This is a Construction Waste Management and Disposal specification document for the Biosolids Project 011139.0465 at Ephrata Borough Authority in Pennsylvania. The project encompasses coordination and interconnection of two new biodryers, demolition and replacement of dewatered solids conveyor systems, select wall demolition and replacement, indoor utility replacements, site piping replacement/relocation, a dumpster loading canopy, and associated electrical improvements. Separate bids are requested for Contract No. EBA26-2 (General Construction) and Contract No. EBA26-3 (Electrical Construction). A pre-bid open house will be held on November 18, 2026, from 8:00 AM to 10:00 AM. Bids will be received through PennBid until December 8, 2026, at 10:00 AM local time, at which point bids will be publicly opened. Bidding documents are available at https://pennbid.bonfirehub.com/.

The contractor must develop and implement a construction waste management plan approved by the Engineer, with the intent of generating cost savings or minimal additional costs for waste disposal. The Owner will pay for solids disposal during construction with specific limitations: at least one centrifuge and conveyor train may be offline for a maximum of three days, and centrifuge cake may be disposed of for a maximum of one month at a time and two months total during construction. Any disposal beyond these limits becomes the contractor's responsibility. The contractor must collect waste in marked bins, maintain separation between biodryer and centrifuge solids, prevent environmental pollution and fire hazards, and obtain receipts for all deliveries to waste processing facilities or landfills. The contractor is responsible for cleaning any biosolids spills within designated areas of the facility to pre-spill conditions.

View the file

Other files

File Type Posted
26 08 00 - Electrical Field Acceptance Tests.pdf PDF
00 63 25 - Substitution Request Form (During Construction).pdf PDF
40 05 36 - Fiberglass-Reinforced Plastic Process Pipe.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 60 00 - Project Forms.pdf PDF
26 29 23 - VFDs .pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
26 05 19 - Conductors.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
05 53 00 - Metal Gratings (VPR).pdf PDF
02 41 19.13 - Selective Building Demolition (VPR).pdf PDF
01 29 00 - Payment Procedures.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 64 00 - Owner Furnished Products.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
40 05 65.23 - Swing Check Valves.pdf PDF
05 50 00 - Metal Fabrications (VPR).pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
26 09 16 - Auxiliary Controls & Relays.pdf PDF
01 10 00 - Project Summary.pdf PDF
05 52 00 - Metal Railings (VPR).pdf PDF
26 24 19 - MCC.pdf PDF
26 05 53 - Electrical System Identification.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 60 00 - Grouting (VPR).pdf PDF
01 61 00 - Product Requirements.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 31 00a Ephrata Boro Record Drawings.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
26 27 16 - Control Panels & Enclosures.pdf PDF
26 05 26 - Grounding.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 01 01 - LA Cover.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
32 92 19 - Seeding.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
05 31 23 - Steel Roof Decking (VPR).pdf PDF
00 52 00b - Agmnt btw Own and Cntr for Const Con Stip Price - Electrical Construction.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

Herbert, Rowland & Grubic, Inc. 01 74 19 - 1 011139.0465

SECTION 01 74 19 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Construction waste management plan.

2. Disposing of nonhazardous demolition and construction waste.

3. Disposing of partially dewatered wastewater solids

B. Related Sections:

1. Section 01 91 13 - Commissioning: General commissioning requirements.

1.2 PLAN REQUIREMENTS

A. Develop and implement construction waste management plan as approved by Engineer.

B. Intent:

1. Generate cost savings or increase minimal additional cost to Project for waste disposal.

1.3 SUBMITTALS

A. Section 01 33 00 - Submittal Procedures contains requirements for submittals.

B. Biosolids Management Plan: Submit biosolids management plan describing methods and procedures for implementation and monitoring compliance including the following:

1. Plan for solids management during construction.

2. On-Site sorting and Site storage methods.

1.4 BIOSOLIDS MANAGEMENT DURING CONSTRUCTION

A. The intent of solids management during construction will be for the Owner to pay for all solids disposal during Construction, aside from the exclusions noted below. Throughout the project, the objective will be to process solids with as little down time as possible.

Time constraints are as listed below:

1. The maximum amount of time that at least one centrifuge and train of conveyors are allowed to be offline is a maximum of three (3) days. This time is to ensure the Owner is able to maintain removal of solids from the biological process. If solids cannot be maintained for a time less than three (3) days, the Contractor will be responsible for costs associated with liquid hauling.

2. The bypass conveyor may be utilized to remove centrifuge cake from the facility at key points during construction. The Owner will handle solids once they are transported into the proposed dumpster canopy. The Contractor will be responsible for getting centrifuge cake into the dumpster. Centrifuge cake may only be disposed of for a maximum of one (1) month at a time, and two (2) months total during the course of construction. There are added costs associated

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

Herbert, Rowland & Grubic, Inc. 01 74 19 - 2 011139.0465 with the increased weight of centrifuge solids opposed to biodryer soldis. Any amount of time beyond the two (2) month maximum that solids are being removed from the facility via the bypass conveyor will be the responsibility of the Contractor.

B. Biosolids Spills within the Building: At any point during the construction contract that biosolids are spilled onto the floor of the centrifuge room, biodryer room, bypass conveyor canopy area, conveyor C-625 area, or anywhere else it will be the responsibility of the General Contractor to remove waste and clean the facility to the same conditions as before the spill.

PART 2 - EXECUTION

2.1 CONSTRUCTION WASTE COLLECTION

A. Collect construction waste materials in marked bins or containers and arrange for transportation to recycling centers or adaptive salvage and reuse processing facilities.

B. Maintain separation between biodryer solids and centrifuge solids for disposal by Owner.

C. Store construction waste materials to prevent environmental pollution, fire hazards, hazards to persons and property, and contamination of stored materials.

D. Cover construction waste materials subject to prevent water from entering dewatered solids.

2.2 CONSTRUCTION WASTE DISPOSAL

A. If Contractor is required to dispose of waste per the requirements described in Article 1.4;

deliver construction waste to waste processing facilities. Obtain receipt for deliveries.

B. Dispose of construction waste not capable of being recycled or adaptively reused by delivery to landfill, incinerator, or other legal disposal facility. Obtain receipt for deliveries.

2.1 Wastewater and biosolids Disposal

A. Request Owner to isolate existing process tanks and equipment where Work is required, as described.

B. Move all solids within the building during construction to Owner disposal areas.

C. Transport, treat and dispose of the removed contents in compliance with all regulations.

PART 3 – NOT USED

END OF SECTION

PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Construction waste management plan.
2. Disposing of nonhazardous demolition and construction waste.
3. Disposing of partially dewatered wastewater solids
B. Related Sections:
1. Section 01 91 13 - Commissioning: General commissioning requirements.
1.2 PLAN REQUIREMENTS
A. Develop and implement construction waste management plan as approved by Engineer.
B. Intent:
1. Generate cost savings or increase minimal additional cost to Project for waste disposal.
1.3 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures contains requirements for submittals.
B. Biosolids Management Plan: Submit biosolids management plan describing methods and procedures for implementation and monitoring compliance including the following:
1. Plan for solids management during construction.
2. On-Site sorting and Site storage methods.
1.4 BIOSOLIDS MANAGEMENT DURING CONSTRUCTION
A. The intent of solids management during construction will be for the Owner to pay for all solids disposal during Construction, aside from the exclusions noted below. Throughout the project, the objective will be to process solids with as little down...
1. The maximum amount of time that at least one centrifuge and train of conveyors are allowed to be offline is a maximum of three (3) days. This time is to ensure the Owner is able to maintain removal of solids from the biological process. If solids c...
2. The bypass conveyor may be utilized to remove centrifuge cake from the facility at key points during construction. The Owner will handle solids once they are transported into the proposed dumpster canopy. The Contractor will be responsible for gett...

B. Biosolids Spills within the Building: At any point during the construction contract that biosolids are spilled onto the floor of the centrifuge room, biodryer room, bypass conveyor canopy area, conveyor C-625 area, or anywhere else it will be the r...

PART 2 - EXECUTION
2.1 CONSTRUCTION WASTE COLLECTION
A. Collect construction waste materials in marked bins or containers and arrange for transportation to recycling centers or adaptive salvage and reuse processing facilities.
B. Maintain separation between biodryer solids and centrifuge solids for disposal by Owner.
C. Store construction waste materials to prevent environmental pollution, fire hazards, hazards to persons and property, and contamination of stored materials.
D. Cover construction waste materials subject to prevent water from entering dewatered solids.
2.2 CONSTRUCTION WASTE DISPOSAL
A. If Contractor is required to dispose of waste per the requirements described in Article 1.4; deliver construction waste to waste processing facilities. Obtain receipt for deliveries.
B. Dispose of construction waste not capable of being recycled or adaptively reused by delivery to landfill, incinerator, or other legal disposal facility. Obtain receipt for deliveries.
2.1 Wastewater and biosolids Disposal
A. Request Owner to isolate existing process tanks and equipment where Work is required, as described.
B. Move all solids within the building during construction to Owner disposal areas.
C. Transport, treat and dispose of the removed contents in compliance with all regulations.
PART 3 – NOT USED