About this file

This file is a table of contents for a Biosolids Project construction contract issued by Ephrata Borough Authority in Pennsylvania. The project encompasses two separate bid contracts: Contract No. EBA26-2 for General Construction and Contract No. EBA26-3 for Electrical Construction. The work scope includes coordination and interconnection of two new owner-procured biodryers, demolition and replacement of dewatered solids conveyor systems, selective wall demolition and replacement, indoor utility replacements, site piping replacement and relocation, construction of a dumpster loading canopy, and associated electrical improvements. Bids are due December 8, 2026 at 10:00 AM local time through PennBid, with public bid opening following submission. A pre-bid open house is scheduled for November 18, 2026 from 8:00 AM to 10:00 AM to allow bidders to view the facility. Bidding documents are available through the designated PennBid website, with all official notifications and addenda distributed exclusively through this platform.

The table of contents details comprehensive specifications organized by construction divisions, including General Requirements, Existing Conditions, Concrete, Metals, Finishes, Electrical Systems, Earthwork, Exterior Improvements, Utilities, Process Integration, and Material Processing Equipment. The document structure indicates standard procurement and contracting requirements applicable to public works projects in Pennsylvania, including provisions for bid bonds, performance bonds, payment bonds, non-collusion affidavits, employment verification, and equal employment opportunity compliance. Specific technical sections address electrical systems, control panels, variable frequency drives, process piping systems, and biosolids equipment integration, reflecting the specialized industrial nature of the wastewater treatment facility upgrades.

View the file

Other files

File Type Posted
26 08 00 - Electrical Field Acceptance Tests.pdf PDF
00 63 25 - Substitution Request Form (During Construction).pdf PDF
40 05 36 - Fiberglass-Reinforced Plastic Process Pipe.pdf PDF
00 60 00 - Project Forms.pdf PDF
26 29 23 - VFDs .pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
26 05 19 - Conductors.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
05 53 00 - Metal Gratings (VPR).pdf PDF
02 41 19.13 - Selective Building Demolition (VPR).pdf PDF
01 29 00 - Payment Procedures.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 64 00 - Owner Furnished Products.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
40 05 65.23 - Swing Check Valves.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
05 50 00 - Metal Fabrications (VPR).pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
26 09 16 - Auxiliary Controls & Relays.pdf PDF
01 10 00 - Project Summary.pdf PDF
05 52 00 - Metal Railings (VPR).pdf PDF
26 24 19 - MCC.pdf PDF
26 05 53 - Electrical System Identification.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 60 00 - Grouting (VPR).pdf PDF
01 61 00 - Product Requirements.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 31 00a Ephrata Boro Record Drawings.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
26 27 16 - Control Panels & Enclosures.pdf PDF
26 05 26 - Grounding.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 01 01 - LA Cover.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
32 92 19 - Seeding.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
05 31 23 - Steel Roof Decking (VPR).pdf PDF
00 52 00b - Agmnt btw Own and Cntr for Const Con Stip Price - Electrical Construction.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Herbert, Rowland & Grubic, Inc. 00 01 10 - 1 011139.0465

BIOSOLIDS PROJECT

CONTRACT NO. EBA26-2 – GENERAL CONSTRUCTION

CONTRACT NO. EBA26-3 – ELECTRICAL CONSTRUCTION

EPHRATA BOROUGH AUTHORITY

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS SECTION: PAGES

SEALS PAGE ....................................................................................................................................... 00 01 07: 1

Procurement Requirements ADVERTISEMENT FOR BIDS ............................................................................................................... 00 11 13: 2 INSTRUCTIONS TO BIDDERS .............................................................................................................. 00 21 13: 11 AVAILABLE PROJECT INFORMATION ................................................................................................. 00 31 00: 130 PERMITS ............................................................................................................................................ 00 31 46: 1 BID BOND .......................................................................................................................................... 00 43 13: 2 NON-COLLUSION AFFIDAVIT ............................................................................................................. 00 45 19: 1

CERTIFICATION OF NON-SEGREGATED FACILITIES AND NON-EMPLOYMENT OF ILLEGAL

ALIEN LABOR ................................................................................................................................ 00 45 33: 1 EEO CERTIFICATE .............................................................................................................................. 00 45 36: 1 PUBLIC WORKS EMPLOYMENT VERIFICATION FORM ....................................................................... 00 45 46: 1

Contracting Requirements AGREEMENT BETWEEN OWNER and CONTRACTOR for CONSTRUCTION CONTRACT: GENERAL .... 00 52 00a: 7 AGREEMENT BETWEEN OWNER and CONTRACTOR for CONSTRUCTION CONTRACT: ELECTRICAL . 00 52 00b: 7 NOTICE TO PROCEED ........................................................................................................................ 00 55 00: 1 PROJECT FORMS ............................................................................................................................... 00 60 00: 1 PERFORMANCE BOND ...................................................................................................................... 00 61 13.13: 4 PAYMENT BOND ............................................................................................................................... 00 61 13.16: 4 CONTRACTORS APPLICATION FOR PAYMENT ................................................................................... 00 62 76: 4 REQUEST FOR INFORMATION FORM ................................................................................................ 00 63 13: 1 SUBSTITUTION REQUEST FORM ........................................................................................................ 00 63 25: 2 FIELD ORDER FORM .......................................................................................................................... 00 63 36: 1 WORK CHANGE DIRECTIVE FORM .................................................................................................... 00 63 49: 1 CHANGE ORDER FORM ..................................................................................................................... 00 63 63: 1 CERTIFICATE OF SUBSTANTIAL COMPLETION FORM ........................................................................ 00 65 16: 1 AFFIDAVIT OF RELEASE OF LIENS FORM ........................................................................................... 00 65 19.16: 1 CONSENT OF SURETY FOR FINAL PAYMENT FORM .......................................................................... 00 65 19.19: 1 NOTICE OF ACCEPTABILITY OF WORK ............................................................................................... 00 65 19.23: 1 GENERAL CONDITIONS ...................................................................................................................... 00 72 00: 94 EQUAL EMPLOYMENT OPPORTUNITY REQUIREMENTS.................................................................... 00 73 36: 4 WAGE RATE REQUIREMENTS ............................................................................................................ 00 73 43: 4 WAGE DETERMINATION SCHEDULE ................................................................................................. 00 73 46: 7 ANTI-POLLUTION MEASURES ............................................................................................................ 00 73 53: 1 STATUTORY REQUIREMENTS ............................................................................................................ 00 73 73: 8

Specifications

DIVISION 01 – GENERAL REQUIREMENTS PAGES

01 10 00 PROJECT SUMMARY

01 12 00 MULTIPLE CONTRACT SUMMARY

01 12 16 WORK SEQUENCE

01 25 00 SUBSTITUTION PROCEDURES

01 26 00 CONTRACT MODIFICATION PROCEDURES

01 26 13 REQUESTS FOR INTERPRETATION

01 29 00 PAYMENT PROCEDURES

01 31 13 PROJECT COORDINATION

01 31 19 PROJECT MEETINGS

TABLE OF CONTENTS

Herbert, Rowland & Grubic, Inc. 00 01 10 - 2 011139.0465

01 32 16 CONSTRUCTION PROGRESS SCHEULE

01 32 26 CONSTRUCTION PROGRESS REPORTING

01 32 33 PHOTOGRAPHIC DOCUMENTATION

01 33 00 SUBMITTAL PROCEDURES

01 40 00 QUALITY REQUIREMENTS

01 42 00 REFERENCES

01 50 00 TEMPORARY FACILITIES AND CONTROLS

01 57 28 TEMPORARY FLOW CONTROL

01 61 00 PRODUCT REQUIREMENTS

01 64 00 OWNER FURNISHED PRODUCTS

01 73 00 EXECUTION REQUIREMENTS

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 77 00 CLOSEOUT PROCEDURES

01 78 23 OPERATION AND MAINTENANCE DATA

01 78 36 WARRANTIES

01 78 39 PROJECT RECORD DOCUMENTS

01 78 44 SPARE PARTS AND MAINTENANCE MATERIALS

01 91 13 GENERAL COMMISSIONING REQUIREMENTS

DIVISION 02 - EXISTING CONDITIONS PAGES

02 41 19.13 SELECTIVE BUILDING DEMOLITION

DIVISION 03 – CONCRETE PAGES

03 10 00 CONCRETE FORMING AND ACCESSORIES

03 20 00 CONCRETE REINFORCING

03 30 00 CAST-IN-PLACE CONCRETE

03 35 00 CONCRETE FINISHING

03 39 00 CONCRETE CURING

03 60 00 GROUTING

DIVISION 05 – METALS PAGES

05 12 00 STRUCTURAL STEEL FRAMING

05 31 23 STEEL ROOF DECKING

05 50 00 METAL FABRICATIONS

05 51 00 METAL STAIRS

05 52 00 METAL RAILINGS

05 53 00 METAL GRATINGS

DIVISION 09 – FINISHES PAGES

09 90 00 PAINTING AND COATING

DIVISION 26 – ELECTRICAL PAGES

26 05 00 ELECTRICAL GENERAL

26 05 10 BASIC ELECTRICAL MATERIALS AND METHODS

26 05 19 CONDUCTORS

26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

26 05 33 RACEWAY

26 05 53 ELECTRICAL SYSTEM IDENTIFICATION

26 05 73 POWER SYSTEM STUDY AND TESTING

26 08 00 ELECTRICAL FIELD ACCEPTANCE TESTS

26 09 16 AUXILIARY CONTROLS & RELAYS

26 24 19 MOTOR CONTROL CENTERS

26 27 16 CONTROL PANELS AND ENCLOSURES

26 28 16.13 OVERCURRENT PROTECTIVE DEVICES

26 28 16.16 DISCONNECT AND SAFETY SWITCHES

Herbert, Rowland & Grubic, Inc. 00 01 10 - 3 011139.0465

26 29 13 CONTACTORS AND MOTOR STARTING EQUIPMENT

26 29 23 VARIABLE FREQUENCY DRIVES

DIVISION 31 – EARTHWORK PAGES

31 05 13 SOILS FOR EARTHWORK

31 05 16 AGGREGATES FOR EARTHWORK

31 05 19.13 GEOTEXTILES FOR EARTHWORK

31 22 13 ROUGH GRADING

31 23 16.13 TRENCHING

31 23 16.26 ROCK REMOVAL

31 23 19 DEWATERING

31 23 23 FILL

31 23 33 TRENCHING AND BACKFILLING FOR UTILITIES

31 25 00 EROSION AND SEDIMENTATION CONTROLS

DIVISION 32 – EXTERIOR IMPROVEMENTS PAGES

32 91 13 SOIL PREPARATION

32 91 19 LANDSCAPE GRADING

32 92 19 SEEDING

DIVISION 33 – UTILITIES PAGES

33 05 05.31 HYDROSTATIC TESTING

33 05 09.33 THRUST RESTRAINT FOR UTILITY PIPING

33 31 23 SANITARY SEWERAGE FORCE MAIN PIPING

DIVISION 40 – PROCESS INTEGRATION PAGES

40 05 06 COUPLINGS, ADAPTERS, AND SPECIALS FOR PROCESS PIPING

40 05 07 HANGERS AND SUPPORTS FOR PROCESS PIPING .............................................................................. X

40 05 19 DUCTILE IRON PROCESS PIPE

40 05 23 STAINLESS STEEL PROCESS PIPE AND TUBING

40 05 31 THERMOPLASTIC PROCESS PIPE

40 05 36 FIBERGLASS-REINFORCED PLASTIC Process Pipe

40 05 51 COMMON REQUIREMENTS FOR PROCESS VALVES

40 05 53 IDENTIFICATION FOR PROCESS PIPING

40 05 62 PLUG VALVES

40 05 63 BALL VALVES

40 05 65.23 SWING CHECK VALVES

40 23 19 NON-POTABLE PLANT WATER PROCESS PIPING

40 23 40 SANITARY WASTEWATER PROCESS PIPING

40 42 13 PROCESS PIPING INSULATION

40 95 13 PROCESS CONTROL PANELS AND HARDWARE

DIVISION 41 – MATERIAL PROCESSING AND HANDLING EQUIPMENT PAGES

41 12 13.36 SCREW BULK MATERIAL CONVEYORS

DIVISION 46 – WATER AND WASTEWATER EQUIPMENT PAGES

46 05 53 IDENTIFICATION FOR WATER AND WASTEWATER EQUIPMENT

DRAWINGS 44