About this file
This is a Notice of Acceptability of Work document issued by Herbert, Rowland & Grubic, Inc., the Engineer, on behalf of the Ephrata Borough Authority (Owner) for the Biosolids Project 011139.0465. The Engineer recommends final payment to the Contractor and certifies that work furnished and performed under the Construction Contract is acceptable, subject to the provisions of the related Contract Documents and the Agreement between Owner and Engineer for Professional Services. The notice applies specifically to work observed during construction and is based on the Engineer's professional opinion and knowledge as of the Notice Date.
The Notice of Acceptability of Work explicitly contains significant limitations and disclaimers. The notice is not a guarantee or warranty of Contractor performance, does not constitute acceptance of defective work discovered after final inspection, and does not relieve the Contractor of any surviving obligations under the Construction Contract. The notice is issued with the skill and care ordinarily used by members of the engineering profession and is subject to the Owner's reservations of rights with respect to completion and final payment. The scope of the Engineer's assessment is expressly limited to facts within the Engineer's knowledge or those reasonably ascertainable through the specific responsibilities assigned under the Engineer's Agreement with the Owner.
View the file
Other files
Show 40 more
Latest 50 of 125 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Modified EJCDC® C 626, Notice of Acceptability of Work. Prepared and published 2016 by the Engineers Joint Contract Documents Committee.
Herbert, Rowland & Grubic, Inc. 00 65 19.23 - 1 011139.0465
NOTICE OF ACCEPTABILITY OF WORK
Owner: Ephrata Borough Authority Owner's Contract No.:
Contractor: Contractor’s Project No.:
Engineer: Herbert, Rowland and Grubic, Inc. Engineer's Project No.: 011139.0465
Project: Effective Date of Contract:
Contract:
The Engineer hereby gives notice to the above Owner and Contractor that Engineer has recommended final payment of Contractor, and that the Work furnished and performed by Contractor under the above Construction Contract is acceptable, expressly subject to the provisions of the related Contract Documents, the Agreement between Owner and Engineer for Professional Services dated ______, and the following terms and conditions of this Notice:
CONDITIONS OF NOTICE OF ACCEPTABILITY OF WORK
The Notice of Acceptability of Work (“Notice”) is expressly made subject to the following terms and conditions to which all those who receive said Notice and rely thereon agree:
1. This Notice is given with the skill and care ordinarily used by members of the engineering profession practicing under similar conditions at the same time and in the same locality.
2. This Notice reflects and is an expression of the Engineer’s professional opinion.
3. This Notice is given as to the best of Engineer’s knowledge, information, and belief as of the Notice Date.
4. This Notice is based entirely on and expressly limited by the scope of services Engineer has been employed by Owner to perform or furnish during construction of the Project (including observation of the Contractor’s work) under Engineer’s Agreement with Owner, and applies only to facts that are within Engineer’s knowledge or could reasonably have been ascertained by Engineer as a result of carrying out the responsibilities specifically assigned to Engineer under such Agreement.
5. This Notice is not a guarantee or warranty of Contractor’s performance under the Construction Contract, an acceptance of Work that is not in accordance with the related Contract Documents, including but not limited to defective Work discovered after final inspection, nor an assumption of responsibility for any failure of Contractor to furnish and perform the Work thereunder in accordance with the Construction Contract Documents, or to otherwise comply with the Construction Contract Documents or the terms of any special guarantees specified therein.
6. This Notice does not relieve Contractor of any surviving obligations under the Construction Contract, and is subject to Owner’s reservations of rights with respect to completion and final payment.
EXECUTED BY ENGINEER:
By:
(Authorized signature)
Name:
Title:
Notice Date:
File details come from the government source that posted it. Updated .