacksonville – Orlando – Boca Raton – Boston
Providing geophysical services to geological/geotechnical, infrastructure/utility, environmental, archaeological & marine investigations.
From: McGlone, Douglas <Douglas.McGlone@arcadis.com> Sent: Thursday, April 25, 2024 12:43 PM To: Mike Wightman <mwightman@geoviewinc.com>; Craig Fusaro <cfusaro@geoviewinc.com> Cc: Hernandez, Christopher <Christopher.Hernandez@arcadis.com> Subject: RE: Dry Clean Depot www.geoviewinc.com
Mike, Please send me a cost to do a utility locate at this site again. We did it Tuesday morning and found too many utilities to drill safely. We think we have found an alternate location about 50 feet north.
Also please let me know your next availability to redo this job.
Thanks
Douglas J. McGlone PG Principal Geologist Arcadis U.S., Inc.
1500 Gateway Blvd., Suite 200 | Boynton Beach, Florida | 33426 | USA M. +1 561.662.7978 www.arcadis.com
Professional Geologist / PG-FL 2405
From: Mike Wightman <mwightman@geoviewinc.com> Sent: Monday, April 22, 2024 10:11 AM To: McGlone, Douglas <Douglas.McGlone@arcadis.com>; Craig Fusaro <cfusaro@geoviewinc.com> Cc: Hernandez, Christopher <Christopher.Hernandez@arcadis.com> Subject: RE: Dry Clean Depot
Arcadis Warning: Exercise caution with email messages from external sources such as this message. Always verify the sender and avoid clicking on links or scanning QR codes unless certain of their authenticity.
Thanks Doug, We look forward to working with you on this project.
Regards, MJW
Mike Wightman, P.G President, GeoView O: 727-209-2334 C: 813-690-6667 mwightman@geoviewinc.com
From: McGlone, Douglas <Douglas.McGlone@arcadis.com> Sent: Monday, April 22, 2024 10:06 AM
Funding Information:
Org. Code E.O.
Object Code
Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/17/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:
1. TA Number: TACO Number: Contract Number:
TACO Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department�s Project Manager: Department�s Project Manager Phone:
Contractor Name: (Contractor ) ntractor�st �s Project Manager: ontractor�s t�s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Name:
4. There are no changes to the TA compensation.
The compensation of the TA is changed to the amounts indicated below:
Amended Price Price Prior to TACO
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. There are no changes to the TA Expiration Date.
The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).
6. There are no changes to the Attachments.
Attachment ___ is replaced with Attachment -____.
7. No Additional Changes.
Additional Changes:
8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.
IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department
Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature)
Date:
Additional signatures attached on separate page.
DC014B 8 HW680
This change order authorizes updated subcontractor costs for downgradient well installations.
Theresa Pepe 850-245-8966 Contractor Arcadis U.S. Inc. Contractor
Contractor Gus Suarez Contractor 813-205-4703
ERIC_4160
Dry Cleaning Depot
$ 49,426.28 $ 48,127.18
$ 49,426.28 $ 48,127.18
Completion Completion 06/07/2024 09/05/2024 90
1 1 8
Arcadis U.S. Inc.
Contractor
Gus Suarez
Contract Manager
Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.
Date: 2024.04.11 15:41:54 -04'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2024.04.11 15:28:51 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
HW680
DC014B
$ 49,426.28
Site Access negotiations and prep work (subtask 2 partial)
Monitor Well Installation Field Logs, and additional sampling (subtask 2 partial & subtask 4)
Monitoring Report/IDW manifest/Project Management (subtasks 1 & 3)
ROW permit and downgradient access
FDEP approval of Site Access negotiations and prep work (subtask 2 partial) Previously Invoiced
FDEP approval of Annual Monitoring Report/IDW manifest/Project Management (subtasks 1 & 3)
FDEP approval of ROW permit and downgradient access
FDEP approval of Monitor Well Installation Field Logs, and additional sampling (subtask 2 partial & subtask 4)
09/15/2023
05/17/2024
07/19/2024
03/29/2024
$ 31,299.10
$ 4,053.01
$ 5,408.01
$ 8,666.16
File details come from the government source that posted it. Updated .