This is a Project Record Documents specification section prepared by Herbert, Rowland & Grubic, Inc. for the Biosolids Project 011139.0465 managed by Ephrata Borough Authority in Pennsylvania. The specification establishes requirements for contractors to maintain comprehensive project record documentation throughout construction, including marked-up drawings, specifications, addenda, change orders, shop drawings, and product data. Contractors must record actual revisions to the work on-site at least weekly, with particular attention to concealed elements, underground utilities, dimensional changes, equipment locations, and field conditions. Record drawings must be marked with erasable red-colored pencil and organized into manageable sets with durable cover sheets identified as "PROJECT RECORD DRAWING." Additionally, contractors must submit a Manual for Materials and Finishes in two preliminary draft copies before work commences, one completed copy 15 days prior to final inspection, two sets of revised final volumes within ten days after final inspection, and a PDF composite electronic indexed file within ten days after final inspection. The manual must include product data with catalog numbers, composition, color and texture designations, manufacturer's care and maintenance instructions, and recommendations for inspections and repair of weather-exposed products.

The specification requires contractors to assemble miscellaneous record submittals including material and equipment test and inspection reports and delivery slips, which must be bound or filed and clearly identified. All record documents must be stored separately from construction documents and maintained with complete and accurate entries to enable future reference by the owner. The specification contains no pricing information, set-asides, or funding details, as it is a technical specification document establishing deliverable standards rather than a bid or contract award document.

View the file

Other files

File Type Posted
26 08 00 - Electrical Field Acceptance Tests.pdf PDF
00 63 25 - Substitution Request Form (During Construction).pdf PDF
40 05 36 - Fiberglass-Reinforced Plastic Process Pipe.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 60 00 - Project Forms.pdf PDF
26 29 23 - VFDs .pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
26 05 19 - Conductors.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
05 53 00 - Metal Gratings (VPR).pdf PDF
02 41 19.13 - Selective Building Demolition (VPR).pdf PDF
01 29 00 - Payment Procedures.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 64 00 - Owner Furnished Products.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
40 05 65.23 - Swing Check Valves.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
05 50 00 - Metal Fabrications (VPR).pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
26 09 16 - Auxiliary Controls & Relays.pdf PDF
01 10 00 - Project Summary.pdf PDF
05 52 00 - Metal Railings (VPR).pdf PDF
26 24 19 - MCC.pdf PDF
26 05 53 - Electrical System Identification.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
03 60 00 - Grouting (VPR).pdf PDF
01 61 00 - Product Requirements.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 31 00a Ephrata Boro Record Drawings.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
26 27 16 - Control Panels & Enclosures.pdf PDF
26 05 26 - Grounding.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 01 01 - LA Cover.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
32 92 19 - Seeding.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
05 31 23 - Steel Roof Decking (VPR).pdf PDF
00 52 00b - Agmnt btw Own and Cntr for Const Con Stip Price - Electrical Construction.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 78 39 – PROJECT RECORD DOCUMENTS

Herbert, Rowland & Grubic, Inc. 01 78 39 - 1 011139.0465

SECTION 01 78 39 - PROJECT RECORD DOCUMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes

1. Project record documents.

2. Manual for Materials and Finishes.

3. Miscellaneous Record Submittals.

B. Related Sections.

1. Section 01 77 00 - Closeout Procedures: general closeout procedures.

2. Individual Sections for specific requirements for Project Record Documents of the

Work in those Sections.

1.2 PROJECT RECORD DOCUMENTS

A. Maintain on Site one set of the following record documents; record actual revisions to the Work:

1. Drawings.

2. Specifications.

3. Addenda.

4. Change Orders and other modifications to the Contract.

5. Reviewed Shop Drawings, product data, and Samples.

6. Manufacturer's instruction for assembly, installation, and adjusting.

B. Ensure entries are complete and accurate, enabling future reference by Owner.

C. Store record documents separate from documents used for construction.

D. Record information concurrent with construction progress, not less than weekly.

E. Specifications: Legibly mark and record, at each product Section, description of actual products installed, including the following:

1. Manufacturer's name and product model and number.

2. Suppliers name and contact.

3. Product substitutions or alternates used.

4. Changes made by Addenda and modifications.

F. Record Drawings: Maintain one set of the Contract Drawings and Shop Drawings.

1. Preparation: Mark Drawings to show the actual installation. Require individual or entity who obtained record data to prepare the marked-up Record Prints.

a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later.

b. Accurately record information in an understandable drawing technique.

c. Record data as soon as possible after obtaining it. Record and check the markup before enclosing concealed installations.

Herbert, Rowland & Grubic, Inc. 01 78 39 - 2 011139.0465

2. Content: Types of items requiring marking include, but are not limited to, the following:

a. Dimensional changes to Drawings.

b. Revisions to details shown on Drawings.

c. Depths of foundations in relation to plant datum.

d. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.

1) Depth of buried utility lines.

2) Dimension distances from permanent facility components that are parallel to utilities.

3) Dimension ends, corners, and junctions of buried utilities to permanent facility components using triangulation.

4) Identify and locate existing buried or concealed items encountered during Project.

e. Revisions to electrical circuitry.

f. Actual equipment locations.

g. Locations of concealed internal utilities.

h. Changes made by Addendum, Field Order, Change Order or Work Change

Directive.

i. Details not on the original Contract Drawings.

j. Field records for variable and concealed conditions.

k. Record information on the Work that is shown only schematically.

3. Mark the Contract Drawings or Shop Drawings, whichever is most capable of showing actual physical conditions, completely and accurately. If Shop Drawings are marked, show cross-reference on the Contract Drawings.

4. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location.

5. Mark important additional information that was either shown schematically or omitted from original Drawings.

6. Note Addendum numbers, Field Order numbers, Work Change Directive numbers, Change Order numbers, and similar identification, where applicable.

7. Prepare new Drawings where neither the Contract Drawings nor Shop Drawings are not suitable to show actual installation.

a. New Drawings may be required when a Change Order is issued as a result of accepting an alternate, substitution, or other modification.

8. Format: Identify and date each Record Drawing; include the designation

"PROJECT RECORD DRAWING" in a prominent location.

a. Cross out Engineer's title block and seal from all sheets and stamp all sheets with name of Contractor.

b. Record Drawings: Organize Record Drawings into manageable sets. Bind each set with durable paper cover sheets. Include identification on cover sheets.

1.3 MANUAL FOR MATERIALS AND FINISHES

A. Submit two copies of preliminary draft or proposed formats and outlines of contents before start of Work. Engineer will review draft and return one copy with comments.

Herbert, Rowland & Grubic, Inc. 01 78 39 - 3 011139.0465

B. For equipment or component parts of equipment put into service during construction and operated by Owner, submit documents within ten days after acceptance.

C. Submit one copy of completed volumes 15 days prior to final inspection. Draft copy be reviewed and returned after final inspection, with Engineer comments. Revise content of document sets as required prior to final submission.

D. Submit 2 sets of revised final volumes within ten days after final inspection.

E. Submit in PDF composite electronic indexed file of final manual within ten days after final inspection.

F. Building Products, Applied Materials, and Finishes: Include product data, with catalog number, size, composition, and color and texture designations.

G. Instructions for Care and Maintenance: Include manufacturer's recommendations for cleaning agents and methods, precautions against detrimental agents and methods, and recommended schedule for cleaning and maintenance.

H. Moisture Protection and Weather Exposed Products: Include product data listing applicable reference standards, chemical composition, and details of installation. Include recommendations for inspections, maintenance, and repair.

I. Additional Requirements: As specified in individual product Specification Sections.

J. Include listing in table of contents for design data, with tabbed fly sheet and space for insertion of data.

1.4 MISCELLANEOUS RECORD SUBMITTALS

A. Assemble miscellaneous records required by other Sections. Bind or file miscellaneous records and identify each. Miscellaneous records include the following:

1. Material and equipment test and inspection reports.

2. Equipment and material delivery slips.

PART 2 - PRODUCTS - Not Used

PART 3 - EXECUTION - Not Used

END OF SECTION

PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes
1. Project record documents.
2. Manual for Materials and Finishes.
3. Miscellaneous Record Submittals.
B. Related Sections.
1. Section 01 77 00 - Closeout Procedures: general closeout procedures.
2. Individual Sections for specific requirements for Project Record Documents of the Work in those Sections.
1.2 PROJECT RECORD DOCUMENTS
A. Maintain on Site one set of the following record documents; record actual revisions to the Work:
1. Drawings.
2. Specifications.
3. Addenda.
4. Change Orders and other modifications to the Contract.
5. Reviewed Shop Drawings, product data, and Samples.
6. Manufacturer's instruction for assembly, installation, and adjusting.
B. Ensure entries are complete and accurate, enabling future reference by Owner.
C. Store record documents separate from documents used for construction.
D. Record information concurrent with construction progress, not less than weekly.
E. Specifications: Legibly mark and record, at each product Section, description of actual products installed, including the following:
1. Manufacturer's name and product model and number.
2. Suppliers name and contact.
3. Product substitutions or alternates used.
4. Changes made by Addenda and modifications.
F. Record Drawings: Maintain one set of the Contract Drawings and Shop Drawings.
1. Preparation: Mark Drawings to show the actual installation. Require individual or entity who obtained record data to prepare the marked-up Record Prints.
a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later.
b. Accurately record information in an understandable drawing technique.
c. Record data as soon as possible after obtaining it. Record and check the markup before enclosing concealed installations.
2. Content: Types of items requiring marking include, but are not limited to, the following:
a. Dimensional changes to Drawings.
b. Revisions to details shown on Drawings.
c. Depths of foundations in relation to plant datum.
d. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.
1) Depth of buried utility lines.
2) Dimension distances from permanent facility components that are parallel to utilities.
3) Dimension ends, corners, and junctions of buried utilities to permanent facility components using triangulation.
4) Identify and locate existing buried or concealed items encountered during Project.
e. Revisions to electrical circuitry.
f. Actual equipment locations.
g. Locations of concealed internal utilities.
h. Changes made by Addendum, Field Order, Change Order or Work Change Directive.
i. Details not on the original Contract Drawings.
j. Field records for variable and concealed conditions.
k. Record information on the Work that is shown only schematically.
3. Mark the Contract Drawings or Shop Drawings, whichever is most capable of showing actual physical conditions, completely and accurately. If Shop Drawings are marked, show cross-reference on the Contract Drawings.
4. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location.
5. Mark important additional information that was either shown schematically or omitted from original Drawings.
6. Note Addendum numbers, Field Order numbers, Work Change Directive numbers, Change Order numbers, and similar identification, where applicable.
7. Prepare new Drawings where neither the Contract Drawings nor Shop Drawings are not suitable to show actual installation.
a. New Drawings may be required when a Change Order is issued as a result of accepting an alternate, substitution, or other modification.
8. Format: Identify and date each Record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location.
a. Cross out Engineer's title block and seal from all sheets and stamp all sheets with name of Contractor.
b. Record Drawings: Organize Record Drawings into manageable sets. Bind each set with durable paper cover sheets. Include identification on cover sheets.
1.3 MANUAL FOR MATERIALS AND FINISHES
A. Submit two copies of preliminary draft or proposed formats and outlines of contents before start of Work. Engineer will review draft and return one copy with comments.
B. For equipment or component parts of equipment put into service during construction and operated by Owner, submit documents within ten days after acceptance.
C. Submit one copy of completed volumes 15 days prior to final inspection. Draft copy be reviewed and returned after final inspection, with Engineer comments. Revise content of document sets as required prior to final submission.
D. Submit 2 sets of revised final volumes within ten days after final inspection.
E. Submit in PDF composite electronic indexed file of final manual within ten days after final inspection.
F. Building Products, Applied Materials, and Finishes: Include product data, with catalog number, size, composition, and color and texture designations.
G. Instructions for Care and Maintenance: Include manufacturer's recommendations for cleaning agents and methods, precautions against detrimental agents and methods, and recommended schedule for cleaning and maintenance.
H. Moisture Protection and Weather Exposed Products: Include product data listing applicable reference standards, chemical composition, and details of installation. Include recommendations for inspections, maintenance, and repair.
I. Additional Requirements: As specified in individual product Specification Sections.
J. Include listing in table of contents for design data, with tabbed fly sheet and space for insertion of data.
1.4 MISCELLANEOUS RECORD SUBMITTALS
A. Assemble miscellaneous records required by other Sections. Bind or file miscellaneous records and identify each. Miscellaneous records include the following:
1. Material and equipment test and inspection reports.
2. Equipment and material delivery slips.
PART 2 - PRODUCTS - Not Used
PART 3 - EXECUTION - Not Used