01 74 19 - Construction Waste Management and Disposal.pdf
PDF 223 KB Posted
- Attached to
- Biosolids Project 011139.0465
- Solicitation number
- US.260443
- Issued by
- Lancaster County, Pennsylvania
About this file
This is a Construction Waste Management and Disposal specification document for the Biosolids Project 011139.0465 at Ephrata Borough Authority in Pennsylvania. The project encompasses coordination and interconnection of two new biodryers, demolition and replacement of dewatered solids conveyor systems, select wall demolition and replacement, indoor utility replacements, site piping replacement/relocation, a dumpster loading canopy, and associated electrical improvements. Separate bids are requested for Contract No. EBA26-2 (General Construction) and Contract No. EBA26-3 (Electrical Construction). A pre-bid open house will be held on November 18, 2026, from 8:00 AM to 10:00 AM. Bids will be received through PennBid until December 8, 2026, at 10:00 AM local time, at which point bids will be publicly opened. Bidding documents are available at https://pennbid.bonfirehub.com/.
The contractor must develop and implement a construction waste management plan approved by the Engineer, with the intent of generating cost savings or minimal additional costs for waste disposal. The Owner will pay for solids disposal during construction with specific limitations: at least one centrifuge and conveyor train may be offline for a maximum of three days, and centrifuge cake may be disposed of for a maximum of one month at a time and two months total during construction. Any disposal beyond these limits becomes the contractor's responsibility. The contractor must collect waste in marked bins, maintain separation between biodryer and centrifuge solids, prevent environmental pollution and fire hazards, and obtain receipts for all deliveries to waste processing facilities or landfills. The contractor is responsible for cleaning any biosolids spills within designated areas of the facility to pre-spill conditions.
View the file
Other files
Show 40 more
Latest 50 of 125 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
Herbert, Rowland & Grubic, Inc. 01 74 19 - 1 011139.0465
SECTION 01 74 19 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Construction waste management plan.
2. Disposing of nonhazardous demolition and construction waste.
3. Disposing of partially dewatered wastewater solids
B. Related Sections:
1. Section 01 91 13 - Commissioning: General commissioning requirements.
1.2 PLAN REQUIREMENTS
A. Develop and implement construction waste management plan as approved by Engineer.
B. Intent:
1. Generate cost savings or increase minimal additional cost to Project for waste disposal.
1.3 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures contains requirements for submittals.
B. Biosolids Management Plan: Submit biosolids management plan describing methods and procedures for implementation and monitoring compliance including the following:
1. Plan for solids management during construction.
2. On-Site sorting and Site storage methods.
1.4 BIOSOLIDS MANAGEMENT DURING CONSTRUCTION
A. The intent of solids management during construction will be for the Owner to pay for all solids disposal during Construction, aside from the exclusions noted below. Throughout the project, the objective will be to process solids with as little down time as possible.
Time constraints are as listed below:
1. The maximum amount of time that at least one centrifuge and train of conveyors are allowed to be offline is a maximum of three (3) days. This time is to ensure the Owner is able to maintain removal of solids from the biological process. If solids cannot be maintained for a time less than three (3) days, the Contractor will be responsible for costs associated with liquid hauling.
2. The bypass conveyor may be utilized to remove centrifuge cake from the facility at key points during construction. The Owner will handle solids once they are transported into the proposed dumpster canopy. The Contractor will be responsible for getting centrifuge cake into the dumpster. Centrifuge cake may only be disposed of for a maximum of one (1) month at a time, and two (2) months total during the course of construction. There are added costs associated
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
Herbert, Rowland & Grubic, Inc. 01 74 19 - 2 011139.0465 with the increased weight of centrifuge solids opposed to biodryer soldis. Any amount of time beyond the two (2) month maximum that solids are being removed from the facility via the bypass conveyor will be the responsibility of the Contractor.
B. Biosolids Spills within the Building: At any point during the construction contract that biosolids are spilled onto the floor of the centrifuge room, biodryer room, bypass conveyor canopy area, conveyor C-625 area, or anywhere else it will be the responsibility of the General Contractor to remove waste and clean the facility to the same conditions as before the spill.
PART 2 - EXECUTION
2.1 CONSTRUCTION WASTE COLLECTION
A. Collect construction waste materials in marked bins or containers and arrange for transportation to recycling centers or adaptive salvage and reuse processing facilities.
B. Maintain separation between biodryer solids and centrifuge solids for disposal by Owner.
C. Store construction waste materials to prevent environmental pollution, fire hazards, hazards to persons and property, and contamination of stored materials.
D. Cover construction waste materials subject to prevent water from entering dewatered solids.
2.2 CONSTRUCTION WASTE DISPOSAL
A. If Contractor is required to dispose of waste per the requirements described in Article 1.4;
deliver construction waste to waste processing facilities. Obtain receipt for deliveries.
B. Dispose of construction waste not capable of being recycled or adaptively reused by delivery to landfill, incinerator, or other legal disposal facility. Obtain receipt for deliveries.
2.1 Wastewater and biosolids Disposal
A. Request Owner to isolate existing process tanks and equipment where Work is required, as described.
B. Move all solids within the building during construction to Owner disposal areas.
C. Transport, treat and dispose of the removed contents in compliance with all regulations.
PART 3 – NOT USED
END OF SECTION
| PART 1 - GENERAL |
| 1.1 SUMMARY |
| A. Section Includes: |
| 1. Construction waste management plan. |
| 2. Disposing of nonhazardous demolition and construction waste. |
| 3. Disposing of partially dewatered wastewater solids |
| B. Related Sections: |
| 1. Section 01 91 13 - Commissioning: General commissioning requirements. |
| 1.2 PLAN REQUIREMENTS |
| A. Develop and implement construction waste management plan as approved by Engineer. |
| B. Intent: |
| 1. Generate cost savings or increase minimal additional cost to Project for waste disposal. |
| 1.3 SUBMITTALS |
| A. Section 01 33 00 - Submittal Procedures contains requirements for submittals. |
| B. Biosolids Management Plan: Submit biosolids management plan describing methods and procedures for implementation and monitoring compliance including the following: |
| 1. Plan for solids management during construction. |
| 2. On-Site sorting and Site storage methods. |
| 1.4 BIOSOLIDS MANAGEMENT DURING CONSTRUCTION |
| A. The intent of solids management during construction will be for the Owner to pay for all solids disposal during Construction, aside from the exclusions noted below. Throughout the project, the objective will be to process solids with as little down... |
| 1. The maximum amount of time that at least one centrifuge and train of conveyors are allowed to be offline is a maximum of three (3) days. This time is to ensure the Owner is able to maintain removal of solids from the biological process. If solids c... |
| 2. The bypass conveyor may be utilized to remove centrifuge cake from the facility at key points during construction. The Owner will handle solids once they are transported into the proposed dumpster canopy. The Contractor will be responsible for gett... |
B. Biosolids Spills within the Building: At any point during the construction contract that biosolids are spilled onto the floor of the centrifuge room, biodryer room, bypass conveyor canopy area, conveyor C-625 area, or anywhere else it will be the r...
| PART 2 - EXECUTION |
| 2.1 CONSTRUCTION WASTE COLLECTION |
| A. Collect construction waste materials in marked bins or containers and arrange for transportation to recycling centers or adaptive salvage and reuse processing facilities. |
| B. Maintain separation between biodryer solids and centrifuge solids for disposal by Owner. |
| C. Store construction waste materials to prevent environmental pollution, fire hazards, hazards to persons and property, and contamination of stored materials. |
| D. Cover construction waste materials subject to prevent water from entering dewatered solids. |
| 2.2 CONSTRUCTION WASTE DISPOSAL |
| A. If Contractor is required to dispose of waste per the requirements described in Article 1.4; deliver construction waste to waste processing facilities. Obtain receipt for deliveries. |
| B. Dispose of construction waste not capable of being recycled or adaptively reused by delivery to landfill, incinerator, or other legal disposal facility. Obtain receipt for deliveries. |
| 2.1 Wastewater and biosolids Disposal |
| A. Request Owner to isolate existing process tanks and equipment where Work is required, as described. |
| B. Move all solids within the building during construction to Owner disposal areas. |
| C. Transport, treat and dispose of the removed contents in compliance with all regulations. |
| PART 3 – NOT USED |
File details come from the government source that posted it. Updated .