This is a Task Assignment (TA) document issued by the State of Florida Department of Environmental Protection (FDEP) to Arcadis U.S. Inc. for groundwater monitoring services at the former Saufley Square Dry Cleaners site located at 4508 Saufley Field Road, Pensacola, Escambia County, Florida. The task assignment is identified as DC021A under Contract Number HW680, with a completion date of October 21, 2022. The FDEP Project Manager is Theresa Pepe, and the Contractor's Project Manager is Gus Suarez. This assignment represents a task order issued under an indefinite delivery vehicle contract with the environmental consulting firm.
The services consist of annual groundwater monitoring and reporting conducted according to Arcadis's May 9, 2022 Work Plan. The work is divided into three subtasks: Project Management (automatically calculated as a percentage of total labor), Annual Groundwater Monitoring (sampling five monitor wells for drycleaning solvents with investigative derived waste disposal), and Reporting (submission of an Annual Monitoring Report with recommendations). The total task assignment value is $6,771.42 on a fixed unit rate basis. Invoice payment is contingent upon FDEP approval of the Annual Monitoring Report, IDW manifest, and Project Management deliverables, with a due date of September 16, 2022. The cost estimate includes direct labor, overhead, general and administrative costs, fringe benefits, vehicle rental, laboratory analytical costs, sample shipping, and field equipment and expendables. All activities are to be conducted in accordance with the submitted work plan and Florida Administrative Code requirements.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW680
DC021A Completion October 21, 2022
Arcadis will conduct annual groundwater monitoring from select wells at the site. All activities will be performed according to the May 9, 2022, Work Plan submitted by Arcadis.
Theresa Pepe 850-245-8966 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Arcadis U.S. Inc.
Arcadis U.S. Inc.
Gus Suarez 813-205-4703
ERIC_4661
4508 Saufley Field Rd, Pensacola, Escambia County
Saufley Square Dry Cleaners
✔ $ 6,771.42
$ 6,771.42
Scope of Work
Gus Suarez
Contract Manager
Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.
Date: 2022.05.12 10:10:04 -04'00'
William E. Burns, Jr.
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2022.05.12 09:11:30 -04'00'
N/A
Lee_JEM Stamp
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Annual Monitoring Report/IDW manifest/Project Management 09/16/2022
FDEP approval of Annual Monitoring Report/IDW manifest/Project Management $ 6,771.42
$ 6,771.42
HW680
DC021A
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: Negotiation File Former Saufley Square Dry Cleaners
FACID NO. 17-9800747; ERIC_4661
Pensacola, Escambia County FROM: Theresa Pepe, Project Manager SUBJECT: Task Assignment DC021A (HW680) DATE: May 11, 2022
Arcadis U.S. Inc. will perform annual groundwater monitoring from select wells at the site. Groundwater monitoring will ensure that natural attenuation of contaminants continues to occur. Natural attenuation is expected to bring the site to unconditional closure within approximately five years. All activities will be conducted in accordance with the May 9, 2022, Work Plan submitted by Shannon Jeffries of Arcadis.
The final task assignment total is $6,771.42. Arcadis may invoice according to the attached schedule.
Specific negotiated subtasks are as follows:
Subtask 1: Project Management Project Management is automatically calculated as a percentage of total labor.
Subtask 2: Annual Groundwater Monitoring Arcadis will sample five wells for drycleaning solvents based on recommendations from the previous monitoring report. IDW will be drummed and disposed by a licensed waste hauler per FDEP’s preference.
Subtask 3: Reporting An Annual Monitoring Report including recommendations for additional actions will be submitted as the final Deliverable.
Hours and costs are comparable to past task assignments of similar scope.
FDEP COST ESTIMATE
Contractor: Arcadis, U.S., Inc.
Date: 5/9/2022
Task #: SubTask 1 Project Management
Site: Saufley Square ERIC_4661 SubTask 2 Annual Groundwater Monitoring
Activity/Phase: Assessment SubTask 3 Reporting
Project Manager: Gus Suarez SubTask 4
SubTask 5
Totals 1 2 3 4 5
Labor Rate Category
$79.12 Project Manager Suarez, Gus (GS) 3 2.9
$61.38 Principal Scientist McGlone, Douglas (DMc) 1 0 1 0 0$61.32 Principal Scientist Dellay, Leah (LD) 0 0 0 0 0
$45.61 Senior Scientist Jeffries, Shannon (SMJ) 18 8 10 0 0$49.19 Senior Scientist O'Connell, Patrick (PJO) 0 0 0 0 0
$39.34 Staff Scientist Riley, Joel (JR) 15 11 4 0 0$36.35 Staff Scientist Chest, Mark (MC) 0 0 0 0 0
$39.67 Drafter/Designer Oliva, Brian (BO) 4 0 4 0 0
$30.96 Project Assistant McLemore, Michele (MMc) 5 1 4 0 0
Total Hours 46 3 20 23 0 0
Direct Labor $2,018.11 $232.17 $828.58 $957.36 $0.00 $0.00
Overhead 79.00% $1,594.30 $183.41 $654.58 $756.31 $0.00 $0.00
Gen & Admin 36.00% $726.52 $83.58 $298.29 $344.65 $0.00 $0.00
Fringe 37.10% $748.72 $86.14 $307.40 $355.18 $0.00 $0.00
Total Labor $5,087.65 $585.30 $2,088.85 $2,413.50 $0.00 $0.00
Travel
Vehicle Rental $120.00 $120.00 $0.00 $0.00 $0.00
Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00
Air Fare $0.00 $0.00 $0.00 $0.00 $0.00
Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00
Total Travel $120.00 $120.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement)
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00
Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00
Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement)
Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00
Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00
Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00
Surveying $0.00 $0.00 $0.00 $0.00 $0.00
Erwin Rem. IDW $100.00 $100.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $100.00 $100.00 $0.00 $0.00 $0.00
Handling Fee $10.00 $10.00 $0.00 $0.00 $0.00
Total Subcontractor Cost $110.00 $110.00 $0.00 $0.00 $0.00
Laboratory
Analytical Costs $365.00 $365.00 $0.00 $0.00 $0.00
Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00
Sample Shipping $150.00 $150.00 $0.00 $0.00 $0.00
Total Laboratory $515.00 $515.00 $0.00 $0.00 $0.00
Field Expenses
Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00
Expendables $40.00 $40.00 $0.00 $0.00 $0.00
Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Analytical related) $290.00 $290.00 $0.00 $0.00 $0.00
Equipment (IDW related) $100.00 $100.00 $0.00 $0.00 $0.00
Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00
Total Field Expenses $430.00 $430.00 $0.00 $0.00 $0.00
Subtotal $6,262.65 $585.30 $3,263.85 $2,413.50 $0.00 $0.00
Completion Fee $508.77 $58.53 $208.89 $241.35 $0.00 $0.00
Total Estimated Cost $6,771.42 $643.83 $3,472.74 $2,654.85 $0.00 $0.00
REV: 02/03 CEF ARCADIS Page 1
SITE : Saufley Square ERIC_4661
SUBTASK 2: Annual Groundwater Monitoring
DATE: 5/9/2022
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
(Subtask Title)Principal Sci (DMc) 0 Senior Sci (SMJ) 8
Staff Sci (JR) Field prep-paperwork, instrument calibration (1hr); equipment/cooler preparation (2hrs); WLs/TDs in MWs (1hr); sample 5 MWs and IDW management on-site (7 hrs); 11Drafter Designer (BO) 0
Project Assistant (MMc) Office support, transcribe field docs, sample tracking 1
TOTAL LABOR 20
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 0 $0.00 $0.00
Van/Truck $120.00 Per Day 1 $120.00 $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
Meals Category/Staff Rate Unit Usage Totals
$36.00 Per Day 0 $0.00
$36.00 Per Day 0 $0.00
Hotel Category/Staff Rate Unit Usage Totals
$150.00 Per Day 0 $0.00
$150.00 Per Day 0 $0.00
Total Meal/Hotel: $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Equipment Procurement
Name Equipment Rate Units Usage Totals $0.00 Per Day 1 $0.00
Total Equip.: $0.00 Services Procurement
Name Purpose Rate Units Usage Totals Erwin Remediation IDW $100.00 Drum 1 $100.00
Handling Fee $0.00 Per Month 1 $0.00
Total Services: $100.00
TOTAL $100.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOC 8260 Aqueous $73.00 1.00 5 $365.00
TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $365.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 1 $150.00
Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $150.00
TOTAL LAB $515.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage TotalsPPE Level D $35.00 Per Man Day 0 $0.00
Total PPE: $0.00 Expendables Miscellaneous Expendables $40.00 Per Day 1 $40.00
Total Expendables: $40.00 Equipment Items 55-gallon Drum $100.00 Each 1 $100.00
Total Equipment Items: $100.00 Equipment Kits Shallow Groundwater Sampling Kit $290.00 Day 1 $290.00
Total Equipment Kits: $290.00
TOTAL EQUIPMENT $430.00
Coord with prop owners and confirm permission to enter three properties (4 hrs); scheduling; order bottles; field support (2 hrs) review field notes (0.5 hr); coordinate IDW contracts and schedule (1.5 hrs)
SITE : Saufley Square ERIC_4661
SUBTASK 3: Reporting
DATE: 5/9/2022
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
(Subtask Title)
Principal Sci (DMc) Report review, PG sign/seal 1
Senior Sci (SMJ) Lab data analysis (1hr); figure markups (2hrs); report prep (7hrs) 10
Staff Sci (JR) Data tables, appendices compilation 4
Drafter Designer (BO) Prepare report illustrations/figures (4hrs) 4
Project Assistant (MMc) Report editing/formatting (2hrs); report production/submittal/delivery (1hr); ADaPT (1hr) 4
TOTAL LABOR 23
Use or disclosure of information contained on this sheet is subject to the restriction and disclaimer located on the signature page of this document.
Arcadis U.S., Inc.
1510 Airport Boulevard Suite 3 Pensacola Florida 32504 Phone: 850 476 8448 Fax: 850 476 3754 www.arcadis.com
FL Engineering License #7917 FL Geology License #GB564 FL Surveying License #LB7062
1/2
Ms. Theresa Pepe Hazardous Waste Cleanup Section Florida Department of Environmental Protection 2600 Blair Stone Road, MS 4520 Tallahassee, Florida 32399
Date: May 9, 2022 Our Ref: 30124789 Subject: Proposal for Annual Groundwater Monitoring and Reporting Former Saufley Square Dry Cleaners Pensacola, Florida
FDEP ERIC_4661
Dear Ms. Pepe, Arcadis is pleased to submit this proposal to complete Annual Groundwater Monitoring / Reporting at the former Saufley Square Dry Cleaners in Pensacola Florida (Site) during 2022. A proposed scope of work, cost estimate, and schedule are included herein.
Scope of Work
Based on the conclusions and recommendations presented in the Annual Groundwater Monitoring Report dated September 2021, subsequent discussions with the Florida Department of Environmental Protection (FDEP), and Chapters 62-780 and 62-777, Florida Administrative Code (FAC), the following tasks are proposed to complete annual groundwater monitoring at the Site.
Task 1: Project Management
This task consists of project management related activities in relation to the completion of Tasks 2 and 3.
Task 2: Annual Groundwater Monitor Event
The next groundwater sampling event will be conducted in June/July 2022. Arcadis personnel will confirm permission to enter the property with the property’s owners. Five Site monitor wells – MW003RR, MW004R, MW005R, MW007R, and MW009R – will be sampled per FDEP standard operating procedures (SOP) (DEP- SOP-001/01). Groundwater samples will be analyzed for volatile organic compounds (VOCs) using United States Environmental Protection Agency (USEPA) Test Method 8260 by the National Environmental Laboratory Accreditation Program (NELAP). Investigative Derived Waste (IDW) will be containerized during the sampling event. Arcadis will coordinate pick-up of IDW to coincide with the field sampling. This coordination with the transportation and disposal contractor will ensure that the IDW does become stolen or inadvertently moved off-site.
Task 3: Reporting
A Groundwater Monitoring Report and ADaPT-compatible EDDs will be submitted to the FDEP within 60 days of completion of the groundwater sampling event. The report will include data tables, figures, appendices, and conclusions / recommendations.
Ms. Theresa Pepe Florida Department of Environmental Protection May 9, 2022
This proposal and its contents shall not be duplicated, used or disclosed — in whole or in part — for any purpose other than to evaluate the proposal. This proposal is not intended to be binding or form the terms of a contract. The scope and price of this proposal will be superseded by the contract. If this proposal is accepted and a contract is awarded to Arcadis as a result of — or in connection with — the submission of this proposal, Arcadis and/or the client shall have the right to make appropriate revisions of its terms, including scope and price, for purposes of the contract. Further, client shall have the right to duplicate, use or disclose the data contained in this proposal only to the extent provided in the resulting contract.
www.arcadis.com Saufley Square Annual Proposal 05092022
2/2
SCHEDULE
The groundwater monitoring event will be completed in June/July 2022. The Groundwater Monitoring Report will be submitted to the FDEP within 60 days of completion of groundwater sampling.
COST ESTIMATE
Estimated costs to complete the well install, monitoring and reporting are presented in Cost Estimate Form (CEF) and Level of Effort (LOE) forms. Arcadis appreciates the opportunity to assist the FDEP at this Site. If you have any questions or wish to discuss this proposal, please do not hesitate to contact me.
Sincerely, Shannon Jeffries Certified Project Manager
Email: shannon.jeffries@arcadis.com Direct Line: 850.476.8448 Mobile: 813.244.8147
Enclosures:
Attachment 1 - CEF/LOE
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
To: Mr. Anthony Boros
1705 Metropolitan Blvd
Tallahassee, FL 32308
May 11, 2022
Re: Drum Disposal Quote – Saufley Square - Pensacola, FL
Mr. Boros:
The price for transportation and disposal of a single (1) 55-gallon drum of non-hazardous groundwater located in Pensacola, FL will be $100.00 per drum, total, for both transportation and disposal.
Respectfully, Jonathan Erwin
Erwin Remediation, Inc.
Email: ErwinRemediation@Gmail.com
Office: (850) 292-6511 mailto:Remediation@Gmail.com
| Peerless Cleaners #3416 Annual Monitoring Proposal 4-18-2022.pdf |
| Annual Groundwater Monitoring |
| Annual Groundwater Monitoring Report |
| Schedule |
| Cost Estimate |
| Closing Remarks |
| saufley negsum.pdf |
| Subtask 1: Project Management |
File details come from the government source that posted it. Updated .