This document is a Task Assignment (TA) issued by the State of Florida Department of Environmental Protection (FDEP) to Arcadis U.S. Inc., a professional services contractor. The Task Assignment DC001F operates under the underlying indefinite delivery vehicle Contract Number HW680 and authorizes Arcadis personnel to attend and support a site review meeting with FDEP's Waste Site Cleanup Section in Tallahassee, Florida. The parties involved include the FDEP (represented by Project Manager Theresa Pepe) and Arcadis U.S. Inc. (represented by Gus Suarez, Contract Manager). The task assignment became effective June 10, 2025, with a completion date of October 3, 2025.
The Task Assignment authorizes three primary subtasks: Project Management (automatically calculated as a percentage of total labor), Site Review Meeting Prep (preparation activities focusing on 16 sites in remediation and design), and Meeting and Travel (attendance by two Arcadis personnel at the July 29, 2025 meeting, including travel, hotel, and per diem costs). The total Task Assignment value is $15,709.72, compensated on a fixed unit rate basis. Deliverables include Site Review Meeting Notes and Project Management documentation due September 12, 2025, with payment contingent upon FDEP approval. The cost estimate includes direct labor for five staff categories totaling 77 hours ($5,389.54), overhead charges (79 percent), general and administrative costs (36 percent), fringe benefits (37.1 percent), and travel costs ($764.00) including vehicle rental ($320.00) and per diem and hotel expenses ($444.00). A completion fee of approximately 9.5 percent is applied to the subtotal.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
Additional signatures attached on separate page.
HW680
DC001F Completion October 3, 2025
This Task Assignment authorizes personnel from Arcadis U.S. Inc. to attend a site review meeting with FDEP in Tallahassee. Activities will be performed according to the June 6, 2025, Work Plan submitted by Arcadis.
Theresa Pepe 850-245-8966 Contractor Arcadis U.S. Inc. Contractor
Contractor Gus Suarez Contractor 813-205-4703 Multiple
Multiple
Multiple
Contractor Contractor
✔ $ 15,709.72
$ 15,709.72
Scope of Work
Arcadis U.S. Inc.
Contractor Gus Suarez
Contract Manager
Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.
Date: 2025.06.10 16:12:35 -04'00'
Mubeen Darji
Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.
Date: 2025.06.09 19:38:35 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Site Review Meeting Notes/Project Management 09/12/2025
FDEP approval of Site Review Meeting Notes/Project Management $ 15,709.72
$ 15,709.72
HW680
DC001F
FFLORIDA DEPARTMENT OF
EEnvironmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Alexis A. Lambert
Secretary
Memorandum
TO: Negotiation File Site Review Meeting
Multiple Sites Tallahassee, Leon County FROM: Theresa Pepe, Project Manager SUBJECT: Task Assignment DC001F (HW680) DATE: June 6, 2025
Arcadis U.S. Inc. will attend a site review meeting with the Waste Site Cleanup Section in Tallahassee, Florida currently scheduled for July 29, 2025. All activities will be conducted in accordance with the June 6, 2025, Work Plan submitted by Gus Suarez of Arcadis.
The final task assignment total is $15,709.72. Arcadis may invoice according to the attached schedule.
Specific negotiated subtasks are as follows:
Subtask 1: Project Management Project Management is automatically calculated as a percentage of total labor.
Subtask 2: Site Review Meeting Prep This subtask provides hours for Arcadis to prepare for the meeting with a focus on those sites in remediation and design. Other sites may be discussed based on priority.
Subtask 3: Meeting and Travel This subtask covers costs for two Arcadis personnel to attend the meeting including travel, hotel and per diem. Other personnel may attend at the expense of Arcadis.
Arcadis will submit a written summary of the meeting notes as the final deliverable.
FDEP COST ESTIMATE
Contractor: Arcadis, U.S., Inc.
Date: 6/6/25
Task #: SubTask 1 Project Management Site: SubTask 2 Site Review Meeting Prep
Activity/Phase: SubTask 3 Site Review Meeting Attendance Project Manager: Gus Suarez SubTask 4
SubTask 5
Totals 1 2 3 4 5 Labor Rate Category
$89.78 Project Manager Suarez, Gus (GS) 7 6.9 $89.78 Principal Engineer Suarez, Gus (GS) 19 4 15 0 0 $73.45 Principal Engineer Perella, John (JFP) 4 4 0 0 0 $73.04 Principal Scientist McGlone, Douglas (DMc) 25 4 21 0 0 $50.00 Senior Engineer Hanna, Chad (CH) 4 4 0 0 0 $41.50 Project Scientist Brooks, Eric (EAB) 16 16 0 0 0 $39.94 Project Assistant Cruz, Michele (MC) 2 2 0 0 0 $0.00 0 0 0 0 0
Total Hours 77 7 34 36 0 0
Direct Labor $5,389.54 $620.04 $1,888.96 $2,880.54 $0.00 $0.00
Overhead 79.00% $4,257.74 $489.83 $1,492.28 $2,275.63 $0.00 $0.00 Gen & Admin 36.00% $1,940.23 $223.21 $680.03 $1,036.99 $0.00 $0.00 Fringe 37.10% $1,999.51 $230.03 $700.80 $1,068.68 $0.00 $0.00 Total Labor $13,587.02 $1,563.11 $4,762.07 $7,261.84 $0.00 $0.00
Travel Vehicle Rental $320.00 $0.00 $320.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $444.00 $0.00 $444.00 $0.00 $0.00 Total Travel $764.00 $0.00 $764.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 IDW EnviroServe $0.00 $0.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $14,351.02 $1,563.11 $4,762.07 $8,025.84 $0.00 $0.00 Completion Fee $1,358.70 $156.31 $476.21 $726.18 $0.00 $0.00
Total Estimated Cost $15,709.72 $1,719.42 $5,238.28 $8,752.02 $0.00 $0.00
Arcadis Site Review Meeting 2025
REV: 02/03 CEF ARCADIS Page 1
SITE : Arcadis Site Review Meeting 2025 SUBTASK 2: Site Review Meeting Prep
DATE: 6/6/25
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
(Subtask Title) Principal Engineer (GS) Meeting prep 4 Principal Scientist (DM) Meeting prep 4 Principal Engineer (JP) Meeting prep 4 Senior Engineer (CH) Meeting prep 4 Project Scientist (EAB) Site prep (16 sites, 1 hr /site) 16 Project Asst (MMc) 2
TOTAL LABOR 34
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 0 $0.00 $0.00 Van/Truck $120.00 Per Day 0 $0.00 $0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
Meals
Category/Staff Rate Unit Usage Totals Total Meal/Hotel: $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Equipment Procurement
Name Equipment Rate Units Usage Totals EESI AWS $0.00 Per Day 0 $0.00
Total Equip.: $0.00 Services Procurement
Name Purpose Rate Units Usage Totals
Total Services: $0.00
TOTAL $0.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00 Rate Units Usage
Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $0.00
TOTAL LAB $0.00
EQUIPMENT
Personal Protection Item Rate Unit Usage Totals
Total PPE: $0.00 Expendables Miscellaneous Expendables $40.00 Per Day 0 $0.00
Total Expendables: $0.00 Equipment Items
Total Equipment Items: $0.00 Total Equipment Kits: $0.00
SITE : Arcadis Site Review Meeting 2025 SUBTASK 3: Site Review Meeting Attendance
DATE: 6/6/25
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
(Subtask Title) Principal Engineer (GS) RT TPA to TLH (8), attend meeting (5), prepare mtg summary (2) 15 Principal Scientist (DM) RT WPB to TLH (16), attend meeting (5) 21 Staff Scientist (JR) Project Asst (MMc) Drafter/Designer(BO)
TOTAL LABOR 36
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 4 $320.00 $320.00 Van/Truck $120.00 Per Day 0 $0.00 $0.00
TOTAL VEHICLE $320.00
PER DIEM STAFF RATE UNIT USEAGE
Meals
Category/Staff Rate Unit Usage Totals Two staff, 2 days each $36.00 Per Day 4 $144.00
$36.00 Per Day 0 $0.00 Hotel
Category/Staff Rate Unit Usage Totals Two staff, 1 night each $150.00 Per Day 2 $300.00
$150.00 Per Day 0 $0.00
Total Meal/Hotel: $444.00
TOTAL PER DIEM $444.00
SUBCONTRACTOR COSTS
Equipment Procurement
Name Equipment Rate Units Usage Totals $0.00 Per Day 0 $0.00
Total Equip.: $0.00 Services Procurement
Name Purpose Rate Units Usage Totals
Total Services: $0.00
TOTAL $0.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00 Rate Units Usage
Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $0.00
TOTAL LAB $0.00
EQUIPMENT
Personal Protection Item Rate Unit Usage Totals
Total PPE: $0.00 Expendables Miscellaneous Expendables $40.00 Per Day 0 $0.00
Total Expendables: $0.00 Equipment Items
Total Equipment Items: $0.00
Use or disclosure of information contained on this sheet is subject to the restriction and disclaimer located on the signature page of this document.
Arcadis U.S., Inc.
4300 W Cypress Street Suite 450 Tampa Florida 33607 Phone: 813 903 3100 Fax: 813 350 9046 www.arcadis.com
FL Engineering License #7917 FL Geology License #GB564 FL Surveying License #LB7062
1/3
Ms. Theresa Pepe Florida Department of Environmental Protection Waste Site Cleanup Section 2600 Blair Stone Road, MS 4515 Tallahassee, Florida 32399-2400
Date: June 6, 2025 Our Ref:
Subject: July 29, 2025 Contractor Review Meeting
Dear Ms. Pepe, Arcadis U.S., Inc. (Arcadis) is pleased to submit the following proposal/cost estimate to attend a site review meeting for currently assigned Arcadis sites, as requested by the Florida Department of Environmental Protection (FDEP) Waste Cleanup Section (WCS). This proposal includes the scope of work pursuant to recent communications with FDEP. An estimate of costs with a schedule for completion is included.
SCOPE OF WORK
Task 1: Project Management
Project management includes technical support and general administrative tasks related to the items below.
Task 2: Site Review Meeting
This task provides funding for a high-level review of site conditions and preparation of review material (e.g., power point slides/figures) to facilitate discussion during the meeting. The presentation will focus on all of Arcadis’ currently assigned State Cleanup Sites (8 sites) and select Drycleaning sites (8 sites). Site reviews will be focused on the following:
Presentation of recent data.
Remedial system updates.
Additional site work required.
Transitioning sites to monitoring.
Status of inactive remedial systems.
Injection sites (additional injections or different technology).
Eligibility for RMO II closure; and, Miscellaneous updates as needed.
Florida Department of Environmental Protection June 6, 2025
Use or disclosure of information contained on this sheet is subject to the restriction and disclaimer located on the signature page of this document. 2/3
Task 3: Meeting Attendance
The July 29, 2025 meeting will be attended by Gus Suarez, P.E./Contract Administrator, Doug McGlone, P.G., and John Perella, P.E. As communicated by FDEP, although we anticipate attendance by three staff, only costs for two Arcadis staff have been included. This task provides funding for travel, related expenses, and meeting attendance. The Final Deliverable will be a written summary of the meeting notes.
SCHEDULE
Arcadis will begin coordinating schedules immediately following receipt of a signed Task Assignment. The currently scheduled meeting date is July 29, 2025 at the FDEP office in Tallahassee, FL.
Florida Department of Environmental Protection June 6, 2025
This proposal and its contents shall not be duplicated, used or disclosed — in whole or in part — for any purpose other than to evaluate the proposal. This proposal is not intended to be binding or form the terms of a contract. The scope and price of this proposal will be superseded by the contract. If this proposal is accepted and a contract is awarded to Arcadis as a result of — or in connection with — the submission of this proposal, Arcadis and/or the client shall have the right to make appropriate revisions of its terms, including scope and price, for purposes of the contract. Further, client shall have the right to duplicate, use or disclose the data contained in this proposal only to the extent provided in the resulting contract.
www.arcadis.com Arcadis July 2025 Site Review Meeting Proposal
3/3
COST ESTIMATE
Level of Effort (LOE) Forms and a Cost Estimate Form (CEF) that present estimated project costs are enclosed as Attachment 1.
CLOSING REMARKS
Arcadis appreciates the opportunity to assist the FDEP WCS. If you have any questions or wish to discuss this proposal, please contact the undersigned.
Sincerely, Arcadis U.S., Inc.
Gus Suarez, P.E.
Project Manager
Email: gus.suarez@arcadis.com Direct Line: 813.353.5778 Mobile: 813.205.4703
Enclosures:
Attachment 1 - CEF-LOE