26 08 00 - Electrical Field Acceptance Tests.pdf
PDF 397 KB Posted
- Attached to
- Biosolids Project 011139.0465
- Solicitation number
- US.260443
- Issued by
- Lancaster County, Pennsylvania
About this file
Summary
This document is Section 26 08 00 of the technical specifications for the Biosolids Project 011139.0465 at Ephrata Borough Authority in Pennsylvania, detailing comprehensive electrical field acceptance testing requirements. The specification establishes mandatory acceptance testing protocols for all electrical equipment furnished under the contract, including wire and cable insulation resistance tests, grounding system verification, switchgear assembly inspections, circuit breaker evaluations, AC motor assessments, motor control testing, instrument transformer validation, metering device calibration, protective relay testing, mechanical and electrical interlock operations, and thermographic termination inspections. All testing must be performed by a fully accredited NETA member testing company and conducted in the presence of the Owner or authorized representative, with a minimum seven-calendar-day advance written notice required. Test reports must include detailed procedures, test equipment specifications, results, recommendations, "as-found" and "as-left" data, and be incorporated into related service manuals with a divider labeled "Electrical Field Acceptance Tests."
The specification mandates that the contractor bear all costs associated with testing and retesting, including expenses resulting from defects or equipment failures to meet specifications, with defective wiring and equipment to be replaced unless specific Owner approval for repair is granted. All test equipment must be calibrated per NETA ATS schedule requirements with accuracy directly traceable to the National Institute of Standards and Technology, and must meet specified accuracy standards ranging from 0.1% to 5% depending on the equipment type. The testing protocol emphasizes safety compliance with OSHA, NFPA 70E, and applicable state and local procedures, with special provisions for protecting solid-state devices and electronic components from damage during high-voltage testing. Upon completion of all testing, the contractor is responsible for providing system description and operation training to the Owner's personnel, maintaining continued consultation services through the warranty period, and executing all required guarantees, warranties, performance certifications, and maintenance agreements before systems are transferred to the Owner for operation.
View the file
Other files
Show 40 more
Latest 50 of 125 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
26 08 00 – ELECTRICAL FIELD ACCEPTANCE TESTS
Herbert, Rowland & Grubic, Inc. 26 08 00 -1 011139.0465
SECTION 26 08 00 - ELECTRICAL FIELD ACCEPTANCE TESTS
PART 1 - GENERAL
1.1 DESCRIPTION
A. Acceptance tests shall be performed for all electrical equipment furnished under this Contract. The test requirements for equipment shall be as required by applicable standards and manufacturer’s recommendations, and in accordance with this specification. In no case will the absence of test requirements herein be construed as alleviation of acceptance testing.
B. The purpose of electrical field acceptance tests is to assure that all electrical equipment is operational and within industry and manufacturer's tolerances and is installed in accordance with the Contract Documents and approved Shop and Working Drawings.
C. Tests are in addition to factory tests at the Manufacturer's facility, and may not substitute for same.
D. Tests are in addition to all other tests specified under other Specification Sections and shall be coordinated by the Contractor.
E. Tests in general shall be conducted after the equipment installation is complete. Tests shall be complete and in order given herein and/or in Specification Section for the particular equipment unless otherwise approved by the Authority.
F. Tests are also intended to provide, ensure, or determine the following:
1. Provide initial acceptance tests and recorded data that can be used as a bench mark for future routine maintenance and trouble shooting by plant personnel.
2. Ensure a successful start-up with a minimum of last minute interruptions and problems.
3. Determine the suitability of the equipment and systems for energization and placing into operation
4. Provide assurance that each system component is not only installed satisfactorily but performs, and will continue to perform, its function in the system with reasonable reliability throughout the life of the equipment.
1.2 RELATED SECTIONS
A. Division 01: General.
B. Division 26: Electrical.
1.3 QUALITY ASSURANCE
A. Reference Standards: Comply with all Federal and local laws or ordinances, as well as all applicable codes, standards, regulations and/or regulatory agency requirements including the partial listing below:
Herbert, Rowland & Grubic, Inc. 26 08 00 -2 011139.0465
1. All inspections and tests shall be in accordance with the latest edition of the following codes, standards, and specifications except as provided otherwise herein.
a. American National Standards Institute - ANSI
b. American Society for Testing and Materials - ASTM
c. Association of Edison Illuminating Companies - AEIC
d. Canadian Standards Association - CSA
e. Institute of Electrical and Electronic Engineers - IEEE
f. Insulated Cable Engineers Association - ICEA
g. International Electrical Testing Association - NETA
h. National Electrical Manufacturer's Association - NEMA
i. National Fire Protection Association - NFPA
j. Occupational Safety and Health Administration - OSHA
k. State and local codes and ordinances
l. Underwriters Laboratory
m. All General and Supplementary Conditions of this Contract.
2. All inspections and tests shall utilize the following references:
a. Contract Documents.
b. Short Circuit and Coordination Study.
c. Service Manuals applicable to each particular apparatus.
1.4 SUBMITTALS
A. General: Submittals shall be accordance with 01 33 00 – Submittal Procedures and Section 26 05 00 – Electrical General. Submit all testing procedures for approval prior to any testing.
B. Shop Drawings: Submit in accordance with 01 33 00 – Submittal Procedures and Section 26 05 00 – Electrical General.
C. Test Reports:
1. Contractor shall submit detailed test procedure including test equipment for all field acceptance testing.
2. Contractor shall submit all interim test reports and a copy of field test sheets. Once all discrepancies have been resolved, contractor shall submit a single final test report. All submittals and reports shall be sent to the engineer.
3. Each test report shall include as a minimum the following:
a. Listing of equipment tested including the list of test equipment used.
b. Test method and standards governing the test.
c. Test results.
d. Recommendations.
4. Test results shall incorporate inspection reports, instrument calibration curves, plotted test results, and all measurements and data.
5. All inspections, tests, and calibrations to be reported in writing on Owner -approved report forms. The recorded data form shall have the signatures of the persons conducting the tests and authorized witnesses. The forms shall be designed to serve as the test and inspection checklist for inspection requirements. The test and checkout data shall also include any data taken prior to the adjustments, repairs, drying out, or similar work prior to final testing and acceptance. "As-found" and "as-left" test data shall be recorded and reported in writing.
Herbert, Rowland & Grubic, Inc. 26 08 00 -3 011139.0465
6. Copies of Test Reports shall be incorporated in each of the related Service Manuals.
The Test Reports shall include those items of equipment contained in the Service Manual. Reports shall be separated by a divider labeled "Electrical Field Acceptance Tests". Reports shall contain data for all power conductors and controls including instrumentation conductors and devices for static and dynamic equipment in the Service Manual. In addition, Operating Tests of the equipment shall be included in this section of the Service Manual.
1.5 QUALIFICATIONS
A. All acceptance testing activities described herein must be performed by a testing company that is a fully accredited NETA member.
PART 2 - PRODUCTS
2.1 EQUIPMENT
A. Provide all necessary test equipment and tools as specified herein and as recommended by the tested equipment manufacturer.
B. All test equipment shall be in good mechanical and electrical conditions, and shall be calibrated per NETA ATS schedule requirements. Records, which show date and results of instrument calibration or testing, must be kept up-to-date and provided with the test report upon request.
C. The accuracy shall be directly traceable to the National Institute of Standards and Technology.
D. Calibrating standard shall be of higher accuracy than that of the instrument tested.
E. Test equipment shall include but not limited to and shall have operating accuracy equal to, or better than listed below:
1. Portable multimeters shall be true RMS measuring.
2. Multimeters shall have the following accuracy limits, or better (for 60Hz where applicable):
a. AC voltage ranges: 0.75%3 last single digits
b. AC current ranges: 0.90%3 last single digits, including adapters, transducers
c. DC voltage ranges: 0.25%1 last single digit
d. Resistance ranges: 0.50%1 last single digit
e. Frequency range: 0.10%1 last single digit.
f. Clamp-on ammeters: AC current 3% of range 1 last single digit.
g. Dissipation/power factor field equipment:
h. 0.1% power factor values up to 2.0%
i. 5% of the reading for power factor values above 2.
3. Low-range DC resistance equipment: 1.0% of reading, 2 last single digits.
4. Transformers turns-ratio test equipment: 0.5% or better.
Herbert, Rowland & Grubic, Inc. 26 08 00 -4 011139.0465
5. Ground electrode test equipment: 2.0% of range.
6. Insulation (Megger) test sets: 0 - 1000 V DC 20% of reading at mid-scale for equipment 600 volts and less and 0 - 2500 volts DC 20% of reading at mid-scale for equipment over 600 volt.
7. Electrical load survey equipment:
a. 5% total error, including sensors
b. 1% resolution
c. Current transformers 2% of range
d. Voltage transformers 0.5% of range.
8. Liquid dielectric strength test equipment: 2% of scale.
9. Infrared scanning equipment: sensitivity of 2C.
10. Phase shifting equipment: 1.0 over entire range.
11. High-current test equipment: 2% of range.
12. DC high potential test equipment: 2% of scale.
13. AC high potential test equipment: 2% of scale.
14. Multi-amp SR-90, or equal, relay test set.
PART 3 - EXECUTION
3.1 TEST COORDINATION AND RESPONSIBILITIES
A. The Contractor shall perform all acceptance tests required.
B. The contractor shall provide all material, equipment, labor, and technical supervision to perform such tests and inspections.
C. All cost associated with the testing shall be the responsibility of the Contractor, including the expenses of retest because of defects and/or failure of equipment to meet Specifications. Wiring and equipment which is defective, or which fails to meet Specifications, shall be replaced by the Contractor, unless specific approval for repair is given by Owner. The Contractor shall bear the costs for either action.
D. Contractor shall open circuits, place and connect all instruments and equipment needed for the tests, remove same and restore circuits when tests are complete.
E. Coordinate activities, and cooperate with others on project, to ensure that systems are energized when required, loads applied, and requirements of other Specification Sections are carried out on timely, coordinated basis.
F. Other Specification Sections may require services of one or more manufacturer's representatives, to ensure that equipment supplied has been installed properly and adjusted to proper working order. Advise representative of all applicable tests in this Section, so that work will be coordinated, and tests combined where feasible.
G. Contractor shall notify the Owner, in writing, at least seven calendar days before the tests are to take place. The tests shall be conducted in the presence of the Owner or their authorized representative and shall not be started without the Owner’s permission.
Herbert, Rowland & Grubic, Inc. 26 08 00 -5 011139.0465
H. Electrical power required for the tests to be in accordance with all applicable standards.
I. All tests shall be performed as closely as possible to conditions of actual use.
J. All testing and checkout work shall be performed with fully qualified personnel skilled in the particular tests being conducted. This is essential for obtaining and properly evaluating data while the tests are in progress and for ensuring that important facts and questionable data are reported.
K. It is important that equipment warranties or guarantees not be voided by the Contractor's testing and checkout work. The tests will normally be supplemental to and compatible with the manufacturer's installation instructions and recommendations. Where deviations are apparent, the manufacturer's review and approval shall be obtained prior to testing.
Reasonable cooperation is to be extended to permit witnessing by the manufacturer's representative if so requested. Where any questionable repairs, modifications, significant adjustments, tests or checks are to be made, the Contractor shall contact the Owner to determine if the work should be performed by or with the manufacturer's representative.
L. The Contractor shall ensure that all testing and checkout work is conducted in a safe manner. Special safety pre-cautions such as the following are to be utilized where appropriate:
1. Occupational Safety and Health Act (OSHA).
2. Accident Prevention Manual for Industrial Operations, National Safety Council.
3. Applicable state and local safety operating procedures.
4. City safety procedures.
5. National Fire Protection Association (NFPA 70E).
6. American National Standards for Personnel Protection.
7. Locking procedures.
8. Barricades.
9. Maintenance of voice communications.
10. Erection of warning signs.
11. Stationing of guards and watchmen.
12. De-energization and/or isolation of equipment prior to testing. Exceptions must be thoroughly reviewed to identify safety hazards and devise adequate safeguards.
M. The sequence of all tests and checks shall be such that the equipment can be energized immediately after the completion of the applicable tests.
3.2 PREPARATION
A. All tests shall be performed with regard to protecting solid state devices and electronic components from potential damage. Where applicable, disconnect solid state devices and electronic components prior to applying testing voltage.
B. Make up no connections at service entrance, transformers, substations, motors, motor control centers, and switchgear permanently until correct phase rotation of all equipment is determined and electrical tests have been completed. Install and insulate these connections temporarily, if necessary. Make permanent connections after proper rotation has been established and subsequent to completion of insulation resistance and dielectric tests.
Herbert, Rowland & Grubic, Inc. 26 08 00 -6 011139.0465
3.3 APPLICATION
A. Wire and Cable Insulation Resistance Tests:
1. Low voltage, 600 V maximum:
a. Inspect wire and cables for physical damage and proper connection in accordance with approved Shop and Working Drawings.
b. Check color-coding with Specifications and NEC standards.
c. Perform continuity test to insure proper connection.
d. Perform insulation-resistance test on each conductor with respect to ground and adjacent conductors. Applied potential shall be 1000 volts DC for one minute.
e. Evaluate test results by comparison with wires and cables of the same length and type. Investigate any values less than 50 megohms.
f. Complete Exhibit “A,” attached, for each conductor system, except not required for receptacle or internal lighting circuits.
B. Grounding Systems:
1. Verify that grounding system is in accordance with Contract Documents and applicable codes.
2. The grounding system shall be tested for continuity of connection and for resistance to flow of current through ground connections:
a. The resistance between the main grounding electrode and ground shall be no greater than five ohms for 600V systems. For electrical substation grounds, the ground resistance shall be no greater than one ohm. All ground tests to be performed a minimum of 10 days after installation.
b. The ground resistance of conduits, equipment cases, and supporting frames shall be only fractionally higher than system ground.
c. Method of measurement of ground resistance shall be as specified by NETA- ATS and be approved by City before the start of tests.
d. Submit a record/report to the Engineer. Include the following:
1) Time, date, temperature, frost information depth (if applicable), and weather conditions.
2) Location of ground grid under test.
3) Date of ground grid installation.
4) Driven depth of electrodes.
5) Moisture content of earth at time of measurement (wet, dry, etc.).
6) Ground test equipment, model numbers, and last date of calibration.
7) Detailed description of method used.
8) Plot of "distance from ground grid versus resistance." Distance of farthest probe is 100 feet, with the movable probe recording at 10-foot increments moving from farthest probe back to ground rod under test. Test each outside ground rod. Resistances shall range from 0 to 50 ohms with enough points to produce a smooth curve.
3. Maintenance information and recommendations (if applicable).
4. Switchgear Assemblies:
a. Inspect for physical, electrical, and mechanical condition.
b. Compare equipment nameplate information with latest one-line diagram.
Herbert, Rowland & Grubic, Inc. 26 08 00 -7 011139.0465
c. Check for proper anchorage, required area clearances, physical damage, and proper alignment.
d. Inspect all bus connections for high resistance as recommended in NETA- ATS standard. Compare bus connection resistance to value of similar connections.
e. Verify torque and provide written certification on all bolts for bus bar connections:
1) Bus bar and terminal connections shall be inspected to ensure that all joints have proper torque tightness.
2) Torque values for all types of joints involved shall be in accordance with manufacturer's recommendations.
f. Check support and bracing:
1) Bus bar support insulators and barriers shall be inspected to ensure that they are free from contamination.
2) Insulators shall be checked for cracks and signs of arc tracking.
Mounting hardware shall be inspected and all joints checked for proper torque value.
g. Test all electrical and mechanical interlock systems for proper operation and sequencing:
1) Closure attempt shall be made on locked-open devices. Opening attempt shall be made on locked-closed devices.
2) Key exchange shall be made with devices operated in off-normal positions.
h. Clean switchgear.
i. Inspect accessible insulators for evidence of physical damage or contaminated surfaces.
j. Verify proper barrier and shutter installation and operation.
k. Verify appropriate contact lubricant on moving current carrying parts and surfaces. Verify appropriate lubrication on moving and sliding surfaces.
l. Exercise all active components.
m. Inspect all mechanical indicating devices for proper operation.
n. Verify proper operation of switchgear heaters. Insure filters and/or vents are clear.
o. Electrical Tests:
1) Solid state devices and electronic components shall be disconnected prior to applying 500 volts or higher to the circuit.
2) Perform tests on all instrument transformers in accordance with this Section.
3) Perform ground-resistance tests in accordance with this Section.
4) Perform insulation-resistance tests on each bus section, phase-to-phase and phase-to-ground for one minute. Test voltages and minimum resistance shall be as shown below:
Herbert, Rowland & Grubic, Inc. 26 08 00 -8 011139.0465
TABLE 26 08 00-1
SWITCHGEAR INSULATION-RESISTANCE TEST VOLTAGE
Voltage Rating Minimum dc Test Voltage Recommended Minimum Insulation Resistance In Megohms
0 - 250V 500V 50 251 - 600V 1000V 100 601 - 5000V 2500V 1000 5001 - 15000V 2500V 5000 15001 - 39000V 5000V 20000
5) Overpotential test voltages shall be applied in accordance with manufacturer’s recommendations or NETA-ATS. Test results are evaluated on a go/no-go basis by slowly raising the test voltage to the required value. The final test voltage shall be applied for one minute.
6) Perform resistance measurements on all bus joints with a low-resistance ohmmeter.
7) Perform insulation-resistance tests at 1000 volts dc on all control wiring. Do not perform the test on wiring connected to solid state components.
8) Perform control wiring performance test. Use the elementary diagrams of the switchgear to identify each remote control and protective device. Conduct tests to verify satisfactory performance of each control feature.
9) Perform the following tests on dry-type control power transformers:
a) Inspect for physical damage, cracked insulation, broken leads, tightness of connections, defective wiring, and overall general condition.
b) Verify that primary and secondary fuse ratings or circuit breakers match drawings.
c) Perform insulation-resistance test. Measurements shall be made from winding-to-winding and windings-to-ground. Test voltages and minimum resistance shall be in accordance with Switchgear Insulation-Resistance Test Voltage table above.
10) Determine accuracy of all meters and calibrate watthour meters per NETA-ATS requirements.
11) Perform current injection test on the entire current circuit in each section of switchgear.
C. Circuit Breakers - Low Voltage:
1. Circuit breakers are to be checked for possible damage during shipment or storage.
2. Inspect the breaker visually for physical damage.
3. Perform several mechanical ON-OFF operations.
4. Conduct circuit continuity check on each pole with the circuit breaker in the closed position.
Herbert, Rowland & Grubic, Inc. 26 08 00 -9 011139.0465
5. Determine short-time pickup and delay, long-time pickup and delay by primary current injection.
6. Tests solid state trip devices at multiple setting range of pickup and time delays.
7. Apply 300 percent of breaker rated continuous current to each pole to determine that the circuit breaker will trip on an overload.
D. AC Motors - Induction Motors:
1. Inspect for physical damage and compare nameplate information with Drawings and
Specifications.
2. Inspect for proper installation, grounding, connection, and lubrication. Motor alignment, wiring capacity, speed and operation shall be checked to verify compliance with Specifications.
3. Check for unusual mechanical or electrical noise or signs of overheating during initial test run.
4. Perform insulation-resistance tests in accordance with ANSI/IEEE standard 43. Test duration as recommended by NETA-ATS.
5. Perform insulation-resistance test on pedestal per manufacturer's instructions.
6. Perform insulation-resistance test on surge protection device in accordance with
NETA-ATS specifications.
7. Check resistance temperature detector (RTD) circuits for conformance with drawings. Check that metering or relaying devices using the RTD's are of the proper rating.
8. Check that the motor space heater is operating.
9. Perform a rotation test to ensure proper shaft direction if the motor has been electrically disconnected.
10. Measure running current and evaluate relative to load conditions and nameplate full-load amperes.
11. The motor shall be run for at least four hours as close to full load as possible.
12. See also Division 11 for additional motor test information.
E. Motor Control:
1. Low and medium voltage motor controls shall be tested in accordance with NETA-
ATS requirements and manufacturer recommendations.
2. Variable frequency drives (VFD) shall be tested as required in VFD specification section and in accordance with manufacturer recommendations.
3. Verify and provide written certification that all factory terminations have been checked for proper storage.
F. Instrument Transformers:
1. Inspect transformers for physical damage and nameplate information for compliance with Drawings and Specifications.
2. Verify proper connection of transformers with system requirements.
3. Verify tightness of all bolted connections and assure that adequate clearances exist between primary circuits and secondary circuit wiring.
4. Verify that all required grounding and shorting connections provide good contact.
5. Verify proper operation of transformer withdrawal mechanism (tip out) and grounding operation when applicable.
6. Electrical Tests - Current transformers:
Herbert, Rowland & Grubic, Inc. 26 08 00 -10 011139.0465
a. Perform insulation-resistance tests on current transformer secondary and wiring-to-ground winding at 1000 volts dc for one minute. Value of test voltage on secondary wiring shall be 1000 volts dc for one minute. Do not perform this test with solid-state devices connected.
b. Perform a polarity test on each transformer winding, and verify manufacturer's polarity markings.
c. Perform a turns-ratio verification test of each current transformer.
d. The test data shall include the following:
1) Manufacturer's stated ratio for each tap position.
2) Test turns ratio results.
3) Percent error per tap position.
4) Manufacturer's indicated polarity.
5) Test result polarity.
e. On each set of transformer windings, the turns ratio shall be determined for all no-loads taps, using the two voltmeter method for control transformers and the two ammeter method for current transformers.
f. Confirm test switch wiring and operation:
1) A functional test shall be performed on the test switch of the current transformer to ensure that the secondary leads are shorted and that no open circuit conditions exist. A functional test shall also be performed on the control transformers to ensure that no short circuit exists across the secondary leads.
2) All control wiring shall be checked to ensure proper operation of the device being powered.
g. Perform other tests specified by the NETA-ATS as required by application.
7. Electrical Tests - Voltage Transformers
a. Perform insulation-resistance tests on voltage transformers, winding-to-winding and windings-to-ground. Value of test voltage on secondary wiring shall be 500 volts dc for one minute. Do not perform this test with solid-state devices connected.
b. Perform a polarity test on each transformer to verify the polarity marks or H1-X1 relationship as applicable.
c. Perform ratio test as specified in NETA-ATS.
d. Perform a dielectric withstand test on the primary windings with the secondary windings connected to ground. The dc dielectric voltage shall be in accordance with “Switchgear Insulation-Resistance Test Voltage” table herein.
G. Metering and Instrumentation:
1. Inspect all devices for physical damage and tightness of electrical connections.
2. Check calibration and accuracy of meters at 25/50/75/100% of full scale.
3. Verify all instrument multipliers.
H. Protective Relays:
1. Inspect relays for physical damage and compliance with Drawings and
Specifications.
2. Standard testing and calibration Specifications:
Herbert, Rowland & Grubic, Inc. 26 08 00 -11 011139.0465
a. To demonstrate that the relay will function as designed throughout the entire range of its operations, acceptance tests shall be performed in accordance with NETA-ATS Protective Relay Testing Specifications.
b. Calibrate and set relays in accordance with approved coordination study.
c. Use approved relay test set.
3. Perform insulation-resistance test on each circuit-to-frame.
4. Test all relays in place to demonstrate that the relaying system will function as specified. Acceptance tests shall be performed as specified and in accordance with
NETA-ATS.
5. Test lockout relays and associated test switch trip links and closing circuit contacts.
The lockout relays shall be functionally tested to ensure proper system operation.
Associated equipment shall be checked for proper alignment and contact closure.
6. All relays shall be checked and calibrated under service conditions against portable standards devices connected in series with the relay-undergoing test. For some in-service testing, the test plugs shall be used to connect devices which shall measure the currents and voltage being applied to the relays.
7. Test all electrical interlocks:
a. Check all electrical interlocks for loose wiring, proper mechanical alignment and operation. Also inspect all contact surfaces to ensure they are clean and not pitted.
b. All relays shall be checked and calibrated using the built-in test switch and test plug.
8. Test for correct settings and operation of all relay trips and operation indicating flags and seal in contacts.
I. Operating Tests - Mechanical and Electrical Interlocks:
1. Mechanical interlocks shall be examined to ensure the interlock is free to operate and that bearing surfaces are free to perform their intended function.
2. Check for correct adjustment of primary disconnect mechanisms in plug-in units.
Plug-in units shall be mechanically interlocked with the door to ensure that the door is held closed with primary disconnect in the ON position.
3. Check for provisions for padlock mechanisms on disconnect operating mechanisms.
4. Check motor starters equipped with a defeater mechanism to ensure that they can be operated to release the door interlock with the disconnect device in the ON position.
J. Operating Tests - Circuit Breaker Operation:
1. Test trip all medium voltage circuit breakers from all devices in the trip circuit and verify operation of all interlocks.
2. Installation and inspection of 480V power circuit breakers shall be in accordance with NEMA Pub. No. SG-3. Perform tests in accordance with NETA-ATS Specification Paragraph 3.3.05.
3. Test all remote control stations for operation:
a. A functional test shall be performed for all remote pushbutton stations and manual motor starters to ensure their proper operation.
b. Control stations tested under actual operating conditions shall perform their intended function.
Herbert, Rowland & Grubic, Inc. 26 08 00 -12 011139.0465
3.4 SYSTEM CHECKS
A. Preliminary
1. Connect all motors to protective devices and controls to give proper motor acceleration and correct motor rotation. Interconnect the control wiring to all the control devices associated with a machine, a group of machines, or other device to produce the correct operation, timing, and/or sequencing of the equipment.
Devices with trip settings left at the maximum allowable setting will not be accepted. All settings shall be made for the protection of the connected equipment.
2. Adjust overload elements in motor starters and check for coordination with the actual installed motor characteristics. Replace any overload element that is inadequate.
3. Check all motor nameplates for verification of proper voltage, horsepower, speed, phase, and power factor.
B. Operational
1. Give equipment an operational test to determine that all components including motors, controls, protective and switching devices, and auxiliary associated equipment are in operable condition and can function as described and shown on relevant specifications, operating instructions, and drawings.
2. Take motor current reading at full load or as close to full load as the driven machine will develop. If the ammeter reading is over the rated full load current or the proper current for the load at which the machine was operated, determine the reason for the discrepancy and take the necessary corrective action.
3. Remove the cause of any motor operating above full load rating instead of increasing the overload relay trip rating.
C. Tests shall be as defined in the appropriate standards.
3.5 CLOSEOUT PROCEDURES
A. General - For each project phase, sequence closeout procedures so that work will not be endangered or damaged, and so that every required performance will be fully tested and demonstrated. Closeout shall be in accordance with Section 01 70 00, Record Documents, and as required herein for each partial Certificate of Substantial Completion.
B. Final Operational Check - Make a check of each item in each system to determine that it is set for proper operation. With the Engineer present, operate each system in a test run of appropriate duration to demonstrate compliance with performance requirements. During the following test runs, make final corrections or adjustments of systems to refine and improve performances where possible, including noise and vibration reductions, elimination of hazards, better response of controls, signals and alarms, and similar system performance improvements. Provide testing or inspection devices to permit observation of actual system performances and shall demonstrate that controls and items requiring service or maintenance are accessible.
C. Cleaning and Lubrication - After final performance test run of each electrical system, clean system both externally and internally, comply with manufacturer's instructions for lubrication of both power and hand operated equipment, and remove excess lubrication, Herbert, Rowland & Grubic, Inc. 26 08 00 -13 011139.0465 touch up minor damage to factory painted finishes and other painting specified as electrical work, and refinish work where damage is extensive.
D. Operating Instructions - General operating instructions are required. In addition to specific training of the Owner's operating personnel specified in the individual sections, and in addition to preparation of written operating instructions and compiled maintenance manuals specified elsewhere in these specifications, provide general operating instructions for each operational system and equipment item of electrical work, and coordinate instructions with instructions for mechanical work, and other equipment where associated with electrical systems or equipment.
E. System Description and Operation
1. Perform in the presence of the Owner, the Owner's operating personnel and the
Engineer.
2. Describe each basic electrical system and explain identification system, displayed diagrams, signals, alarms and audio visual provisions.
3. Describe interfaces with mechanical equipment, including interlocks, sequencing, startup, shutdown, emergency, safety, system failure, security, and similar provisions.
4. In the presence of the Owner's personnel, display and conduct a "thumb through" explanation of maintenance manuals, record drawings, spare parts inventory, storage and extra materials, meter readings, and similar service items.
3.6 CONTINUED SYSTEM OPERATIONS SUPPORT
A. Coordinate the Owner's takeover of electrical systems with takeover of each system, including the provision of skilled electrical operating and maintenance personnel until the time the Owner's personnel take over operation of entire system(s) and electrical plant.
Respond promptly with continued consultation and services (beyond takeover date) on electrical systems, matching required continued services on associated mechanical systems and equipment until the end of the warranty period.
3.7 DOCUMENTATION PROCEDURE
A. Signed commitments are required. The transfer of electrical systems to the Owner for operation will not proceed until guarantees, warranties, performance certifications, maintenance agreements and similar commitments to be signed by Contractor and other entities have been executed and transmitted to and accepted by the Engineer for placement in the Owner's records.
3.8 THERMOGRAPH INSPECTIONS
A. Perform thermograph inspections on all feeder terminations, subfeed terminations, major power splices, transformer terminations, MCC terminations, motor terminations for motors 5 HP or larger, and major power distribution breakers, switches, and contactors. Testing on major power distribution equipment will be performed with the plant running at a minimum of 70 percent capacity or the highest load that can be operated. Testing on individual pieces of equipment will be performed while the unit is operational at rated load and has operated for at least 30 minutes for continuously operated equipment or near the end of a cycle for
Herbert, Rowland & Grubic, Inc. 26 08 00 -14 011139.0465 equipment that operates on/off. Loads shall be minimum of 40 percent of full load.
Readings at overcurrent devices and starters will be for line and load; motors will be connections in motor terminal boxes; and for transformers, primary and secondary terminations. Provide a report of test results to the Owner including indication of any actions taken to resolve abnormal readings. See Exhibit B at the end of this section. All thermographic tests shall be reported on this form.
3.9 MEASUREMENT AND PAYMENT
A. No separate payment will be made for Work performed under this Section. Payment will be included as part of the lump sum payment for this Project.
(CONTINUED)
Herbert, Rowland & Grubic, Inc. 26 08 00-15 011139.0465
EXHIBIT A
TESTING AND INSPECTION
ELECTRICAL INSULATION TEST RECORD
INSULATION RESISTANCE TEST
EQUIP. I.D.
CKT/MARK NO.
TEST
VOLTAGE
PHASE TO GND. MEG OHMS
PHASE TO PHASE MEG OHMS
DATE
TESTED
A
B
C
N
A-B
A-N
B-C
B-N
C-A
C-N
TEST EQUIPMENT CONTROL NO. __________________ __________________ __________________ _________________
REMARKS:
PERFORMED BY: _______________________________________________ DATE:
APPROVED BY: ________________________________________________ DATE:
Test Engineer
Herbert, Rowland & Grubic, Inc. 26 08 00-16 11139.0465
EXHIBIT B
TESTING AND INSPECTION
THERMOGRAPHIC TERMINATION TEST
LINE/PRIMARY LOAD/SECONDARY LOAD
CONDITION (%
OF FULL)
EQUIPMENT AMBIENT(1) 1 2 3 1 2 3 COMMENTS(2,3)
Thermograph Model
Date of Test ____________________ Conducted by
Outdoor Temperature _____________ Room Temperature
Owner/Engineer Witness
(1) Ambient is the breaker case temperature, transformer winding temperature, or motor housing temperature. For bus or cabling, it shall be the temperature of the bus or cable a minimum of 24 inches from the splice or termination.
(2) TEMPERATURE DIFFERENCE CONDITION ACTION
1C to 3C Possible deficiency Investigate, i.e., clean terminations/retorque
4C to 15C Deficiency Determine problem and repair; retest
16C and above Major deficiency Immediate shutdown; determine problem and repair and retest
(3) Indicate any discrepancies the cause of any temperature differences and indicate action to be taken.
Test Parameters:
• Imaging equipment shall be capable of detecting a minimum temperature difference of 2 degree at
30 degrees C.
• Equipment shall detect and convert emitted radiation to a visual signal.
• Tests to be run during periods of maximum possible loading, but at least 40 percent of rated load
END OF SECTION