32 91 19 - Landscape Grading.pdf

PDF 222 KB Posted

Attached to
Biosolids Project 011139.0465
Solicitation number
US.260443
Issued by
Lancaster County, Pennsylvania

About this file

This is a technical specification document (Section 32 91 19 - Landscape Grading) prepared by Herbert, Rowland & Grubic, Inc. for the Biosolids Project 011139.0465 managed by Ephrata Borough Authority in Pennsylvania. The specification details final grading and topsoil placement requirements for finish landscaping as part of a larger biosolids facility project. The work includes substrate preparation, topsoil placement to a nominal depth of 4 inches in seeding areas, fine grading to maintain specified profiles and contours, and temporary surfacing provisions when weather conditions prevent permanent surface placement. Key execution requirements mandate verification of existing conditions before work begins, removal of debris and stones exceeding 1/4 inch, scarification of surfaces to 3 inches depth where topsoil is scheduled, manual spreading of topsoil near utilities and structures to prevent damage, and light compaction of placed topsoil. Tolerances for the top of topsoil are specified at plus or minus 1/2 inch. The contractor must submit the name of imported materials sources and manufacturer's certificates confirming products meet specified requirements, with all topsoil materials sourced from a single supplier throughout the work.

The specification establishes contractor responsibility for maintenance and protection of temporary surfacing, with permanent surfacing required within thirty days of temporary placement or as soon as environmental conditions allow. Prior to final surfacing placement, the contractor and Authority Representative must inspect all restoration areas, with the contractor bearing responsibility for any necessary material replacement, regrading, or additional material placement deemed unacceptable by the Authority Representative or Engineer. The contractor must also manage grade adjustments for utilities, manholes, frames, covers, and other facilities before final surfacing, and remove and dispose of temporary surfacing to achieve the specified grades for final sub-base, base, and surface layers. Construction traffic over topsoil is prohibited to protect the installed work. The specification references related sections covering soils for exterior improvements, trenching and backfilling for utilities, and seeding for finish ground cover.

View the file

Other files

File Type Posted
26 08 00 - Electrical Field Acceptance Tests.pdf PDF
00 63 25 - Substitution Request Form (During Construction).pdf PDF
40 05 36 - Fiberglass-Reinforced Plastic Process Pipe.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 60 00 - Project Forms.pdf PDF
26 29 23 - VFDs .pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
26 05 19 - Conductors.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
05 53 00 - Metal Gratings (VPR).pdf PDF
02 41 19.13 - Selective Building Demolition (VPR).pdf PDF
01 29 00 - Payment Procedures.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 64 00 - Owner Furnished Products.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
40 05 65.23 - Swing Check Valves.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
05 50 00 - Metal Fabrications (VPR).pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
26 09 16 - Auxiliary Controls & Relays.pdf PDF
01 10 00 - Project Summary.pdf PDF
05 52 00 - Metal Railings (VPR).pdf PDF
26 24 19 - MCC.pdf PDF
26 05 53 - Electrical System Identification.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 60 00 - Grouting (VPR).pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 31 00a Ephrata Boro Record Drawings.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
26 27 16 - Control Panels & Enclosures.pdf PDF
26 05 26 - Grounding.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 01 01 - LA Cover.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
32 92 19 - Seeding.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
05 31 23 - Steel Roof Decking (VPR).pdf PDF
00 52 00b - Agmnt btw Own and Cntr for Const Con Stip Price - Electrical Construction.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

32 91 19 - LANDSCAPE GRADING

Herbert, Rowland & Grubic, Inc. 32 91 19 - 1 011139.0465

SECTION 32 91 19 - LANDSCAPE GRADING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Final grade topsoil for finish landscaping.

B. Related Sections:

1. Section 31 05 13 - Soils for Exterior Improvements.

2. Section 31 23 33 – Trenching and Backfilling for Utilities: Backfilling trenches.

3. Section 32 92 19 - Seeding: Finish ground cover.

1.2 SUBMITTALS

A. Section 01 33 00 - Submittal Procedures: Submittal procedures.

B. Materials Source: Submit name of imported materials source.

C. Manufacturer's Certificate: Certify Products meet or exceed specified requirements.

1.3 QUALITY ASSURANCE

A. Furnish each topsoil material from single source throughout the Work.

PART 2 - PRODUCTS

2.1 MATERIAL

A. Topsoil: As specified in Section 31 05 13 – Soils for Earthwork.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Section 01 73 00 - Execution Requirements: Verification of existing conditions before starting work.

B. Verify building and trench backfilling have been inspected.

C. Verify substrate base has been contoured and compacted.

3.2 TEMPORARY SURFACING:

A. In the event the permanent surfacing cannot be placed due to the weather limitations set forth herein, provide a temporary surface in lieu thereof.

Herbert, Rowland & Grubic, Inc. 32 91 19 - 2 011139.0465

B. The Contractor shall be responsible for the maintenance and protection of all temporary surfacing until such time as that the permanent pavement or surface can be placed.

Permanent surfacing must be placed no later than thirty days following the placement of temporary surfacing. In the event that environmental conditions do not allow for placement of permanent surfacing within the thirty days specified, permanent surfacing must be placed as soon as conditions allow.

C. Prior to placement of final surfacing, the Contractor and Authority Representative shall inspect all areas to be restored. The Contractor shall be responsible for any replacement of material, regarding, or addition of material deemed necessary by the Authority Representative or Engineer in any areas found to be unacceptable for receipt of final surfacing.

D. Contractor shall be responsible for the removal and disposal of the temporary surfacing to the grade required for the placement of the final sub-base, base, and surface at the specified depths.

E. The Contractor shall be responsible for any necessary adjustments to grade for manholes, frame and covers, and other facilities or structures prior to final surfacing.

F. Temporary surfacing shall be placed where directed by the Authority Representative or Engineer.

3.3 PREPARATION

A. Protect landscaping and other features remaining as final Work.

B. Protect existing structures, fences, sidewalks, utilities, paving, and curbs.

3.4 SUBSTRATE PREPARATION

A. Eliminate uneven areas and low spots.

B. Remove debris, roots, branches, stones, in excess of 1/4 inch in size. Remove contaminated subsoil.

C. Scarify surface to depth of 3 inches where topsoil is scheduled. Scarify in areas where equipment used for hauling and spreading topsoil has compacted subsoil.

3.5 PLACING TOPSOIL

A. Place topsoil in areas where seeding is required to nominal depth of 4 inches. Place topsoil during dry weather.

B. Fine grade topsoil to eliminate rough or low areas. Maintain profiles and contour of subgrade.

C. Remove roots, weeds, rocks, and foreign material while spreading.

Herbert, Rowland & Grubic, Inc. 32 91 19 - 3 011139.0465

D. Manually spread topsoil close to utilities, building, and pavement to prevent damage.

E. Lightly compact placed topsoil.

F. Remove surplus subsoil and topsoil from site.

3.6 TOLERANCES

A. Section 01 40 00 - Quality Requirements: Tolerances.

B. Top of Topsoil: Plus or minus 1/2 inch.

3.7 PROTECTION OF INSTALLED WORK

A. Section 01 73 00 - Execution Requirements: Requirements for protecting finished Work.

B. Prohibit construction traffic over topsoil.

END OF SECTION

PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Final grade topsoil for finish landscaping.
B. Related Sections:
1. Section 31 05 13 - Soils for Exterior Improvements.
2. Section 31 23 33 – Trenching and Backfilling for Utilities: Backfilling trenches.
3. Section 32 92 19 - Seeding: Finish ground cover.
1.2 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Submittal procedures.
B. Materials Source: Submit name of imported materials source.
C. Manufacturer's Certificate: Certify Products meet or exceed specified requirements.
1.3 QUALITY ASSURANCE
A. Furnish each topsoil material from single source throughout the Work.
PART 2 - PRODUCTS
2.1 MATERIAL
A. Topsoil: As specified in Section 31 05 13 – Soils for Earthwork.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Section 01 73 00 - Execution Requirements: Verification of existing conditions before starting work.
B. Verify building and trench backfilling have been inspected.
C. Verify substrate base has been contoured and compacted.
3.2 TEMPORARY SURFACING:
A. In the event the permanent surfacing cannot be placed due to the weather limitations set forth herein, provide a temporary surface in lieu thereof.
B. The Contractor shall be responsible for the maintenance and protection of all temporary surfacing until such time as that the permanent pavement or surface can be placed. Permanent surfacing must be placed no later than thirty days following the pl...
C. Prior to placement of final surfacing, the Contractor and Authority Representative shall inspect all areas to be restored. The Contractor shall be responsible for any replacement of material, regarding, or addition of material deemed necessary by t...
D. Contractor shall be responsible for the removal and disposal of the temporary surfacing to the grade required for the placement of the final sub-base, base, and surface at the specified depths.
E. The Contractor shall be responsible for any necessary adjustments to grade for manholes, frame and covers, and other facilities or structures prior to final surfacing.
F. Temporary surfacing shall be placed where directed by the Authority Representative or Engineer.
3.3 PREPARATION
A. Protect landscaping and other features remaining as final Work.
B. Protect existing structures, fences, sidewalks, utilities, paving, and curbs.
3.4 SUBSTRATE PREPARATION
A. Eliminate uneven areas and low spots.
B. Remove debris, roots, branches, stones, in excess of 1/4 inch in size. Remove contaminated subsoil.
C. Scarify surface to depth of 3 inches where topsoil is scheduled. Scarify in areas where equipment used for hauling and spreading topsoil has compacted subsoil.
3.5 PLACING TOPSOIL
A. Place topsoil in areas where seeding is required to nominal depth of 4 inches. Place topsoil during dry weather.
B. Fine grade topsoil to eliminate rough or low areas. Maintain profiles and contour of subgrade.
C. Remove roots, weeds, rocks, and foreign material while spreading.
D. Manually spread topsoil close to utilities, building, and pavement to prevent damage.
E. Lightly compact placed topsoil.
F. Remove surplus subsoil and topsoil from site.
3.6 TOLERANCES
A. Section 01 40 00 - Quality Requirements: Tolerances.
B. Top of Topsoil: Plus or minus 1/2 inch.
3.7 PROTECTION OF INSTALLED WORK
A. Section 01 73 00 - Execution Requirements: Requirements for protecting finished Work.
B. Prohibit construction traffic over topsoil.

File details come from the government source that posted it. Updated .