This document is a Task Assignment (TA) and Task Assignment Change Order (TACO) issued by the State of Florida Department of Environmental Protection (FDEP) to Arcadis U.S. Inc. for environmental remediation work at Donna's Cleaners facility (Facility ID No. 35-9502053; ERIC_4824) located at 1421 W. Main Street, Leesburg, Lake County, Florida. The original task assignment (DC013D) was executed on September 14, 2023, with a completion date of January 26, 2024. Change Order DC013D-1 (TACO Number 1), executed on January 26, 2024, extends the completion date by sixty days to March 26, 2024, to allow for review and approval of deliverables and facilitate discussions regarding remediation pathways.
The scope of work requires Arcadis to conduct annual groundwater monitoring from select wells at the site according to the September 8, 2023, Work Plan submitted by the contractor. The total task assignment value is $20,423.02 on a fixed unit rate basis, with no cost changes resulting from the change order. Deliverables include a Groundwater Monitoring Event (due October 6, 2023) and an Annual Monitoring Report with IDW manifest and project management documentation (due January 19, 2024 under the change order). Invoice payments are contingent upon FDEP approval: $12,049.40 upon approval of the Groundwater Monitoring Event and $8,373.62 upon approval of the Annual Monitoring Report, IDW manifest, and project management deliverables. The project manager for FDEP is Theresa Pepe (850-245-8966), and the contractor's project manager is Gus Suarez (813-205-4703).
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/17/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:
1. TA Number: TACO Number: Contract Number:
TACO Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department’s Project Manager: Department’s Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Name:
4. ☐ There are no changes to the TA compensation.
☐ The compensation of the TA is changed to the amounts indicated below:
Amended Price Price Prior to TACO ☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. ☐ There are no changes to the TA Expiration Date.
☐ The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).
6. ☐ There are no changes to the Attachments.
☐ Attachment ___ is replaced with Attachment -____.
7. ☐ No Additional Changes.
☐ Additional Changes:
8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.
IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
DC013D 1 HW680
This change order authorizes a time extension of sixty days for review and approval.
Theresa Pepe 850-245-8966 Contractor Contractor
Contractor Contractor
Contractor
Arcadis U.S. Inc.
Gus Suarez 813-205-4703
ERIC_4824
Donna's Cleaners
$ 0.00 $ 0.00 Completion
Completion✔ 01/26/2024 03/26/2024 60
✔ 1 1 1
Arcadis U.S. Inc.
Gus Suarez
Contract Manager
Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.
Date: 2024.01.26 09:51:18 -05'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2024.01.26 09:38:15 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 01_18
Contract Number:
Task Assignment #:
Change Order #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
HW680
DC013D
$ 20,423.02
Groundwater Monitoring Event
Annual Monitoring Report/IDW manifest/Project Management
FDEP approval of Groundwater Monitoring Event
FDEP approval of Annual Monitoring Report/IDW manifest/Project Management
10/06/2023
01/19/2024
$ 8,373.62
$ 12,049.40
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: Negotiation File Donna’s Cleaners Facility ID No. 35-9502053; ERIC_4824 Leesburg, Lake County FROM: Theresa C. Pepe, Project Manager SUBJECT: Task Assignment Change Order DC013D-1 (HW680) DATE: January 24, 2024
Arcadis has submitted the final deliverable. A time extension of sixty days will allow for review and approval of the deliverable. It will also allow time for a teleconference between FDEP and Arcadis to discuss a path forward for remediation at the site.
This change order adds sixty days to the completion date. There is no cost change to the task assignment. Arcadis may invoice according to the attached schedule.
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
Additional signatures attached on separate page.
HW680
DC013D Completion January 26, 2024
Arcadis will conduct annual groundwater monitoring from select wells at the site. All activities will be performed according to the September 8, 2023, Work Plan submitted by Arcadis.
Theresa Pepe 850-245-8966 Contractor Arcadis U.S. Inc. Contractor
Contractor Gus Suarez Contractor 813-205-4703
ERIC_4824
1421 W. Main Street, Leesburg, Lake County
Donna's Cleaners
Contractor Contractor
✔ $ 20,423.02
$ 20,423.02
Scope of Work
Arcadis U.S. Inc.
Contractor Gus Suarez
Contract Manager
Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.
Date: 2023.09.14 15:27:50 -04'00'
Kelly Crain
Kelly Crain Digitally signed by Kelly Crain Date: 2023.09.14 13:59:33 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Groundwater Monitoring Event 10/06/2023
Annual Monitoring Report/IDW manifest/Project Management 12/08/2023
FDEP approval of Groundwater Monitoring Event $ 12,049.40
FDEP approval of Annual Monitoring Report/IDW manifest/Project Management $ 8,373.62
$ 20,423.02