This is a technical specification document for identification systems for process piping, prepared for the Biosolids Project 011139.0465 by Ephrata Borough Authority in Pennsylvania. The specification establishes requirements for nameplates, tags, stencils, pipe markers, ceiling tacks, labels, and lockout devices to identify process piping systems in compliance with ASME A13.1 standards. The specification includes provisions for plastic tags (laminated three-layer plastic with engraved black letters), metal tags (stainless-steel construction with stamped letters), information tags (clear plastic with printed danger/caution/warning text, minimum 3-1/4 by 5-5/8 inches), and stencils with letter heights ranging from 1/2-inch to 1-3/4-inch depending on pipe outside diameter. Approved manufacturers include Seton Identification Products and Craftmark Pipe Markers. Installation requirements specify that piping identification shall not exceed 20 feet on straight runs, be positioned adjacent to each valve and tee, at each structure penetration, and at each obstruction. Underground plastic pipe markers must be installed 6 to 8 inches below finished grade directly above buried pipe. All identification devices must be installed after completion of coverings and painting using corrosion-resistant fasteners or adhesive.
The specification requires surface preparation including degreasing and cleaning prior to installation of adhesive-backed identification materials. Shop drawings must indicate wording, symbols, letter size, and color-coding for mechanical identification and valve charts. Maintenance material submittals include furnishing two containers of spray-on adhesive and special crimpers for the owner. Labels must be installed with sufficient adhesive for permanent adhesion and sealed with clear lacquer. Tags on valves in main and branch piping shall be numbered consecutively by location using corrosion-resistant chain, and piping 3/4-inch diameter and smaller must be identified with tags that indicate service, flow direction, and pressure. The specification references related sections including Section 09 90 00 (Painting and Coating) and Section 40 05 51 (Common Requirements for Process Valves), and requires compliance with manufacturer instructions for storage, handling, and installation.
View the file
Other files
Show 40 more
Latest 50 of 125 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
40 05 53 - IDENTIFICATION FOR PROCESS PIPING
Herbert, Rowland & Grubic, Inc. 40 05 53 - 1 011139.0465
SECTION 40 05 53 - IDENTIFICATION FOR PROCESS PIPING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Nameplates.
2. Tags.
3. Stencils.
4. Pipe markers.
5. Ceiling tacks.
6. Labels.
7. Lockout devices.
B. Related Requirements:
1. Section 09 90 00 - Painting and Coating: Requirements for painting as specified by this Section.
2. Section 40 05 51 - Common Requirements for Process Valves: Basic materials and methods for valves.
1.2 REFERENCE STANDARDS
A. ASME International:
1. ASME A13.1 - Scheme for the Identification of Piping Systems.
1.3 PREINSTALLATION MEETINGS
A. Section 01 31 19 – Project Meetings: Requirements for preinstallation meeting.
1.4 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Product Data: Submit manufacturer's catalog literature for each specified product.
C. Shop Drawings:
1. Indicate list of wording, symbols, letter size, and color-coding for mechanical identification and valve chart and schedule.
2. Indicate valve tag number, location, function, and valve manufacturer's name and model number.
D. Manufacturer's Certificate: Certify that products meet or exceed specified requirements.
E. Manufacturer Instructions: Submit detailed instructions on installation requirements, including storage and handling procedures.
Herbert, Rowland & Grubic, Inc. 40 05 53 - 2 011139.0465
1.5 CLOSEOUT SUBMITTALS
A. Section 01 77 00 - Closeout Requirements: Requirements for submittals.
B. Project Record Documents: Record actual locations of tagged valves; include valve tag numbers.
1.6 MAINTENANCE MATERIAL SUBMITTALS
A. Section 01 78 13 – Operations and Maintenance Manual Requirements: Requirements for maintenance materials.
B. Extra Stock Materials: Furnish two containers of spray-on adhesive for Owner.
C. Tools: Furnish special crimpers and other devices required for Owner to reinstall tags.
1.7 QUALITY ASSURANCE
A. Piping Color Scheme and Lettering Size: Comply with ASME A13.1.
1.8 DELIVERY, STORAGE, AND HANDLING
A. Section 01 61 00 - Product Requirements: Requirements for transporting, handling, storing, and protecting products.
B. Inspection: Accept materials on Site in manufacturer's original packaging and inspect for damage.
C. Store materials according to manufacturer instructions.
D. Protection:
1. Protect materials from moisture and dust by storing in clean, dry location remote from construction operations areas.
2. Provide additional protection according to manufacturer instructions.
PART 2 - PRODUCTS
2.1 TAGS
A. Plastic Tags:
1. Manufacturers:
a. Seton Identification Products.
b. Craftmark Pipe Markers, or
c. Approved equal.
d. Substitutions: Section 01 61 00 - Product Requirements.
2. Description:
a. Laminated three-layer plastic with engraved black letters on light, contrasting background color.
Herbert, Rowland & Grubic, Inc. 40 05 53 - 3 011139.0465
B. Metal Tags:
1. Manufacturers:
a. Seton Identification Products.
b. Craftmark Pipe Markers.
c. Or equal.
d. Substitutions: Section 01 61 00 - Product Requirements.
2. Description:
a. Stainless-steel construction; stamped letters.
C. Information Tags:
1. Description:
a. Clear plastic with printed text of [DANGER] [CAUTION] or [WARNING].
b. Minimum Tag Size: 3-1/4 by 5-5/8 inches.
c. Furnish grommet and self-locking nylon ties.
2. Tag Chart: Typewritten, letter-size list of applied tags and location.
2.2 STENCILS
A. Description:
1. Quality: Clean-cut symbols.
2. Letters:
a. Up to 2-Inch OD of Insulation or Pipe: 1/2-inch-high letters.
b. 2-1/2- to 6-Inch OD of Insulation or Pipe: 1-inch-high letters.
c. More Than 6-Inch OD of Insulation or Pipe: 1-3/4-inch high letters.
B. Stencil Paint:
1. Description: Semigloss enamel.
2. As specified in Section 09 90 00 - Painting and Coating.
2.3 PIPE MARKERS
A. Plastic Pipe Markers:
1. Manufacturers:
a. Seton Identification Products,
b. Craftmark Pipe Markers, or
c. Approved equal.
d. Substitutions: Section 01 61 00 - Product Requirements.
2. Description:
a. Factory-fabricated, flexible, and semi-rigid plastic.
b. Preformed to fit around pipe or pipe covering.
c. Larger sizes may be of maximum sheet size, with spring fastener.
B. Plastic Tape Pipe Markers:
1. Description: Flexible, vinyl film tape with pressure-sensitive adhesive backing and printed markings.
2.4 LABELS
A. Description:
Herbert, Rowland & Grubic, Inc. 40 05 53 - 4 011139.0465
1. Material: Laminated Mylar.
2. Minimum Size: 1.9 by 0.75 inches.
3. Adhesive backed, with printed identification.
2.5 LOCKOUT DEVICES
A. Manufacturers
1. Brady ID.
2. Masterlock Company.
3. Or Equal.
4. Substitutions: As specified in Section 01 61 00 - Product Requirements.
B. Lockout Hasps:
1. Description:
a. Material: Anodized aluminum or Reinforced nylon.
b. Furnish hasp with erasable label surface.
c. Minimum Size: 7-1/4 by 3 inches.
C. Valve Lockout Devices:
1. Description:
a. Material: Nylon.
b. Furnish device to restrict access to valve operator and to accept lock shackle.
PART 3 - EXECUTION
3.1 PREPARATION
A. Section 01 73 00 - Execution Requirements: Requirements for installation preparation.
B. Degrease and clean surfaces to receive adhesive for identification materials.
C. Stencil Painting: Prepare surfaces as specified in Section 09 90 00 - Painting and Coating.
3.2 INSTALLATION
A. According to manufacturer instructions.
B. Apply stencil painting as specified in Section 09 90 00 - Painting and Coating.
C. Install identifying devices after completion of coverings and painting.
D. Install plastic nameplates with corrosion-resistant mechanical fasteners or adhesive.
E. Labels:
1. Install labels with sufficient adhesive for permanent adhesion and seal with clear lacquer.
2. For unfinished covering, apply paint primer before applying labels.
Herbert, Rowland & Grubic, Inc. 40 05 53 - 5 011139.0465
F. Tags:
1. Identify valves in main and branch piping with tags.
2. Install tags using corrosion-resistant chain.
3. Number tags consecutively by location or as shown on Drawings.
G. Install underground plastic pipe markers 6 to 8 inches below finished grade, directly above buried pipe.
H. Piping:
1. Identify piping, concealed or exposed, with plastic pipe markers.
2. Use tags on piping 3/4-inch diameter and smaller.
3. Identify service, flow direction, and pressure.
4. Install in clear view and align with axis of piping.
5. Locate identification not to exceed 20 feet on straight runs, including risers and drops, adjacent to each valve and tee, at each side of penetration of structure or enclosure, and at each obstruction.
END OF SECTION
| PART 1 - GENERAL |
| 1.1 SUMMARY |
| A. Section Includes: |
| 1. Nameplates. |
| 2. Tags. |
| 3. Stencils. |
| 4. Pipe markers. |
| 5. Ceiling tacks. |
| 6. Labels. |
| 7. Lockout devices. |
| B. Related Requirements: |
| 1. Section 09 90 00 - Painting and Coating: Requirements for painting as specified by this Section. |
| 2. Section 40 05 51 - Common Requirements for Process Valves: Basic materials and methods for valves. |
| 1.2 REFERENCE STANDARDS |
| A. ASME International: |
| 1. ASME A13.1 - Scheme for the Identification of Piping Systems. |
| 1.3 PREINSTALLATION MEETINGS |
| A. Section 01 31 19 – Project Meetings: Requirements for preinstallation meeting. |
| 1.4 SUBMITTALS |
| A. Section 01 33 00 - Submittal Procedures: Requirements for submittals. |
| B. Product Data: Submit manufacturer's catalog literature for each specified product. |
| C. Shop Drawings: |
| 1. Indicate list of wording, symbols, letter size, and color-coding for mechanical identification and valve chart and schedule. |
| 2. Indicate valve tag number, location, function, and valve manufacturer's name and model number. |
| D. Manufacturer's Certificate: Certify that products meet or exceed specified requirements. |
| E. Manufacturer Instructions: Submit detailed instructions on installation requirements, including storage and handling procedures. |
| 1.5 CLOSEOUT SUBMITTALS |
| A. Section 01 77 00 - Closeout Requirements: Requirements for submittals. |
| B. Project Record Documents: Record actual locations of tagged valves; include valve tag numbers. |
| 1.6 MAINTENANCE MATERIAL SUBMITTALS |
| A. Section 01 78 13 – Operations and Maintenance Manual Requirements: Requirements for maintenance materials. |
| B. Extra Stock Materials: Furnish two containers of spray-on adhesive for Owner. |
| C. Tools: Furnish special crimpers and other devices required for Owner to reinstall tags. |
| 1.7 QUALITY ASSURANCE |
| A. Piping Color Scheme and Lettering Size: Comply with ASME A13.1. |
| 1.8 DELIVERY, STORAGE, AND HANDLING |
| A. Section 01 61 00 - Product Requirements: Requirements for transporting, handling, storing, and protecting products. |
| B. Inspection: Accept materials on Site in manufacturer's original packaging and inspect for damage. |
| C. Store materials according to manufacturer instructions. |
| D. Protection: |
| 1. Protect materials from moisture and dust by storing in clean, dry location remote from construction operations areas. |
| 2. Provide additional protection according to manufacturer instructions. |
| PART 2 - PRODUCTS |
| 2.1 TAGS |
| A. Plastic Tags: |
| 1. Manufacturers: |
| a. Seton Identification Products. |
| b. Craftmark Pipe Markers, or |
| c. Approved equal. |
| d. Substitutions: Section 01 61 00 - Product Requirements. |
| 2. Description: |
| a. Laminated three-layer plastic with engraved black letters on light, contrasting background color. |
| B. Metal Tags: |
| 1. Manufacturers: |
| a. Seton Identification Products. |
| b. Craftmark Pipe Markers. |
| c. Or equal. |
| d. Substitutions: Section 01 61 00 - Product Requirements. |
| 2. Description: |
| a. Stainless-steel construction; stamped letters. |
| C. Information Tags: |
| 1. Description: |
| a. Clear plastic with printed text of [DANGER] [CAUTION] or [WARNING]. |
| b. Minimum Tag Size: 3-1/4 by 5-5/8 inches. |
| c. Furnish grommet and self-locking nylon ties. |
2. Tag Chart: Typewritten, letter-size list of applied tags and location.
| 2.2 STENCILS |
| A. Description: |
| 1. Quality: Clean-cut symbols. |
| 2. Letters: |
| a. Up to 2-Inch OD of Insulation or Pipe: 1/2-inch-high letters. |
| b. 2-1/2- to 6-Inch OD of Insulation or Pipe: 1-inch-high letters. |
| c. More Than 6-Inch OD of Insulation or Pipe: 1-3/4-inch high letters. |
| B. Stencil Paint: |
| 1. Description: Semigloss enamel. |
| 2. As specified in Section 09 90 00 - Painting and Coating. |
| 2.3 PIPE MARKERS |
| A. Plastic Pipe Markers: |
| 1. Manufacturers: |
| a. Seton Identification Products, |
| b. Craftmark Pipe Markers, or |
| c. Approved equal. |
| d. Substitutions: Section 01 61 00 - Product Requirements. |
| 2. Description: |
| a. Factory-fabricated, flexible, and semi-rigid plastic. |
| b. Preformed to fit around pipe or pipe covering. |
| c. Larger sizes may be of maximum sheet size, with spring fastener. |
| B. Plastic Tape Pipe Markers: |
| 1. Description: Flexible, vinyl film tape with pressure-sensitive adhesive backing and printed markings. |
| 2.4 LABELS |
| A. Description: |
| 1. Material: Laminated Mylar. |
| 2. Minimum Size: 1.9 by 0.75 inches. |
| 3. Adhesive backed, with printed identification. |
| 2.5 LOCKOUT DEVICES |
| A. Manufacturers |
| 1. Brady ID. |
| 2. Masterlock Company. |
| 3. Or Equal. |
| 4. Substitutions: As specified in Section 01 61 00 - Product Requirements. |
| B. Lockout Hasps: |
| 1. Description: |
| a. Material: Anodized aluminum or Reinforced nylon. |
| b. Furnish hasp with erasable label surface. |
| c. Minimum Size: 7-1/4 by 3 inches. |
| C. Valve Lockout Devices: |
| 1. Description: |
| a. Material: Nylon. |
| b. Furnish device to restrict access to valve operator and to accept lock shackle. |
| PART 3 - EXECUTION |
| 3.1 PREPARATION |
| A. Section 01 73 00 - Execution Requirements: Requirements for installation preparation. |
| B. Degrease and clean surfaces to receive adhesive for identification materials. |
| C. Stencil Painting: Prepare surfaces as specified in Section 09 90 00 - Painting and Coating. |
| 3.2 INSTALLATION |
| A. According to manufacturer instructions. |
| B. Apply stencil painting as specified in Section 09 90 00 - Painting and Coating. |
| C. Install identifying devices after completion of coverings and painting. |
| D. Install plastic nameplates with corrosion-resistant mechanical fasteners or adhesive. |
| E. Labels: |
| 1. Install labels with sufficient adhesive for permanent adhesion and seal with clear lacquer. |
| 2. For unfinished covering, apply paint primer before applying labels. |
| F. Tags: |
| 1. Identify valves in main and branch piping with tags. |
| 2. Install tags using corrosion-resistant chain. |
| 3. Number tags consecutively by location or as shown on Drawings. |
| G. Install underground plastic pipe markers 6 to 8 inches below finished grade, directly above buried pipe. |
| H. Piping: |
| 1. Identify piping, concealed or exposed, with plastic pipe markers. |
| 2. Use tags on piping 3/4-inch diameter and smaller. |
| 3. Identify service, flow direction, and pressure. |
| 4. Install in clear view and align with axis of piping. |
| 5. Locate identification not to exceed 20 feet on straight runs, including risers and drops, adjacent to each valve and tee, at each side of penetration of structure or enclosure, and at each obstruction. |