This document is a Task Assignment (TA) issued by the State of Florida Department of Environmental Protection (FDEP) to Arcadis U.S., Inc., a private environmental consulting firm, pursuant to Contract Number HW680. The task assignment pertains to environmental remediation activities at the Plant City Laundry and Cleaners facility located at 401 E Reynolds Street in Plant City, Hillsborough County, Florida (FDEP Facility ID ERIC_4722). The Department Project Manager is Theresa Pepe, and the contractor's Project Manager is Gus Suarez. The task assignment was executed on January 12, 2024, with a completion date of March 29, 2024.
Under this task assignment, Arcadis will conduct a structural and geotechnical review of the coffer dam design for a deeper excavation (73' x 33' x 12') planned at the site and submit a written report of findings to the FDEP Waste Site Cleanup Section. All activities will be performed according to Arcadis's January 11, 2024, Work Plan. The total task assignment value is $1,648.05 on a fixed unit rate basis. The cost includes direct labor (11 hours across multiple staff members including principal engineers and a senior engineer), overhead calculated at 79 percent, general and administrative costs at 36 percent, fringe benefits at 37.1 percent, and a completion fee. The single deliverable is the Design Review report/Project Management, due January 31, 2024, with invoicing upon submittal of the coffer dam review memo. No travel, subcontractor, laboratory, or field equipment costs are included in this estimate.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number) Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
Additional signatures attached on separate page.
HW680
DC044A Completion March 29, 2024
Per FDEP's request, Arcadis will conduct a review of the site's coffer dam design. All activities will be performed according to the January 11, 2024, Work Plan submitted by Arcadis.
Theresa Pepe 850-245-8966 Contractor Arcadis U.S. Inc. Contractor
Contractor Gus Suarez Contractor 813-205-4703
ERIC_4722
401 E Reynolds St, Plant City, Hillsborough County
Plant City Laundry and Cleaners
Contractor Contractor
✔ $ 1,648.05
$ 1,648.05
Scope of Work
Arcadis U.S. Inc.
Contractor Gus Suarez
Contract Manager
Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.
Date: 2024.01.12 13:14:02 -05'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2024.01.12 12:35:57 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Design Review report/Project Management 01/31/2024
Design Review report/Project Management $ 1,648.05
$ 1,648.05
HW680
DC044A
FFLORIDA DEPARTMENT OF
EEnvironmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette NNuñez
Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: Negotiation File Plant City Laundry and Cleaners
FACID NO. 29-9501205; ERIC_4722
Plant City, Hillsborough County FROM: Theresa Pepe, Project Manager SUBJECT: Task Assignment DC044A (HW680) DATE: January 12, 2024
Per the request of the Waste Site Cleanup Program’s engineer, Arcadis U.S. Inc. will perform a review of the coffer dam design for Plant City Laundry. All activities will be conducted in accordance with the January 11, 2024, Work Plan submitted by Gus Suarez of Arcadis.
The final task assignment total is $1,648.05. Arcadis may invoice according to the attached schedule.
Specific negotiated subtasks are as follows:
Subtask 1: Project Management Project Management is automatically calculated as a percentage of total labor.
Subtask 2: Coffer Dam Design Review & Report Signed and sealed design documents have been submitted by another Drycleaning Solvent Cleanup Program contractor. Arcadis will perform a structural/geotechnical review of the documents and submit a written report of their comments to the Waste Site Cleanup Section.
FDEP COST ESTIMATEContractor: Arcadis, U.S., Inc.
Date: 1/11/2024
Task #: SubTask 1 Project Management Site: Coffer Dam Design Review SubTask 2 Coffer Damn Design Review
Activity/Phase: SubTask 3 Project Manager: Gus Suarez SubTask 4
SubTask 5
Totals 1 2 3 4 5 Labor Rate Category
$85.87 Project Manager Suarez, Gus (GS) 1 0.8 $100.00 Principal Engineer Bedessem, Jim (JMB) 0 0 0 0 0 $88.68 Principal Engineer Burtnett, Susan (SB) 1 1 0 0 0 $85.87 Principal Engineer Suarez, Gus (GS) 0 0 0 0 0 $67.57 Principal Engineer Perella, John (JP) 0 0 0 0 0 $50.00 Senior Engineer Cardoso, Antonio (AC) 8 8 0 0 0 $37.25 Project Assistant Cruz, Michele (MC) 1 1 0 0 0
Total Hours 11 1 10 0 0 0
Direct Labor $594.30 $68.37 $525.93 $0.00 $0.00 $0.00
Overhead 79.00% $469.49 $54.01 $415.48 $0.00 $0.00 $0.00 Gen & Admin 36.00% $213.94 $24.61 $189.33 $0.00 $0.00 $0.00 Fringe 37.10% $220.49 $25.37 $195.12 $0.00 $0.00 $0.00 Total Labor $1,498.22 $172.36 $1,325.86 $0.00 $0.00 $0.00
Travel Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $1,498.22 $172.36 $1,325.86 $0.00 $0.00 $0.00 Completion Fee $149.83 $17.24 $132.59 $0.00 $0.00 $0.00
Total Estimated Cost $1,648.05 $189.60 $1,458.45 $0.00 $0.00 $0.00
REV: 02/03 CEF ARCADIS Page 1
SITE : Coffer Dam Design Review SUBTASK 2: Coffer Damn Design Review
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
(Subtask Title) Burtnett, Susan (SB) PE Final Rpt review 1
Cardoso, Antonio (AC) Coffer Dam design review and report memo 8
McLemore, Michele (MMc) Rpt deliverable prep 1
TOTAL LABOR 10
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Equipment Procurement
Name Equipment Rate Units Usage Totals $0.00 Per Day 0 $0.00
Total Equip.: $0.00 Services Procurement
Name Purpose Rate Units Usage Totals Handling Fee $0.00 Per Month 0 $0.00
Total Services: $0.00
TOTAL $0.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $0.00
TOTAL LAB $0.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage Totals Total PPE: $0.00
Expendables Miscellaneous Expendables $40.00 Per Day 0 $0.00
Total Expendables: $0.00 Equipment Items
Total Equipment Items: $0.00 Equipment Kits
Total Equipment Kits: $0.00
TOTAL EQUIPMENT $0.00
Arcadis U.S., Inc.
4300 West Cypress Street Suite 450 Tampa Florida 33607 Phone: 813 903 3100 Fax: 813 903 9115 www.arcadis.com
FL Engineering License #7917 FL Geology License #GB564 FL Surveying License #LB7062
1/2
Ms. Theresa Pepe Florida Department of Environmental Protection Waste Site Cleanup Section 2600 Blairstone Road, MS 4520 Tallahassee, FL 32399-2400
Date: January 11, 2024 Subject: Coffer dam design review Plant City Laundry and Cleaners 401 East Reynolds Street Plant City, Florida FDEP Facility ID:
Contract No.: HW680
Dear Ms. Pepe, Arcadis U.S., Inc. (Arcadis) is pleased to submit the following proposal/cost estimate to provide document review services to the Florida Department of Environmental Protection (FDEP) Waste Management/Waste Site Cleanup Section. This proposal includes the scope of work pursuant to recent communications with FDEP regarding documents prepared for the subject site. An estimate of costs with a schedule for completion is included.
Scope Of Work
Task 1: Project Management This task consists of project management activities in relation to the completion of Task 2.
Task 2: Coffer Dam Design Review and Reporting
Arcadis will perform a structural/geotechnical design review of the documents provided by FDEP. The design was prepared by GHD for the subject site in Plant City, FL. The scope of work at the site includes a large shallow excavation and a small deeper (73’x33’x12’) excavation in the saturated zone of the site. The coffer dam design is for the deeper excavation, thus Arcadis’ review will be focused on that aspect of the site. Arcadis will prepare a report memorandum summarizing the findings of the review.
Ms. Theresa Pepe Florida Department of Environmental Protection January 11, 2024 www.arcadis.com 2024 Coffer Dam Review.Proposal
2/2
Cost Estimate A CEF and a LOE Form are attached for the above scope of work. The total cost to complete this scope of work is $1,648.05 (Attachment 1). Arcadis proposes the following invoicing schedule:
Invoice Amount Milestone
$1,648.05 Submittal of Coffer Dam Review Memo (includes PM)
Closing Remarks Arcadis appreciates the opportunity to assist the FDEP on this site. If you have any questions or wish to discuss this proposal further, please do not hesitate to contact us.
Sincerely, Arcadis U.S., Inc.
Gus Suarez, P.E.
Project Manager
Email: Gus.suarez@aracdis.com Direct Line: 813-353-5778 Mobile: 813-205-4703
Enclosures:
Attachment 1: CEF and a LOF Form