01 57 28 - Temporary Flow Control.pdf
PDF 249 KB Posted
- Attached to
- Biosolids Project 011139.0465
- Solicitation number
- US.260443
- Issued by
- Lancaster County, Pennsylvania
About this file
Summary
This is a Temporary Flow Control specification document for the Biosolids Project 011139.0465 being undertaken by Ephrata Borough Authority in Pennsylvania. The specification establishes the contractor's responsibilities for managing temporary flow control systems during construction, including water control and pollution control measures for sanitary sewers, storm sewers, pump stations, and force mains. Key deliverables include a Temporary Flow Control Plan (due 10 days before work begins), an Emergency Cleanup Plan, and product submittals detailing pump specifications, curves, controls, valves, and piping. The work encompasses bypass pumping systems, temporary sewer plugs, flow interception and discharge locations, and maintenance of centrate flow to designated tankage at rates up to 400 gallons per minute. The contractor must maintain sludge dewatering operations throughout construction and comply with Pennsylvania Department of Environmental Protection temporary sanitary flow bypass requirements. The specification references coordination with temporary facilities outlined in Sections 01 50 00 and 01 74 19 and requires permits for placement of temporary facilities within or near public roadways.
Equipment requirements include solids-handling pumps capable of handling three-inch diameter spheres that can run dry for extended periods, with noise levels not exceeding 86 decibels at 50 feet; electric power generators with automatic transfer switches for unattended operation; and standby equipment including one pump of each size and minimum one backup generator onsite at all times. Temporary plugs must accommodate pressure gauges and air hoses and must be mechanical or pneumatic for pipes 24 inches or smaller, with inflatable bag stoppers in two or more pieces for larger diameters from manufacturers such as Lansas or Cherne Industries. Upon completion of work, the contractor must remove all temporary equipment and materials, clean and repair any damage, and restore existing and permanent facilities to original or specified conditions. No specific pricing, set-asides, or contract award dates are identified in this specification document.
View the file
Other files
Show 40 more
Latest 50 of 125 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 57 28 - TEMPORARY FLOW CONTROL
Herbert, Rowland & Grubic, Inc. 01 57 28 - 1 011139.0465
SECTION 01 57 28 - TEMPORARY FLOW CONTROL
PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Responsibilities for temporary facilities and controls.
B. Temporary Controls:
1. Water control.
2. Pollution control.
C. Removal of utilities, facilities, and controls.
1.2 DEFINITIONS
A. Bypass Pumping: Temporary flow control accomplished by diverting flow away from the Work area using one or more pumps.
B. Temporary Flow Control: Reducing, limiting, or excluding flow in or to a sanitary sewer, storm sewer, pump station, force main, or other facility as required for performing the Work under the Contract. Draining, handling, and disposal of sanitary sewage and stormwater from pipelines and other facilities as required for performing the Work under the Contract is also part of temporary flow control.
C. Temporary Flow Control Plan: Plan prepared by Contractor containing complete information on how Contractor proposes to perform temporary flow control in accordance with specified requirements.
1.3 SYSTEM DESCRIPTION
A. Provide facilities and controls required to intercept, convey, and discharge flow to be controlled; include redundant standby and emergency equipment.
B. Conform to regulatory requirements.
C. Protect water resources and other natural resources.
D. Temporary flow control shall be done in a manner that will not interfere or disrupt facility operations, property, or create a nuisance or public menace. Flow shall be conveyed in enclosed pipes that are adequately protected from traffic or other hazards.
E. Centrifuge Feed Positive Displacement Pumps:
1. It is not anticipated that the existing solids handling pumps in the centrifuge room will be taken off line during construction. If they are required to be, Contractor will be responsible to provide temporary solids handling pumps or temporary power to the existing pumps.
F. Centrate Force Main:
Herbert, Rowland & Grubic, Inc. 01 57 28 - 2 011139.0465
1. Maintain centrate flow to the designated tankage as directed by the Owner during construction.
2. Contractor shall (if required) install submersible pumps capable of 400gpm into the centrate pump station wet well during installation of the proposed force main. Flexible piping may be utilized to transport centrate into the tank designated by owner (where the force main is shown to discharge on Contract Drawings). The existing pumps may be utilized, but the Contractor must demonstrate during submittals that the pumps can maintain flow rates via the proposed temporary bypass piping. Total Dynamic Head and Flow calculations must be provided for approval.
3. If temporary pumps are utilized, it is recommended that a float system be established in the wet well for operation of temporary pumps.
4. Discharge of waste in any form to storm sewers or onto the ground, is strictly prohibited.
1.4 CONDITIONS
A. Obtain approval and secure permits for placement of temporary flow control facilities within or near public roadways.
B. Coordinate Temporary flow controls of Temporary Digested Sludge Dewatering Facilities in Section 01 50 00 and Section 01 74 19.
1.5 SUBMITTALS
A. Informational Submittals
1. Temporary Flow Control Plan
2. Emergency Cleanup Plan
3. Coordinate Submittals with Temporary Facilities in Section 01 50 00 and Section
01 74 19.
B. Products: Pump information with curves, controls, valves, piping and connections
1.6 QUALITY ASSURANCE
A. Regulatory Requirements: Comply with Pennsylvania Department of Environmental Protection temporary sanitary flow bypass requirements.
1.7 TEMPORARY FLOW CONTROL PLAN
A. Prepare and submit Temporary Flow Control Plan at least ten (10) days before starting the Work requiring temporary flow control; include following information:
1. Drawings indicating location of temporary sewer plugs, valve controls and bypass discharge lines.
2. Locations where flow will be intercepted and discharged.
3. Complete descriptions and performance characteristics of pumps, electric power generators, and standby equipment.
4. Plan shall include all work required to maintain sludge dewatering operations of the facility including but not limited to:
Herbert, Rowland & Grubic, Inc. 01 57 28 - 3 011139.0465
a. Pumping systems described above,
b. Temporary dewatering facilities and controls – See Section 01 50 00 –
Temporary Facilities and Controls,
c. Temporary plugs (if required),
d. Excavation, and
e. Other work required to maintain flows during construction.
1.8 EMERGENCY CLEANUP PLAN
A. Prepare and submit an emergency cleanup plan. As a minimum plan shall include the following:
1. Procedures for removal of water.
2. Procedures for determining nature and extent of damage and required restoration where restoration is possible.
3. Backup for temporary dewatering facilities outage.
1.9 WATER CONTROL
A. Grade Site to drain. Maintain excavations free of water. Provide, operate, and maintain necessary pumping equipment.
B. Protect Site from puddles or running water.
1.10 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS
A. Remove temporary equipment and materials after startup and successful operation systems.
B. Clean and repair damage caused by installation or use of temporary Work.
C. Restore existing facilities used during construction to original condition. Restore permanent facilities used during construction to specified condition.
PART 2 - PRODUCTS
2.1 EQUIPMENT AND MATERIALS
A. General:
1. Provide materials and equipment that will ensure continuous and successful operation of temporary flow control systems.
2. Repair or modify systems as necessary.
3. Unless otherwise shown or specified, materials and equipment may be new or used at Contractor’s option.
4. Coordinate needs of bypass pumping system with requirement for the temporary digested sludge dewatering facilities in Section 01 50 00 – Temporary Facilities and Controls.
B. Plugs:
Herbert, Rowland & Grubic, Inc. 01 57 28 - 4 011139.0465
1. Provide with taps for connection of pressure gauges and air hoses, and flow-through capability.
2. Pipe Diameters 24 Inches and Smaller: Use mechanical plugs with rubber gaskets or pneumatic plugs with rubber boots.
3. Pipe Diameters Larger than 24 Inches:
4. Use inflatable bag stoppers made in two (2) or more pieces.
5. Manufacturers:
a. Lansas.
b. Cherne Industries.
C. Pumps:
1. Solids handling design with ability to pump minimum three (3)-inch diameter sphere.
2. Able to run dry for long periods of time to accommodate cyclical nature of flows.
3. Engine: Equipped to minimize noise. Noise levels shall not exceed 86 dBA at a distance of fifty (50) feet from source.
D. Electric Power Generators:
1. Be able to simultaneously start and run electric powered pumps required for flow to be controlled.
2. Equipped to minimize noise. Noise levels shall not exceed 86 dBA at a distance of fifty (50) feet from source.
3. Include automatic transfer switch if flow control system is to operate unattended.
E. Standby Equipment:
1. Standby Pump: One (1) of each size to be available onsite at all times.
2. Electric Power Generators: Minimum of 1 if temporary flow control system contains electric powered pump. Able to simultaneously start and run electric powered pumps required for flow to be controlled.
PART 3 - EXECUTION
3.1 GENERAL
A. Install temporary flow control facilities in a location acceptable to Owner’s Operations and Facility Maintenance.
B. Operate and maintain temporary flow control while area of Work is out of service.
3.2 BLOCKING FLOW
A. Flow control may consist of blocking flow with mechanical or pneumatic plugs if adequate storage is available.
B. When blocking flow is no longer needed for performance and acceptance of the Work, remove plugs in a manner that permits sewage flow to slowly return to normal without surcharging or causing other major disturbances downstream.
C. Remove temporary plugs at end of each working day and restore normal flow. If
Herbert, Rowland & Grubic, Inc. 01 57 28 - 5 011139.0465 downstream work is not or cannot be completed during workday provide, operate, and maintain bypass pumping system or other method of flow control to accommodate flows.
END OF SECTION
| PART 1 - GENERAL |
| 1.1 SECTION INCLUDES |
| A. Responsibilities for temporary facilities and controls. |
| B. Temporary Controls: |
| 1. Water control. |
| 2. Pollution control. |
C. Removal of utilities, facilities, and controls.
| 1.2 DEFINITIONS |
| A. Bypass Pumping: Temporary flow control accomplished by diverting flow away from the Work area using one or more pumps. |
| B. Temporary Flow Control: Reducing, limiting, or excluding flow in or to a sanitary sewer, storm sewer, pump station, force main, or other facility as required for performing the Work under the Contract. Draining, handling, and disposal of sanitary s... |
| C. Temporary Flow Control Plan: Plan prepared by Contractor containing complete information on how Contractor proposes to perform temporary flow control in accordance with specified requirements. |
| 1.3 SYSTEM DESCRIPTION |
| A. Provide facilities and controls required to intercept, convey, and discharge flow to be controlled; include redundant standby and emergency equipment. |
| B. Conform to regulatory requirements. |
| C. Protect water resources and other natural resources. |
| D. Temporary flow control shall be done in a manner that will not interfere or disrupt facility operations, property, or create a nuisance or public menace. Flow shall be conveyed in enclosed pipes that are adequately protected from traffic or other h... |
| E. Centrifuge Feed Positive Displacement Pumps: |
| 1. It is not anticipated that the existing solids handling pumps in the centrifuge room will be taken off line during construction. If they are required to be, Contractor will be responsible to provide temporary solids handling pumps or temporary powe... |
| F. Centrate Force Main: |
| 1. Maintain centrate flow to the designated tankage as directed by the Owner during construction. |
| 2. Contractor shall (if required) install submersible pumps capable of 400gpm into the centrate pump station wet well during installation of the proposed force main. Flexible piping may be utilized to transport centrate into the tank designated by own... |
| 3. If temporary pumps are utilized, it is recommended that a float system be established in the wet well for operation of temporary pumps. |
| 4. Discharge of waste in any form to storm sewers or onto the ground, is strictly prohibited. |
| 1.4 CONDITIONS |
| A. Obtain approval and secure permits for placement of temporary flow control facilities within or near public roadways. |
| B. Coordinate Temporary flow controls of Temporary Digested Sludge Dewatering Facilities in Section 01 50 00 and Section 01 74 19. |
| 1.5 SUBMITTALS |
| A. Informational Submittals |
| 1. Temporary Flow Control Plan |
| 2. Emergency Cleanup Plan |
| 3. Coordinate Submittals with Temporary Facilities in Section 01 50 00 and Section 01 74 19. |
B. Products: Pump information with curves, controls, valves, piping and connections
| 1.6 QUALITY ASSURANCE |
| A. Regulatory Requirements: Comply with Pennsylvania Department of Environmental Protection temporary sanitary flow bypass requirements. |
| 1.7 TEMPORARY FLOW CONTROL PLAN |
| A. Prepare and submit Temporary Flow Control Plan at least ten (10) days before starting the Work requiring temporary flow control; include following information: |
| 1. Drawings indicating location of temporary sewer plugs, valve controls and bypass discharge lines. |
| 2. Locations where flow will be intercepted and discharged. |
| 3. Complete descriptions and performance characteristics of pumps, electric power generators, and standby equipment. |
| 4. Plan shall include all work required to maintain sludge dewatering operations of the facility including but not limited to: |
| a. Pumping systems described above, |
| b. Temporary dewatering facilities and controls – See Section 01 50 00 – Temporary Facilities and Controls, |
| c. Temporary plugs (if required), |
| d. Excavation, and |
| e. Other work required to maintain flows during construction. |
| 1.8 EMERGENCY CLEANUP PLAN |
| A. Prepare and submit an emergency cleanup plan. As a minimum plan shall include the following: |
| 1. Procedures for removal of water. |
| 2. Procedures for determining nature and extent of damage and required restoration where restoration is possible. |
| 3. Backup for temporary dewatering facilities outage. |
| 1.9 WATER CONTROL |
| A. Grade Site to drain. Maintain excavations free of water. Provide, operate, and maintain necessary pumping equipment. |
| B. Protect Site from puddles or running water. |
| 1.10 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS |
| A. Remove temporary equipment and materials after startup and successful operation systems. |
| B. Clean and repair damage caused by installation or use of temporary Work. |
| C. Restore existing facilities used during construction to original condition. Restore permanent facilities used during construction to specified condition. |
| PART 2 - PRODUCTS |
| 2.1 EQUIPMENT AND MATERIALS |
| A. General: |
| 1. Provide materials and equipment that will ensure continuous and successful operation of temporary flow control systems. |
| 2. Repair or modify systems as necessary. |
| 3. Unless otherwise shown or specified, materials and equipment may be new or used at Contractor’s option. |
| 4. Coordinate needs of bypass pumping system with requirement for the temporary digested sludge dewatering facilities in Section 01 50 00 – Temporary Facilities and Controls. |
| B. Plugs: |
| 1. Provide with taps for connection of pressure gauges and air hoses, and flow-through capability. |
| 2. Pipe Diameters 24 Inches and Smaller: Use mechanical plugs with rubber gaskets or pneumatic plugs with rubber boots. |
| 3. Pipe Diameters Larger than 24 Inches: |
| 4. Use inflatable bag stoppers made in two (2) or more pieces. |
| 5. Manufacturers: |
| a. Lansas. |
| b. Cherne Industries. |
| C. Pumps: |
| 1. Solids handling design with ability to pump minimum three (3)-inch diameter sphere. |
| 2. Able to run dry for long periods of time to accommodate cyclical nature of flows. |
| 3. Engine: Equipped to minimize noise. Noise levels shall not exceed 86 dBA at a distance of fifty (50) feet from source. |
| D. Electric Power Generators: |
| 1. Be able to simultaneously start and run electric powered pumps required for flow to be controlled. |
| 2. Equipped to minimize noise. Noise levels shall not exceed 86 dBA at a distance of fifty (50) feet from source. |
| 3. Include automatic transfer switch if flow control system is to operate unattended. |
| E. Standby Equipment: |
| 1. Standby Pump: One (1) of each size to be available onsite at all times. |
| 2. Electric Power Generators: Minimum of 1 if temporary flow control system contains electric powered pump. Able to simultaneously start and run electric powered pumps required for flow to be controlled. |
| PART 3 - EXECUTION |
| 3.1 GENERAL |
| A. Install temporary flow control facilities in a location acceptable to Owner’s Operations and Facility Maintenance. |
| B. Operate and maintain temporary flow control while area of Work is out of service. |
| 3.2 BLOCKING FLOW |
| A. Flow control may consist of blocking flow with mechanical or pneumatic plugs if adequate storage is available. |
| B. When blocking flow is no longer needed for performance and acceptance of the Work, remove plugs in a manner that permits sewage flow to slowly return to normal without surcharging or causing other major disturbances downstream. |
| C. Remove temporary plugs at end of each working day and restore normal flow. If downstream work is not or cannot be completed during workday provide, operate, and maintain bypass pumping system or other method of flow control to accommodate flows. |
File details come from the government source that posted it. Updated .