41 12 13.36 - Screw Bulk Material Conveyors.pdf

PDF 324 KB Posted

Attached to
Biosolids Project 011139.0465
Solicitation number
US.260443
Issued by
Lancaster County, Pennsylvania

About this file

This specification document outlines the screw bulk material conveyor requirements for the Biosolids Project 011139.0465 being administered by Ephrata Borough Authority in Pennsylvania. The project encompasses the procurement and installation of screw-type conveyors for conveying dewatered and dried sludge solids, including both extensions to existing conveyors (C-606 and C-607) and new shaftless screw conveyors (C-601 through C-605B, and C-625). The conveyor extensions shall be manufactured by SAVECO/WAM GROUP with a design capacity of 350 cubic feet per hour, while new conveyors by JDV Equipment range in capacity from 260 to 790 cubic feet per hour depending on the specific unit and media type. Bids for the overall project are due December 8, 2026, at 10:00 AM local time through PennBid, with a pre-bid open house scheduled for November 18, 2026, from 8:00 AM to 10:00 AM. The contract includes separate bids for General Construction (EBA26-2) and Electrical Construction (EBA26-3).

All conveyor materials shall be constructed of AISI 304 stainless steel components with 1-inch flight thickness and 3/8-inch thick ultrahigh molecular polyethylene wear liners. Motors shall be 460-volt, three-phase, inverter-duty rated severe duty motors with Variable Frequency Drive (VFD) control capability, and all electrical systems must comply with Section 26 specifications. The specification requires an 18-month manufacturer's warranty for proposed conveyors and mandates comprehensive factory testing with video documentation, minimum four-day on-site manufacturer representation for installation and startup, and four to eight hours of operational field testing prior to equipment acceptance. Welders must be AWS-qualified within the previous 12 months, and the manufacturer must have minimum three years of documented experience in conveyor manufacturing. All shop drawings, welder certificates, quality control test results, and installation certificates must be submitted for approval prior to payment.

View the file

Other files

File Type Posted
26 08 00 - Electrical Field Acceptance Tests.pdf PDF
00 63 25 - Substitution Request Form (During Construction).pdf PDF
40 05 36 - Fiberglass-Reinforced Plastic Process Pipe.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 60 00 - Project Forms.pdf PDF
26 29 23 - VFDs .pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
26 05 19 - Conductors.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
05 53 00 - Metal Gratings (VPR).pdf PDF
02 41 19.13 - Selective Building Demolition (VPR).pdf PDF
01 29 00 - Payment Procedures.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 64 00 - Owner Furnished Products.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
40 05 65.23 - Swing Check Valves.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
05 50 00 - Metal Fabrications (VPR).pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
26 09 16 - Auxiliary Controls & Relays.pdf PDF
01 10 00 - Project Summary.pdf PDF
05 52 00 - Metal Railings (VPR).pdf PDF
26 24 19 - MCC.pdf PDF
26 05 53 - Electrical System Identification.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 60 00 - Grouting (VPR).pdf PDF
01 61 00 - Product Requirements.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 31 00a Ephrata Boro Record Drawings.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
26 27 16 - Control Panels & Enclosures.pdf PDF
26 05 26 - Grounding.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 01 01 - LA Cover.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
32 92 19 - Seeding.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
05 31 23 - Steel Roof Decking (VPR).pdf PDF
00 52 00b - Agmnt btw Own and Cntr for Const Con Stip Price - Electrical Construction.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

41 12 13.36 – SCREW BULK MATERIAL CONVEYORS

Herbert Rowland & Grubic Inc. 41 12 13.36 - 1 011139.0465

SECTION 41 12 13.36 - SCREW BULK MATERIAL CONVEYORS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: Screw-type conveyors for conveying bulk material solids.

B. Related Requirements:

1. Section 05 50 00 - Metal Fabrications: Miscellaneous metalwork and fasteners as required by this Section.

2. Section 09 90 00 - Painting and Coating: Painting, coating, and touchups as required by this Section.

3. Section 26 29 23 - Variable-Frequency Motor Controllers: Variable-speed drive controllers as required by this Section.

1.2 REFERENCE STANDARDS

A. American Bearing Manufacturers Association:

1. ABMA 9 - Load Ratings and Fatigue Life for Ball Bearings.

2. ABMA 11 - Load Ratings and Fatigue Life for Roller Bearings.

B. American Gear Manufacturers Association:

1. AGMA 6013 - Standard for Industrial Enclosed Gear Drives.

C. American Welding Society:

1. AWS D14.1/D14.1M - Specification for Welding of Industrial and Mill Cranes and

Other Material Handling Equipment.

1.3 SUBMITTALS

A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.

B. Product Data: Submit manufacturer's product information for conveyor and component equipment.

C. Shop Drawings:

1. Submit dimensional drawings and details. Following field verification.

2. Indicate schedule of conveyor components.

3. Indicate materials of construction.

4. Submit detailed wiring and control diagrams.

5. Indicate installation and anchoring requirements, including fasteners and other details.

6. Indicate mounting details, and location and elevation of electrical controls and panels.

Herbert Rowland & Grubic Inc. 41 12 13.36 - 2 011139.0465

D. Manufacturer's Certificate: Certify that products meet or exceed specified requirements.

E. Welder Certificates: Certify welders and welding procedures employed on the Work, verifying AWS qualification within previous 12 months.

F. Manufacturer Instructions: Submit detailed instructions on installation requirements, including storage and handling procedures.

G. Source Quality-Control Submittals: Indicate results of factory tests and inspections.

H. Field Quality-Control Submittals: Indicate results of Contractor-furnished tests and inspections.

I. Manufacturer Reports: Certify that equipment has been installed according to manufacturer instructions.

J. Qualifications Statements:

1. Submit qualifications for manufacturer, installer, and welder.

1.4 QUALITY ASSURANCE

A. Welding: Comply with AWS D14.1/D14.1M.

1.5 QUALIFICATIONS

A. Manufacturer: Company specializing in manufacturing products specified in this Section with minimum three years' documented experience.

B. Welders: AWS qualified within previous 12 months for employed weld types.

1.6 DELIVERY, STORAGE, AND HANDLING

A. Section 01 60 00 - Product Requirements: Requirements for transporting, handling, storing, and protecting products.

B. Inspection: Accept materials on Site in manufacturer's original packaging and inspect for damage.

C. Store materials according to manufacturer instructions.

D. Protection:

1. Protect materials from moisture and dust by storing in clean, dry location remote from construction operations areas.

2. Provide additional protection according to manufacturer instructions.

Herbert Rowland & Grubic Inc. 41 12 13.36 - 3 011139.0465

1.7 WARRANTY

A. Section 01 70 00 - Execution and Closeout Requirements: Requirements for warranties.

B. Furnish 18-month manufacturer's warranty for screw conveyors and appurtenances, following substantial completion. Warranty shall only apply to conveyors provided under Article 2.2 (proposed conveyors, not extension).

PART 2 - PRODUCTS

2.1 CONVEYOR EXTENSIONS (C-606 AND C-607, AS SHOWN ON DRAWINGS)

A. Manufacturers:

1. SAVECO/WAM GROUP, No Substitutes.

B. Performance and Design Criteria

1. Design Capacity: 350 ft3/hr.

2. Screw Type: Shaftless.

3. Service Duty: Intermittent, daily.

4. Location: Indoor.

5. Media: Dewatered Sludge (20-22% Solids).

6. Material Density: 40+/- lb/ft3.

C. Description

1. Conveyors C-606 and C-607 shall be extended as shown on the Contract

Drawings. The existing manufacturer is SAVECO/WAM GROUP. The design intent is to utilize the existing motor, and extend the trough and spiral as shown on Drawings. Extend all components as required to interface with proposed bypass system (trough, liner, screw, cover, stops, etc.) and yield a complete operable system.

2. The existing motor is to be reutilized and be controlled by a Variable Frequence Drive (VFD). See Division 26 for VFD specifications.

3. Configuration: As indicated on Drawings.

4. Screw:

a. Material: To match existing.

b. Flight capable of conveying product capacity and all horsepower and torque loadings without exceeding 0.08 in/ft compression/deflection.

5. Flight Thickness: Match existing to be extended.

6. Trough:

a. Style: U-trough, with formed top flanges and integral end flanges.

b. Cover: Flat.

c. Material:

- To match existing.

d. Coupling: Manufacture’s Standard.

e. Hangers/Supports: Match existing.

f. Liners: Match existing.

7. Hardware: Type 304 Stainless Steel.

Herbert Rowland & Grubic Inc. 41 12 13.36 - 4 011139.0465

2.2 SCREW-TYPE BULK MATERIAL CONVEYORS

A. Manufacturers:

1. JDV Equipment, No Substitutions.

B. Performance and Design Criteria:

1. Design Capacity: See capacities listed below.

2. Screw Type: Shaftless.

3. Service Duty: Intermittent, daily.

4. Location: Indoor and outdoor.

5. Media: See table below.

C. Description:

1. Conveyor Designations:

a. C-601.

b. C-602.

c. C-603.

d. C-604.

e. C-605A.

f. C-605B.

g. C-625.

2. The shaftless screw conveyor system shall be designed to meet the following minimum performance and design requirements:

POSITION C-601 C-602 C-603 C-604 C-605A C-605B C-625

Type Shaftless Shaftless Shaftless Shaftless Shaftless Shaftless Shafted

Capacity (ft.³/hr.)

260 260 520 520 520 520 790

Material Sludge Sludge Sludge Sludge Sludge Sludge Dried Sludge

Material Density (lbs./ft.³)

40 40 40 40 40 40 45

Max Solids 22% 22% 22% 22% 22% 22% 99%

Angle (1) 20° 25° 28° 28° 0° 0° 0°

Max Screw Speed

(RPM)

20 20 20 20 20 20 20

Max Trough Fill

50% 50% 50% 50% 50% 50% 30%

Minimum Flight OD

11.2” 11.2” 12.4” 12.4” 14.3” 14.3” 18”

Min. Spiral Weight (per Ft.)

27 lbs. 27 lbs. 27 lbs. 27 lbs. 27 lbs. 27 lbs. 27 lbs.

Herbert Rowland & Grubic Inc. 41 12 13.36 - 5 011139.0465

POSITION C-601 C-602 C-603 C-604 C-605A C-605B C-625

Min.

Trough Width

12.5” 12.5” 14” 14” 16.5” 16.5” 17”

Min. HP 5.0 5.0 10.0 10.0 10.0 5.0 10.0

Drive Location

Discharge Discharge Discharge Discharge Discharge Discharge Discharge

Motor Type

TEFC TEFC XP XP XP XP TEFC

Reversing Screw

Yes Yes Yes Yes No Yes No

VFD Yes Yes Yes Yes No Yes No

Notes:

(1) See Drawings for locations and angles. All dimensions and lengths shall be field verified and fabricated accordingly.

3. Length: As indicated on Drawings and field verified.

4. Configuration: As indicated on Drawings.

5. Materials:

a. Chutes: AISI 304, ASTM A167, 18-8.

b. Troughs, End Plates, Covers: AISI 304, ASTM A167, 18-8.

c. Supports: AISI 304, ASTM A167, 18-8.

d. Hoppers: AISI 304, ASTM A167, 18-8.

e. Spiral Flighting: Cold formed, High Strength Micro Alloy Carbon Steel with a minimum hardness of 220 Brinell.

f. Wear Liner: Ultrahigh molecular polyethylene.

g. Bolts, Nuts, and Washers for conveyor support: SS Type.

h. For Conveyor Trough, Lids and Drive: SS Type.

i. Flighting capable of conveying product capacity and all horsepower and torque loadings without exceeding 0.08 in/ft compression/deflection.

6. Flight Thickness: 1 inch.

7. Trough:

a. Style: U-trough, with formed top flanges and integral end flanges.

b. Cover: Flat.

c. Material:

1) Type 304 stainless steel.

2) Trough Thickness: #11 gauge, minimum.

3) Cover Thickness: #12 gauge, minimum.

d. Couplings: Manufacturer's standard.

e. Hangers/Supports: Type 304 stainless steel, as shown on Drawings.

f. Liners: 3/8” thick, replaceable, UHMWP, held in place with fastener clips.

g. Low point of inclined conveyors shall include a 4-inch threaded drain connection.

D. Drive:

1. Type: severe duty motor.

a. 460V, 3-Phase, inverter-duty rated.

2. Bearings: Manufacturer’s standard.

Herbert Rowland & Grubic Inc. 41 12 13.36 - 6 011139.0465

3. Gear Reducers:

a. Comply with AGMA 6013.

b. Housing: Fully enclosed and oiltight.

c. Open Gearing: Enclosed with safety guard and removable covers for inspection and maintenance.

E. Emergency Shutdown

1. Full length trip cord and safety switch.

F. Manual Slide Gate

1. Size: As indicated on Drawings.

2. Operating Handle:

a. Provide manual operation T-handle for opening manual slide gates.

3. Material

a. Gate slide frame body: Type 304 stainless steel.

b. Slide gate blade: Type 304 Stainless steel, ¼” minimum thickness.

G. Electro-Mechanically Operated Slide Gates

1. Description: The slide gates shall be designed with a maximum vertical dimension of 10" including the electric operator. The slide gate shall be designed so that in the full, open position at least one rotation of the spiral is exposed to the opening in the direction of transport. The slide gates shall have an opening at least the full width of the conveyor. Minimum opening size shall be 12" x 14". The slide gates shall be fabricated entirely of AISI 304 stainless steel and suitable non-metallic components, all minimum 3/16" thickness.

2. Actuator:

a. NEMA 4X housing.

b. 480V, three-phase, TENV, high starting torque motor.

c. All metal gearing.

d. Anti-friction drive bearings.

e. Local control station on actuator to open/close gate when local Hand-Off-

Auto selector switch is in Hand.

f. Internal, independently adjustable positional switches to indicate fully open and close positions. Switches shall limit overtravel of actuator.

g. Internal control of actuator motor via external commands to open and close the slide gate.

h. Manual Override

3. Material:

a. Gate slide frame body: Type 304 stainless steel.

b. Slide gate blade: Type 304 stainless steel, 3/16” minimum thickness.

4. Actuator control & indicators:

a. In Auto.

b. Open.

c. Close.

d. Opened.

e. Closed.

f. Fail.

Herbert Rowland & Grubic Inc. 41 12 13.36 - 7 011139.0465

H. Flexible Connections: rubber impregnated 18 oz./yd. minimum canvas.

I. Operation:

1. Electrical Characteristics:

a. As specified in Section 26 05 03 - Equipment Wiring Connections.

b. Voltage: 460 V, three phase, 60 Hz.

c. Maximum Circuit Breaker Size: As shown on Electrical Drawings.

2. Motors: Explosion proof unless otherwise stated.

3. Control Panel: NEMA 4x.

4. Zero Speed Switch:

a. Non-contacting probe type, with stainless steel mounting hardware.

b. Built-in start-up time delay and zero-speed trip time delay.

c. SPDT, NO/NC Contact, 120VAC operating voltage.

5. Disconnect Switch: As shown on Drawings.

6. Operation Sequences: Centrifuge cake shall be transferred into the biodryer room via C-601, C-602, C-603, and C-604. Bypass Conveyors C-605A and C-605B will transport sludge out of the building if there are failures in the biodryer dryers or biodryer conveyors, to the outside bypass dumpster. Following biodryer processing, dried solids will be transported under normal operation via C-625 outside of the building to dumpster.

J. Finishes: To match existing or Manufacturer's standard.

K. Accessories:

1. Motion sensor.

2. Bearing sensor.

3. Emergency shutdown. Cord length full conveyor.

4. Support Feet and Saddles: Type 304 stainless steel.

2.3 SOURCE QUALITY CONTROL

A. Section 01 40 00 - Quality Requirements: Requirements for testing, inspection, and analysis.

B. Provide shop inspection and testing of completed assembly.

C. Conveyors shall be inspected and operated in the shop with the actual drive unit for this project in its entire length. Conveyor longer then the required shipping lengths will have the screws tack welded together and tested in their entire length. Conveyors should be operated for a minimum of 15 minutes and observed for alignment and abnormal operation. Conveyors shall be corrected as necessary. Prior to shipment the tack welds will be broken apart and conveyors suitably prepared for shipment. A video of the test should be supplied to the Contractor to be forwarded on to the Engineer for record purposes. Video must be received to get paid.

D. Control Panel:

1. Perform factory test of completed control panel by demonstrating operation of control functions, and provide certified test results.

Herbert Rowland & Grubic Inc. 41 12 13.36 - 8 011139.0465

2. Factory-assemble and test each control and alarm function.

3. Test sequence of operation.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Section 01 73 00 - Execution: Requirements for installation examination.

B. Verify that items provided by other Sections of Work are ready to receive Work of this Section.

3.2 INSTALLATION

A. According to manufacturer instructions and as indicated on Shop Drawings.

B. Touchup Painting and Coating: According to manufacturer instructions.

3.3 FIELD QUALITY CONTROL (FOR BOTH CONVEYOR MANUFACTURERS)

A. Section 01 40 00 - Quality Requirements: Requirements for inspecting and testing.

B. Inspection:

1. Ensure that hanger bearings and shafts are not loose.

2. Ensure that drive equipment is adequately braced.

3. Inspect for proper alignment of drive, tail, and coupling shafts.

4. Ensure that bearings are adequately lubricated.

5. Operate screw conveyor for four to eight hours and during this time inspect for:

a. Loud or unusual noise.

b. Excess vibration.

c. Overheated bearings.

d. Overheated drive assembly.

e. Contact or scrubbing of screw with trough or other components.

C. Manufacturer Services (for each Manufacturer): Furnish services of manufacturer's representative experienced in installation of products furnished under this Section for not less than four (4) days (8 hour days) on Site for installation, inspection, startup, field testing, and instructing Owner's personnel in operation and maintenance of equipment.

The manufacturers’ representative shall furnish to the Owner, through the Engineer, a written report certifying that the equipment has been properly installed and lubricated, is in accurate alignment, is free from any undue stress imposed by connecting piping or anchorage, and has been operated under full load conditions and that it operates satisfactorily.

D. Equipment Acceptance:

Herbert Rowland & Grubic Inc. 41 12 13.36 - 9 011139.0465

1. Adjust, repair, modify, or replace components failing to perform as specified and rerun tests.

2. Make final adjustments to equipment under direction of manufacturer's representative.

E. Furnish installation certificate from equipment manufacturer's representative attesting that equipment has been properly installed and is ready for startup and testing.

3.4 DEMONSTRATION

A. Section 01 73 00 - Requirements for demonstration and training.

B. Demonstrate equipment startup, shutdown, routine maintenance, and emergency repair procedures to Owner's personnel.

END OF SECTION

PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes: Screw-type conveyors for conveying bulk material solids.
B. Related Requirements:
1. Section 05 50 00 - Metal Fabrications: Miscellaneous metalwork and fasteners as required by this Section.
2. Section 09 90 00 - Painting and Coating: Painting, coating, and touchups as required by this Section.
3. Section 26 29 23 - Variable-Frequency Motor Controllers: Variable-speed drive controllers as required by this Section.
1.2 REFERENCE STANDARDS
A. American Bearing Manufacturers Association:
1. ABMA 9 - Load Ratings and Fatigue Life for Ball Bearings.
2. ABMA 11 - Load Ratings and Fatigue Life for Roller Bearings.
B. American Gear Manufacturers Association:
1. AGMA 6013 - Standard for Industrial Enclosed Gear Drives.
C. American Welding Society:
1. AWS D14.1/D14.1M - Specification for Welding of Industrial and Mill Cranes and Other Material Handling Equipment.
1.3 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Product Data: Submit manufacturer's product information for conveyor and component equipment.
C. Shop Drawings:
1. Submit dimensional drawings and details. Following field verification.
2. Indicate schedule of conveyor components.
3. Indicate materials of construction.
4. Submit detailed wiring and control diagrams.
5. Indicate installation and anchoring requirements, including fasteners and other details.
6. Indicate mounting details, and location and elevation of electrical controls and panels.
D. Manufacturer's Certificate: Certify that products meet or exceed specified requirements.
E. Welder Certificates: Certify welders and welding procedures employed on the Work, verifying AWS qualification within previous 12 months.
F. Manufacturer Instructions: Submit detailed instructions on installation requirements, including storage and handling procedures.
G. Source Quality-Control Submittals: Indicate results of factory tests and inspections.
H. Field Quality-Control Submittals: Indicate results of Contractor-furnished tests and inspections.
I. Manufacturer Reports: Certify that equipment has been installed according to manufacturer instructions.
J. Qualifications Statements:
1. Submit qualifications for manufacturer, installer, and welder.
1.4 QUALITY ASSURANCE
A. Welding: Comply with AWS D14.1/D14.1M.
1.5 QUALIFICATIONS
A. Manufacturer: Company specializing in manufacturing products specified in this Section with minimum three years' documented experience.
B. Welders: AWS qualified within previous 12 months for employed weld types.
1.6 DELIVERY, STORAGE, AND HANDLING
A. Section 01 60 00 - Product Requirements: Requirements for transporting, handling, storing, and protecting products.
B. Inspection: Accept materials on Site in manufacturer's original packaging and inspect for damage.
C. Store materials according to manufacturer instructions.
D. Protection:
1. Protect materials from moisture and dust by storing in clean, dry location remote from construction operations areas.
2. Provide additional protection according to manufacturer instructions.
1.7 WARRANTY
A. Section 01 70 00 - Execution and Closeout Requirements: Requirements for warranties.
B. Furnish 18-month manufacturer's warranty for screw conveyors and appurtenances, following substantial completion. Warranty shall only apply to conveyors provided under Article 2.2 (proposed conveyors, not extension).
PART 2 - PRODUCTS
2.1 CONVEYOR EXTENSIONS (C-606 AND C-607, AS SHOWN ON DRAWINGS)
A. Manufacturers:
1. SAVECO/WAM GROUP, No Substitutes.
B. Performance and Design Criteria
1. Design Capacity: 350 ft3/hr.
2. Screw Type: Shaftless.
3. Service Duty: Intermittent, daily.
4. Location: Indoor.
5. Media: Dewatered Sludge (20-22% Solids).
6. Material Density: 40+/- lb/ft3.
C. Description
1. Conveyors C-606 and C-607 shall be extended as shown on the Contract Drawings. The existing manufacturer is SAVECO/WAM GROUP. The design intent is to utilize the existing motor, and extend the trough and spiral as shown on Drawings. Extend all comp...
2. The existing motor is to be reutilized and be controlled by a Variable Frequence Drive (VFD). See Division 26 for VFD specifications.
3. Configuration: As indicated on Drawings.
4. Screw:
a. Material: To match existing.
b. Flight capable of conveying product capacity and all horsepower and torque loadings without exceeding 0.08 in/ft compression/deflection.
5. Flight Thickness: Match existing to be extended.
6. Trough:
a. Style: U-trough, with formed top flanges and integral end flanges.
b. Cover: Flat.
c. Material:
- To match existing.
d. Coupling: Manufacture’s Standard.
e. Hangers/Supports: Match existing.
f. Liners: Match existing.

7. Hardware: Type 304 Stainless Steel.

2.2 SCREW-TYPE BULK MATERIAL CONVEYORS
A. Manufacturers:
1. JDV Equipment, No Substitutions.
B. Performance and Design Criteria:
1. Design Capacity: See capacities listed below.
2. Screw Type: Shaftless.
3. Service Duty: Intermittent, daily.
4. Location: Indoor and outdoor.
5. Media: See table below.
C. Description:
1. Conveyor Designations:
a. C-601.
b. C-602.
c. C-603.
d. C-604.
e. C-605A.
f. C-605B.
g. C-625.
2. The shaftless screw conveyor system shall be designed to meet the following minimum performance and design requirements:
Notes:
(1) See Drawings for locations and angles. All dimensions and lengths shall be field verified and fabricated accordingly.
3. Length: As indicated on Drawings and field verified.
4. Configuration: As indicated on Drawings.
5. Materials:
a. Chutes: AISI 304, ASTM A167, 18-8.
b. Troughs, End Plates, Covers: AISI 304, ASTM A167, 18-8.
c. Supports: AISI 304, ASTM A167, 18-8.
d. Hoppers: AISI 304, ASTM A167, 18-8.
e. Spiral Flighting: Cold formed, High Strength Micro Alloy Carbon Steel with a minimum hardness of 220 Brinell.
f. Wear Liner: Ultrahigh molecular polyethylene.
g. Bolts, Nuts, and Washers for conveyor support: SS Type.
h. For Conveyor Trough, Lids and Drive: SS Type.
i. Flighting capable of conveying product capacity and all horsepower and torque loadings without exceeding 0.08 in/ft compression/deflection.
6. Flight Thickness: 1 inch.
7. Trough:
a. Style: U-trough, with formed top flanges and integral end flanges.
b. Cover: Flat.
c. Material:
1) Type 304 stainless steel.
2) Trough Thickness: #11 gauge, minimum.
3) Cover Thickness: #12 gauge, minimum.
d. Couplings: Manufacturer's standard.
e. Hangers/Supports: Type 304 stainless steel, as shown on Drawings.
f. Liners: 3/8” thick, replaceable, UHMWP, held in place with fastener clips.
g. Low point of inclined conveyors shall include a 4-inch threaded drain connection.
D. Drive:
1. Type: severe duty motor.
a. 460V, 3-Phase, inverter-duty rated.
2. Bearings: Manufacturer’s standard.
3. Gear Reducers:
a. Comply with AGMA 6013.
b. Housing: Fully enclosed and oiltight.
c. Open Gearing: Enclosed with safety guard and removable covers for inspection and maintenance.
E. Emergency Shutdown
1. Full length trip cord and safety switch.
F. Manual Slide Gate
1. Size: As indicated on Drawings.
2. Operating Handle:
a. Provide manual operation T-handle for opening manual slide gates.
3. Material
a. Gate slide frame body: Type 304 stainless steel.
b. Slide gate blade: Type 304 Stainless steel, ¼” minimum thickness.
G. Electro-Mechanically Operated Slide Gates
1. Description: The slide gates shall be designed with a maximum vertical dimension of 10" including the electric operator. The slide gate shall be designed so that in the full, open position at least one rotation of the spiral is exposed to the openi...
2. Actuator:
a. NEMA 4X housing.
b. 480V, three-phase, TENV, high starting torque motor.
c. All metal gearing.
d. Anti-friction drive bearings.
e. Local control station on actuator to open/close gate when local Hand-Off-Auto selector switch is in Hand.
f. Internal, independently adjustable positional switches to indicate fully open and close positions. Switches shall limit overtravel of actuator.
g. Internal control of actuator motor via external commands to open and close the slide gate.
h. Manual Override
3. Material:
a. Gate slide frame body: Type 304 stainless steel.
b. Slide gate blade: Type 304 stainless steel, 3/16” minimum thickness.
4. Actuator control & indicators:
a. In Auto.
b. Open.
c. Close.
d. Opened.
e. Closed.
f. Fail.
H. Flexible Connections: rubber impregnated 18 oz./yd. minimum canvas.
I. Operation:
1. Electrical Characteristics:
a. As specified in Section 26 05 03 - Equipment Wiring Connections.
b. Voltage: 460 V, three phase, 60 Hz.
c. Maximum Circuit Breaker Size: As shown on Electrical Drawings.
2. Motors: Explosion proof unless otherwise stated.
3. Control Panel: NEMA 4x.
4. Zero Speed Switch:
a. Non-contacting probe type, with stainless steel mounting hardware.
b. Built-in start-up time delay and zero-speed trip time delay.
c. SPDT, NO/NC Contact, 120VAC operating voltage.
5. Disconnect Switch: As shown on Drawings.
6. Operation Sequences: Centrifuge cake shall be transferred into the biodryer room via C-601, C-602, C-603, and C-604. Bypass Conveyors C-605A and C-605B will transport sludge out of the building if there are failures in the biodryer dryers or biodry...
J. Finishes: To match existing or Manufacturer's standard.
K. Accessories:
1. Motion sensor.
2. Bearing sensor.
3. Emergency shutdown. Cord length full conveyor.
4. Support Feet and Saddles: Type 304 stainless steel.
2.3 SOURCE QUALITY CONTROL
A. Section 01 40 00 - Quality Requirements: Requirements for testing, inspection, and analysis.
B. Provide shop inspection and testing of completed assembly.
C. Conveyors shall be inspected and operated in the shop with the actual drive unit for this project in its entire length. Conveyor longer then the required shipping lengths will have the screws tack welded together and tested in their entire length....
D. Control Panel:
1. Perform factory test of completed control panel by demonstrating operation of control functions, and provide certified test results.
2. Factory-assemble and test each control and alarm function.
3. Test sequence of operation.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Section 01 73 00 - Execution: Requirements for installation examination.
B. Verify that items provided by other Sections of Work are ready to receive Work of this Section.
3.2 INSTALLATION
A. According to manufacturer instructions and as indicated on Shop Drawings.
B. Touchup Painting and Coating: According to manufacturer instructions.
3.3 FIELD QUALITY CONTROL (FOR BOTH CONVEYOR MANUFACTURERS)
A. Section 01 40 00 - Quality Requirements: Requirements for inspecting and testing.
B. Inspection:
1. Ensure that hanger bearings and shafts are not loose.
2. Ensure that drive equipment is adequately braced.
3. Inspect for proper alignment of drive, tail, and coupling shafts.
4. Ensure that bearings are adequately lubricated.
5. Operate screw conveyor for four to eight hours and during this time inspect for:
a. Loud or unusual noise.
b. Excess vibration.
c. Overheated bearings.
d. Overheated drive assembly.
e. Contact or scrubbing of screw with trough or other components.
C. Manufacturer Services (for each Manufacturer): Furnish services of manufacturer's representative experienced in installation of products furnished under this Section for not less than four (4) days (8 hour days) on Site for installation, inspection...
D. Equipment Acceptance:
1. Adjust, repair, modify, or replace components failing to perform as specified and rerun tests.
2. Make final adjustments to equipment under direction of manufacturer's representative.

E. Furnish installation certificate from equipment manufacturer's representative attesting that equipment has been properly installed and is ready for startup and testing.

3.4 DEMONSTRATION
A. Section 01 73 00 - Requirements for demonstration and training.
B. Demonstrate equipment startup, shutdown, routine maintenance, and emergency repair procedures to Owner's personnel.