01 73 00 - Execution Requirements.pdf

PDF 265 KB Posted

Attached to
Biosolids Project 011139.0465
Solicitation number
US.260443
Issued by
Lancaster County, Pennsylvania

About this file

This is an Execution Requirements specification document prepared by Herbert, Rowland & Grubic, Inc. for the Biosolids Project 011139.0465 at Ephrata Borough Authority in Pennsylvania. The specification establishes comprehensive execution standards for construction work including field engineering, system startup, demonstration and instructions, testing and balancing, examination procedures, preparation protocols, cutting and patching requirements, protection of installed construction, progress cleaning, and correction of defective work. The project involves coordination and interconnection of two new owner-procured biodryers, demolition and replacement of dewatered solids conveyor systems, select wall demolition and replacement, indoor utility replacements, site piping replacement/relocation, a dumpster loading canopy, and associated electrical improvements. Bids for two separate contracts—Contract No. EBA26-2 (General Construction) and Contract No. EBA26-3 (Electrical Construction)—were due December 8, 2026 at 10:00 AM local time through PennBid. A pre-bid open house was scheduled for November 18, 2026 from 8:00 AM to 10:00 AM to allow prospective bidders to view the facility.

The specification requires contractors to provide seven days' notice to the Engineer prior to startup of equipment and systems, with manufacturers' representatives responsible for supervising startup and inspecting installation. Demonstration of operations and maintenance to Owner personnel must occur two weeks prior to Substantial Completion. Requirements include daily progress cleaning of the project site with waste material disposal compliance to NFPA 241 standards, prohibiting on-site burial or burning of materials and prohibiting washing waste into sewers or waterways. Contractors must maintain one set of manufacturer installation instructions on-site through construction completion and must report any defective work, incompatible conditions, or hazardous substances to the Engineer. The specification emphasizes skilled and experienced installers for cutting and patching work affecting structural integrity, weather-exposed elements, safety, or visual qualities, with fire-resistant material required at penetrations of fire-rated construction elements. No pricing terms, set-asides, incumbents, or specific funding amounts are identified in this execution requirements document.

View the file

Other files

File Type Posted
26 08 00 - Electrical Field Acceptance Tests.pdf PDF
00 63 25 - Substitution Request Form (During Construction).pdf PDF
40 05 36 - Fiberglass-Reinforced Plastic Process Pipe.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 60 00 - Project Forms.pdf PDF
26 29 23 - VFDs .pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
26 05 19 - Conductors.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
05 53 00 - Metal Gratings (VPR).pdf PDF
02 41 19.13 - Selective Building Demolition (VPR).pdf PDF
01 29 00 - Payment Procedures.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 64 00 - Owner Furnished Products.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
40 05 65.23 - Swing Check Valves.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
05 50 00 - Metal Fabrications (VPR).pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
26 09 16 - Auxiliary Controls & Relays.pdf PDF
01 10 00 - Project Summary.pdf PDF
05 52 00 - Metal Railings (VPR).pdf PDF
26 24 19 - MCC.pdf PDF
26 05 53 - Electrical System Identification.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 60 00 - Grouting (VPR).pdf PDF
01 61 00 - Product Requirements.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 31 00a Ephrata Boro Record Drawings.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
26 27 16 - Control Panels & Enclosures.pdf PDF
26 05 26 - Grounding.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 01 01 - LA Cover.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
32 92 19 - Seeding.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
00 01 07 - Seal Page.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
05 31 23 - Steel Roof Decking (VPR).pdf PDF
00 52 00b - Agmnt btw Own and Cntr for Const Con Stip Price - Electrical Construction.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 73 00 EXECUTION REQUIREMENTS

Herbert, Rowland & Grubic, Inc. 01 73 00 - 1 011139.0465

SECTION 01 73 00 - EXECUTION REQUIREMENTS

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Field engineering.

B. Starting of systems.

C. Demonstration and instructions.

D. Testing, adjusting, and balancing.

E. Examination.

F. Preparation.

G. Execution.

H. Cutting and patching.

I. Protecting installed construction.

J. Progress Cleaning

K. Correction of Defective Work

1.2 STARTING OF SYSTEMS

A. Coordinate schedule for startup of various equipment and systems.

B. Notify Engineer seven days prior to startup of each item.

C. Verify that each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, and for conditions which may cause damage.

D. Verify that tests, meter readings, and electrical characteristics agree with those required by equipment or system manufacturer.

E. Verify that wiring and support components for equipment are complete and tested.

F. Execute startup under supervision of manufacturer's representative or Contractors' personnel according to manufacturer's instructions.

G. When specified in individual Specification Sections, require manufacturer to provide authorized representative who will be present at Site to inspect, check, and approve equipment or system installation prior to startup and will supervise placing equipment or system in operation.

Herbert, Rowland & Grubic, Inc. 01 73 00 - 2 011139.0465

H. Submit a written report according to Section 01 33 00 - Submittal Procedures that equipment or system has been properly installed and is functioning correctly.

1.3 DEMONSTRATION AND INSTRUCTIONS

A. Demonstrate operation and maintenance of products to Owner's personnel two weeks prior to date of Substantial Completion.

B. Demonstrate Project equipment and instructed by manufacturer's representative who is knowledgeable about the Project.

C. Use operation and maintenance manuals as basis for instruction. Review contents of manual with Owner's personnel in detail to explain all aspects of operation and maintenance.

D. Demonstrate startup, operation, control, adjustment, troubleshooting, servicing, maintenance, and shutdown of each item of equipment at agreed time at equipment location.

E. Prepare and insert additional data in operations and maintenance manuals when need for additional data becomes apparent during instruction.

F. Required instruction time for each item of equipment and system is specified in individual Specification Sections.

PART 2 - PRODUCTS - Not Used

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that existing Site conditions (including improvements and utilities) and substrate surfaces are acceptable for subsequent Work. Beginning new Work means acceptance of existing conditions.

B. Verify that existing substrate is capable of structural support or attachment of new Work being applied or attached.

C. Examine and verify specific space and conditions described in individual Specification Sections.

D. Verify that utility services are available with correct characteristics and in correct locations.

E. Failure to so inspect, verify and report shall constitute an acceptance of the field condition, or other work, as fit and proper for the reception of his work.

F. Promptly report to the Engineer any defects in such work that render it unsuitable for such proper execution and results; written report shall include:

1. Description of the Work.

Herbert, Rowland & Grubic, Inc. 01 73 00 - 3 011139.0465

2. List of detrimental conditions, including substrates.

3. List of unacceptable installation tolerances.

4. Recommended corrections.

5. Verify compatibility with and suitability of substrates.

6. Examine roughing-in systems to verify actual locations of connections before equipment and fixture installation.

7. Examine walls, floors, and roofs for suitable conditions where products and systems are to be installed.

8. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work indicates acceptance of surfaces and conditions.

3.2 PREPARATION

A. Clean substrate surfaces prior to applying next material or substance according to manufacturer's instructions.

B. Seal cracks or openings of substrate prior to applying next material or substance.

C. Apply manufacturer-required or -recommended substrate primer, sealer, or conditioner prior to applying new material or substance in contact or bond.

3.3 EXECUTION

A. Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.

1. Make vertical work plumb and make horizontal work level.

2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement.

3. Conceal pipes, ducts, and wiring in finished areas, unless otherwise indicated.

4. Maintain minimum headroom clearance of 8 feet in spaces without a suspended ceiling.

B. Comply with manufacturer's installation instructions, performing each step in sequence.

Maintain one set of manufacturer's installation instructions at Project Site during installation and until completion of construction.

C. When manufacturer's installation instructions conflict with Contract Documents, request clarification from Engineer before proceeding.

D. Verify that field measurements are as indicated on approved Shop Drawings or as instructed by manufacturer.

E. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, or disfigurement.

1. Secure Work true to line and level and within specified tolerances, or if not specified, industry-recognized tolerances.

2. Physically separate products in place, provide electrical insulation, or provide protective coatings to prevent galvanic action or corrosion between dissimilar metals.

Herbert, Rowland & Grubic, Inc. 01 73 00 - 4 011139.0465

3. Exposed Joints: Provide uniform joint width and arrange to obtain best visual effect. Refer questionable visual-effect choices to Architect/Engineer for final decision.

F. Allow for expansion of materials and building movement.

G. Joints: Make joints of uniform width. Where joint locations in exposed work are not indicated, arrange joints for the best visual effect. Fit exposed connections together to form hairline joints.

H. Climatic Conditions and Project Status: Install each unit of Work under conditions to ensure best possible results in coordination with entire Project.

1. Isolate each unit of Work from incompatible Work as necessary to prevent deterioration.

2. Coordinate enclosure of Work with required inspections and tests to minimize necessity of uncovering Work for those purposes.

I. Mounting Heights: Where not indicated, mount individual units of Work at industry recognized standard mounting heights for particular application indicated.

1. Refer questionable mounting heights choices to Engineer for final decision.

2. Elements Identified as Accessible to Handicapped: Comply with applicable codes and regulations.

J. Adjust operating products and equipment to ensure smooth and unhindered operation.

K. Clean and perform maintenance on installed Work as frequently as necessary through remainder of construction period. Lubricate operable components as recommended by manufacturer.

3.4 CUTTING AND PATCHING

A. Employ skilled and experienced installers to perform cutting and patching.

B. Submit written request in advance of cutting or altering elements affecting:

1. Structural integrity of element.

2. Integrity of weather-exposed or moisture-resistant elements.

3. Efficiency, maintenance, or safety of element.

4. Visual qualities of sight-exposed elements.

5. Work of Owner or separate contractor.

C. Execute cutting, fitting, and patching to complete Work and to:

1. Fit the several parts together, to integrate with other Work.

2. Uncover Work to install or correct ill-timed Work.

3. Remove and replace defective and nonconforming Work.

4. Remove samples of installed Work for testing.

5. Provide openings in elements of Work for penetrations of mechanical and electrical Work.

D. Execute Work by methods to avoid damage to other Work and to provide proper surfaces to receive patching and finishing.

Herbert, Rowland & Grubic, Inc. 01 73 00 - 5 011139.0465

E. Cut masonry and concrete materials using masonry saw or core drill.

F. Restore Work with new products according to requirements of Contract Documents.

G. Fit Work tight to pipes, sleeves, ducts, conduits, and other penetrations through surfaces.

H. Maintain integrity of wall, ceiling, or floor construction; completely seal voids.

I. At penetrations of fire-rated walls, partitions, ceiling, or floor construction, completely seal voids with fire-resistant material to full thickness of penetrated element.

J. Refinish surfaces to match adjacent finishes. For continuous surfaces, refinish to nearest intersection; for assembly, refinish entire unit.

K. Identify hazardous substances or conditions exposed during the Work to Architect/Engineer for decision or remedy.

3.5 PROTECTING INSTALLED CONSTRUCTION

A. Protect installed Work and provide special protection where specified in individual Specification Sections.

B. Provide temporary and removable protection for installed products. Control activity in immediate Work area to prevent damage.

C. Provide protective coverings at walls, projections, jambs, sills, and soffits of openings.

D. Use durable sheet materials to protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects.

E. Prohibit traffic or storage upon waterproofed or roofed surfaces. When traffic or activity is necessary, obtain recommendations for protection from waterproofing or roofing material manufacturer.

F. Prohibit traffic from landscaped areas.

3.6 PROGRESS CLEANING

A. General: Clean Project site and work areas daily, including common areas. Coordinate progress cleaning for joint-use areas where more than one installer has worked. Enforce requirements strictly. Dispose of materials lawfully.

1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris.

2. Do not hold materials more than 7 days during normal weather or 3 days if the temperature is expected to rise above 80 deg F (27 deg C).

3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations.

Herbert, Rowland & Grubic, Inc. 01 73 00 - 6 011139.0465

B. Site: Maintain Project site free of waste materials and debris.

C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.

1. Remove liquid spills promptly.

2. Where dust would impair proper execution of the Work, broom-clean or vacuum the entire work area, as appropriate.

D. Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use cleaning materials that are not hazardous to health or property and that will not damage exposed surfaces.

E. Concealed Spaces: Remove debris from concealed spaces before enclosing the space.

F. Exposed Surfaces in Finished Areas: Clean exposed surfaces and protect as necessary to ensure freedom from damage and deterioration at time of Substantial Completion.

G. Waste Disposal: Burying or burning waste materials on-site will not be permitted.

Washing waste materials down sewers or into waterways will not be permitted.

H. During handling and installation, clean and protect construction in progress and adjoining materials already in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.

I. Clean and provide maintenance on completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.

J. Limiting Exposures: Supervise construction operations to assure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period.

3.7 CORRECTION OF DEFECTIVE WORK

A. Repair or remove and replace defective construction. Restore damaged substrates and finishes.

1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.

B. Restore permanent facilities used during construction to their specified condition.

C. Remove and replace damaged surfaces that are exposed to view if surfaces cannot be repaired without visible evidence of repair.

D. Repair components that do not operate properly. Remove and replace operating components that cannot be repaired.

Herbert, Rowland & Grubic, Inc. 01 73 00 - 7 011139.0465

E. Remove and replace chipped, scratched, and broken glass or reflective surfaces.

END OF SECTION

PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Field engineering.
B. Starting of systems.
C. Demonstration and instructions.
D. Testing, adjusting, and balancing.
E. Examination.
F. Preparation.
G. Execution.
H. Cutting and patching.
I. Protecting installed construction.
J. Progress Cleaning
K. Correction of Defective Work
1.2 STARTING OF SYSTEMS
A. Coordinate schedule for startup of various equipment and systems.
B. Notify Engineer seven days prior to startup of each item.
C. Verify that each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, and for conditions which may cause damage.
D. Verify that tests, meter readings, and electrical characteristics agree with those required by equipment or system manufacturer.
E. Verify that wiring and support components for equipment are complete and tested.
F. Execute startup under supervision of manufacturer's representative or Contractors' personnel according to manufacturer's instructions.
G. When specified in individual Specification Sections, require manufacturer to provide authorized representative who will be present at Site to inspect, check, and approve equipment or system installation prior to startup and will supervise placing e...
H. Submit a written report according to Section 01 33 00 - Submittal Procedures that equipment or system has been properly installed and is functioning correctly.
1.3 DEMONSTRATION AND INSTRUCTIONS
A. Demonstrate operation and maintenance of products to Owner's personnel two weeks prior to date of Substantial Completion.
B. Demonstrate Project equipment and instructed by manufacturer's representative who is knowledgeable about the Project.
C. Use operation and maintenance manuals as basis for instruction. Review contents of manual with Owner's personnel in detail to explain all aspects of operation and maintenance.
D. Demonstrate startup, operation, control, adjustment, troubleshooting, servicing, maintenance, and shutdown of each item of equipment at agreed time at equipment location.
E. Prepare and insert additional data in operations and maintenance manuals when need for additional data becomes apparent during instruction.
F. Required instruction time for each item of equipment and system is specified in individual Specification Sections.
PART 2 - PRODUCTS - Not Used
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify that existing Site conditions (including improvements and utilities) and substrate surfaces are acceptable for subsequent Work. Beginning new Work means acceptance of existing conditions.
B. Verify that existing substrate is capable of structural support or attachment of new Work being applied or attached.
C. Examine and verify specific space and conditions described in individual Specification Sections.
D. Verify that utility services are available with correct characteristics and in correct locations.
E. Failure to so inspect, verify and report shall constitute an acceptance of the field condition, or other work, as fit and proper for the reception of his work.
F. Promptly report to the Engineer any defects in such work that render it unsuitable for such proper execution and results; written report shall include:
1. Description of the Work.
2. List of detrimental conditions, including substrates.
3. List of unacceptable installation tolerances.
4. Recommended corrections.
5. Verify compatibility with and suitability of substrates.
6. Examine roughing-in systems to verify actual locations of connections before equipment and fixture installation.
7. Examine walls, floors, and roofs for suitable conditions where products and systems are to be installed.
8. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work indicates acceptance of surfaces and conditions.
3.2 PREPARATION
A. Clean substrate surfaces prior to applying next material or substance according to manufacturer's instructions.
B. Seal cracks or openings of substrate prior to applying next material or substance.
C. Apply manufacturer-required or -recommended substrate primer, sealer, or conditioner prior to applying new material or substance in contact or bond.
3.3 EXECUTION
A. Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.
1. Make vertical work plumb and make horizontal work level.
2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement.
3. Conceal pipes, ducts, and wiring in finished areas, unless otherwise indicated.
4. Maintain minimum headroom clearance of 8 feet in spaces without a suspended ceiling.
B. Comply with manufacturer's installation instructions, performing each step in sequence. Maintain one set of manufacturer's installation instructions at Project Site during installation and until completion of construction.
C. When manufacturer's installation instructions conflict with Contract Documents, request clarification from Engineer before proceeding.
D. Verify that field measurements are as indicated on approved Shop Drawings or as instructed by manufacturer.
E. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, or disfigurement.
1. Secure Work true to line and level and within specified tolerances, or if not specified, industry-recognized tolerances.
2. Physically separate products in place, provide electrical insulation, or provide protective coatings to prevent galvanic action or corrosion between dissimilar metals.
3. Exposed Joints: Provide uniform joint width and arrange to obtain best visual effect. Refer questionable visual-effect choices to Architect/Engineer for final decision.
F. Allow for expansion of materials and building movement.
G. Joints: Make joints of uniform width. Where joint locations in exposed work are not indicated, arrange joints for the best visual effect. Fit exposed connections together to form hairline joints.
H. Climatic Conditions and Project Status: Install each unit of Work under conditions to ensure best possible results in coordination with entire Project.
1. Isolate each unit of Work from incompatible Work as necessary to prevent deterioration.
2. Coordinate enclosure of Work with required inspections and tests to minimize necessity of uncovering Work for those purposes.
I. Mounting Heights: Where not indicated, mount individual units of Work at industry recognized standard mounting heights for particular application indicated.
1. Refer questionable mounting heights choices to Engineer for final decision.
2. Elements Identified as Accessible to Handicapped: Comply with applicable codes and regulations.
J. Adjust operating products and equipment to ensure smooth and unhindered operation.
K. Clean and perform maintenance on installed Work as frequently as necessary through remainder of construction period. Lubricate operable components as recommended by manufacturer.
3.4 CUTTING AND PATCHING
A. Employ skilled and experienced installers to perform cutting and patching.
B. Submit written request in advance of cutting or altering elements affecting:
1. Structural integrity of element.
2. Integrity of weather-exposed or moisture-resistant elements.
3. Efficiency, maintenance, or safety of element.
4. Visual qualities of sight-exposed elements.
5. Work of Owner or separate contractor.
C. Execute cutting, fitting, and patching to complete Work and to:
1. Fit the several parts together, to integrate with other Work.
2. Uncover Work to install or correct ill-timed Work.
3. Remove and replace defective and nonconforming Work.
4. Remove samples of installed Work for testing.
5. Provide openings in elements of Work for penetrations of mechanical and electrical Work.
D. Execute Work by methods to avoid damage to other Work and to provide proper surfaces to receive patching and finishing.
E. Cut masonry and concrete materials using masonry saw or core drill.
F. Restore Work with new products according to requirements of Contract Documents.
G. Fit Work tight to pipes, sleeves, ducts, conduits, and other penetrations through surfaces.
H. Maintain integrity of wall, ceiling, or floor construction; completely seal voids.
I. At penetrations of fire-rated walls, partitions, ceiling, or floor construction, completely seal voids with fire-resistant material to full thickness of penetrated element.
J. Refinish surfaces to match adjacent finishes. For continuous surfaces, refinish to nearest intersection; for assembly, refinish entire unit.
K. Identify hazardous substances or conditions exposed during the Work to Architect/Engineer for decision or remedy.
3.5 PROTECTING INSTALLED CONSTRUCTION
A. Protect installed Work and provide special protection where specified in individual Specification Sections.
B. Provide temporary and removable protection for installed products. Control activity in immediate Work area to prevent damage.
C. Provide protective coverings at walls, projections, jambs, sills, and soffits of openings.
D. Use durable sheet materials to protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects.
E. Prohibit traffic or storage upon waterproofed or roofed surfaces. When traffic or activity is necessary, obtain recommendations for protection from waterproofing or roofing material manufacturer.
F. Prohibit traffic from landscaped areas.
3.6 PROGRESS CLEANING
A. General: Clean Project site and work areas daily, including common areas. Coordinate progress cleaning for joint-use areas where more than one installer has worked. Enforce requirements strictly. Dispose of materials lawfully.
1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris.
2. Do not hold materials more than 7 days during normal weather or 3 days if the temperature is expected to rise above 80 deg F (27 deg C).
3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations.
B. Site: Maintain Project site free of waste materials and debris.
C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.
1. Remove liquid spills promptly.
2. Where dust would impair proper execution of the Work, broom-clean or vacuum the entire work area, as appropriate.
D. Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are ...
E. Concealed Spaces: Remove debris from concealed spaces before enclosing the space.
F. Exposed Surfaces in Finished Areas: Clean exposed surfaces and protect as necessary to ensure freedom from damage and deterioration at time of Substantial Completion.
G. Waste Disposal: Burying or burning waste materials on-site will not be permitted. Washing waste materials down sewers or into waterways will not be permitted.
H. During handling and installation, clean and protect construction in progress and adjoining materials already in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.
I. Clean and provide maintenance on completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.
J. Limiting Exposures: Supervise construction operations to assure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period.
3.7 CORRECTION OF DEFECTIVE WORK
A. Repair or remove and replace defective construction. Restore damaged substrates and finishes.
1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.
B. Restore permanent facilities used during construction to their specified condition.
C. Remove and replace damaged surfaces that are exposed to view if surfaces cannot be repaired without visible evidence of repair.
D. Repair components that do not operate properly. Remove and replace operating components that cannot be repaired.
E. Remove and replace chipped, scratched, and broken glass or reflective surfaces.