This is a Task Assignment (TA) document DC032C issued under Contract Number HW680 between the State of Florida Department of Environmental Protection (FDEP) and Arcadis U.S. Inc. for environmental remediation services at the Parisian Deluxe Cleaners facility located at 8731 SW 136th Street, Miami, Miami-Dade County, Florida (FACID No. ERIC_4378). The Department Project Manager is Theresa Pepe, and the Contractor's Project Manager is Gus Suarez. The task assignment is effective upon signature and has a completion date of April 10, 2026.

Arcadis will conduct groundwater monitoring from select wells at the site in accordance with the November 11, 2025 Work Plan submitted by Arcadis. The scope includes three subtasks: Project Management (calculated as a percentage of total labor), Groundwater Monitoring (sampling eight monitor wells for drycleaning solvents, measuring water levels to confirm groundwater flow direction, and disposing of investigation-derived waste), and Reporting (preparation of a Groundwater Monitoring Report with recommendations for additional actions). The total Task Assignment Value is $6,704.53 on a fixed unit rate basis. Field activities are scheduled to occur in December 2025, with the deliverable (Monitoring Report/IDW manifest/Project Management) due March 6, 2026 and invoicing contingent upon FDEP approval of the monitoring report and project management documentation. Hours and costs are comparable to past task assignments of similar scope.

View the file

Other files

File Type Posted
CN-370000-HW680-DC001C.pdf PDF
CN-370000-HW680-DC002B.pdf PDF
CN-370000-HW680-DC003A.pdf PDF
CN-370000-HW680-DC004A.pdf PDF
CN-370000-HW680-DC004B.pdf PDF
CN-370000-HW680-DC004E.pdf PDF
CN-370000-HW680-DC007A.pdf PDF
CN-370000-HW680-DC008A.pdf PDF
CN-370000-HW680-DC008B.pdf PDF
CN-370000-HW680-DC010C.pdf PDF
CN-370000-HW680-DC011B.pdf PDF
CN-370000-HW680-DC013D.pdf PDF
CN-370000-HW680-DC013E.pdf PDF
CN-370000-HW680-DC013F.pdf PDF
CN-370000-HW680-DC014A.pdf PDF
CN-370000-HW680-DC014B.pdf PDF
CN-370000-HW680-DC014G.pdf PDF
CN-370000-HW680-DC014H.pdf PDF
CN-370000-HW680-DC015B.pdf PDF
CN-370000-HW680-DC015C.pdf PDF
CN-370000-HW680-DC015D.pdf PDF
CN-370000-HW680-DC015E.pdf PDF
CN-370000-HW680-DC016D.pdf PDF
CN-370000-HW680-DC016E.pdf PDF
CN-370000-HW680-DC018A.pdf PDF
CN-370000-HW680-DC019D.pdf PDF
CN-370000-HW680-DC01ACO2.pdf PDF
CN-370000-HW680-DC021C.pdf PDF
CN-370000-HW680-DC022D.pdf PDF
CN-370000-HW680-DC023A.pdf PDF
CN-370000-HW680-DC023C.pdf PDF
CN-370000-HW680-DC024C.pdf PDF
CN-370000-HW680-DC025B.pdf PDF
CN-370000-HW680-DC026A.pdf PDF
CN-370000-HW680-DC026C.pdf PDF
CN-370000-HW680-DC031C.pdf PDF
CN-370000-HW680-DC031D.pdf PDF
CN-370000-HW680-DC032A.pdf PDF
CN-370000-HW680-DC032B.pdf PDF
CN-370000-HW680-DC038A.pdf PDF
CN-370000-HW680-DC038C.pdf PDF
CN-370000-HW680-DC03BCO2.pdf PDF
CN-370000-HW680-DC040C.pdf PDF
CN-370000-HW680-DC040D.pdf PDF
CN-370000-HW680-DC041A.pdf PDF
CN-370000-HW680-DC042B.pdf PDF
CN-370000-HW680-DC052B.pdf PDF
CN-370000-HW680-DC053A.pdf PDF
CN-370000-HW680-DC05ACO1.pdf PDF
CN-370000-HW680-DC05ACO2.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

Additional signatures attached on separate page.

HW680

DC032C Completion April 10, 2026

Arcadis will conduct groundwater monitoring from select wells at the site. All activities will be performed according to the November 11, 2025, Work Plan submitted by Arcadis.

Theresa Pepe 850-245-8966 Contractor Arcadis U.S. Inc. Contractor

Contractor Gus Suarez Contractor 813-205-4703

ERIC_4378

8731 SW 136th St., Miami, Miami-Dade County

Parisian Deluxe Cleaners

Contractor Contractor

✔ $ 6,704.53

$ 6,704.53

Scope of Work

Arcadis U.S. Inc.

Contractor Gus Suarez

Contract Manager

Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.

Date: 2025.12.09 11:40:34 -05'00'

Mubeen Darji

Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.

Date: 2025.12.09 07:41:29 -05'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Monitoring Report/IDW manifest/Project Management 03/06/2026

FDEP approval of Monitoring Report/IDW manifest/Project Management $ 6,704.53

$ 6,704.53

HW680

DC032C

FFLORIDA DEPARTMENT OF

EEnvironmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jay Collins

Lt. Governor

Alexis A. Lambert Secretary

Memorandum

TO: Negotiation File Parisian Deluxe Cleaners

FACID NO. 13-9501174; ERIC_4378

Miami, Miami-Dade County FROM: Theresa Pepe, Project Manager SUBJECT: Task Assignment DC032C (HW680) DATE: November 18, 2025

Arcadis U.S. Inc. will perform groundwater monitoring from select wells at the site per the recommendation of the Waste Site Cleanup Section geologist. All activities will be conducted in accordance with the November 11, 2025, Work Plan submitted by Doug McGlone of Arcadis.

The final task assignment total is $6,704.53. Arcadis may invoice according to the attached schedule.

Specific negotiated subtasks are as follows:

Subtask 1: Project Management Project Management is automatically calculated as a percentage of total labor.

Subtask 2: Groundwater Monitoring Arcadis will sample eight wells for drycleaning solvents to supplement the assessment and aid in determining a path forward for the site. Additionally, Arcadis will measure water levels to confirm the direction of groundwater flow. IDW will be disposed of by a licensed waste hauler.

Subtask 3: Reporting Arcadis will submit a Groundwater Monitoring Report including recommendations for additional actions as the final deliverable.

Hours and costs are comparable to past task assignments of similar scope.

FDEP COST ESTIMATEContractor: Arcadis, U.S., Inc.

Date: 11/11/2025

Task #: SubTask 1 Project Management

Site: SubTask 2 Monitoring

Activity/Phase: Monitoring SubTask 3 Reporting

Project Manager: Theresa Pepe SubTask 4

SubTask 5

TTotals 1 2 3 4 5 Labor Rate Category

$89.78 Principal Engineer Suarez, Gus (GS) 2.2 $73.04 Principal Scientist McGlone, Douglas (DMc) 5 3 2 0 0 $50.00 Senior Engineer Hays, Timothy (TPH) 0 0 0 0 0 $39.34 Staff Engineer Tran, Thuy-Min (MT) 13 1 12 0 0

$34.89 Technician Fox, Brian (BF) 13 13 0 0 0 $39.67 Drafter/Design Oliva, Brian (BO) 3 0 3 0 0 $39.94 Project Assistant Cruz, Michele (MC) 2 0 2 0 0

$0.00 0 0 0 0 0 $0.00 0 0 0 0 0

Total Hours 38 2.2 17.0 19.0 0.0 0.0

Direct Labor $1,727.86 $198.78 $712.03 $817.05 $0.00 $0.00

Overhead 79.00% $1,365.01 $157.04 $562.50 $645.47 $0.00 $0.00 Gen & Admin 36.00% $622.03 $71.56 $256.33 $294.14 $0.00 $0.00 Fringe 37.10% $641.04 $73.75 $264.16 $303.13 $0.00 $0.00 Total Labor $4,355.94 $501.13 $1,795.02 $2,059.79 $0.00 $0.00

Travel Vehicle $120.00 $120.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Meals $0.00 $0.00 $0.00 $0.00 $0.00 Hotel $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $120.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00

Erwin IDW $125.00 $125.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00 Utility Location $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $125.00 $125.00 $0.00 $0.00 $0.00 Handling Fee $12.50 $12.50 $0.00 $0.00 $0.00 Total Subcontractor Cost $137.50 $137.50 $0.00 $0.00 $0.00

Laboratory Analytical Costs $584.00 $584.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $150.00 $150.00 $0.00 $0.00 $0.00 Total Laboratory $734.00 $734.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 Equipment (Drilling Related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $76.50 $76.50 $0.00 $0.00 $0.00 Equipment (IDW related) $100.00 $100.00 $0.00 $0.00 $0.00 Equipment (Other) $705.00 $705.00 $0.00 $0.00 $0.00 Total Field Expenses $921.50 $921.50 $0.00 $0.00 $0.00

Subtotal $6,268.94 $501.13 $3,708.02 $2,059.79 $0.00 $0.00 Completion Fee $435.59 $50.11 $179.50 $205.98 $0.00 $0.00

Total Estimated Cost $6,704.53 $551.24 $3,887.52 $2,265.77 $0.00 $0.00

Parisian Deluxe

REV: 09/25 CEF ARCADIS Page 1

SITE : Parisian Deluxe 0 SUBTASK 2: Monitoring

DATE: 11/11/25

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Activities and Email Updates Principal / DMc Event coordination, site owner/tenant access, subcontractor agreement 3 Technician / BF Mob/demob (3 hrs), sample 8 monitor wells, (9 hrs), pack/ship (1 hr) 13 Staff Engineer / MT Lab coordination 1

TOTAL LABOR 17

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Per Day 0 $0.00 $0.00 Van/Truck $120.00 Per Day 1 $120.00 $120.00

TOTAL VEHICLE $120.00

STAFF RATE UNIT USEAGE

Meals Category/Staff Rate Unit Usage Totals

Hotel Total Meal/Hotel: $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

Equipment Procurement

Name Equipment Rate Units Usage Totals $0.00 Per Day 0 $0.00

Total Equip.: $0.00 Services Procurement

Name Purpose Rate Units Usage Totals NAME OF COMPANY Direct push services $0 00 Lump Sum 0 $0 00 Erwin IDW $125.00 per drum 1 $125.00

Total Services: $125.00

TOTAL $125.00

LABORATORY COSTS

Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals

VOC 8260 Aqueous $73.00 1.00 8 $584.00 Dissolved Solids Total SM2540 C Aqueous $16 00 1 00 0 $0 00

TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $584.00 Rate Units Usage

Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 1 $150.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00

Total Shipping: $150.00

TOTAL LAB $734.00

EQUIPMENT

Personal Protection

Item Rate Unit Usage Totals Total PPE: $0.00

Expendables Miscellaneous Expendables $40.00 Per Day 1 $40.00

Total Expendables: $40.00 Equipment Items Tubing, Poly/HDPE $0.30 Per Foot 175 $52.50 Tubing, Silicon 3/16x3/8 $3.00 Per Foot 8 $24.00 55-gallon Drum $100.00 Each 1 $100.00

Total Equipment Items: $176.50 Equipment Kits Site Reconnaissance Kit $150 00 Day 0 $0 00 Shallow Groundwater Sampling Kit $290.00 Day 1 $290.00 Deep Groundwater Sampling Kit $415.00 Day 1 $415.00

Total Equipment Kits: $705.00

Total Equipment Kits: $921.50

SITE : Parisian Deluxe 0 SUBTASK 3: Reporting

DATE: 11/11/25

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Activities and Email Updates Principal / DMc PG certification of report 2 Staff Engineer / MT Monitoring report preparation 12 Project Assistant / MMc Report production/submittal 2 Designer / BO Report figures 3

TOTAL LABOR 19

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Per Day 0 $0.00 $0.00 Van/Truck $120.00 Per Day 0 $0.00 $0.00

TOTAL VEHICLE $0.00

STAFF RATE UNIT USEAGE

Meals

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

Equipment Procurement

Name Equipment Rate Units Usage Totals $2,000.00 Per Day 0 $0.00

Total Equip.: $0.00 Services Procurement

Name Purpose Rate Units Usage Totals Handling Fee $0.00 Per Month 0 $0.00

Total Services: $0.00

TOTAL $0.00

LABORATORY COSTS

Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals

TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00 Rate Units Usage

Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00

Total Shipping: $0.00

TOTAL LAB $0.00

EQUIPMENT

Personal Protection

Item Rate Unit Usage Totals Total PPE: $0.00

Expendables Miscellaneous Expendables $40.00 Per Day 0 $0.00

Total Expendables: $0.00 Equipment Items

Total Equipment Items: $0.00 Equipment Kits

Total Equipment Kits: $0.00

Total Equipment Kits: $0.00

Use or disclosure of information contained on this sheet is subject to the restriction and disclaimer located on the signature page of this document.

arcadis.com C:\Users\pepe_t\Desktop\Parisian 2025 Monitoring Proposal.docx

Page:

1/2

Theresa Pepe, Contract Manager Hazardous Waste Cleanup Section Florida Department of Environmental Protection Bob Martinez Center, MS 4520 2600 Blair Stone Road Tallahassee, Florida 32399-2400

Subject:

Proposal for Annual Groundwater Monitoring & Reporting Parisian Deluxe Cleaners 8731 SW 136th Street, Miami, Florida Facility ID No. ERIC_4378

Dear Ms. Pepe:

Arcadis is pleased to provide the Florida Department of Environmental Protection (FDEP) this proposal for the Parisian Deluxe Cleaners site, located in Miami, Miami-Dade County, Florida.

SCOPE OF WORK

The following sections provide a brief description of the tasks to be completed by Arcadis.

Task 1 – Project Management

This task includes project management activities associated with completion of Tasks 2 through 3.

Task 2 – Monitor Wells sampling – VOH

As requested, groundwater samples will be collected from eight monitor wells (MW001, MW002, MW003, MW004, MW005, PZ001, PZ002 and MW-X) for analysis of VOHs by EPA Method 8260 by an accredited laboratory. Water levels will be measured in the five wells for purposes of preparing a flow map. Purge water will be drummed for offsite disposal.

Task 3 – Reporting - VOH

An Annual Groundwater Monitoring Report documenting the sampling and results will be prepared and include conclusions and recommendations for future site work.

ENVIRONMENT

Date:

November 1 , 2025

Contact:

Doug McGlone

Phone:

561.662.7978

Email:

Douglas.mcglone@arcadis.com

Our ref:

Parisian Monitoring 2025

This proposal and its contents shall not be duplicated, used or disclosed — in whole or in part — for any purpose other than to evaluate the proposal. This proposal is not intended to be binding or form the terms of a contract. The scope and price of this proposal will be superseded by the contract. If this proposal is accepted and a contract is awarded to Arcadis as a result of — or in connection with — the submission of this proposal, Arcadis and/or the client shall have the right to make appropriate revisions of its terms, including scope and price, for purposes of the contract. Further, client shall have the right to duplicate, use or disclose the data contained in this proposal only to the extent provided in the resulting contract.

arcadis.com C:\Users\pepe_t\Desktop\Parisian 2025 Monitoring Proposal.docx

Annual Monitoring Proposal 18 November 2025

Page:

2/2

SCHEDULE

Arcadis will schedule field activities immediately upon receipt of the Task Assignment. Sampling is expected to occur in December 2025. The deliverable will be submitted within 45 days of completion of field work.

COST ESTIMATE

A Cost Estimate Form and Level of Effort (CEF-LOE) Form are attached for the above scope of work (Attachment 1).

CLOSING REMARKS

Arcadis appreciates the opportunity to assist the FDEP at this site. If you have any questions or wish to discuss this proposal, please do not hesitate to contact us.

Sincerely, Arcadis U.S., Inc.

Douglas J. McGlone, P.G.

Principal Geologist