AF Form 66 - B847.xlsx

XLSX spreadsheet 77 KB Posted

Attached to
B847 Repair HVAC & Electrical Federal contract opportunity
Solicitation number
FA302224R0006
Issued by
Department of the Air Force Air Education and Training Command

About this file

This document is an AF Form 66 (Substitute) - Schedule of Material Submittals related to a federal contract opportunity to repair HVAC and electrical systems in Building 847. The key details are:

The project, titled "REPAIR HVAC/ELECTRICAL, B847", has a project number of EEPZ230570 and a start date of 18-Apr-24. The contract number is not provided. The document lists numerous material submittals required from the contractor, including work/construction plans, as-built drawings, progress schedule, guarantees and warranties, hazardous materials reports, and submittals for various HVAC, plumbing, electrical, and architectural components. The document provides a detailed tracking sheet for the contractor to list hazardous materials to be used during the project.

The related federal contract opportunity is for a project to replace, modify, and upgrade mechanical and electrical equipment in Building 847, with an estimated value between $250,000 and $500,000. The solicitation number is FA302224R0006. A site visit is highly encouraged but not mandatory, with a deadline to notify the point of contact. All Requests for Information must be submitted by 12:00 PM CST on 11-Jul-24. Contractors must complete CUI training and sign an acknowledgment to gain access to the associated drawings and documents.

View the file

Other files for this federal contract opportunity

Other files attached to B847 Repair HVAC & Electrical, newest first.
File Type Posted
Solicitation Amendment FA302224R00060001 SF 30.pdf PDF
B847 Design Build SOW -- Revised 22 Jul 24.pdf PDF
RFI_01 Answers FA302224R0006.pdf PDF
B847 Electricity Consumption.xlsx XLSX spreadsheet
Contractor CUI Training Slides.pptx PPTX presentation
Appendix A - Cost Breakdown.xlsx XLSX spreadsheet
CAFB Mechanical Standards.pdf PDF
CAFB Electrical Standards.pdf PDF
Solicitation - FA302224R0006.pdf PDF
Design Build SOW -- B847.pdf PDF
Wage Determination DBA MS20240045.pdf PDF
MFR Contractor CUI Training Acknowledgment for Solicitations.pdf PDF
CAFB Special Construction.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

General

Project No:Project Title:Date:
EEPZ230570REPAIR HVAC/ELECTRICAL, B84718-Apr-24
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
1Work/Construction/phasing PlanBASICX
3As-Built DrawingsBASICX
4Progress ScheduleBASICX
5Guarantees and WarrantiesBASICX
6Superintendent's Qualifications and ExperienceBASICX

AF Form 66 (Substitute) GENERAL Page&Pof&N

SCHEDULE OF MATERIAL SUBMITTALS

Environmental

Project No:Project Title:Date:
EEPZ230570REPAIR HVAC/ELECTRICAL, B84718-Apr-24
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
7Appropriate SDSBASIC
8Hazardous waste reportBASIC
9Hazardous Material Report (AF Form 3000)BASIC
10Recycled Material Report/Construction Debris reportBASIC
11Storm Water Pollution Prevention Plan with Best Management Practices IdentifiedBASIC
12Weekly Inspection Reports for ProjectsBASIC

AF Form 66 (Substitute) Environmental Page&Pof &N

SCHEDULE OF MATERIAL SUBMITTALS

Architectural

Project No:Project Title:Date:
EEPZ230570REPAIR HVAC/ELECTRICAL, B84718-Apr-24
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
13DoorsXX

AF Form 66 (Substitute) Architectural Page&Pof&N

Civil

Project No:Project Title:Date:
EEPZ230570REPAIR HVAC/ELECTRICAL, B84718-Apr-24
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
14ConcreteX

AF Form 66 (Substitute) CIVIL Page&Pof &N

Mechanical

Project No:Project Title:Date:
EEPZ230570REPAIR HVAC/ELECTRICAL, B84718-Apr-24
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
17Air handlerXXX
Chilled water pumpXXX
Heated water pumpXXX
Circulating pumpXXX
ChillerXXX
Chilled water pipingX
15Heated water pipingX
16Piping insulationX
17Expansion tanksX
18Backflow preventerX
19Control valvesX
20SensorsX
21GaugesX
22Isolation valvesX
23Balancing valvesX
24Make up water pipingX
25Chemical feederXXX
26Exhaust fanXXX
27Hydronic heater

AF Form 66 (Substitute) Mechanical Page&Pof&N

Electrical

Project No:Project Title:Date:
EEPZ230570REPAIR HVAC/ELECTRICAL, B84718-Apr-24
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
28Air handler VFDXXX
29Hands Off Auto switchesXXX
30DisconnectsXXX
31BreakersX
32WiringX
33ConduitX
34LightsXXX

AF Form 66 (Substitute) Electrical Page&Pof &N

Special Systems

Project No:Project Title:Date:
EEPZ230570REPAIR HVAC/ELECTRICAL, B84718-Apr-24
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
NONE

AF Form 66 (Substitute) Special Systems Page&Pof &N

HAZMAT Tracking Sheet

Contractor Hazardous Materials Usage Tracking Form
Return this form to Contracting/Project Manager with Manufacturers original SDS
EEPZ230570REPAIR HVAC/ELECTRICAL, B847Contract #
Start Date:End Date:Cotractor:
Product Name as seen on SDS
Process (How is material used)Part #ManufacturerType of
ContainerSize of ContainerTotal

Quantity

UsedEESOH MSN
1
Process:
2
Process:
3
Process:
4
Process:
5
Process:
6
Process:
7
Process:
8
Process:
9
Process:
10
Process:
11
Process:
12
Process:
13
Process:
14
Process:
15
Process:
16
Process:
17
Process:
18
Process:
19
Process:
20
Process:
21
Process:
22
Process:
23
Process:
24
Process:
25
Process:
26
Process:
27
Process:
28
Process:

Example and Instructions

WORKSHEET INSTRUCTIONS
BLOCKDESCRIPTIONINFORMATION REQUIRED
AProject NumberProject number or Opportunity number assigned to the project by Civil Engineering.
BProject TitleThe title of the project.
CContract NumberThe contract number or delivery order assigned by contracting.
DProduct NameThe name of the product as listed on the SDS.
EProcessA Brief description of the work performed with each material.
FPart #The part number as listed on the SDS.
GManufacturerThe name of the Manufacturer of the product (not the distributor)
HType of ContainerThe type of container that the product comes in. Example: can, barrel, bottle, container, cylinder, drum, etc…
ISize of ContainerSize as listed on container. Example: oz, lbs, Liter, Quart, Gallon, etc…
JTotal Quantity UsedThis will be the amount that you anticipate using for the first submission. At the conclusion of the project you will need to provide a final list with updated quantities.
KEESOH MSNThis is the Material Stock Number assigned for EESOH-MIS tracking. (The Air Force Hazardous Materials Manager will provide this number)

NOTE: Complete the HAZMAT Tracking Sheet located on the first TAB of this Excel spreadsheet with all hazardous materials to be used during the duration of the construction project. Once completed, save the sheet as a .pdf file and submit to the contracting officer with an AF Form 3000 Submittal form. This data will need to be submitted prior to construction start. When construction is complete, you will submit a final revised report with updated quanties.