This document is a Past Performance Questionnaire (PPQ) template for the Naval Facilities Engineering Command (NAVFAC) solicitation N6247026R0012, designed to capture contractor performance evaluations for federal contract submissions. The PPQ provides a comprehensive evaluation framework with detailed rating scales across seven performance categories: Quality, Schedule/Timeliness, Customer Satisfaction, Management/Personnel/Labor, Cost/Financial Management, Safety/Security, and General Performance. Contractors are expected to submit either a completed Contractor Performance Assessment Reporting System (CPARS) evaluation or this PPQ for each project included in their proposal, with ratings ranging from Exceptional (E) to Unsatisfactory (U) across multiple sub-elements.

The solicitation specifically relates to a Multiple Award Construction Contract (MACC) for design-build and design-bid-build construction projects primarily located at Portsmouth Naval Shipyard in Kittery, ME, and Norfolk Naval Shipyard in Portsmouth, VA. Offerors must carefully complete the PPQ, ensuring accurate client contact information and following submission guidelines, which include the option to have clients submit questionnaires directly to the government point of contact, Weston Polen, via email prior to the proposal closing date. The document emphasizes that contractors will not be rated lower than Satisfactory solely for not performing beyond contract requirements and provides a structured method for clients to assess a contractor's performance across critical project dimensions.

View the file

Other files

File Type Posted
AMENDMENT 0011 Attachments.zip ZIP file
Solicitation Amendment N6247026R00120011 SF 30.pdf PDF
Att. GG) Amendment 0011 Attachment Table of Contents.pdf PDF
222_M-703_R1_AMENDMENT 010.pdf PDF
96_AE105_R2_AMENDMENT 010.pdf PDF
183_P-701_R1_AMENDMENT 010.pdf PDF
123_AE444_R1_AMENDMENT 010.pdf PDF
Att. Y) PPI responses AMD 0010.pdf PDF
Att. FF) Amendment 0010 Attachment Table of Contents.pdf PDF
14 24 23_AMENDMENT 010.pdf PDF
120_AE441_R1_AMENDMENT 010.pdf PDF
179_P-402_R1_AMENDMENT 010.pdf PDF
171_P-103_R1_AMENDMENT 010.pdf PDF
01 11 00.00 22_AMENDMENT 010.pdf PDF
164_PD102_R1_AMENDMENT 010.pdf PDF
132_AE601_R1_AMENDMENT 010.pdf PDF
275_ET102_R1_AMENDMENT 010.pdf PDF
182_P-601_R2_AMENDMENT 010.pdf PDF
126_AE511_R1_AMENDMENT 010.pdf PDF
101_AE121_R1_AMENDMENT 010.pdf PDF
74_SP101_R1_AMENDMENT 010.pdf PDF
176_P-108_R1_AMENDMENT 010.pdf PDF
178_P-401_R2_AMENDMENT 010.pdf PDF
_B60_Continuation Sheet_Amendment 010_03-31-26.pdf PDF
173_P-105_R1_AMENDMENT 010.pdf PDF
119_AE440_R1_AMENDMENT 010.pdf PDF
138_AE640_R1_AMENDMENT 010.pdf PDF
174_P-106_R1_AMENDMENT 010.pdf PDF
180_P-403_R1_AMENDMENT 010.pdf PDF
172_P-104_R1_AMENDMENT 010.pdf PDF
186_MD102_R1_AMENDMENT 010.pdf PDF
169_P-101_R1_AMENDMENT 010.pdf PDF
177_P-109_R1_AMENDMENT 010.pdf PDF
114_AE401_R1_AMENDMENT 010.pdf PDF
677 attach Attic_AFPR.pdf PDF
161_Q-601_R2_AMENDMENT 010.pdf PDF
170_P-102_R1_AMENDMENT 010.pdf PDF
Solicitation Amendment N6247026R00120010 SF 30.pdf PDF
175_P-107_R1_AMENDMENT 010.pdf PDF
01 30 10.00 22_AMENDMENT 010.pdf PDF
Att. T) Price Schedule AMD 0010.pdf PDF
115_AE402_R1_AMENDMENT 010.pdf PDF
249_EP102_R1_AMENDMENT 009.pdf PDF
252_EP105_R1_AMENDMENT 009.pdf PDF
256_EP502_R1_AMENDMENT 009.pdf PDF
255_EP501_R1_AMENDMENT 009.pdf PDF
Att. EE) Amendment 0009 Attachment Table of Contents.pdf PDF
18_HM101_R1_AMENDMENT 009.pdf PDF
07 22 00_R1_AMENDMENT 009.pdf PDF
238_FX400_R1_AMENDMENT 009.pdf PDF
Show 40 more

Latest 50 of 157 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT C

Solicitation Submittal Requirements: IF A COMPLETED CPARS EVALUATION IS AVAILABLE, IT SHALL BE SUBMITTED WITH THE PROPOSAL. IF THERE IS NOT A COMPLETED CPARS EVALUATION, the Past Performance Questionnaire (PPQ) included in the solicitation is provided for the offeror or its team members to submit to the client for each project the offeror includes in its proposal for Factor 1, Corporate Experience. AN OFFEROR SHALL NOT SUBMIT A PPQ WHEN A COMPLETED CPARS IS AVAILABLE.

IF A CPARS EVALUATION IS NOT AVAILABLE, ensure correct phone numbers and email addresses are provided for the client point of contact. Completed PPQs should be submitted with your proposal. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror should complete and submit with the proposal the first page of the PPQ (Attachment C), which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government's point of contact, Weston Polen, via email at Weston.c.polen.civ@us.navy.mil prior to proposal closing date. Offerors shall not incorporate by reference into their proposal PPQs or CPARS previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.

Solicitation TitleNXXXXX-XX-R-XXXX
LocationSource Selection Plan

N62470-26-R-0012 Attachment C

Revised April 2012 51

SOURCE SELECTION SENSITIVE INFORMATION

DISCLOSURE LIMITATIONS AS OUTLINED IN FAR 2.101 & 3.104 APPLY

ATTACHMENT C

NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0)

CONTRACT INFORMATION (Contractor to complete Blocks 1-4)

1. Contractor Information
Firm Name:CAGE Code:
Address:Entity Identifier Number:

Phone Number:

Email Address:

Point of Contact: Contact Phone Number:

2. Work Performed as: |_| Prime Contractor |_| Sub Contractor |_| Joint Venture |_| Other (Explain) Percent of project work performed:

If subcontractor, who was the prime (Name/Phone #):

3. Contract Information Contract Number:

Delivery/Task Order Number (if applicable):

Contract Type: |_| Firm Fixed Price |_| Cost Reimbursement |_| Other (Please specify):

Contract Title:

Contract Location:

Award Date (mm/dd/yy):

Contract Completion Date (mm/dd/yy):

Actual Completion Date (mm/dd/yy):

Explain Differences:

Original Contract Price (Award Amount):

Final Contract Price (to include all modifications, if applicable):

Explain Differences:

4. Project Description:

Complexity of Work |_| High |_| Med |_| Routine How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)

CLIENT INFORMATION (Client to complete Blocks 5-8)

5. Client Information Name:

Title:

Phone Number:

Email Address:

6. Describe the client’s role in the project:

7. Date Questionnaire was completed (mm/dd/yy):

8. Client’s Signature:

NOTE: NAVFAC REQUESTS THAT THE CLIENT COMPLETE THIS QUESTIONNAIRE AND SUBMIT DIRECTLY BACK TO THE OFFEROR. THE OFFEROR WILL SUBMIT THE COMPLETED QUESTIONNAIRE TO NAVFAC WITH THEIR PROPOSAL, AND MAY DUPLICATE THIS QUESTIONNAIRE FOR FUTURE SUBMISSION ON NAVFAC SOLICITATIONS. CLIENTS ARE HIGHLY ENCOURAGED TO SUBMIT QUESTIONNAIRES DIRECTLY TO THE OFFEROR. HOWEVER, QUESTIONNAIRES MAY BE SUBMITTED DIRECTLY TO NAVFAC. PLEASE CONTACT THE OFFEROR FOR NAVFAC POC INFORMATION. THE GOVERNMENT RESERVES THE RIGHT TO VERIFY ANY AND ALL INFORMATION ON THIS FORM.

ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE

RATING DEFINITION NOTE

(E) Exceptional
Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.
An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.
(VG) Very Good
Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.
(S) Satisfactory
Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract. There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.
(M) Marginal
Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.
A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.
(U) Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.
An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.
(N) Not Applicable
No information or did not apply to your contract
Rating will be neither positive nor negative.

Contractor Information (Firm Name): ________________________________________________ Client Information (Name): ________________________________________________________

TO BE COMPLETED BY CLIENT

PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST REFLECTS

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.

1. QUALITY:

a) Quality of technical data/report preparation efforts
E VG S M U N
b) Ability to meet quality standards specified for technical performance
E VG S M U N
c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance
E VG S M U N
d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)
E VG S M U N

2. SCHEDULE/TIMELINESS OF PERFORMANCE:

a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)
E VG S M U N
b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract
E VG S M U N

3. CUSTOMER SATISFACTION:

a) To what extent were the end users satisfied with the project?
E VG S M U N
b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes; responsiveness to administrative reports, businesslike and communication)
E VG S M U N
c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer?
E VG S M U N
d) Overall customer satisfaction
E VG S M U N

4. MANAGEMENT/ PERSONNEL/LABOR

a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force?
E VG S M U N
b) Ability to hire, apply, and retain a qualified workforce to this effort
E VG S M U N
c) Government Property Control
E VG S M U N
d) Knowledge/expertise demonstrated by contractor personnel
E VG S M U N
e) Utilization of Small Business concerns
E VG S M U N
f) Ability to simultaneously manage multiple projects with multiple disciplines
E VG S M U N
g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes
E VG S M U N
h) Effectiveness of overall management (including ability to effectively lead, manage and control the program)
E VG S M U N

5. COST/FINANCIAL MANAGEMENT

a) Ability to meet the terms and conditions within the contractually agreed price(s)?
E VG S M U N

Contractor Information (Firm Name): ________________________________________________ Client Information (Name): ________________________________________________________

b) Contractor proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client
E VG S M U N
c) If this is/was a Government cost type contract, please rate the Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns)
E VG S M U N
d) Is the Contractor’s accounting system adequate for management and tracking of costs? If no, please explain in Remarks section.
Yes No
e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.
Yes No
f) Have there been any indications that the contractor has had any financial problems? If yes, please explain below.
Yes No

6. SAFETY/SECURITY

a) To what extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues? (Includes: following the users rules, regulations, and requirements regarding housekeeping, safety, correction of noted deficiencies, etc.)
E VG S M U N
b) Contractor complied with all security requirements for the project and personnel security requirements.
E VG S M U N

7. GENERAL

a) Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).
E VG S M U N
b) Compliance with contractual terms/provisions (explain if specific issues)
E VG S M U N
c) Would you hire or work with this firm again? (If no, please explain below)
Yes No
d) In summary, provide an overall rating for the work performed by this contractor.
E VG S M U N

Please provide responses to the questions above (if applicable) and/or additional remarks. Furthermore, please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk (please attach additional pages if necessary):