This Task Assignment (TA DC020A) represents a state contract between the State of Florida Department of Environmental Protection (FDEP) and Arcadis U.S. Inc. for environmental remediation services at the Ridgewood Laundry and Dry Cleaning facility located at 930-C Blanding Boulevard, Orange Park, Clay County, Florida (ERIC_4262). The contract is entered under the indefinite delivery vehicle Contract Number HW680. Theresa Pepe serves as the FDEP Project Manager, while Gus Suarez represents Arcadis U.S. Inc. as the Contractor's Project Manager. The TA is effective as of May 11, 2022, with a completion date of October 7, 2022.
The scope of work requires Arcadis to conduct annual groundwater monitoring from six select monitoring wells (MW001R, MW005, MW007, MW008, MW009, and MW011) at the site to ensure natural attenuation of drycleaning solvents continues to occur, with natural attenuation expected to bring the site to unconditional closure within approximately three years. The contract is structured as a fixed unit rate of $5,676.99, with a total TA value of $5,676.99. The work encompasses three subtasks: Project Management (automatically calculated as a percentage of total labor), Annual Groundwater Monitoring (including sampling six wells for volatile organic compounds, water level measurements, and disposal of investigation-derived waste), and Reporting (submission of an Annual Monitoring Report with recommendations). All activities are conducted in accordance with the May 4, 2022 Work Plan submitted by Arcadis. The single deliverable—an Annual Monitoring Report with IDW manifest and project management documentation—is due September 9, 2022, with payment contingent upon FDEP approval. No additional funding information or optional renewal periods are specified in the documentation.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW680
DC020A Completion October 7, 2022
Arcadis will conduct annual groundwater monitoring from select wells at the site. All activities will be performed according to the May 4, 2022, Work Plan submitted by Arcadis.
Theresa Pepe 850-245-8966 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Arcadis U.S. Inc.
Arcadis U.S. Inc.
Gus Suarez 813-205-4703
ERIC_4262
930-C Blanding Blvd, Orange Park, Clay County
Ridgewood Laundry and Dry Cleaning
✔ $ 5,676.99
$ 5,676.99
Scope of Work
Gus Suarez
Contract Manager
Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.
Date: 2022.05.11 16:34:36 -04'00'
William E. Burns, Jr.
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2022.05.11 15:07:28 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Annual Monitoring Report/IDW manifest/Project Management 09/09/2022
FDEP approval of Annual Monitoring Report/IDW manifest/Project Management $ 5,676.99
$ 5,676.99
HW680
DC020A
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: Negotiation File Ridgewood Laundry and Dry Cleaning
FACID NO. 10-9501247; ERIC_4262
Orange Park, Clay County FROM: Theresa Pepe, Project Manager SUBJECT: Task Assignment DC020A (HW680) DATE: May 11, 2022
Arcadis U.S. Inc. will perform annual groundwater monitoring from select wells at the site. Groundwater monitoring will ensure that natural attenuation of contaminants continues to occur. Natural attenuation is expected to bring the site to unconditional closure within approximately three years. All activities will be conducted in accordance with the May 4, 2022, Work Plan submitted by Doug McGlone of Arcadis.
The final task assignment total is $5,676.99. Arcadis may invoice according to the attached schedule.
Specific negotiated subtasks are as follows:
Subtask 1: Project Management Project Management is automatically calculated as a percentage of total labor.
Subtask 2: Annual Groundwater Monitoring Arcadis will sample six wells for drycleaning solvents based on recommendations from the previous monitoring report. IDW will be drummed and disposed by a licensed waste hauler per FDEP’s preference.
Subtask 3: Reporting An Annual Monitoring Report including recommendations for additional actions will be submitted as the final Deliverable.
Hours and costs are comparable to past task assignments of similar scope.
FDEP COST ESTIMATE
Contractor: Arcadis, U.S., Inc.
Date: 4/5/2022
Task #: SubTask 1 Project Management
Site: Ridgewood Laundry & Cleaners SubTask 2 Groundwater Monitoring
Activity/Phase: Monitoring SubTask 3 Reporting
Project Manager: Doug McGlone SubTask 4
SubTask 5
Totals 1 2 3 4 5
Labor Rate Category
$61.38 Project Manager McGlone, Douglas (DMc) 3 2.9
$96.76 Principal Engineer Bedessem, Jim (JMB) 0 0 0 0 0
$61.69 Principal Scientist Burke, Brian (BRB) 0 0 0 0 0
$61.38 Principal Scientist McGlone, Douglas (DMc) 4 2 2 0 0
$39.34 Staff Scientist Riley, Joel (JR) 21 11 10 0 0
$39.67 Drafter/Designer Oliva, Brian (BO) 4 0 4 0 0
$30.96 Project Assistant McLemore, Michele (MMc) 5 2 3 0 0
Total Hours 37 3 15 19 0 0
Direct Labor $1,565.21 $180.07 $617.42 $767.72 $0.00 $0.00
Overhead 79.00% $1,236.52 $142.26 $487.76 $606.50 $0.00 $0.00
Gen & Admin 36.00% $563.48 $64.83 $222.27 $276.38 $0.00 $0.00
Fringe 37.10% $580.69 $66.81 $229.06 $284.82 $0.00 $0.00
Total Labor $3,945.90 $453.97 $1,556.51 $1,935.42 $0.00 $0.00
Travel
Vehicle Rental $120.00 $120.00 $0.00 $0.00 $0.00
Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00
Air Fare $0.00 $0.00 $0.00 $0.00 $0.00
Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00
Total Travel $120.00 $120.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement)
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00
Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00
Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement)
Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00
Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00
Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00
Surveying $0.00 $0.00 $0.00 $0.00 $0.00
IDW $150.00 $150.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $150.00 $150.00 $0.00 $0.00 $0.00
Handling Fee $15.00 $15.00 $0.00 $0.00 $0.00
Total Subcontractor Cost $165.00 $165.00 $0.00 $0.00 $0.00
Laboratory
Analytical Costs $438.00 $438.00 $0.00 $0.00 $0.00
Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00
Sample Shipping $110.00 $110.00 $0.00 $0.00 $0.00
Total Laboratory $548.00 $548.00 $0.00 $0.00 $0.00
Field Expenses
Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00
Expendables $40.00 $40.00 $0.00 $0.00 $0.00
Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Analytical related) $363.50 $363.50 $0.00 $0.00 $0.00
Equipment (IDW related) $100.00 $100.00 $0.00 $0.00 $0.00
Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00
Total Field Expenses $503.50 $503.50 $0.00 $0.00 $0.00
Subtotal $5,282.40 $453.97 $2,893.01 $1,935.42 $0.00 $0.00
Completion Fee $394.59 $45.40 $155.65 $193.54 $0.00 $0.00
Total Estimated Cost $5,676.99 $499.37 $3,048.66 $2,128.96 $0.00 $0.00
REV: 02/03 CEF ARCADIS Page 1
SITE : Ridgewood Laundry & Cleaners SUBTASK 2: Groundwater Monitoring
DATE: 4/5/2022
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Groundwater Monitoring Pricipal / DMc Owner/property mgr interaction & access; correspondence with FDEP 2 Staff Scientist / JR Prep for fieldwork (1 hr), mob/demob (2 hrs); round of WLs, purge & sample 6 wells (7 hrs), pack ship (1 hr) 11 Project Asst - MMc Field notes processing, sample tracking 2
TOTAL LABOR 15
VEHICLE TYPE RATE UNIT USEAGE
Van/Truck $120.00 Per Day 1 $120.00 $120.00
TOTAL VEHICLE $120.00
SUBCONTRACTOR COSTS
Services Procurement
Name Purpose Rate Units Usage Totals Lump Sum $0.00
Clark IDW $150.00 Drum 1 $150.00
Total Services: $150.00
TOTAL $150.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOC (Halocarbons Only) 8260 Aqueous $73.00 1.00 6 $438.00 TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $438.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 1 $110.00
Total Shipping: $110.00
TOTAL LAB $548.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage TotalsPPE Level D $35.00 Per Man Day 0 $0.00 Total PPE: $0.00
Expendables Miscellaneous Expendables $40.00 Per Day 1 $40.00
Total Expendables: $40.00 Equipment ItemsPID/FID Combo or FID $125.00 Per Day 0 $0.00 Tubing, Poly/HDPE $0.30 Per Foot 125 $37.50 Tubing, Silicon 3/16x3/8 $3.00 Per Foot 12 $36.00Miscellaneous Expendables $40.00 Per Day 0 $0.00 55-gallon Drum $100.00 Each 1 $100.00
Total Equipment Items: $173.50 Equipment KitsMonitor Well Installation Kit $325.00 Day 0 $0.00 Shallow Groundwater Sampling Kit $290.00 Day 1 $290.00
Total Equipment Kits: $290.00
TOTAL EQUIPMENT $503.50
SITE : Ridgewood Laundry & Cleaners SUBTASK 3: Reporting
DATE: 4/5/2022
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Data Evaluation and Letter Report Principal / DMc Technical review; sign and seal report 2 Staff Scientist / JR Data evaluation and preparation of a brief letter report 10 Drafter / BO Figures production for report 4 Project Asst - MMc Process field notes, report assembly, submittals, ADaPT processing/upload 3
TOTAL LABOR 19
VEHICLE TYPE RATE UNIT USEAGE
Van/Truck $120.00 Per Day 0 $0.00 $0.00
TOTAL VEHICLE $0.00
SUBCONTRACTOR COSTS
Services Procurement
Name Purpose Rate Units Usage Totals Drum $0.00
Total Services: $0.00
TOTAL $0.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOC (Halocarbons Only) 8260 Aqueous $73.00 1.00 0 $0.00 TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00
Total Shipping: $0.00
TOTAL LAB $0.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage Totals Total PPE: $0.00
Expendables Miscellaneous Expendables $40.00 Per Day 0 $0.00
Total Expendables: $0.00 Equipment Items Tubing, Poly/HDPE $0.30 Per Foot 0 $0.00
Total Equipment Items: $0.00 Equipment Kits Deep Groundwater Sampling Kit $415.00 Day 0 $0.00
Total Equipment Kits: $0.00
TOTAL EQUIPMENT $0.00
Use or disclosure of information contained on this sheet is subject to the restriction and disclaimer located on the signature page of this document.
Arcadis U.S., Inc.
1500 Gateway Blvd
Suite 200
Boynton Beach
Florida 33426
Tel 561 697 7000
Fax 561 369 4731 www.arcadis.com
Page:
1/3
Ms. Theresa Pepe, Contract Manager Florida Department of Environmental Protection Bob Martinez Center, MS 4520 2600 Blair Stone Road Tallahassee, Florida 32399-2400
Subject:
Proposal for Annual Groundwater Monitoring & Reporting Ridgewood Coin Laundry & Cleaners 930-C Blanding Boulevard, Orange Park, FL Facility ID No. 10-9501247, ERIC_4262
Dear Ms. Pepe:
Arcadis U.S., Inc. (Arcadis) is pleased to submit this proposal/cost estimate for annual groundwater monitoring and reporting at the subject facility. This proposal includes a description of the proposed scope of services, and an estimated cost and schedule for their completion.
PROPOSED SCOPE OF WORK
Task 1: Project Management
Task 1 is reserved for project management.
Task 2: Groundwater Monitoring
Following receipt of a Task Assignment from FDEP, Arcadis will schedule the Annual Groundwater Monitoring event for June 2022 (i.e., one year after previous groundwater monitoring event and six years after ISR activities). Per the FDEP-approved ISR Work Plan, dated October 2015, and recommendations in the April 2021, Annual Groundwater Monitoring Report, groundwater from six monitor wells (MW001R, MW005, MW007, MW008, MW009, and MW011) will be sampled in accordance with FDEP SOPs. Samples will be analyzed at a NELAP-accredited laboratory for volatile organic compounds by EPA Test Method 8260.
In addition, per FDEP email dated March 28, 2017, the requirements for UIC sampling have been met, so UIC parameters will not need to be monitored. Prior
ENVIRONMENTAL
Date:
May 4, 2022
Contact:
Doug McGlone
Phone:
561.662.7978
Email:
Douglas.mcglone@arcadis.c om
Our ref:
WF900229
Florida License Numbers
Engineering
Geology
GB564
Surveying
LB7062
Use or disclosure of information contained on this sheet is subject to the restriction and disclaimer located on the signature page of this document.
C:\Users\Pepe_T\Desktop\Ridgewood Annual GWMR Proposal_050422.docx
Theresa Pepe 4 May 2022
Page:
2/3 to collecting groundwater samples, a full round of water levels in all site wells will be measured and recorded.
Task 3: Annual Reporting
Approximately 60 days following the groundwater monitoring event, Arcadis will update data tables and figures, and submit an Annual Groundwater Monitoring Report including conclusions and recommendations.
PROPOSED SCHEDULE
Arcadis will schedule the annual groundwater monitoring event for June 2021, after our receipt of a TA from FDEP. Arcadis suggests invoicing for the fieldwork and reporting tasks.
COST ESTIMATE
Level of Effort (LOE) Forms and a Cost Estimate Form (CEF) that present estimated project costs are presented as Attachment 1.
This proposal and its contents shall not be duplicated, used or disclosed — in whole or in part — for any purpose other than to evaluate the proposal. This proposal is not intended to be binding or form the terms of a contract. The scope and price of this proposal will be superseded by the contract. If this proposal is accepted and a contract is awarded to Arcadis as a result of — or in connection with — the submission of this proposal, Arcadis and/or the client shall have the right to make appropriate revisions of its terms, including scope and price, for purposes of the contract. Further, client shall have the right to duplicate, use or disclose the data contained in this proposal only to the extent provided in the resulting contract.
arcadis.com C:\Users\Pepe_T\Desktop\Ridgewood Annual GWMR Proposal_050422.docx
Theresa Pepe 4 May 2022
Page:
3/3
CLOSING REMARKS
Arcadis appreciates the opportunity to assist the FDEP in addressing the chlorinated solvent impacts at this Site. If you have any questions or wish to discuss this proposal, please contact us.
Sincerely, Arcadis U.S., Inc.
Douglas J. McGlone, P.G.
Senior Geologist
Enclosures:
Attachment
1 CEF-LOE
6/9/2021 Clark Environmental Inc.: Quote Builder file:///C:/Users/channa/AppData/Local/Microsoft/Windows/INetCache/Content.Outlook/55TP28C8/Arcadis 1530 1st.html 1/2
Quote Number: 18737
QUOTE
QUOTED TO: Chad Hanna QUOTE DATE: 6/9/2021 COMPANY NAME: Arcadis QUOTED BY: Steve Harris PHONE NUMBER: 813-480-8498 Ext.
FAX NUMBER: email only PROJECT REFERENCE: Transportation and Disposal of Non Haz. Water Drum.
CUSTOMER PO:
CONTACT EMAIL:
SITE ADDRESS: 1530 1st Street Sarasota FL
CLARK ENVIRONMENTAL, INC. IS PLEASED TO PROVIDE THE
FOLLOWING COST ESTIMATE FOR THE SITE/ PROJECT LISTED
ABOVE.
DESCRIPTION PRICE QTY. UNIT TOTAL
NON HAZ. "WATER" DRUM DISPOSAL W/CUSTOMER SUPPLIED
ACCEPTABLE NON HAZ. ANALYTICAL AND PROFILE STATING SAME.
$60.00 1 55 GAL $60.00
DRUM TRANSPORTTATION <100 MILES FROM CLARK ENVIRONMENTAL
INC. DRUM LOCATED ON HARD BLACK TOP OR CONCRETE SURFACE
EASILY ACCESSIBLE WITH 53 FOOT TRACTOR TRAILER WITH
LIFTGATE NO CURBS, GRASS OR DIRT TO CROSS.
$40.00 1 55 GAL $40.00
DRUM LOW VOLUME STOP CHARGE FOR 5 DRUMS OR LESS. $50.00 1 FLAT RATE $50.00
TOTAL REQUIRED ITEMS $150.00
TOTAL OPTIONAL ITEMS $0.00
GRAND TOTAL $150.00
NOTES: Quote is based on acceptable customer supplied non haz. analyticals and matching profile. TCLP Metals and Volatiles Analitical Testing will be required .Quote based on DOT shippable drums from this location easily accessable with 53 foot tractor trailer with no grass, curbs or sand to cross.If Required, I will need a signed accepted quote with purchase order and non haz. profile. Please call with any questions. Thanks. Steve Harris 863-559-
This quote will remain valid for thirty (30) days from the date listed above except for transportation which is subject to weekly change and is based on upon payment in net 30 days. Quote based on an accepted and approved profile. Please sign and return to accept this quotation and by signing agree to all terms and conditions.
| Peerless Cleaners #3416 Annual Monitoring Proposal 4-18-2022.pdf |
| Annual Groundwater Monitoring |
| Annual Groundwater Monitoring Report |
| Schedule |
| Cost Estimate |
| Closing Remarks |
| negsum.pdf |
| Subtask 1: Project Management |
| Ridgewood Annual GWMR Proposal_050422.pdf |
| Proposed Scope of Work |
| Task 1: Project Management |
| Task 2: Groundwater Monitoring |
| Task 3: Annual Reporting |
| Proposed Schedule |
| Cost Estimate |
| Closing Remarks |