Solicitation - FA302224R0006.pdf

PDF 945 KB Posted

Attached to
B847 Repair HVAC & Electrical Federal contract opportunity
Solicitation number
FA302224R0006
Issued by
Department of the Air Force Air Education and Training Command

About this file

This document is a solicitation for the repair of HVAC and electrical systems in Building 847. The requirement is to replace, modify, and upgrade the mechanical and electrical equipment in the building, including the mechanical room and yard. The government is offering a site visit on July 9, 2024, which is highly encouraged but not mandatory. All requests for information must be submitted by July 11, 2024. The range of magnitude for this procurement is between $250,000 and $500,000. Contractors must complete CUI training and submit an acknowledgment form to gain access to the drawings and associated documentation. The solicitation number is FA302224R0006, and it is being issued by the Department of the Air Force Air Education and Training Command.

View the file

Other files for this federal contract opportunity

Other files attached to B847 Repair HVAC & Electrical, newest first.
File Type Posted
Solicitation Amendment FA302224R00060001 SF 30.pdf PDF
B847 Design Build SOW -- Revised 22 Jul 24.pdf PDF
RFI_01 Answers FA302224R0006.pdf PDF
B847 Electricity Consumption.xlsx XLSX spreadsheet
Appendix A - Cost Breakdown.xlsx XLSX spreadsheet
CAFB Mechanical Standards.pdf PDF
CAFB Electrical Standards.pdf PDF
AF Form 66 - B847.xlsx XLSX spreadsheet
Design Build SOW -- B847.pdf PDF
Wage Determination DBA MS20240045.pdf PDF
MFR Contractor CUI Training Acknowledgment for Solicitations.pdf PDF
CAFB Special Construction.pdf PDF
Contractor CUI Training Slides.pptx PPTX presentation
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR

INFORMATION CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

CODE

6. PROJECT NUMBER

8. ADDRESS OFFER TO

4. CONTRACT NUMBER

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

INVITATION FOR BID

NEGOTIATED (RFP)

REQUEST FOR PROPOSAL

3. DATE ISSUED PAGE OF PAGES

Created On:

25 Jun 2024, 15:47 PM Central Daylight Time

AWARD (To be completed by Government)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES

CODE AT

27. PAYMENT WILL BE MADE BY

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

Section A - Solicitation/Contract Form

Repair HVAC & Electrical, B847

Header only - Purchase Requisition Number: F1N3BC4120AW01 Date: 22 May 2024

Product Service Code: Z2NB Date: 22 May 2024

FA302224R0006

Section B - Supplies or Services & Prices or Costs

Additional Information/Notes

Item Supplies/Service Quantity Unit Unit Price Amount

Complete requirement IAW attached

SOW.

Product Service Code: Z1FB Signal Code: A Weapon System Code: 000 Claimant Program Code: C2 Pricing Arrangement: Firm Fixed Price

1 Job

000101 Funding SLIN only. PR # TBD.

Section C - Description/Specifications/Statement of Work

Requirements Repair HVAC and Electrical, B847

Section D - Packaging and Marking

Section E - Inspection and Acceptance

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate/ Deviation

Variation Effective Date

52.246-12 Inspection of Construction. Aug 1996

Overall Contract Inspection/Acceptance Locations

Inspection and Acceptance Location

Both Destination Instructions: Period of Performance is 210 days.

DoDAAC: F1N3BC CountryCode: USA

14 CES CECC

AF BPN NO MILSBILLS PROCESSES, 555 SIMLER BLVD STE 110

COLUMBUS, MS 39710-6010

UNITED STATES

Section F - Deliveries or Performance

Overall Contract Delivery Period

From date of lead time event to beginning of performance 10 Calendar Days Date of Notice to Proceed Receipt

From date of lead time event to completion of performance 210 Calendar Days Date of Notice to Proceed Receipt

Line Item Delivery Schedule Quantity Address and POC

Delivery Schedule From date of lead time event to completion of performance 210 Calendar Days Date of Notice to Proceed Receipt

1 Job Place of Performance DoDAAC: F1N3BC CountryCode: USA

14 CES CECC

AF BPN NO MILSBILLS PROCESSES, 555 SIMLER

BLVD STE 110

COLUMBUS, MS 39710-6010

UNITED STATES

Section G - Contract Administration Data

DFARS Clauses Incorporated by Reference

Number Title Effective Date

Alternate/ Deviation

Variation Effective Date

252.231-7000 Supplemental Cost Principles Dec 1991 252.232-7003 Electronic Submission of Payment Requests and Receiving Reports. Dec 2018 252.236-7000 Modification Proposals--Price Breakdown. Dec 1991

DFARS Clauses Incorporated by Full Text

252.232-7006 Wide Area WorkFlow Payment Instructions. (Jan 2023)

As prescribed in 232.7004(b), use the following clause:

WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)

(a) Definitions. As used in this clause-

"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.

"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.

"Payment request" and "receiving report" are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall-

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/

(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:

(1) Document type. The Contractor shall submit payment requests using the following document type(s):

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items-

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

Combo

(Contracting Officer: Insert applicable invoice and receiving report document type(s) for fixed price line items that require shipment of a deliverable.)

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.

Combo

(Contracting Officer: Insert either "Invoice 2in1" or the applicable invoice and receiving report document type(s) for fixed price line items for services.)

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial financing, submit a commercial financing request.

(2) ) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

[Note: The Contractor may use a WAWF "combo" document type to create some combinations of invoice and receiving report in one step.]

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF Pay Official DoDAAC F877700 Issue By DoDAAC FA3022 Admin DoDAAC FA3022 Inspect By DoDAAC F1N3BC Ship To Code N/A Ship From Code N/A Mark For Code N/A Service Approver (DoDAAC) F1N3BC Service Acceptor (DoDAAC) F1N3BC Accept at Other DoDAAC N/A LPO DoDAAC N/A DCAA Auditor DoDAAC N/A Other DoDAAC(s) N/A (*Contracting Officer: Insert applicable DoDAAC information. If multiple ship to/acceptance locations apply, insert "See Schedule" or "Not applicable.")

(**Contracting Officer: If the contract provides for progress payments or performance-based payments, insert the DoDAAC for the contract administration office assigned the functions under FAR 42.302(a)(13).)

(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.

N/A

(Contracting Officer: Insert applicable information or "Not applicable.")

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

(End of clause)

Section H - Special Contract Requirements

Section I - Contract Clauses

52.204-29 Federal Acquisition Supply Chain Security Act Orders--Representation and Disclosures.

As prescribed in , insert the following provision: (b)4.2306

Federal Supply Chain Security Act Orders--Representation and Disclosures (Dec 2023) Acquisition

(a) Definitions. As used in this provision, Covered article, FASCSA order, Intelligence community, National security system, Reasonable inquiry, and have the meaning provided in the clause , Sensitive compartmented information, Sensitive compartmented information system, Source 52.204-30

Federal Supply Chain Security Act Orders--Prohibition. Acquisition

(b) Prohibition. Contractors are prohibited from providing or using as part of the performance of the contract any covered article, or any or products services produced or provided by a source, if the prohibition is set out in an applicable Federal Supply Chain Security Act (FASCSA) Acquisition order, as described in paragraph (b)(1) of FAR , Federal Supply Chain Security Act Orders--Prohibition. 52.204-30 Acquisition

(c) Procedures.

(1) The search for the phrase "FASCSA order" in the )( for any covered Offeror shall System for Award Management (SAM )https://www.sam.gov article, or any or services produced or provided by a source, if there is an applicable FASCSA order described in paragraph (b)(1) of FAR products

, Federal Supply Chain Security Act Orders--Prohibition.52.204-30 Acquisition

(2) The review the for any FASCSA orders that are not in SAM, but are effective and do apply to the and Offeror shall solicitation solicitation resultant contract (see FAR (c)(2)). 4.2303

(3) FASCSA orders issued after the date of do not apply unless added by an amendment to the . solicitation solicitation

(d) Representation. By submission of this , the represents that it has conducted a reasonable inquiry, and that the does not propose offer offeror offeror to provide or use in response to this any covered article, or any or services produced or provided by a source, if the covered solicitation products article or the source is prohibited by an applicable FASCSA order in effect on the date the was issued, except as waived by the solicitation solicitation , or as disclosed in paragraph (e).

(e) Disclosures. The purpose for this disclosure is so the Government decide whether to issue a waiver. For any covered article, or any may products or services produced or provided by a source, if the covered article or the source is subject to an applicable FASCSA order, and the is unable Offeror to represent compliance, then the provide the following information as part of the : Offeror shall offer

(1) Name of the product or service provided to the Government;

(2) Name of the covered article or source subject to a FASCSA order;

(3) If applicable, name of the vendor, including the Commercial and Government Entity code and (if known), that supplied the unique entity identifier covered article or the product or service to the ; Offeror

(4) Brand;

(5) Model number (original equipment manufacturer number, manufacturer part number, or wholesaler number);

(6) Item description;

(7) Reason why the applicable covered article or the product or service is being provided or used;

(f) review of disclosures.Executive agency The will review disclosures provided in paragraph (e) to determine if any waiver contracting officer may be sought. A choose not to pursue a waiver for covered articles or sources otherwise subject to a FASCSA order and contracting officer may may instead make an award to an that does not require a waiver. offeror

(End of provision)

52.211-10 Commencement, Prosecution, and Completion of Work.

FA302224R0006

https://www.acquisition.gov/far/part-4#FAR_4_2306 https://www.acquisition.gov/far/part-52#FAR_52_204_30 https://www.acquisition.gov/far/part-52#FAR_52_204_30 https://www.sam.gov/ https://www.acquisition.gov/far/part-52#FAR_52_204_30 https://www.acquisition.gov/far/part-4#FAR_4_2303

As prescribed in , insert the following clause in and contracts when a fixed-price contract is contemplated. The (b)11.404 solicitations construction clause be changed to accommodate the issuance of orders under indefinite-delivery contracts for . may construction

Commencement, Prosecution, and Completion of Work (Apr 1984)

The Contractor be required to (a) commence work under this contract within _________ [ ] calendar days after shall insert numberContracting Officer the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than ______________.* The time stated for completion include final cleanup of the premises. shall

* The specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date. Contracting Officer shall

(End of clause)

IAlternate (Apr 1984). If the completion date is expressed as a specific calendar date, computed on the basis of the contractor receiving the notice to proceed by a certain , add the following paragraph to the basic clause: day

The completion date is based on the assumption that the successful will receive the notice to proceed by _______________ [ offeror Contracting ]. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice insert dateOfficer to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the . offer

(End of clause)

52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving.

As prescribed in , insert the following clause: 26.605

Encouraging Contractor Policies to Ban While Driving ( 2024) Text Messaging MAY

(a) Definitions. As used in this clause-

"Driving"-

(1) Means operating a motor vehicle on an active roadway with the motor running, including while temporarily stationary because of traffic, a traffic light, stop sign, or otherwise.

(2) Does not include operating a motor vehicle with or without the motor running when one has pulled over to the side of, or off, an active roadway and has halted in a location where one can safely remain stationary.

Text messaging means reading from or entering data into any handheld or other electronic device, including for the purpose of short message service texting, e-mailing, instant messaging, obtaining navigational information, or engaging in any other form of electronic data retrieval or electronic data communication. The term does not include glancing at or listening to a navigational device that is secured in a commercially designed holder affixed to the vehicle, provided that the destination and route are programmed into the device either before driving or while stopped in a location off the roadway where it is safe and legal to park.

(b) This clause implements Executive Order 13513, Federal Leadership on Reducing While Driving, dated October 1, 2009. Text Messaging

FA302224R0006

https://www.acquisition.gov/far/part-11#FAR_11_404 https://www.acquisition.gov/far/part-26#FAR_26_605

(c) The Contractor is encouraged to-

(1) Adopt and enforce policies that ban while driving- text messaging

(i) Company-owned or rented vehicles or Government-owned vehicles; or

(ii) Privately-owned vehicles when on official Government business or when performing any work for or on behalf of the Government.

(2) Conduct initiatives in a manner commensurate with the size of the business, such as-

(i) Establishment of new rules and programs or reevaluation of existing programs to prohibit while driving; and text messaging

(ii) Education, awareness, and other outreach to employees about the safety risks associated with texting while driving.

(d) Subcontracts. The Contractor insert the substance of this clause, including this paragraph (d), in all subcontracts that exceed the shall micro- , as defined in Federal Regulation on the date of subcontract award.purchase threshold Acquisition 2.101

(End of clause)

52.249-2 Termination for Convenience of the Government (Fixed-Price).

As prescribed in (b)(1)(i), insert the following clause: 49.502

Termination for Convenience of the Government (Fixed-Price) (Apr 2012)

(a) The Government terminate performance of work under this contract in whole or, from time to time, in part if the may Contracting Officer determines that a termination is in the Government's interest. The terminate by delivering to the Contractor a Notice of Contracting Officer shall Termination specifying the extent of termination and the effective date.

(b) After receipt of a Notice of Termination, and except as directed by the , the Contractor immediately proceed with the Contracting Officer shall following obligations, regardless of any delay in determining or adjusting any amounts due under this clause:

(1) Stop work as specified in the notice.

(2) Place no further subcontracts or orders (referred to as subcontracts in this clause) for materials, services, or facilities, except as necessary to complete the . continued portion of the contract

(3) Terminate all subcontracts to the extent they relate to the work terminated.

(4) Assign to the Government, as directed by the , all right, title, and interest of the Contractor under the subcontracts terminated, Contracting Officer in which case the Government have the right to settle or to pay any termination settlement proposal arising out of those terminations. shall

(5) With approval or ratification to the extent required by the , settle all outstanding liabilities and termination settlement Contracting Officer proposals arising from the termination of subcontracts; the approval or ratification will be final for purposes of this clause.

(6) As directed by the , transfer title and deliver to the Government- Contracting Officer

(i) The fabricated or unfabricated parts, work in process, completed work, , and other material produced or acquired for the work terminated; supplies and

FA302224R0006

https://www.acquisition.gov/far/part-2#FAR_2_101 https://www.acquisition.gov/far/part-49#FAR_49_502

(ii) The completed or partially completed plans, drawings, information, and other property that, if the contract had been completed, would be required to be furnished to the Government.

(7) Complete performance of the work not terminated.

(8) Take any action that be necessary, or that the direct, for the protection and preservation of the property related to this may Contracting Officer may contract that is in the possession of the Contractor and in which the Government has or acquire an interest. may

(9) Use its best efforts to sell, as directed or authorized by the , any property of the types referred to in paragraph (b)(6) of this Contracting Officer clause; , however, that the Contractor (i)is not required to extend credit to any purchaser and (ii) acquire the property under the provided may conditions prescribed by, and at prices approved by, the . The proceeds of any transfer or disposition will be applied to reduce any Contracting Officer payments to be made by the Government under this contract, credited to the price or cost of the work, or paid in any other manner directed by the

.Contracting Officer

(c) The Contractor submit complete schedules no later than 120 days from the , unless shall termination inventory effective date of termination extended by the upon written request of the Contractor within this 120- period. in writing Contracting Officer day

(d) After expiration of the plant clearance period as defined in Subpart of the Federal Regulation, the Contractor submit to the 49.001 Acquisition may a list, certified as to quantity and quality, of not previously disposed of, excluding items authorized for Contracting Officer termination inventory disposition by the . The Contractor request the Government to remove those items or enter into an agreement for their Contracting Officer may storage. Within 15 days, the Government will accept title to those items and remove them or enter into a storage agreement. The Contracting Officer verify the list upon removal of the items, or if stored, within 45 days from submission of the list, and correct the list, as necessary, before may shall final settlement.

(e) After termination, the Contractor submit a final termination settlement proposal to the in the form and with the shall Contracting Officer certification prescribed by the . The Contractor submit the proposal promptly, but no later than 1 year from the Contracting Officer shall effective date

, unless extended by the upon written request of the Contractor within this 1-year period. However, if theof termination in writing Contracting Officer determines that the facts justify it, a termination settlement proposal be received and acted on after 1 year or any extension. If Contracting Officer may the Contractor fails to submit the proposal within the time allowed, the determine, on the basis of information available, the Contracting Officer may amount, if any, due the Contractor because of the termination and pay the amount determined. shall

(f) Subject to paragraph (e) of this clause, the Contractor and the agree upon the whole or any part of the amount to be paid Contracting Officer may or remaining to be paid because of the termination. The amount include a reasonable allowance for profit on work done. However, the agreed may amount, whether under this paragraph (f) or paragraph (g) of this clause, exclusive of costs shown in paragraph (g)(3) of this clause, not exceed may the total contract price as reduced by (1) the amount of payments previously made and (2) the contract price of work not terminated. The contract shall be modified, and the Contractor paid the agreed amount. Paragraph (g) of this clause not limit, restrict, or affect the amount that be agreed shall may upon to be paid under this paragraph.

(g) If the Contractor and the fail to agree on the whole amount to be paid because of the termination of work, the Contracting Officer Contracting pay the Contractor the amounts determined by the as follows, but without duplication of any amounts agreed on Officer shall Contracting Officer under paragraph (f) of this clause:

(1) The contract price for completed or services accepted by the Government (or sold or acquired under paragraph (b)(9) of this clause) not supplies previously paid for, adjusted for any saving of and other charges. freight

(2) The total of-

(i) The costs incurred in the performance of the work terminated, including initial costs and preparatory expense allocable thereto, but excluding any costs attributable to or services paid or to be paid under paragraph (g)(1) of this clause; supplies

(ii) The cost of settling and paying termination settlement proposals under terminated subcontracts that are properly chargeable to the terminated if not included in subdivision (g)(2)(i) of this clause; andportion of the contract

(iii) A sum, as profit on subdivision (g)(2)(i) of this clause, determined by the under of the Federal Regulation, Contracting Officer 49.202 Acquisition in effect on the date of this contract, to be fair and reasonable; however, if it appears that the Contractor would have sustained a loss on the entire contract had it been completed, the allow no profit under this subdivision (g)(2)(iii) and reduce the settlement to reflect Contracting Officer shall shall the indicated rate of loss.

(3) The reasonable costs of settlement of the work terminated, including-

(i) Accounting, legal, clerical, and other expenses reasonably necessary for the preparation of termination settlement proposals and supporting data;

(ii) The termination and settlement of subcontracts (excluding the amounts of such settlements); and

(iii) Storage, transportation, and other costs incurred, reasonably necessary for the preservation, protection, or disposition of the . termination inventory

(h) Except for normal spoilage, and except to the extent that the Government expressly assumed the risk of loss, the exclude Contracting Officer shall from the amounts payable to the Contractor under paragraph (g) of this clause, the fair value as determined by the , for the loss of Contracting Officer the Government property.

FA302224R0006

https://www.acquisition.gov/far/part-49#FAR_49_001 https://www.acquisition.gov/far/part-49#FAR_49_202

(i) The cost principles and procedures of of the Federal Regulation, in effect on the date of this contract, govern all costs part 31 Acquisition shall claimed, agreed to, or determined under this clause.

(j) The Contractor have the right of appeal, under the Disputes clause, from any determination made by the under paragraph shall Contracting Officer (e), (g), or (l) of this clause, except that if the Contractor failed to submit the termination settlement proposal or request for equitable adjustment within the time provided in paragraph (e) or (l), respectively, and failed to request a time extension, there is no right of appeal.

(k) In arriving at the amount due the Contractor under this clause, there be deducted- shall

(1) All unliquidated advance or other payments to the Contractor under the terminated portion of this contract;

(2) Any which the Government has against the Contractor under this contract; and claim

(3) The agreed price for, or the proceeds of sale of, materials, , or other things acquired by the Contractor or sold under the provisions of this supplies clause and not recovered by or credited to the Government.

(l) If the termination is partial, the Contractor file a proposal with the for an equitable adjustment of the price(s) of the may Contracting Officer . The make any equitable adjustment agreed upon. Any proposal by the Contractor for an continued portion of the contract Contracting Officer shall equitable adjustment under this clause be requested within 90 days from the unless extended by the shall effective date of termination in writing .Contracting Officer

(m)

(1) The Government , under the terms and conditions it prescribes, make partial payments and payments against costs incurred by the Contractor may for the , if the believes the total of these payments will not exceed the amount to which the terminated portion of the contract Contracting Officer Contractor will be entitled.

(2) If the total payments exceed the amount finally determined to be due, the Contractor repay the excess to the Government upon demand, shall together with interest computed at the rate established by the Secretary of the Treasury under 50 U.S.C. App.1215(b)(2). Interest be computed shall for the period from the date the excess payment is received by the Contractor to the date the excess is repaid. Interest not be charged on any shall excess payment due to a reduction in the Contractor's termination settlement proposal because of retention or other disposition of termination until 10 days after the date of the retention or disposition, or a later date determined by the because of the circumstances.inventory Contracting Officer

(n) Unless otherwise provided in this contract or by statute, the Contractor maintain all records and documents relating to the terminated portion shall of this contract for 3 years after final settlement. This includes all books and other evidence bearing on the Contractor's costs and expenses under this contract. The Contractor make these records and documents available to the Government, at the Contractor's office, at all reasonable times, shall without any direct charge. If approved by the , photographs, microphotographs, or other authentic reproductions be Contracting Officer may maintained instead of original records and documents.

(End of clause)

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate/ Deviation

Variation Effective Date

52.202-1 Definitions. Jun 2020 52.203-3 Gratuities. Apr 1984 52.203-5 Covenant Against Contingent Fees. May 2014 52.203-6 Restrictions on Subcontractor Sales to the Government. Jun 2020 52.203-7 Anti-Kickback Procedures. Jun 2020 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity. May 2014 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity. May 2014 52.203-12 Limitation on Payments to Influence Certain Federal Transactions. Jun 2020 52.203-13 Contractor Code of Business Ethics and Conduct. Nov 2021 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements. Jan 2017 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper. May 2011 52.204-9 Personal Identity Verification of Contractor Personnel. Jan 2011 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. Jun 2020 52.204-13 System for Award Management Maintenance. Oct 2018 52.204-18 Commercial and Government Entity Code Maintenance. Aug 2020 52.204-19 Incorporation by Reference of Representations and Certifications. Dec 2014

52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities.

Dec 2023

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

Nov 2021

52.204-27 Prohibition on a ByteDance Covered Application. Jun 2023 Protecting the Government's Interest When Subcontracting with Contractors Debarred, FA302224R0006 https://www.acquisition.gov/far/part-31#FAR_Part_31

52.209-6 Suspended, or Proposed for Debarment. Nov 2021 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters. Oct 2018 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations. Nov 2015 52.211-13 Time Extensions. Sep 2000 52.213-1 Fast Payment Procedure. May 2006 52.219-3 Notice of HUBZone Set-Aside or Sole-Source Award. Oct 2022 52.219-6 Notice of Total Small Business Set-Aside. Nov 2020 52.219-6 Notice of Total Small Business Set-Aside. (Alternate I) Nov 2020 Alternate I Mar 2020 52.219-8 Utilization of Small Business Concerns. Feb 2024

52.219-27 Notice of Set-Aside for, or Sole-Source Award to, Service-Disabled Veteran-Owned Small Business (SDVOSB) Concerns Eligible Under the SDVOSB Program.

Feb 2024

52.219-29 Notice of Set-Aside for, or Sole-Source Award to, Economically Disadvantaged Women- Owned Small Business Concerns.

Oct 2022

52.219-30 Notice of Set-Aside for, or Sole-Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program.

Oct 2022

52.219-33 Nonmanufacturer Rule. Sep 2021 52.222-3 Convict Labor. Jun 2003 52.222-4 Contract Work Hours and Safety Standards -Overtime Compensation. May 2018 52.222-6 Construction Wage Rate Requirements. Aug 2018 52.222-7 Withholding of Funds. May 2014 52.222-8 Payrolls and Basic Records. Jul 2021 52.222-9 Apprentices and Trainees. Jul 2005 52.222-10 Compliance with Copeland Act Requirements. Feb 1988 52.222-11 Subcontracts (Labor Standards). May 2014 52.222-12 Contract Termination-Debarment. May 2014 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations. May 2014 52.222-14 Disputes Concerning Labor Standards. Feb 1988 52.222-15 Certification of Eligibility. May 2014 52.222-21 Prohibition of Segregated Facilities. Apr 2015 52.222-26 Equal Opportunity. Sep 2016 52.222-27 Affirmative Action Compliance Requirements for Construction. Apr 2015

52.222-30 Construction Wage Rate Requirements-Price Adjustment (None or Separately Specified Method).

Aug 2018

52.222-35 Equal Opportunity for Veterans. Jun 2020 52.222-36 Equal Opportunity for Workers with Disabilities. Jun 2020 52.222-37 Employment Reports on Veterans. Jun 2020 52.222-41 Service Contract Labor Standards. Aug 2018

52.222-43 Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment (Multiple Year and Option Contracts).

Aug 2018

52.222-54 Employment Eligibility Verification. May 2022 52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026. Jan 2022 52.222-62 Paid Sick Leave Under Executive Order 13706. Jan 2022 52.223-5 Pollution Prevention and Right-to-Know Information. May 2011 52.223-6 Drug-Free Workplace. May 2001

52.223-12 Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners.

Jun 2016

52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. Jun 2020 52.223-21 Foams. Jun 2016 52.225-13 Restrictions on Certain Foreign Purchases. Feb 2021 52.228-2 Additional Bond Security. Oct 1997 52.228-5 Insurance-Work on a Government Installation. Jan 1997 52.229-3 Federal, State, and Local Taxes. Feb 2013 52.229-12 Tax on Certain Foreign Procurements. Feb 2021 52.232-17 Interest. May 2014 52.232-18 Availability of Funds. Apr 1984 52.232-23 Assignment of Claims. May 2014 52.232-33 Payment by Electronic Funds Transfer-System for Award Management. Oct 2018 52.232-39 Unenforceability of Unauthorized Obligations. Jun 2013 52.232-40 Providing Accelerated Payments to Small Business Subcontractors. Mar 2023 52.233-1 Disputes. May 2014 52.233-4 Applicable Law for Breach of Contract Claim. Oct 2004 52.236-2 Differing Site Conditions. Apr 1984 52.236-3 Site Investigation and Conditions Affecting the Work. Apr 1984 52.236-5 Material and Workmanship. Apr 1984 52.236-6 Superintendence by the Contractor. Apr 1984 52.236-7 Permits and Responsibilities. Nov 1991 52.236-8 Other Contracts. Apr 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. Apr 1984 52.236-10 Operations and Storage Areas. Apr 1984 52.236-11 Use and Possession Prior to Completion. Apr 1984 52.236-12 Cleaning Up. Apr 1984 52.236-15 Schedules for Construction Contracts. Apr 1984

52.236-17 Layout of Work. Apr 1984 52.236-21 Specifications and Drawings for Construction. Feb 1997 52.242-13 Bankruptcy. Jul 1995 52.242-14 Suspension of Work. Apr 1984 52.243-4 Changes. Jun 2007 52.244-6 Subcontracts for Commercial Products and Commercial Services. Feb 2024 52.249-10 Default (Fixed-Price Construction). Apr 1984 52.253-1 Computer Generated Forms. Jan 1991

DFARS Clauses Incorporated by Reference

Number Title Effective Date

Alternate/ Deviation

Variation Effective Date

252.203-7000 Requirements Relating to Compensation of Former DoD Officials. Sep 2011 252.203-7001 Prohibition on Persons Convicted of Fraud or Other Defense-Contract-Related Felonies. Jan 2023 252.203-7002 Requirement to Inform Employees of Whistleblower Rights. Dec 2022 252.203-7003 Agency Office of the Inspector General. Aug 2019 252.203-7004 Display of Hotline Posters. Jan 2023 252.204-7000 Disclosure of Information. Oct 2016 252.204-7003 Control of Government Personnel Work Product. Apr 1992 252.204-7004 Antiterrorism Awareness Training for Contractors. Jan 2023 252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting. Jan 2023 252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support. Jan 2023

252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services.

Jan 2023

252.204-7020 NIST SP 800-171 DoD Assessment Requirements. Nov 2023 252.205-7000 Provision of Information to Cooperative Agreement Holders. Jun 2023

252.209-7004 Subcontracting with Firms that are Owned or Controlled by the Government of a Country that is a State Sponsor of Terrorism.

May 2019

252.222-7002 Compliance with Local Labor Laws (Overseas). Jun 1997 252.222-7006 Restrictions on the Use of Mandatory Arbitration Agreements. Jan 2023 252.223-7004 Drug-Free Work Force. Sep 1988 252.223-7006 Prohibition on Storage, Treatment, and Disposal of Toxic or Hazardous Materials. Sep 2014 252.223-7008 Prohibition of Hexavalent Chromium. Jan 2023 252.225-7048 Export-Controlled Items. Jun 2013 252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime. Jan 2023

252.226-7001 Utilization of Indian Organizations, Indian-Owned Economic Enterprises, and Native Hawaiian Small Business Concerns.

Jan 2023

252.232-7010 Levies on Contract Payments. Dec 2006 252.236-7005 Airfield Safety Precautions. Dec 1991 252.237-7010 Prohibition on Interrogation of Detainees by Contractor Personnel. Jan 2023 252.239-7001 Information Assurance Contractor Training and Certification. Jan 2008 252.242-7005 Contractor Business Systems. Feb 2012 252.242-7006 Accounting System Administration. Feb 2012 252.243-7001 Pricing of Contract Modifications. Dec 1991 252.243-7002 Requests for Equitable Adjustment. Dec 2022 252.244-7000 Subcontracts for Commercial Products or Commercial Services. Nov 2023 252.246-7004 Safety of Facilities, Infrastructure, and Equipment for Military Operations. Oct 2010 252.247-7023 Transportation of Supplies by Sea. Jan 2023

FAR Clauses Incorporated by Full Text

52.204-1 Approval of Contract. (Dec 1989)

As prescribed in 4.103 , insert the following clause:

Approval of Contract (Dec 1989)

This contract is subject to the written approval of ____[identify title of designated agency official here] and shall not be binding until so approved.

(End of clause)

52.211-10 Commencement, Prosecution, and Completion of Work. (Apr 1984)

As prescribed in 11.404(b), insert the following clause in solicitations and contracts when a fixed-price construction contract is contemplated. The clause may be changed to accommodate the issuance of orders under indefinite-delivery contracts for construction.

Commencement, Prosecution, and Completion of Work (Apr 1984)

The Contractor shall be required to (a) commence work under this contract within ____[Contracting Officer insert number] calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than ____.

* The time stated for completion shall include final cleanup of the premises.

* The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.

(End of clause)

52.211-10 Commencement, Prosecution, and Completion of Work. (Alternate I) (Apr 1984) Alternate I (Apr 1984)

Alternate I (Apr 1984). If the completion date is expressed as a specific calendar date, computed on the basis of the contractor receiving the notice to proceed by a certain day, add the following paragraph to the basic clause:

The completion date is based on the assumption that the successful offeror will receive the notice to proceed by ____[Contracting Officer insert date].

The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.

52.211-12 Liquidated Damages-Construction. (Sep 2000)

As prescribed in 11.503(b), insert the following clause in solicitations and contracts:

Liquidated Damages-Construction (Sept 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $301.22[Contracting Officer insert amount] for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of clause)

52.217-9 Option to Extend the Term of the Contract. (Mar 2000)

As prescribed in 17.208(g), insert a clause substantially the same as the following:

Option to Extend the Term of the Contract (Mar 2000)

(a) The Government may extend the term of this contract by written notice to the Contractor within ____[insert the period of time within which the Contracting Officer may exercise the option]; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least ____ days[60days unless a different number of days is inserted] before the contract expires. The preliminary notice does not commit the Government to an extension.

(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.

(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed ____(months) (years).

(End of clause)

52.219-14 Limitations on Subcontracting. (Oct 2022)

As prescribed in 19.507(e), insert the following clause:

Limitations on Subcontracting (Oct 2022)

(a) This clause does not apply to the unrestricted portion of a partial set-aside.

(b) Definition. Similarly situated entity, as used in this clause, means a first-tier subcontractor, including an independent contractor, that-

(1) Has the same small business program status as that which qualified the prime contractor for the award (e.g., for a small business set-aside contract, any small business concern, without regard to its socioeconomic status); and

(2) Is considered small for the size standard under the North American Industry Classification System (NAICS) code the prime contractor assigned to the subcontract.

(c) Applicability. This clause applies only to-

(1) Contracts that have been set aside for any of the small business concerns identified in 19.000(a)(3);

(2) Part or parts of a multiple-award contract that have been set aside for any of the small business concerns identified in 19.000(a)(3);

(3) Contracts that have been awarded on a sole-source basis in accordance with subparts 19.8, 19.13, 19.14, and 19.15;

(4) Orders expected to exceed the simplified acquisition threshold and that are-

(i) Set aside for small business concerns under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or

(ii) Issued directly to small business concerns under multiple-award contracts as described in 19.504(c)(1)(ii);

(5) Orders, regardless of dollar value, that are-

(i) Set aside in accordance with subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F);

or

(ii) Issued directly to concerns that qualify for the programs described in subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 19.504(c)(1)(ii); and

(6) Contracts using the HUBZone price evaluation preference to award to a HUBZone small business concern unless the concern waived the evaluation preference.

(d) Independent contractors. An independent contractor shall be considered a subcontractor.

(e) Limitations on subcontracting. By submission of an offer and execution of a contract, the Contractor agrees that in performance of a contract assigned a North American Industry Classification System (NAICS) code for-

(1) Services (except construction), it will not pay more than 50 percent of the amount paid by the Government for contract performance to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded. When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract;

(2) Supplies (other than procurement from a nonmanufacturer of such supplies), it will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded. When a contract includes both supplies and services, the 50 percent limitation shall apply only to the supply portion of the contract;

(3) General construction, it will not pay more than 85 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 85 percent subcontract amount that cannot be exceeded; or

(4) Construction by special trade contractors, it will not pay more than 75 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 75 percent subcontract amount that cannot be exceeded.

(f) The Contractor shall comply with the limitations on subcontracting as follows:

(1) For contracts, in accordance with paragraphs (c)(1), (2), (3) and (6) of this clause-

[Contracting Officer check as appropriate.]

[ ] By the end of the base term of the contract and then by the end of each subsequent option period; or

[ ] By the end of the performance period for each order issued under the contract.

(2) For orders, in accordance with paragraphs (c)(4) and (5) of this clause, by the end of the performance period for the order.

(g) A joint venture agrees that, in the performance of the contract, the applicable percentage specified in paragraph (e) of this clause will be performed by the aggregate of the joint venture participants.

(1) In a joint venture comprised of a small business protégé and its mentor approved by the Small Business Administration, the small business protégé shall perform at least 40 percent of the work performed by the joint venture. Work performed by the small business protégé in the joint venture must be more than administrative functions.

(2) In an 8(a) joint venture, the 8(a) participant(s) shall perform at least 40 percent of the work performed by the joint venture. Work performed by the 8(a) participants in the joint venture must be more than administrative functions.

(End of clause)

52.219-28 Post-Award Small Business Program Rerepresentation. (Feb 2024)

As prescribed in 19.309(c)(1), insert the following clause:

Post-Award Small Business Program Rerepresentation (Feb 2024)

(a) Definitions. As used in this clause-

Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .