00 73 43 - Wage Rate Requirements.pdf

PDF 264 KB Posted

Attached to
Biosolids Project 011139.0465
Solicitation number
US.260443
Issued by
Lancaster County, Pennsylvania

About this file

This is a Wage Rate Requirements document for the Biosolids Project 011139.0465 in Ephrata, Pennsylvania, establishing prevailing wage compliance standards under the Pennsylvania Prevailing Wage Act. The document outlines mandatory wage rate requirements and contractor obligations for both general construction (Contract No. EBA26-2) and electrical construction (Contract No. EBA26-3) on a project involving coordination and interconnection of two new biodryers, demolition and replacement of dewatered solids conveyor systems, wall demolition and replacement, indoor utility replacements, site piping relocation, a dumpster loading canopy, and associated electrical improvements. Bids are due December 8, 2026 at 10:00 AM local time through PennBid, with a pre-bid open house scheduled for November 18, 2026 from 8:00 AM to 10:00 AM. The project is being administered by Ephrata Borough Authority.

All contractors and subcontractors must pay workers at or above prevailing wage rates as determined by the Pennsylvania Secretary of Labor and Industry, maintain detailed payroll records for two years, and post wage rate notices prominently at the project site. Contractors are required to file weekly payroll certifications under oath using the prescribed Pennsylvania Department of Labor and Industry Form LLC-25, certifying full compliance with prevailing wage provisions. At project completion, contractors must submit statements documenting any unpaid wages as a prerequisite for owner acceptance. Contractors and subcontractors must make employees available for interviews regarding compliance and cannot subcontract work to any debarred entities under the Pennsylvania Prevailing Wage Act. Workers who believe they have been underpaid retain civil rights of action for wage recovery within six months.

View the file

Other files

File Type Posted
26 08 00 - Electrical Field Acceptance Tests.pdf PDF
00 63 25 - Substitution Request Form (During Construction).pdf PDF
40 05 36 - Fiberglass-Reinforced Plastic Process Pipe.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 60 00 - Project Forms.pdf PDF
26 29 23 - VFDs .pdf PDF
26 05 19 - Conductors.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
05 53 00 - Metal Gratings (VPR).pdf PDF
02 41 19.13 - Selective Building Demolition (VPR).pdf PDF
01 29 00 - Payment Procedures.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 64 00 - Owner Furnished Products.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
40 05 65.23 - Swing Check Valves.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
05 50 00 - Metal Fabrications (VPR).pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
26 09 16 - Auxiliary Controls & Relays.pdf PDF
01 10 00 - Project Summary.pdf PDF
05 52 00 - Metal Railings (VPR).pdf PDF
26 24 19 - MCC.pdf PDF
26 05 53 - Electrical System Identification.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 60 00 - Grouting (VPR).pdf PDF
01 61 00 - Product Requirements.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 31 00a Ephrata Boro Record Drawings.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
26 27 16 - Control Panels & Enclosures.pdf PDF
26 05 26 - Grounding.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 01 01 - LA Cover.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
32 92 19 - Seeding.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
05 31 23 - Steel Roof Decking (VPR).pdf PDF
00 52 00b - Agmnt btw Own and Cntr for Const Con Stip Price - Electrical Construction.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

00 73 43 – WAGE RATE REQUIREMENTS

Herbert, Rowland & Grubic, Inc. 00 73 43 - 1 011139.0465

SECTION 00 73 43 – WAGE RATE REQUIREMENTS

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Duties and requirements of Contractor under Pennsylvania Prevailing Wage Act.

1.2 RELATED SECTIONS

A. Document 00 72 00 – General Conditions.

B. Document 00 73 46– Wage Determination Schedule.

1.3 DUTIES AND REQUIREMENTS

A. Contained with Section 00 72 00 are references to Laws and Regulations. The Pennsylvania Prevailing Wage Act (Act No. 442 - Session of 1961, as amended) (and also Act 101 of 2026, which will take effect December 21, 2026) shall apply to this Project.

Contractor is responsible for compliance with the law, including the following specific requirements:

1. All workmen employed by this Project shall be paid not less than the minimum wage rates, including employee benefits, which have been determined by the Secretary of Labor and Industry.

2. Each Contractor and Subcontractor shall keep an accurate record showing the name, craft and the actual hourly rate of wage paid to each workman employed by him in connection with this public Work. This record shall be preserved for two years from date of Project. This record shall be open to the inspection of the Owner, or representative thereof, and to the Secretary of Labor and Industry.

3. Contractor and Subcontractors shall post for the entire period of construction the general prevailing minimum wages for each craft and classification involved, as determined by the Secretary of Labor and Industry, and in a prominent and easily accessible place at the Site of the Work. At a minimum, the posted notice of wage rates must contain the following information:

a. Name of Project.

b. Name of public body for which it is being constructed.

c. The crafts and classifications of workmen listed in the Secretary's general prevailing minimum wage rate determination for the particular Project.

d. The general prevailing minimum wage rates determined for each craft and classification and the effective date of any changes.

e. A statement advising workmen that if they have been paid less than the general prevailing minimum wage rate for their job classification or that the Contractor and/or Subcontractor are not complying with the Act or these Regulations in any manner whatsoever, they may file a protest with the Secretary of Labor and Industry. Any workmen paid less than the rate specified shall have a civil right of action for the difference between the wage paid and the wages stipulated, which right of action must be exercised within six months from the occurrence of the event creating such right.

00 73 43 – WAGE RATE REQUIREMENTS

Herbert, Rowland & Grubic, Inc. 00 73 43 - 2 011139.0465

4. At the completion of the Work and as a prerequisite for acceptance by the Owner, each Contractor and Subcontractor shall file statements with the Owner of the names and amounts of unpaid wages.

5. Each Contractor and each Subcontractor shall file a statement each week under oath and in form satisfactory to the Secretary certifying that all workmen have been paid wages in strict conformity with the provisions, if any wages remain unpaid, to set forth the amount of wages due and owing to each workmen respectively.

6. Contractor and Subcontractors shall make employees available for interviews by the Owner or representative thereof or to the Secretary on a reasonable basis.

Interviews shall be limited to the employee's name, address, dates worked on the Project, hourly rate, job classification, duties, tools and equipment utilized and comments regarding compliance with the labor standards.

B. Attached to this Section are the forms to be used for weekly payroll certifications:

1. Pennsylvania Department of Labor and Industry “WEEKLY PAYROLL

CERTIFICATION FOR PUBLIC WORKS PROJECTS” Form LLC-25, rev 10/03.

END OF SECTION

LLC-25 REV 10-03 (Page 1)

WEEKLY PAYROLL CERTIFICATION FOR PUBLIC WORKS PROJECTS

Contractor or Subcontractor (Please check one) ALL INFORMATION MUST BE COMPLETED

BUREAU OF LABOR LAW COMPLIANCE

PREVAILING WAGE DIVISION

7TH & FORSTER STREETS

HARRISBURG, PA 17120

1-800-932-0665

CONTRACTOR SUBCONTRACTOR

ADDRESS ADDRESS

PAYROLL NUMBER WEEK ENDING DATE PROJECT AND LOCATION

PROJECT SERIAL # PROJECT #

EMPLOYEE NAME

APPR.

RATE

WORK

CLASSIFICATION

DAY AND DATE

HOURS WORKED EACH DAY

S-

TIME

0-

TIME

BASE

HOURLY

RATE

TOTAL FRINGE

BENEFITS

(C=Cash)

(FB=Contributions)*

TOTAL

DEDUCTIONS

GROSS PAY

FOR

PREVAILING

RATE JOB(S)

CHECK #

C:

FB:

C:

FB:

C:

FB:

C:

FB:

C:

FB:

*SEE REVERSE SIDE

PAGE NUMBER ___________ OF ____________

THE NOTARIZATION MUST BE COMPLETED ON FIRST AND LAST SUBMISSIONS ONLY. ALL OTHER

INFORMATION MUST BE COMPLETED WEEKLY.

*FRINGE BENEFITS EXPLANATION (FB): Bona fide benefits contribution, except those required by Federal or State Law (unemployment tax, workers’ compensation, income taxes, etc.)

Please specify the type of benefits provided and contributions per hour:

1) Medical or hospital care__________________________________________________________________________

2) Pension or retirement ____________________________________________________________________________

3) Life insurance _________________________________________________________________________________

4) Disability _____________________________________________________________________________________

5) Vacation, holiday _______________________________________________________________________________

6) Other (please specify) ___________________________________________________________________________

CERTIFIED STATEMENT OF COMPLIANCE

1. The undersigned, having executed a contract with _____________________________________________________

______________________________ for the construction of the above-identified project, acknowledges that:

(a) The prevailing wage requirements and the predetermined rates are included in the aforesaid contract.

(b) Correction of any infractions of the aforesaid conditions is the contractor’s or subcontractor’s responsibility.

(c) It is the contractor’s responsibility to include the Prevailing Wage requirements and the predetermined rates in any subcontract or lower tier subcontract for this project.

2. The undersigned certifies that:

(a) Neither he nor his firm, nor any firm, corporation or partnership in which he or his firm has an interest is debarred by the Secretary of Labor and Industry pursuant to Section 11(e) of the PA Prevailing Wage Act, Act of August 15, 1961, P.L. 987 as amended, 43 P.S.§ 165-11(e).

(b) No part of this contract has been or will be subcontracted to any subcontractor if such subcontractor or any firm, corporation or partnership in which such subcontractor has an interest is debarred pursuant to the aforementioned statute.

3. The undersigned certifies that:

(a) the legal name and the business address of the contractor or subcontractor are: _________________________

(b) The undersigned is:

(c) The name, title and address of the owner, partners or officers of the contractor/subcontractor are:

The willful falsification of any of the above statements may subject the contractor to civil or criminal prosecution, provided in the PA Prevailing Wage Act of August 15, 1961, P.L. 987, as amended, August 9, 1963, 43 P.S. § 165.1 through 165.17.

(AWARDING AGENCY, CONTRACTOR OR SUBCONTRACTOR)

a single proprietorship a corporation organized in the state of ______________ a partnership other organization (describe) ____________________________

NAME TITLE ADDRESS

(DATE)

SEAL

(SIGNATURE)

(TITLE)

Taken, sworn and subscribed before me this _________ Day of ___________________________________ A.D., ___________LLC-25 REV 10-03 (Page 2)