This is a Task Assignment (TA) document DC035C issued under Contract Number HW680 between the State of Florida Department of Environmental Protection (FDEP) and Arcadis U.S., Inc. The task assignment is effective November 3, 2025, with a completion date of January 15, 2026, and pertains to site closure activities at the A&B Cleaners facility located at 6350 W Indiantown Road, Jupiter, Palm Beach County, Florida. The project is identified by FDEP Project Number ERIC_5172 and FACID Number 50-9502143. Key personnel include Theresa Pepe as the FDEP Project Manager and Gus Suarez as the Arcadis Project Manager.

The scope of work involves proper abandonment of eight monitoring and MAG wells that were installed during a previous site assessment, performed in accordance with an October 10, 2025 Work Plan submitted by Arcadis. The task assignment is structured on a fixed unit rate basis with a total value of $6,772.07, comprised of three subtasks: Project Management ($398.74), Site Closure/Well Abandonment ($5,074.68), and Reporting ($1,298.65). The single deliverable is a Well Abandonment/Site Closure Report with Project Management due December 12, 2025, with payment contingent upon FDEP approval. Drilling services were procured through competitive bidding, with Preferred Drilling Solutions selected as the subcontractor at $2,860.00 based on the lowest of three bids received. No funding information was provided in the document.

View the file

Other files

File Type Posted
CN-370000-HW680-DC001C.pdf PDF
CN-370000-HW680-DC002B.pdf PDF
CN-370000-HW680-DC003A.pdf PDF
CN-370000-HW680-DC004A.pdf PDF
CN-370000-HW680-DC004B.pdf PDF
CN-370000-HW680-DC004E.pdf PDF
CN-370000-HW680-DC007A.pdf PDF
CN-370000-HW680-DC008A.pdf PDF
CN-370000-HW680-DC008B.pdf PDF
CN-370000-HW680-DC010C.pdf PDF
CN-370000-HW680-DC011B.pdf PDF
CN-370000-HW680-DC013D.pdf PDF
CN-370000-HW680-DC013E.pdf PDF
CN-370000-HW680-DC013F.pdf PDF
CN-370000-HW680-DC014A.pdf PDF
CN-370000-HW680-DC014B.pdf PDF
CN-370000-HW680-DC014G.pdf PDF
CN-370000-HW680-DC014H.pdf PDF
CN-370000-HW680-DC015B.pdf PDF
CN-370000-HW680-DC015C.pdf PDF
CN-370000-HW680-DC015D.pdf PDF
CN-370000-HW680-DC015E.pdf PDF
CN-370000-HW680-DC016D.pdf PDF
CN-370000-HW680-DC016E.pdf PDF
CN-370000-HW680-DC018A.pdf PDF
CN-370000-HW680-DC019D.pdf PDF
CN-370000-HW680-DC01ACO2.pdf PDF
CN-370000-HW680-DC021C.pdf PDF
CN-370000-HW680-DC022D.pdf PDF
CN-370000-HW680-DC023A.pdf PDF
CN-370000-HW680-DC023C.pdf PDF
CN-370000-HW680-DC024C.pdf PDF
CN-370000-HW680-DC025B.pdf PDF
CN-370000-HW680-DC026A.pdf PDF
CN-370000-HW680-DC026C.pdf PDF
CN-370000-HW680-DC031C.pdf PDF
CN-370000-HW680-DC031D.pdf PDF
CN-370000-HW680-DC032A.pdf PDF
CN-370000-HW680-DC032B.pdf PDF
CN-370000-HW680-DC038A.pdf PDF
CN-370000-HW680-DC038C.pdf PDF
CN-370000-HW680-DC03BCO2.pdf PDF
CN-370000-HW680-DC040C.pdf PDF
CN-370000-HW680-DC040D.pdf PDF
CN-370000-HW680-DC041A.pdf PDF
CN-370000-HW680-DC042B.pdf PDF
CN-370000-HW680-DC052B.pdf PDF
CN-370000-HW680-DC053A.pdf PDF
CN-370000-HW680-DC05ACO1.pdf PDF
CN-370000-HW680-DC05ACO2.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

Additional signatures attached on separate page.

HW680

DC035C Completion January 15, 2026

FDEP has issued a Site Rehabilitation Completion Order for No Further Actions without Institutional Controls. Therefore, Arcadis will properly abandon all remaining wells installed during the Site Assessment. All activities will be performed according to the October 10, 2025, Work Plan submitted by Arcadis.

Theresa Pepe 850-245-8966 Contractor Arcadis U.S. Inc. Contractor

Contractor Gus Suarez Contractor 813-205-4703

ERIC_5172

6350 W Indiantown Rd, Jupiter, Palm Beach County

A&B Cleaners

Contractor Contractor

✔ $ 6,772.07

$ 6,772.07

Scope of Work

Arcadis U.S. Inc.

Contractor Gus Suarez

Contract Manager

Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.

Date: 2025.11.03 12:09:15 -05'00'

Mubeen Darji

Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.

Date: 2025.11.01 11:18:53 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Well Abandonment/Site Closure Report & Project Management 12/12/2025

FDEP approval of Well Abandonment/Site Closure Report & Project Management $ 6,772.07

$ 6,772.07

HW680

DC035C

FFLORIDA DEPARTMENT OF

EEnvironmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jay Collins

Lt. Governor

Alexis A. Lambert Secretary

Memorandum

TO: Negotiation File A & B Cleaners

FACID NO. 50-9502143; ERIC_5172

Jupiter, Palm Beach County FROM: Theresa C. Pepe, Project Manager SUBJECT: Task Assignment DC035C (HW680) DATE: October 20, 2025

The site qualified for No Further Action without Engineering or Institutional Controls according to Chapter 62-780.680(1) F.A.C. FDEP issued a Site Rehabilitation Completion Order (SRCO) on September 29, 2025. Therefore, Arcadis U.S., Inc. will properly abandon all remaining wells to close out the site. Work will be performed as described in the October 10, 2025, Work Plan from Doug McGlone of Arcadis.

The final task assignment total is $6,772.07. Arcadis may invoice according to the attached schedule.

Specific negotiated subtasks are as follows:

Subtask 1: Project Management Project Management is automatically calculated based on a percentage of total labor.

Subtask 2: Site Closure/Well Abandonment This subtask provides costs for abandoning five monitoring wells and three MAGS wells installed during the site assessment. This includes both interior and exterior wells.

Preferred Drilling Solutions was chosen as the drilling subcontractor based on their low bid of three bids solicited.

Subtask 3: Reporting Arcadis will submit a brief report and site photos to document the above activities.

FDEP COST ESTIMATEContractor: Arcadis, U.S., Inc.

Date: 10/10/2025

Task #: SubTask 1 Project Management

Site: SubTask 2 Well Abandonment

Activity/Phase: Well Abandonment SubTask 3 Reporting

Project Manager: Theresa Pepe SubTask 4

SubTask 5

TTotals 1 2 3 4 5 Labor Rate Category

$89.78 Principal Engineer Suarez, Gus (GS) 1.6 $73.45 Principal Engineer Perella, John (JFP) 0 0 0 0 0 $73.04 Principal Scientist McGlone, Douglas (DMc) 4 3 1 0 0 $50.00 Senior Engineer Hays, Timothy (TPH) 0 0 0 0 00 0 0 0 0 $39.34 Staff Engineer Tran, Thuy-Min (MT) 6 0 6 0 0 $34.89 Technician Fox, Brian (BF) 12 12 0 0 0 $39.67 Drafter/Design Oliva, Brian (BO) 2 0 2 0 00 0 0 0 0 $39.94 Project Assistant Cruz, Michele (MC) 2 0 2 0 0

$0.00 0 0 0 0 0 $0.00 0 0 0 0 0

Total Hours 28 1.6 15.0 11.0 0.0 0.0

Direct Labor $1,249.89 $143.79 $637.80 $468.30 $0.00 $0.00

Overhead 79.00% $987.41 $113.59 $503.86 $369.96 $0.00 $0.00 Gen & Admin 36.00% $449.96 $51.76 $229.61 $168.59 $0.00 $0.00 Fringe 37.10% $463.71 $53.35 $236.62 $173.74 $0.00 $0.00 Total Labor $3,150.97 $362.49 $1,607.89 $1,180.59 $0.00 $0.00

Travel Vehicle $120.00 $120.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Meals $0.00 $0.00 $0.00 $0.00 $0.00 Hotel $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $120.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $2,860.00 $2,860.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00

Erwin IDW $0.00 $0.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00 Utility Location $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $2,860.00 $2,860.00 $0.00 $0.00 $0.00 Handling Fee $286.00 $286.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $3,146.00 $3,146.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 Equipment (Drilling Related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $40.00 $40.00 $0.00 $0.00 $0.00

Subtotal $6,456.97 $362.49 $4,913.89 $1,180.59 $0.00 $0.00 Completion Fee $315.10 $36.25 $160.79 $118.06 $0.00 $0.00

Total Estimated Cost $6,772.07 $398.74 $5,074.68 $1,298.65 $0.00 $0.00

A&B Cleaners

REV: 09/25 CEF ARCADIS Page 1

SITE : A&B Cleaners 0 SUBTASK 2: Well Abandonment

DATE: 10/10/25

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Activities and Email Updates Principal / DMc Event coordination, site owner/tenant access, subcontractor agreement 3 Technician / BF Mob/demob (2 hrs), oversee/document well abandonment (10 hrs) 12

TOTAL LABOR 15

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Per Day 0 $0.00 $0.00 Van/Truck $120.00 Per Day 1 $120.00 $120.00

TOTAL VEHICLE $120.00

STAFF RATE UNIT USEAGE

Meals Category/Staff Rate Unit Usage Totals

$36.00 Per Day 0 $0.00 $36.00 Per Day 0 $0.00

Hotel Category/Staff Rate Unit Usage Totals

Hotel charged as Cost Reimbursement $150.00 Per Day 0 $0.00 Provide room rate including taxes & fees $150.00 Per Day 0 $0.00 Exceeds $225 per night, require add info

Total Meal/Hotel: $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

Equipment Procurement

Name Equipment Rate Units Usage Totals $2,000.00 Per Day 0 $0.00

Total Equip.: $0.00 Services Procurement

Name Purpose Rate Units Usage Totals NAME OF COMPANY Direct-push services $0.00 Lump Sum 0 $0.00 PDS Drilling services (DPT, MAG wells, SBs, VPs) $2,860.00 Lump Sum 1 $2,860.00

Total Services: $2,860.00

TOTAL $2,860.00

LABORATORY COSTS

Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals

TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00 Rate Units Usage

Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00

Total Shipping: $0.00

TOTAL LAB $0.00

EQUIPMENT

Personal Protection

Item Rate Unit Usage Totals PPE Level D $35 00 Per Man Day 0 $0 00

Total PPE: $0.00 Expendables Miscellaneous Expendables $40.00 Per Day 1 $40.00

Total Expendables: $40.00 Equipment Items

Total Equipment Items: $0.00 Equipment Kits

Total Equipment Kits: $0.00

Total Equipment Kits: $40.00

SITE : A&B Cleaners 0 SUBTASK 3: Reporting

DATE: 10/10/25

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Activities and Email Updates Principal / DMc PG certification of report 1 Staff Engineer / MT Well abandonment report preparation 6 Project Assistant / MMc Report production/submittal 2 Designer / BO Report figures 2

TOTAL LABOR 11

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Per Day 0 $0.00 $0.00 Van/Truck $120.00 Per Day 0 $0.00 $0.00 Automobile $320 00 Week 0 $0 00 $0 00

TOTAL VEHICLE $0.00

STAFF RATE UNIT USEAGE

Meals Category/Staff Rate Unit Usage Totals

$36.00 Per Day 0 $0.00 $36.00 Per Day 0 $0.00

Hotel Category/Staff Rate Unit Usage Totals

Hotel charged as Cost Reimbursement $150.00 Per Day 0 $0.00 Provide room rate including taxes & fees $150.00 Per Day 0 $0.00 Exceeds $225 per night, require add info

Total Meal/Hotel: $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

Equipment Procurement

Name Equipment Rate Units Usage Totals $2,000.00 Per Day 0 $0.00

Total Equip.: $0.00 Services Procurement

Name Purpose Rate Units Usage Totals Total Services: $0.00

TOTAL $0.00

LABORATORY COSTS

Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals

TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00 Rate Units Usage

Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00

Total Shipping: $0.00

TOTAL LAB $0.00

EQUIPMENT

Personal Protection

Item Rate Unit Usage Totals PPE Level D $35 00 Per Man Day 0 $0 00

Total PPE: $0.00 Expendables Miscellaneous Expendables $40.00 Per Day 0 $0.00

Total Expendables: $0.00 Equipment Items PID/FID Combo or FID $125 00 Per Day 0 $0 00

Total Equipment Items: $0.00 Equipment Kits

Use or disclosure of information contained on this sheet is subject to the restriction and disclaimer located on the signature page of this document.

Arcadis U.S., Inc.

1500 Gateway Boulevard Suite 200 Boynton Beach Florida 33426 Phone: 561 697 7000 Fax: 561 369 4731 www.arcadis.com

FL Engineering License #7917 FL Geology License #GB564 FL Surveying License #LB7062

1/2

Ms. Theresa Pepe, Project Manager Hazardous Waste Cleanup Section Florida Department of Environmental Protection 2600 Blair Stone Road, MS 4520 Tallahassee, Florida 32399-2400

Date: October 10, 2025 Our Ref: 30232877 Subject: Proposal for Well Abandonment Activities

Dear Ms. Pepe, Enclosed is a proposal to complete well abandonment activities at A & B Cleaners (ERIC_5172) – this will include abandoning five (5) monitor wells or piezometers and three (3) MAGs wells; photo documentation of field activities; and reporting these activities to FDEP. A proposed scope of work, schedule, and CEF-LOE are included herein, along with copies of contractor bids.

Scope of Work In accordance with Chapter 62-780 of the Florida Administrative Code (FAC), the following scope of work is proposed:

Task 1 This task is reserved for project management activities.

Task 2 The following site rehabilitation activities are proposed:

Obtaining site access from current operator/owner;

Abandonment of five (5) monitor wells or piezometers;

Abandonment three (3) MAG wells; and

Photographing and documenting activities and providing brief letter report to FDEP.

Theresa Pepe

FDEP

October 8, 2025

This proposal and its contents shall not be duplicated, used or disclosed — in whole or in part — for any purpose other than to evaluate the proposal. This proposal is not intended to be binding or form the terms of a contract. The scope and price of this proposal will be superseded by the contract. If this proposal is accepted and a contract is awarded to Arcadis as a result of — or in connection with — the submission of this proposal, Arcadis and/or the client shall have the right to make appropriate revisions of its terms, including scope and price, for purposes of the contract. Further, client shall have the right to duplicate, use or disclose the data contained in this proposal only to the extent provided in the resulting contract.

www.arcadis.com A&B Well Abandonment Proposal

2/2

Schedule Arrangements will be conducted immediately upon receipt of a Task Assignment (TA) from the FDEP. We currently anticipate that the work can be completed/reported within 45 days of receipt of the TA.

Estimated Cost A Cost Estimate Form and Level of Effort forms (CEF/LOE) that present estimated project costs are presented in the enclosures.

Closing Remarks Arcadis appreciates the opportunity to assist the FDEP in completing the remaining site rehabilitation activities at this site. If you have any questions or wish to discuss this proposal, please contact us.

Sincerely, Arcadis U.S., Inc.

Douglas J. McGlone, P.G.

Senior Hydrogeologist

Email: douglas.mcglone@arcadis.com Mobile: 561-662-7978

Enclosures: CEFLOE

Preferred Drilling Solutions, Inc.

8820 66th St, Pinellas Park, FL 33782

Ph: 727-561-7477 Fax: 727-561-9028 www.pdsflorida.com

Date: 10/6/25 FAC ID#:

*Note: It is against PDS policy to drill in Pea Gravel. Borings in Pea Gravel will be terminated or can proceed solely at the risk of the consultant, DEP or Property Owner

Unit Unit Rate Number of Units Extended Price

Rig Type: Auger/Mud Rotary_____

HSA Drilling & Split Spoon Collection (continuous or 5' intervals) (can be used in conjunction with well installation)

<50 foot boring depth per foot $0.00 50 foot to 100 foot boring depth per foot $0.00 >100 foot boring depth per foot $0.00

Borehole Grouting

4 - inch borehole diameter per foot $0.00 6 - inch borehole diameter per foot $0.00 8 - inch borehole diameter per foot $0.00

1" - 2" Well Installation (includes screen, riser, sand pack, seal and grout)

<50 foot boring depth per foot $0.00 50 foot to 100 foot boring depth per foot $0.00 >100 foot boring depth per foot $0.00

4" Well Installation (includes screen, riser, sand pack, seal and grout)

<50 foot boring depth per foot $0.00 50 foot to 100 foot boring depth per foot $0.00 >100 foot boring depth per foot $0.00

Double Cased Well $0.00

6" Surface Casing per foot $0.00 per well $0.00

1"- 2" Well Abandonment (includes grouting) per foot $15.00 84.0 $1,260.00 3"- 4" Well Abandonment (includes grouting) per foot $0.00 5"- 6" Well Abandonment (includes grouting) per foot $0.00 2' x 2' Well Pad Removal and Patch each $150.00 5 $750.00

Mobilization roundtrip $750.00 1 $750.00

Per Diem per crew / per night $0.00 DOT Approved 55-gal Drum each $0.00 lump sum $100.00 1 $100.00

$0.00

$0.00

$0.00 Standby/Delay/Difficult Access Time per hour $0.00 Additional Development Time per hour $0.00 Additional Decontamination Time per hour $0.00

TOTAL QUOTE PRICE $2,860.00

Project No.:

Signature and Title of Person Submitting Quote: _____________________________________ Rose Hood, Estimating & Scheduling Mgr Date: 10/6/25

Days to Complete Scope of Work: 1

6274 W Indiantown Rd, Palm Beach, Palm Beach County, FL

Well Completion (includes MH w/ cover, concrete pad, locking well cap, DRILLING

MISCELLANEOUS

Permits/Well Completion or Abandonment Reports

Consultant Name: Arcadis

Site Name & Location: Fmr A&B Cleaners

PROPOSED SCOPE OF WORK:

Abandon (8) 1" - 2" wells, depths 4' - 29', total footage: 84', remove pads and manholes, restore grade

Some work indoors, indoor wells to have rig removed & flush patch

Arcadis, Fmr A&B Cleaners, Palm Beach, FL.xlsx

EARTH TECH DRILLING

2703 NW 19TH STREET, POMPANO BEACH, FL 33069

954.974.2424 FAX:954.9742423

Date: 10/6/2025

FAC ID#:

Unit Unit Rate Number of Units Extended Price per foot $14.00 84 $1,176.00 per foot $0.00 per foot $0.00 per foot $0.00 per foot $0.00 each $135.00 8 $1,080.00 roundtrip $550.00 1 $550.00 per crew / per night $0.00 each $80.00 0 $0.00 each $85.00 1 $85.00 each $0.00 each $50.00 0 $0.00 lump sum $0.00

$0.00 per hour $495.00 $0.00

TOTAL QUOTE PRICE $2,891.00

Date: 10/6/2025

Days to Complete Scope of Work: 1 Day

Subcontract Company Name: EARTH TECH DRILLING 954.974.2424

DOT Approved 55-gal Drum

Traffic Safety Cones (Left onsite)

Permits & Well Completion Reports

Debris Disposal

Subcontract Mailing Address: 2703 NW 19th St., Pompano Bch. FL 33069

Signature and Title of Person Submitting Quote: Charles Bucher / Sr. Project Manager

8" - 10" Well Abandonment (includes grouting)

Grout Abandon (3) 2" MAGs = 12' Total - Remove Well Completions and Patch (2 Inside)

DRILLING

MISCELLANEOUS

Standby/Delay/Difficult Access Time

5"- 6" Well Abandonment (includes grouting)

Contractor Name: Arcadis - Doug McGlone - 561 662-7978

Site Name: A & B Cleaners - 6274 W Indiantown Rd - Jupiter, FL

Permits & Well Completion Reports

PROPOSED SCOPE OF WORK:

Mobilization

3"- 4" Well Abandonment (includes grouting)

1"- 2" Well Abandonment (includes grouting)

Per Diem

Rig Type: Well Abandonment

Grout Abandon (5) 1" MW/PZ's = 72' Total - Remove Well Completions and Patch (1 Inside)

Remove Standard Pad/Manhole

16" Well Abandonment (includes grouting)

Monitoring Wells Sparge Wells Horizontal and Vertical Vapor Extraction Wells Geotechnical Drilling Direct Push

Arcadis 10/8/2025 7000 North Federal HWY 206935 Boca Raton, FL 33487

Palm Beach, FL

Douglas McGlone 6278 W. Indiantown Road douglas.mcglone@arcdais.com Palm Beach

561-662-7978 FL

33458

Cascade Rep Contact Information

Scope of Work

Quantity Unit Sales Price Subtotal Mobilization/Demobilization 1 Each 3,200.00$ 3,200.00$ DPT Rig and Crew Daily Rate 2 Day 2,250.00$ 4,500.00$ Per Diem and Lodging (per worker) 4 Man/Day 225.00$ 900.00$ 1" PVC well abandonment 72 Foot 2.00$ 144.00$ 2" PVC well abandonment 12 Foot 2.00$ 24.00$ Patch 8 Each 15.00$ 120.00$ Rubble removal 1 Lump Sum 200.00$ 200.00$ Florida permit 1 Lump Sum 100.00$ 100.00$

Pre-Tax Total

Tax Percentage

Taxes

Quote Total

Contact Name Project Address Email Project City Phone Project State

Cascade will provide a track mounted Geoprobe unit with a 2-man crew to provide the following.

Abandon Eight (8) existing monitoring wells by grouting them in place and destroying the top 5' of casing. All exterior wells we will remove the pads and patch to existing.

The interior wells we will remove the ring and patch with concrete.

Decon all tooling between locations. Decon is included in the day rate.

Cacsade will obtain the abandonment permit.

No union/prevailing wages or additional training is expected.

Work schedule will be daily work hours of 8am - 4:30pm including lunch and safety meetings.

Level D PPE is expected.

Cascade estimates 2 days to complete this project. All quantities are estimates. Actual accrued totals will be invoiced. Day rate includes a crew of 2. Additional crew at the site will require additional charges. Standby time, if accrued, is included in the day rate.

Description

$9,188.00

Account Name Bid Date Address Quote Number

Quote Revision Date

Bill To Account Project Zip

Project Name

Number

Prepared By Email zfordley@cascade-env.comZachary Fordley, Project Manager

This quote is based on information provided by you and is valid for 45 days from the bid date. Unless previously agreed, Cascade requires a 2-week notice prior to mobilization. Your firm is responsible for 1) Obtaining any site specific permits, 2) Locating and clearly marking underground installations or utilities, 3) Furnishing dig Alert numbers at least three working days prior to scheduled start date and proof of private locating services, 4) Obtaining access to site with no overhead wires within 20' of the holes. Cascade Drilling shall not be responsible for damages to underground improvements not clearly and accurately marked. If bedrock, cobbles, flowing sands or other adverse or unsafe drilling conditions are encountered, drilling may continue on a time and materials basis or be terminated at the discretion of Cascade. Additional costs may apply if scope is significantly changed. Well development by others may void some or all of Cascade warranties of workmanship and materials. Prices assume standard labor rates and no work hour restrictions. Due to a volatile pricing environment, Cascade is unable to guarantee the pricing for a period longer than SIX MONTHS from the date of the bid submittal. If the work extends past this DATE, the agreement can be amended to extend the period of performance and address any potential adjustment in pricing resulting from actual increases in costs of labor, materials, and fuel. If you would like to discuss it further, please feel free to reach out to Will Burdette.

$9,188.00